7/29/2019 HAZOP HAZID-Aug-Bal Corrective Action
http://slidepdf.com/reader/full/hazop-hazid-aug-bal-corrective-action 1/6
S# REF # RECOMMENDATIONS BY Applicability Status Transmittal No.
1 001.1.1 To provide flow operating range of pumps P - 105 / 106 / 107 / 108 / 109. GS Soil Washing Apprvd-B 50757-GSK-T-0624
2 001.1.2 To supply work plan for continuous feed of soil washing system. Soil Washing waiting 50757-GSK-T-0753
3 002.1.1 To finalize inspection , maintenance & operation procedures for soil washing unit. Soil Washing Apprvd-B 50757-GSK-T-0654
4 003.1.1 Refer To recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-06545 004.1.1 Refer To recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
6 005.1.1 Refer To recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
7 006.1.1 Refer To recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
8 007.2.1 To update P&IDs to include local gauges & control logic of equipment as per cause & effect diagram. GS Soil WashingApprvd-B 50757-GSK-T-0560
9 009.1.1 To update cause & ef fect diagram to include all alarms & trips for the soil washing system. GS Soil Washing Apprvd-B 50757-GSK-T-0560
10 011.1.1 to implement proper training of operation / maintenance personnel (provide training record) Soil Washing waiting 50757-GSK-T-0830
11 011.2.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
12 014.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-065413 015.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
14 017.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
15 017.1.2 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
16 018.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
17 019.1.1 To include upstream screening and crushing procedures in project execution plan. Soil Washing waiting 50757-GSK-T-0753
18 029.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
19 030.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
20 031.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
21 034.1.1 refer to recommendation 2.1.1 Soil WashingApprvd-B
50757-GSK-T-065422 035.2.1 refer to recommendation 9.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
23 036.1.1 To provide design flow of pumps P-201 / 202 /203 /110 . GS Soil Washing Apprvd-B 50757-GSK-T-0624
24 037.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
25 038.1.1 refer to recommendation 9.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
26 047.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
27 064.1.1 refer to recommendation 7.2.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
28 074.1.1 to update P&IDs P-6 to show PS 102/103 downstream bag filters on suction of P-102/103 GS Soil Washing Apprvd-B 50757-GSK-T-0560
29 075.1.1 To update P&IDs P-8 to show low flow switch on polyblend water to ME 313. GS Soil Washing Apprvd-B 50757-GSK-T-0560
30 078.1.1 refer to recommendation 74.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
31 085.1.1 To update P&IDs to show correct setting rating of chemical discharge hoses. GS Soil Washing Apprvd-B 50757-GSK-T-0560
32 086.1.1 To update P&ID P- 6 revision 7 to show rupture disk A on discharge of P- 102/103. GS Soil Washing waiting 50757-GSK-T-0560
33 086.1.2 to update training program to include high pressure water system. Soil Washing waiting 50757-GSK-T-0830
34 087.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
35 088.1.1 to provide QA/QC plan for chemical control and usage Soil Washing Apprvd-B 50757-GSK-T-0656
36 089.1.1 to provide safe routing of caustic / acid to safe containment . GS Soil Washing waiting submitted
37 091.1.1 refer to recommendation 88.1.1 Soil Washing waiting 50757-GSK-T-0656
38 092.1.1 to provide design flow of pumps P 301 /302A/B / 303 GS Soil Washing Apprvd-B 50757-GSK-T-0624
39 093.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
40 094.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-065441 095.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
42 100.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
43 113.1.1 to provide design flow of P- 304 A/B/C / P- 317/318. GS Soil Washing Apprvd-B 50757-GSK-T-0624
44 113.1.2 to update P&IDs P 9 Rev 6 to include sonic sludge level sensors on T-302 A/B. GS Soil Washing Apprvd-B 50757-GSK-T-0560
45 114.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
46 114.2.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
47 117.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
48 118.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
49 119.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
50 120.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
51 121.1.1 refer to recommendation 9.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
52 123.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
53 125.1.1 to update P&ID 9 Rev 6 to show check valve on discharge of P-318 GS Soil Washing Apprvd-B 50757-GSK-T-0560
54 139 1 1 f t d ti 9 1 1 GS S il W hi A d B 50757 GSK T 0560
HAZOP Corrective Actions & Recommendations
7/29/2019 HAZOP HAZID-Aug-Bal Corrective Action
http://slidepdf.com/reader/full/hazop-hazid-aug-bal-corrective-action 2/6
55 139.1.2 refer to recommendation 7.2.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
56 141.1.1 refer to recommendation 9.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
57 142.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
58 143.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
59 143.1.2 to include in operating procedure safety precautions required for relative equipment Soil Washing waiting submitted
60 144.1.1 refer to recommendation 9.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
61 144.1.2 refer to recommendation 7.2.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
62 145.1.1 to provide design flow of pumps P- 307 / 308 /309 / 310 GS Soil Washing waiting 50757-GSK-T-062463 145.1.2 to supply HAZOP report for vendor packages (Ultrafiltration Unit, Reverse Osmosis) or perform HAZOP study for these packages. GS Soil Washing Apprvd-B
64 148.1.1 refer to recommendation 9.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
65 153.1.1
to develop and document the proper engineering / operational solution for preventing damage of membranes leading to shutdown due to high
temperature . Soil Washing Apprvd-B
66 162.1.1 refer to recommendation 9.1.1 GS Soil Washing Apprvd-B 50757-GSK-T-0560
67 173.1.1 Refer To Recommendation 153.1.1 Soil Washing waiting submitted
68 179.1.1 refer to recommendation 10 in HAZID . Soil Washing waiting 50757-GSK-T-0696
69 192.1.1 refer to recommendation 2 in HAZID . Soil Washing waiting submitted
70 192.1.2 to demonstrate layout of oil facilities in soil washing is in accordance with KOC - L-028 standard. GS Soil Washing waiting 50757-GSK-T-067171 193.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
72 193.1.2 to add level gauge on oil skimmer tanks T-101 / 304 / 313 and include tank monitoring in operating manual procedure. GS Soil Washing Apprvd-B 50757-GSK-T-0560
73 197.1.1 to include air tank on P&IDs P7 Rev 7 . GS Soil Washing Apprvd-B 50757-GSK-T-0560
74 197.1.2 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
75 203.1.1 to provide high pressure protection set ting on air compressor discharge system. GS Soil Washing Apprvd-B 50757-GSK-T-0560
76 205.1.1 refer to recommendation 2.1.1 Soil Washing Apprvd-B 50757-GSK-T-0654
77 206.1.1. to update P&IDs & cause &effect to include safeguarding alarmsand trips of the oil recovery unit. GS Oil Recovery Apprvd-B 50757-GSK-T-0570
78 208.1.1. refer torecommendation206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
79 209.1.1. to demonstrate mechanical design of heat exchanger tubing can handle 230 degc. GS Oil Recovery Apprvd-B 50757-GSK-T-057080 212.1.1. to update P&ID 23 to show TC on TIT 203. GS Oil Recovery Apprvd-B 50757-GSK-T-0570
81 213.1.1. refer to recommendation 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
82 214.1.1. to provide operating and maintenance manual for oil recovery unit equipment . Oil Recovery Apprvd-B 50757-GSK-T-0610
83 215.1.1. refer to recommendation 214.1.1. Oil Recovery Apprvd-B 50757-GSK-T-0610
84 217.1.1. to supply pressure relief valve on pump P-101. GS Oil Recovery Apprvd-B 50757-GSK-T-0609
85 221.1.1. refer to recommendation 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
86 223.2.1. to demonstrate overheating protection on pumps P-102 A/B. GS Oil Recovery Apprvd-B 50757-GSK-T-0570
87 224.1.1. refer to recommendation 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
88 224.2.1. to demonstrate overheating protection on pumps P-102 A/B. GS Oil Recovery Apprvd-B 50757-GSK-T-057089 225.1.1. refer to recommendation 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
90 226.1.1. refer to recommendation 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
91 227.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
92 229.2.1. to demonstrate layout of oil facilities in Oil Recovery is in accordance with KOC -L-028 standard. GS Oil Recovery Apprvd-B 50757-GSK-T-0671
93 232.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
94 233.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
95 234.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
96 235.1.1. To provide evidence high pressure mechanical protection on P – 102 A/B GS Oil Recovery Apprvd-B 50757-GSK-T-0609
97 235.1.2. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-057098 235.2.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
99 236.1.1.To demonstrate alarm setting of PICA - 401A provides sufficient time to enable operator to take action (small difference between alarm setting and PSV setting does not enable
operator to take action)GS Oil Recovery
Apprvd-B 50757-GSK-T-0597
100 236.1.2. To define criteria of PSVs design showing calculations and various design cases (Blocked outlet, fire case, thermal relief. GS Oil Recovery Apprvd-B 50757-GSK-T-0597
101 237.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
102 238.1.1. Refer To 206.1.1. GS Oil Recovery Apprvd-B 50757-GSK-T-0570
103 240.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
104 241.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
105 242.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
106 243.1.1. To update the P&ID # 26 to show LV downstream V - 103 A to L as normal manual valve GS Oil Recovery Apprvd-B 50757-GSK-T-0570
107 243.1.2. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
108 245.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
109 246.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
7/29/2019 HAZOP HAZID-Aug-Bal Corrective Action
http://slidepdf.com/reader/full/hazop-hazid-aug-bal-corrective-action 3/6
113 267.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
114 267.1.2. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
115 269.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
116 271.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
117 271.2.1. Refer To206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
118 272.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
119 273.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
120 276.1.1. To update P&ID to show check valve on discharge of P - 800 A/B GS Oil Recovery Apprvd-B 50757-GSK-T-0570121 277.1.1. To confim setting of high temperature alarm and trip (TICA – 4101 H/HH) for protection of heating medium system against over heating GS Oil Recovery Apprvd-B 50757-GSK-T-0609
122 278.1.1. Refer to HAZID (burner management system design) GS Oil Recovery Apprvd-B 50757-GSK-T-0609
123 280.1.1. Refer to HAZID (burner management system design) GS Oil Recovery Apprvd-B 50757-GSK-T-0609
124 282.1.1. To supply design definition and line up procedure for P - 801 for protection against pump damage and over pressurization of heating medium. GS Oil Recovery Apprvd-B 50757-GSK-T-0609
125 284.1.1. To supply design definition of LS-4200 function for prevention of P-801 damage GS Oil Recovery Apprvd-B 50757-GSK-T-0609
126 285.1.1. To supply data for over flow protection on tanks V-800 A/B GS Oil Recovery Apprvd-B 50757-GSK-T-0609
127 287.1.1. To supply Mechanical High Pressure protection on P-105 GS Oil Recovery Apprvd-B 50757-GSK-T-0609
128 287.1.2. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
129 291.1.1. To supply temperature indication on V - 106 and include periodic monitoring in operating procedure. Oil Recovery Apprvd-B 50757-GSK-T-0610130 294.1.1. To Provide data, configuration and sizing basis of tank vent V - 106 GS Oil Recovery Apprvd-B 50757-GSK-T-0671
131 294.1.2. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
132 295.1.1. To supply containment for tank V - 106 in accordance with KOC standards. GS Oil Recovery Apprvd-B 50757-GSK-T-0777
133 300.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
134 301.1.1. Refer To 206.1.1. GS Oil Recovery Apprvd-B 50757-GSK-T-0570
135 305.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
136 306.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
137 307.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
138 308.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610139 309.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
140 310.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
141 314.1.1. To supply sizing data and data sheet for PSV – 301 A/B/C GS Oil Recovery Apprvd-B 50757-GSK-T-0597
142 316.1.1. Refer To 206.1.1 GS Oil Recovery Apprvd-B 50757-GSK-T-0570
143 319.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
144 319.2.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
145 321.2.1. To provide evidence for high discharge pressure protection on G – 703 C/D GS Oil Recovery Apprvd-B 50757-GSK-T-0609
146 321.3.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
147 322.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610148 323.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
149 325.1.1. Refer To214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
150 327.1.1. Refer To 206.1.1 (No Heat tracing on P-107 A/B suction) GS Oil Recovery Apprvd-B 50757-GSK-T-0570
151327.1.2. To provide the engineering solution for maintaining discharge design flow of P - 107 A/B to GC (Inspite of high viscosity) GS /KOC Oil Recovery
PENDING
152 329.1.1. To define connection system bewteen Tie-in point and GC - 11 / GC – 19 / BCRP and ensure suitable pressure rating. KOC Oil Recovery PENDING
153 335.1.1 Refer to HAZID Oil Recovery PENDING
154 335.1.2 To demostrate high pressure protection for blocked case and fire case scenarios GS Oil Recovery waiting 50757-GSK-T-0903
155 337.1.1 Refer to HAZID Oil Recovery PENDING
156 338.1.1 Refer to HAZID Oil Recovery PENDING
157 344.1.1 Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
158 349.1.1. Refer To 214.1.1 Oil Recovery Apprvd-B 50757-GSK-T-0610
A- Available , N/A - Not/AvailableLegend
7/29/2019 HAZOP HAZID-Aug-Bal Corrective Action
http://slidepdf.com/reader/full/hazop-hazid-aug-bal-corrective-action 4/6
A N/A
W
W
W
W
W
W
W
7/29/2019 HAZOP HAZID-Aug-Bal Corrective Action
http://slidepdf.com/reader/full/hazop-hazid-aug-bal-corrective-action 5/6
W
W
W
W
W
7/29/2019 HAZOP HAZID-Aug-Bal Corrective Action
http://slidepdf.com/reader/full/hazop-hazid-aug-bal-corrective-action 6/6
P
P
P
W
P
P