![Page 1: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/1.jpg)
1
HANYA STATION PH2 PROJECT Health Management Plan for SELECT TO EXECUTE Phases
Revision Record
01 09/11/2017 Approval from SELECT to EXECUTE Phase
Nadiya Al Harthy
MCOH2
Olufemi Daodui CHSG5
Jose Petrizzo
MCOH1
Rev. Date Reason for
Issue
Originator Checker Approver
Copyright: This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means (electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
![Page 2: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/2.jpg)
2
Responsible RTA’s distribution list:
Hold Record
Specify any outstanding issues in the document
Hold No. Section Description of Hold
Revision Tracking Specify significant changes from previous revisions of the document (sorted by date)
Rev. Date Description of Revision
01 09/11/2017 Issued for approval from SELECT to EXECUTE
Phase
User Notes:
1. A controlled copy of the current version of this document is on PDO's live link. Before making reference to this document, it is the user's responsibility to ensure that any hard copy, or electronic copy, is current. For assistance, contact the Document Custodian.
2. Users are encouraged to participate in the ongoing improvement of this document by providing constructive feedback.
Name Function Signature
Petrizzo, Jose MCOH1 Sr. IH
Daodu, Olufemi
CHSG5 Project TSE
Rawahi, Saif UEP11H FEED HSE
Habsi, A. Rahman
CTOG2, CTOG ORA
Harthy, Mohammed
CTOM
M&I
![Page 3: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/3.jpg)
3
TABLE OF CONTENTS
ACRONYSM 4
1. INTRODUCTION 5
2. PROJECT DESCRIPTION 6
3. HEALTH SECTION 8
3.1 Health Standards 8 3.1.1 Health Impact Assessment (HIA) 8 3.1.2 Health Risk Assessments (HRA) 8 3.1.3 Human Factors Engineering (HFE) in Projects 9 3.1.4 Medical Emergency Response Plan (MERP) 9 3.1.5 Fitness to work (FtW) 10
3.2 Health resources scoping and deliverables 10 3.2.1 Health Risk Assessment 16 3.2.2 Health Impact Assessment 16 3.2.3 MER Plan 16 3.2.4 HFE Strategy 16
4. ANNEXES 19
4.1 Health Risk Management Priorities 19
4.2 DCAF Overview for MCOH 19
5. REFERENCES 20
![Page 4: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/4.jpg)
4
ACRONYMS
ATA Accountable Technical Authority
CMF Control management Framework
FtW Fitness To Work
HEMP Hazards and Effects Management Process
HIA Health Impact Assessment
HPO Health Project Owner
HSSE & SP (HSE) Health, Safety, Security, Environment and Social Performance
IIE Initial Impact Evaluation
MER Medical Emergency Response
PDO Petroleum Development Oman
PPE / RPE Personal Protective Equipment / Respiratory Protective Equipment
PR Procedure
ALARP As Low As Reasonably Practicable
BFD Basis for Design
CS+PE Carbon Steel + Polyethylene
CSR Concept Selection Report
DCAF Discipline Controlled Assurance Framework
DD Detailed design
DEM Design Engineering Manual
DEP Design Engineering Practice
ESD Emergency Shutdown
FG Fuel Gas
FEED Front End Engineering Design
HAZID Hazard Identification
HAZOP Hazard and Operability (study)
HFE Human Factor Engineering
HRA Health Risk Assessment
HS Hanya Station
HSDP Hanya Station Development Project
IA Instrument Air
IPF Instrumented Protective Function
KOD Knock-Out Drum
LMS Local Manifold Station
MSV Multi-port Selector Valve
PCAP Project Control and Assurance Plan
PMR Pole Mounted Automatic Re-closers
RAM Risk Assessment Matrix
![Page 5: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/5.jpg)
5
1. INTRODUCTION
A Health Plan brings together all essential health information that must be
produced for each project phase from Identify to Operate. The Health Plan must
be developed since the IDENTIFY PHASE, because it is especially important in
areas with medical care challenges, where there will be a focus on Medical
Emergency Response and individual fitness.
An Occupational Health Technical Authority (TA) must sign off all health reports
and plans. The Health Plan will identify activities and control measures for the
Health aspects of the PDO Corporate Management Framework (CMF) and
where these are integrated into the project, in order to comply with it and with
DCAF. Furthermore, Health should be considered as an opportunity for input into
the project sustainable development strategy and plan.
This Health Plan summarizes the Health elements (HRA, HFE, HIA, FtW, and
MERP) that are required for the Hanya Station PH2 Project from SELECT to
EXECUTE PHASES. These Health elements will be developed, updated and
delivered according to the HSSE & SP Project Activity Plan along the project
cycle.
This plan pursues two main objectives:
Ensure that Health requirements and specifications are comprehensively implemented during the project cycle.
Complete specific Health assessments mandated by the HSE CMF, Opportunity Realization Process (ORP), Discipline Controls and Assurance Framework (DCAF), local legislation and rules on the project.
![Page 6: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/6.jpg)
6
2. PROJECT DESCRIPTION
The main objectives of the Hanya Station Development Project phase 2 are:
To deliver a robust Field Development Plan utilizing analogue information from Lower Shuaiba developments.
To develop, analyze and select the optimum surface and subsurface development concepts that facilitate this requirement and that abide and support the below business/value drivers and critical success factors..
HSDP Phase 2 consists of RMSs and a gathering station (HG) which is the remainder of the scope after completion of Phase 1.
Phase 2 will bring in additional MSVs divided over RMS-1, RMS-2 and LMS (in addition to the MSV installed by Phase 1), WI/test and production trunk lines (from RMSs to HGS), WIMs, production and test separators, Hydro cyclone package, water injection pumps, utilities (e.g. Flare, Demulsifiers, Drains, Back-up Propane) and the required supporting infrastructure (e.g. Electrical, C&A, Civil, etc).
The design will replicate the existing surface facilities design of Musallim and Upper Shuaiba Projects to the extent possible in order achieve cost saving by standardization of equipments through PDO price agreement and repeat order arrangement which will minimize customized design requirements.
![Page 7: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/7.jpg)
7
3. HEALTH SECTION
The Health elements of the plan for the current phase are related to the following DCAF components: a) Project HSSE Activity Plan b) Project HSSE CMF c) HSSE & SP Hazards & Effect Register d) Impact Assessment e) Concept ALARP demonstration Report f) Cross-discipline engagement Some of these components are Health deliverables; others will require Health input along the project cycle.
3.1 Health Standards
3.1.1 Health Impact Assessment (HIA)
HIA is used to identify and assess the potential health impacts of a project “outside the facility fence” in order to implement measures so that negative impacts are minimized and positive impacts are optimized. HIA is one of the applications of the Hazards and Effects Management Process Hazards and
Effects Management Process (HEMP) for projects.
HIA applies to projects being:
new Major Installations and pipeline developments;
new exploration and drilling activities;
modification of existing activities, including Major installations and pipeline developments, having impacts with potential Consequences of 4 or 5 on the RAM; and
Decommissioning or abandonment of existing activities, including Major Installations and pipeline developments.
3.1.2 Health Risk Assessments (HRA)
Health Risk Assessment (HRA) is a process of identifying, evaluating, controlling and managing health risks associated with work to prevent acute and chronic health effects. HRA also serves to advise if monitoring or health surveillance is required for a specific job or process.
The overall objective is to manage the risk of harm to people by identifying and assessing health risks and by implementing control and recovery measures.
![Page 8: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/8.jpg)
8
The HRA shall consider risks arising from chemical, physical, biological, ergonomic and psychological hazards associated with the work environment. HRA shall be covered in all activities including new projects, acquisition, closure, divestment an abandonment of facilities. Refer to the PDO Health Hazard Inventory (HHI) available on the PDO HSE – Health webpage.
3.1.3 Human Factors Engineering (HFE) in Projects
The terms Ergonomics and Human Factors are often used interchangeably. However, ergonomics focuses on how the work affects people and human factors focuses on the worker machine interface. Good design requires a detailed knowledge of how humans interact with the work system. HFE:
Increase the operational performance, safety, health and comfort of the work system (Reduce HSE Risk).
Reduce the likelihood of or prevent human errors and to limit the consequences (Reliability).
Enhance the productivity of human efforts (Efficiency).
Enhance overall system performance by improving the ease and efficiency of use (Productivity).
Incorporate user/operator knowledge in the design of the system/product (Usability).
HFE principles shall be considered and applied from SELECT phase of new facilities projects where design can have a critical impact on equipment usability and user safety and health.
HFE shall be applied in the following projects:
New plants/facilities
Revamp of existing plant/facility (unless there is no change to the work system)
Buildings and workstations design (e.g. central control rooms, offices, workshops and laboratories)
IT software/hardware, instrumentation
3.1.4 Medical Emergency Response Plan (MERP)
Medical Emergency Response Plan (MERP) provides a framework for the management of medical emergencies and describes the appropriate response, outlines the facilities and equipment available at a Site and defines the organization and procedures for responding to a medical emergency.
![Page 9: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/9.jpg)
9
The objective of the MERP is to help ensure an effective response to medical emergencies by:
Documenting the organization roles and responsibilities of personnel
managing the medical emergency.
Defining interfaces between the different response teams.
Providing clear concise instructions and guidance on what action to take in
response to a medical emergency.
Detailing communication requirements.
Providing templates to facilitate the medical emergency response.
Specifying equipment / facilities / resources that are available during the
medical emergency.
3.1.5 Fitness to work (FtW)
Fitness to Work is a medical specification for HSE critical Jobs that as a minimum require specialist FtW assessments. Jobs relevant for Projects which require FtW assessment include:
Use of Breathing Apparatus
Catering and food handling
Professional drivers, light and heavy equipment driving
Emergency response team and rescue work
Fire fighters
![Page 10: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/10.jpg)
10
3.2 Health resources scoping and deliverables
The following table summarizes the Health requirements and resources for compliance with local legislation and PDO CMF. It also allows the appropriate action tracking for the Plan.
DELIVERABLE
PHASE
SELECT DEFINE EXECUTE Comments
Health Management Plan
(HMP)
The assigned PDO Health Technical
Authority (ATA2), José Petrizzo as
Health Project Owner (HPO), will
provide Health deliverables required
for Hanya Station PH2 Project as
described in this plan.
Health content of the Hanya Station
PH2 Project HSSE Plan and
Procedures will be reviewed to
determine if they are applicable to
the project and identify any
concerns/issues.
HMP to be updated
by MCOH1 if
necessary
Q3 2018 EXECUTE phase
projected to start
![Page 11: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/11.jpg)
11
DELIVERABLE
PHASE
SELECT DEFINE EXECUTE Comments
Human Factor
Engineering (HFE)
Elements
HFE Screening and Strategy has
been completed on 07/03/2017
during SELECT phase
Budget considerations for HFE need
to be ensured during this phase in
order to implement strategy along the
project cycle.
HFE Studies to be
facilitated by AP
during DEFINE
phase (FEED). HFE
Close Out Report to
be delivery by FEED
on Q1 2018
Implementation and
validation will
continue by AP,
Project TSE advisor
and HFE TAs
It is vital to check
that what is
constructed is true
to the HFE design
requirements, and
the design intent, at
intervals during the
construction stage.
Health Risk Assessment
(HRA) HRA for Hanya Station PH2 Project
has been planned to be issued for
approval on 09/11/2017.
HRA for construction
to be performed by
contractors 3
months in advance
EXECUTE
(Construction)
Phase starts. PDO
MCOH Dep. will
validate the
contractor’s
deliverable
PDO MCOH Dep.
has completed an
HRA for this project.
![Page 12: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/12.jpg)
12
DELIVERABLE
PHASE
SELECT DEFINE EXECUTE Comments
Health Impact Assessment (HIA)
The project team performed the ESHIA screening on 07/2017.
According to PDO MCOH department there is no detectable or perceived adverse health risks on livelihood, community health, vulnerable population and/or company and contract workers living/working (off plot) in the surroundings.
![Page 13: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/13.jpg)
13
DELIVERABLE
PHASE
SELECT DEFINE EXECUTE Comments
Medical Emergency Response Plan (MERP)
Aspects that link the MERP Contractors. Interface should be defined in the
applicable “Construction Contractors HSSE management Plan”.
Contractor’s MERP and any bridging document shall be deliverable 3 months in advance of EXECUTE (Construction) phase starts.
PDO MCOH Dep.
Will validate
contractor’s
deliverables
The PDO for
Hanya Station PH2
Project is bridged to
YIBAL MERP. It was updated and
meets the specific
project needs (particularly
resources and Tier
response times) at this moment. The
assigned
functional HPO will review
continuously the
Site MERP to
ensure is updated.
![Page 14: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/14.jpg)
14
DELIVERABLE
PHASE
SELECT DEFINE EXECUTE Comments
Fitness to Work (FtW) Contractors
performing work
during construction
shall utilize PDO
approved clinics for
FtW assessments.
Results must be
presented and
validated 3 months
in advance
EXECUTE
(Construction)
phase starts
Based on the HRA all PDO jobs have to be identified where workers will need to pass FTW requirements (Professional drivers, crane operators, catering, and SCBA/BA users in ERP). Procedures are included as part of the HSE CMF and Human Resources (HR) policies. Mina Al Fahal (MAF) Clinic shall be selected as the clinic to execute FtW medical examinations for PDO staff.
Cross-discipline
engagement HPO or any Health TA will engage with other disciplines within the project team for
support in the update of HSE Technical Plans and any other none Technical Risk
Assessments.
PDO MCOH Dep.
continuous support
and long term
commitment as
business partner
![Page 15: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/15.jpg)
15
DELIVERABLE
PHASE
SELECT DEFINE EXECUTE Comments
CMF Health Specifications The assigned HPO will engage with project team for supporting the implementation of CMF
Health Specifications along the project cycle, regarding following Specifications:
Fitness to Work (SP-1230 – Medical Examination, Treatment and Facilities)
Health Risk Assessment (SP-1231 – Occupational Health)
Public Health (SP-1232 – Public Health)
Human Factors Engineering (SP-2215 – HFE in Projects)
Medical Emergency Response (PR-1243 – Medical Emergency Response Manual)
Reporting and investigation of HSE incidents (PR 1418 – Incident Notification, Reporting and Follow-up Procedure Part 1)
Chemicals Management and SHOC) (SP 1194- Chemical Management)
Exposure Monitoring (SP1231- Occupational Health)
Smoking, alcohol and drug policy (SP 1233 – Smoking, Drugs and alcohol)
MCOH To reinforce
compulsory
compliment by
Contractors
![Page 16: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/16.jpg)
16
3.2.1 Health Risk Assessment
The HRA is the application of the Hazards & Effects Management Process (HEMP) to Health hazards. Management programs must be in place to identify, assess, control & document Health risks from chemical, physical, biological, ergonomic & psychological hazards in both the development/construction and operational work environments, which have been identified as high or medium on the PDO Risk Assessment Matrix (RAM). Health risks must be considered so that controls can be implemented to eliminate the risks or reduce (mitigate) exposures to ALARP.
A new section for YIBAL Production Area HRA will be created once the Project is over, if necessary.
An HRA for construction health hazards will be performed in the EXECUTE phases (Construction) and will provide input for any update of project HAZID and HSSE Hazards and Effects Register. PDO MCOH Dep. will provide long term support for the HRA administration and update.
3.2.2 Health Impact Assessment
PDO MCOH Dep. will assess the need for input in the project stakeholder identification process integrating efforts with Impact Assessment (IA) team. However this project does not need an HIA.
3.2.3 MER Plan
PDO MCOH Dep. will review and update if needed the Medical Emergency Response Plan/Strategy in upcoming phases of the Project, and will verify the criteria listed in HSSE CMF is met. PDO MCOH Dep. also will review contractors MER Plan(s) or bridging documents).
3.2.4 HFE Strategy
PDO HFE ATAs will support the implementation of project HFE Strategy. Key aspects of the strategy are: HFE verifications along the project cycle, PDO MCOH Dep. will provide technical support on as needed basis, ensuring that HFE design requirements are adopted in DEPs 30.00.60.series and other acceptance criteria are brought to the attention of the main contractors. Ensuring that, as far as possible, HFE objectives are integrated with related project activities (such as operability and maintainability reviews, material handling studies, drawing and 3-D model reviews, constructability reviews, etc).
![Page 17: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/17.jpg)
17
The degree of HFE involvement and focus during a construction review should be commensurate with the scale and complexity of the project. The HFE AP should liaise with the project’s Flawless and/or OR&A representative regarding construction inspections or yard visits: their operability and maintenance requirements and objectives are similar and there is usually value in a combined approach.
.
![Page 18: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/18.jpg)
18
4. ANNEXES
4.1 Health Risk Management Priorities
4.2 DCAF Overview for MCOH
![Page 19: HANYA STATION PH2 PROJECT - PDO€¦ · Project TSE Rawahi, Saif UEP11H FEED HSE Habsi, A. Rahman CTOG2, CTOG ORA Harthy, Mohammed CTOM M&I. 3 TABLE OF CONTENTS ACRONYSM 4 1. INTRODUCTION](https://reader035.fdocuments.in/reader035/viewer/2022062604/5f77ef2b5030f403203d200c/html5/thumbnails/19.jpg)
19
5. REFERENCES
Discipline Controls and Assurance Framework (DCAF) Tool.
HFE Shell DEPs Version 41.
Fitness to Work (SP-1230 – Medical Examination, Treatment and Facilities).
Health Risk Assessment (SP-1231 – Occupational Health).
Public Health (SP-1232 – Public Health).
Smoking, alcohol and drug policy (SP 1233 – Smoking, Drugs and alcohol).
Medical Emergency Response (PR-1243 – Medical Emergency Response
Manual).
Reporting and investigation of HSE incidents (PR 1418 – Incident Notification, Reporting and Follow-up Procedure Part 1).
Hanya Station PH2 Project Process Design Basis and Standard Project Description. Project ID NOY000HN0130-01.
Hanya Station PH2 Project HAZID Report ID NOY000HN0130-01.
Hanya Station PH2 Project HFE Screening Report.
Hanya Station PH2 Project Environmental Impact Assessment Report.