HCAL RBX for HB, HE, and HO Status and Planning
description
Transcript of HCAL RBX for HB, HE, and HO Status and Planning
![Page 1: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/1.jpg)
HCAL RBX for HB, HE, and HO Status and Planning
R. RuchtiDepartment of Physics
University of Notre DameNotre Dame, IN 46556 USA
![Page 2: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/2.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 2
RBX Working Group•Notre Dame
–B. Baumbaugh, B. Beiersdorf, L. Castle, T. Loughran, D. Karmgard, J. Marchant, M. McKenna, R. Ruchti, D. Wiand
•Fermilab–A. Baumbaugh, J. Elias, J. Freeman, R. Foltz, S. Los, C. Rivetta, A. Ronzhin, T. Shaw, J. Whitmore
•Florida State–V. Hagopian, K. Johnson
•UI Chicago–D. Dwyer, M. Adams
•Iowa–Y. Onel
•Minnesota–A. Heering
•Mississippi–M. Booke, M. Reep, J. Reidy
![Page 3: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/3.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 3
HCAL Subsystem Locations
![Page 4: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/4.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 4
Overview of RBX Placement
![Page 5: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/5.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 5
RBX contents for all subsystems
• All components reside in an enclosure/shell which acts as mechanical enclosure and distribution point for services.
• All components are modular – and can be inserted and removed as units.
• RM-19 (HB, HE, and HO subsystems)• RM-73 (HB and HE only)• Calibration Module• CCM (Clock and Control Module)• HV/BV termination• LV termination• Water cooling • Gas manifold for nitrogen inerting of ODU/RM
![Page 6: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/6.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 6
Assembly of HB- in Spain
![Page 7: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/7.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 7
HB- Wedge being loaded on cradle
![Page 8: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/8.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 8
HB RBX mounting on Wedge
![Page 9: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/9.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 9
HB RBX (r,z) viewand (r,r) view
12.323 [313.00]
37.992 [965.00]
LOW VOLTAGE
AND PIPING AREA
4.173 [106.00]
CALIBRATIONMODULE
CCMMODULE
TOP VIEW
FRONT VIEW HB RBX COMPOSITE ASSEMBLY DRAWING
R. FOLTZ, FERMI LABJ. MARCHANT, UNIV. OF NOTRE DAMEAS OF 23 FEBRUARY 2001 9 AM CST
COOLING WATERIN & OUT
19-CHANNELRM-1
19-CHANNELRM-2
73-CHANNELRM
19-CHANNELRM-3
19-CHANNELRM-4
CHUNC
![Page 10: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/10.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 10
HB RBX Front Face
![Page 11: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/11.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 11
Topics
• Overview of RBX Design and Placement– HB RBX– HE RBX– HO RBX
• Services and Access• Planning and Schedule
![Page 12: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/12.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 12
Cooling Routing on RBX enclosure outer surface
![Page 13: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/13.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 13
HB RBX Issues
• Design: compact and limited space• Status: advanced, ready for production• Integration: careful interaction with Tracker and
ECAL services and panels required.• Challenge: accessibility of modules, particularly
the RM-73.• Schedule: Testing of Megatiles in Building 186,
May 2001. Mounting of RBX on HB- wedges Summer 2001 in building 186.
![Page 14: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/14.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 14
HB RBX Assembly
Full RBX with 19 ch RMs
RBX Interior -- HV distributor and backplane
![Page 15: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/15.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 15
HB RBX Module Routing Channels
![Page 16: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/16.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 16
RM-19 QIE Top View
![Page 17: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/17.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 17
RM-19 QIE Front Face
![Page 18: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/18.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 18
Readout Module for 19-channel HPD RM19
![Page 19: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/19.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 19
RM19 Sidewall removed
![Page 20: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/20.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 20
HB RBX Electrical
![Page 21: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/21.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 21
RM19 Rear and Front Views
![Page 22: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/22.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 22
ODU showing patch panel, cookie support plate, HPD, ZIF socket and interface card
![Page 23: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/23.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 23
Module Extractor (CHUNC)
![Page 24: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/24.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 24
RM-73
![Page 25: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/25.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 25
RM-73 Front Face
7.441 [189.00]
3.923 [99.65]
![Page 26: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/26.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 26
RM-73 Rear View
![Page 27: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/27.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 27
HB Mapping ExampleQIE Cards to Megatiles
19.4 19.3 19.2 19.1
1 1 1 12 2 2 2
Tower PIN RO Tower PIN RO Tower PIN RO 3 3 3 3Card Card Card 4 4 4 4
16 A13 3 16 A8 2 15 A4 1 5 5 5 515 C15 3 14 B12 2 13 B5 1 6 6 6 612 C2 3 11 L16 2 10 L15 1 7 7 7 79 G2 3 8 G1 2 7 P15 1 8 8 8 86 R12 3 5 R5 2 4 P2 1 9 9 9 93 T13 3 2 T8 2 1 T4 1 10 10 10 10
11 11 11 1112 12 12 1213 13 13 1314 14 14 1415 15 15 1516 16 16 1615 15 15 1516 16 16 16
![Page 28: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/28.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 28
RBX Services
• Water for cooling in/out• Nitrogen gas for ODU/RM inerting in only• HV/BV + termination• LV• Optical signals QIE out• CCM and slow controls• Laser calibration signals
![Page 29: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/29.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 29
HV/BV Cable Termination
![Page 30: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/30.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 30
HV/BV Distributor
![Page 31: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/31.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 31
Calibration Module
![Page 32: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/32.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 32
General Comment about RBX and Components
• The structures are modular. This allows us to gain in the schedule, as assembly, Q/C and testing can be “factorized”.
• RBX enclosures can be built, tested and mounted, independent of components which can be added later.
• RM can be fabricated mechanically. ODU can be fabricated. Electronics and HPDs can be incorporated when available.
![Page 33: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/33.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 33
Additionals
• Copper fittings and jumper between roof and floor water cooling pipes
• Gas manifold• LV module• CCM• CHUNC• RM pinning• Front protection cover Status of Costing Status of Costing
panels• RM-19 (QIE) and RM-73• Retrofit of holes in RBX flooring for mounts
![Page 34: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/34.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 34
HB RBX Production Status
• HB PPP-1– At CERN in mockup at Prevessin Site.
• HB PPP-2– At Fermilab for electrical integration and 186 testing
• HB PPP-3– At Notre Dame for thermal tests and 186 testing
• HB PPP-4– Under fabrication at an outside vendor and assembled at
Mississippi. Production drawing test bed.• HB RBX production begins April 2001
![Page 35: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/35.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 35
HB access/serviceability issues
• RM-19• Removal of optical cable protective covers• Removal of optical cables, calibration cables• Removal of any blocking services/cables• Direct extraction using CHUNC
• RM-73, CCM and Calibration Modules• Similar to above, except RM-19s must be removed
first.• Removal of any blocking services/cables.• Extraction using CHUNC
![Page 36: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/36.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 36
HB access/serviceability issues
• HV/VB termination and LV termination• Removal of RM-19• Extraction using CHUNC• Service in situ
• HV/VB backplane, electrical backplane• Removal of all RM, CCM and Calib Module• Removal of HV/BV and LV terminations• Full extraction
![Page 37: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/37.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 37
Service Paths + Panels
HB RBX FRONT VIEW WITH SERVICES DRAWING
R. FOLTZ, FERMI LABJ. MARCHANT, UNIV. OF NOTRE DAMEAS OF 23 FEBRUARY 2001
![Page 38: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/38.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 38
Servicing View
HB RBX FRONT VIEW WITH SERVICES DRAWING
R. FOLTZ, FERMI LABJ. MARCHANT, UNIV. OF NOTRE DAMEAS OF 23 FEBRUARY 2001
![Page 39: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/39.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 39
HB Mockup in Lab 5 at Fermilab
19.419.3 CCM Cal 73 19.2
19.419.4 19.1
![Page 40: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/40.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 40
Mockup at Fermilab
![Page 41: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/41.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 41
![Page 42: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/42.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 42
HB RBXExtracting ODU 19.2
![Page 43: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/43.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 43
View of Mockup: edge of wedge
![Page 44: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/44.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 44
View behind ECAL cooling conduits
![Page 45: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/45.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 45
HB RBX environs(lateral shift of TK patch panel)
![Page 46: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/46.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 46
HB RBXExtracting ODU 19.4
![Page 47: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/47.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 47
HB RBXExtracting ODU 19.2
![Page 48: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/48.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 48
HB RBX with TK patch panelno clearance for ODU-73
![Page 49: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/49.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 49
HB RBXExtracting ODU 19.1
![Page 50: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/50.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 50
HB RBXODU 73 clearance issues
![Page 51: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/51.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 51
HB RBXODU 73 clearance problems
![Page 52: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/52.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 52
Suggestion to allow ODU 73 access
![Page 53: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/53.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 53
Accessibility Issues
• All optical cables for RM-19 visible and accessible in an unobstructed manner for visibility and access to mounting screws.
• Same requested for RM-73, but may not be possible.• Use of compact extraction tool CHUNC to remove
and reinsert modules• Use of floor tracking to assure proper module
insertion at odd angles.• Mockup studies, Fermilab Lab 5 and Prevessin.
![Page 54: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/54.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 54
HE RBX Issues
• Design: laterally compact, but good access in principle
• Status: enclosure design quite advanced• Integration: careful interaction with Preshower
(SE) and ECAL (EE) services.• Challenge: cooling issues and ODU fiber routing.• Schedule: PPP in June 2001
![Page 55: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/55.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 55
HE RBX Status
• Drawings in progress• Builds as much as possible upon the design
of HB where possible. • Layout of various internal modules in
progress• ODU in mockup phase
![Page 56: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/56.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 56
HE RBX (r,z) view
ThermalInsulator
![Page 57: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/57.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 57
HE RBX (z,r) viewSection through CCM
ThermalInsulator
![Page 58: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/58.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 58
HE RBX (z,r) viewSection through Calib Module
ThermalInsulator
![Page 59: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/59.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 59
HE RBX (r,z) view
RM 19Module
RM 19Module
LV
RM 73Module
RM 19Module
RM 19Module
Calibration CCM
HV
![Page 60: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/60.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 60
HO RBX Issues
• Design: vertically very compact. Resides within muon absorber which provides for magnetic “focussing” for HPD, and shortened optical cables from HO megatiles.
• Status: enclosure in design, but not advanced• Integration: careful interaction with muon
chamber systems.• Challenge: ODU/HPD cookie placement,
servicing, and optical cable routing to megatiles.• Schedule: PPP in winter 2001
![Page 61: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/61.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 61
HO RBX Status
• Drawings in formative stage• Awaiting final results from study of
magnetic field situation• Appears that a solution is possible with RBX
located at the large z ends of the muon wheels.
![Page 62: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/62.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 62
HO RBX Concept
Front part of box Rear Part of boxG-10
HPD
Cal
ibra
tion
TTCLV HV
ODU
HPD
ODU
HPD
ODU
HPD
ODU
QIEElect
QIEElect
QIEElect QIE
ElectQIEElect
TOP View
Front ViewODU ODU ODU ODUCal
Side ViewODUQIETTC
HO RBX Mechanical Sketch
![Page 63: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/63.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 63
HO (r,z) Schematic
HPD
Cal
ibra
tion
TTC LVHV
ODU
HPD
ODU
HPD
ODU
HPD
ODU
QIEElect
QIEElect
QIEElect QIE
ElectQIEElect
Bottom View
![Page 64: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/64.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 64
HO RM schematic
HV Connectors
ODU
Cooling by-pass
Base Extrusion for HO ODUs
![Page 65: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/65.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 65
HO RBX Mechanical: Bottom Coverplate
HPD
Cal
ibra
tion
TTC LVHV
ODU
HPD
ODU
HPD
ODU
HPD
ODU
QIEElect
QIEElect
QIEElect QIE
ElectQIEElect
Bottom View
Bottom Cover/Mechanical Support
![Page 66: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/66.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 66
HO Mechanical: Top Coverplate
Front part of box Rear Part of boxG-10
HPD
Calib
ratio
n
TTCLV HV
ODU
HPD
ODU
HPD
ODU
HPD
ODU
QIEElect
QIEElect
QIEElect QIE
ElectQIEElect
TOP View
Front ViewODU ODU ODU ODUCal
Side ViewODUQIETTC
HO RBX Mechanical Sketch
TOP Cover/Mechanical Support
![Page 67: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/67.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 67
Request of CMS
• Approval of HB RBX design and agreement that HB RBX production can begin.
• Approval of design concept of HE RBX and that once full drawing set is available, that production can begin of the HE RBX.
• Approval of design concept and placement of HO RBX within iron of the Muon Wheels.
![Page 68: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/68.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 68
HB RBX Accessing Issues
12.3228 [313.00]
37.9920 [965.00]
3.9370 [100.00]2.7559 [70.00]
3.9370 [100.00]2.7559 [70.00]
1.9685 [50.00]
LV
3.1496 [80.00]
19.6850 [500.00]
4.0034 [101.69]
1.3447 [34.16]11.8207 [300.25]
CL of RBX vs CL of TPP
1.6406 [41.67]1.5149 [38.48]
6.6929 [170.00]
1.7717 [45.00]
4.3307 [110.00]
2.4340 [61.82]
LOW VOLTAGE
AND PIPING AREA
CALIBRATION
MODULE
CCMMODULE
COOLING WATERIN & OUT
19-CHANNELRM-1
19-CHANNELRM-2
73-CHANNELRM
19-CHANNELRM-3
19-CHANNELRM-4
CHUNC
HB RBX COMPOSITE ASSEMBLY DRAWINGTOP VIEW WITH SERVICES
R. FOLTZ, FERMI LABJ. MARCHANT, UNIV. OF NOTRE DAMEAS OF 27 FEBRUARY 2001
![Page 69: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/69.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 69
HE ODU Fiber Mockup
![Page 70: HCAL RBX for HB, HE, and HO Status and Planning](https://reader036.fdocuments.in/reader036/viewer/2022062500/56815a9d550346895dc82370/html5/thumbnails/70.jpg)
PRR for HCAL RBX 1-March 2001 R.Ruchti 70
HE ODU fiber routing test