Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock...

86
Hansen – Managing Safely 1 CDM – An Appreciation CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd

Transcript of Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock...

Page 1: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 1

CDM – An AppreciationCDM – An Appreciation Mark Mallen

Health and Safety ManagerFenlock Hansen Ltd

Page 2: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 2

IntroductionIntroduction

Effective at the start of 1995Place statutory obligations on

more partiesReflect good construction

management To improve the industry’s

appalling accident record

Page 3: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 3

IntroductionIntroduction

By encouraging

– Time to plan– Early appointment of key people– Competent duty holders– Early identification and reduction of

risks– Co-operation

Page 4: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 4

IntroductionIntroduction

The principal duty holders

– The Client– The Designer

Page 5: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 5

IntroductionIntroduction

Newly created post-holders

– Planning Supervisor– Principal Contractor

Page 6: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 6

IntroductionIntroduction

The HSC has provided guidance - an Approved Code of Practice

CONIAC has produced specific guidance for designers and managers

Page 7: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 7

Objectives Objectives

Be able to name duty holdersName the ACOPName key documentsDescribe key designer dutiesDescribe the hierarchy of controlDescribe the purpose of the

regulations

Page 8: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 8

Content Content

Legal FrameworkThe RegulationsThe ACOP and Guidance –

Managing Health and Safety in Construction

Summary

Page 9: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 9

The RegulationsThe Regulations

Regulation 1 Citation and Commencement

Regulation 2 Interpretation Regulation 3 Application of Regulations Regulation 4 Clients and Agents of Clients Regulation 5 Requirements on Developer Regulation 6 Appointments of Planning

Supervisor and Principal Contractor

Page 10: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 10

The RegulationsThe Regulations

Regulation 7 Notification of Project Regulation 8 Competence of

Planning Supervisor, Designers, and Contractors

Regulation 9 Provision for Health and Safety

Regulation 10 Start of Construction Phase

Page 11: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 11

The RegulationsThe Regulations

Regulation 11 Client to ensure information is available

Regulation 12 Client to ensure health and Safety File is available for inspection

Regulation 13 Requirements on Designer

Regulation 14 Requirements on Planning Supervisor

Page 12: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 12

The RegulationsThe Regulations

Regulation 15 Requirements relating to the Health and Safety Plan

Regulation 16 Requirements on and powers of Principal Contractor

Regulation 17 Information and Training Regulation 18 Advice from, and views of,

persons at work

Page 13: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 13

The RegulationsThe Regulations

Regulation 19 Requirements and prohibitions on contractors

Regulation 20 Extension outside Great Britain

Regulation 21 Exclusion of Civil Liability

Page 14: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 14

The RegulationsThe Regulations

Regulation 22 EnforcementRegulation 23 Transitional

provisionsRegulation 24 Repeals,

revocations, and modifications

Page 15: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 15

Approved Code of PracticeApproved Code of Practice

Managing Health and Safety in Construction

Guidance upon the areas of practical concern

– Since the Regulations came into force

Page 16: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 16

Approved Code of PracticeApproved Code of Practice

IntroductionApplication, Interpretation, and

Notification The ClientThe DesignerThe Planning SupervisorThe Principal Contractor

Page 17: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 17

Approved Code of PracticeApproved Code of Practice

ContractorsCompetence and Resources Information and Training Involving the WorkforceThe Health and Safety PlanThe Health and Safety File

Page 18: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 18

Approved Code of PracticeApproved Code of Practice

Appendices

The CDM Regulations 1994 Extracts from the Management and

Health and Safety at Work Regulations 1999

The contents of the Health and Safety Plan

The contents of the Health and Safety File

Page 19: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 19

Approved Code of PracticeApproved Code of Practice

The standard Form of Notification - Form 10 (Rev)

GlossarySummary of CDM duties for duty

holders

Page 20: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 20

Application, Interpretation and Application, Interpretation and NotificationNotificationCDM applies to construction work

Carrying out buildingCivil or engineering construction

Page 21: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 21

Application, Interpretation and Application, Interpretation and NotificationNotificationCleaning and maintenanceDemolition and dismantling Installation of fixed plant - 2 metre

fallOffshore construction within

territorial watersExploratory work for construction

projectsConstruction of temporary

structures

Page 22: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 22

Application, Interpretation and Application, Interpretation and NotificationNotificationNot construction work

Dismantling and erection of tents and marquees

Maintenance of fixed plantTree plantingArchaeological investigations

Page 23: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 23

Application, Interpretation and Application, Interpretation and NotificationNotificationPositioning and removal of

lightweight partitionsSurveyingErecting scaffolds for non

construction workManufacture of items to be used

in construction

Page 24: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 24

NotificationNotification

Expected to last more than 30 days Involves more than 500 person daysForm F10 to local HSENot necessary to notify for a slight

changeNotify ASAP after PS appointmentForward missing information when

available

Page 25: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 25

The ClientThe Client

Must appoint

The Planning SupervisorThe Principal Contractor(s)PS and PC appointments can be

changedPS should be appointed at or

before the start of design

Page 26: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 26

The ClientThe Client

May become designers, if – Specify materials – Methods of working

Not required to monitor performance

Page 27: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 27

The ClientThe Client

Needs to make specific appointments

– Notification of the Project– The preparation of the pre-tender H & S

Plan– The Construction Phase H & Safety Plan – The preparation of the Health and

safety File– Request advice from the Planning

Supervisor

Page 28: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 28

The ClientThe Client

Give information on hazards to contractors

Do not have to approve the H & S Plan– Should arrange for the PS to do so

Upon commencement– No duty to check pre-tender H & S Plan– Principal Contractor's responsibility

Page 29: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 29

The DesignerThe Designer

ArchitectsConsulting engineersQuantity surveyorsChartered surveyorsSpecifiersPrincipal contractorsSpecialist contractors

Page 30: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 30

The DesignerThe Designer

Design includes

DrawingsDesign detailsSpecificationsBills of quantity

Page 31: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 31

The DesignerThe Designer

Key duties

Make Clients aware of their duties Should not prepare any designs until

done Give due regard to health and safety Provide adequate information on risks Co-operate with the PS and other

designers

Page 32: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 32

The DesignerThe Designer

If sub-contracting work, ensure that– Sub-contractors are sufficiently

competent and resourced Duties also apply to modifications

to designs

Page 33: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 33

The DesignerThe Designer

Key role

Can affect those involved in– Construction– Maintenance– Repair

Cradle to Grave

Page 34: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 34

The DesignerThe Designer

Not required to

Deal with unforeseeable hazards and risks

Specify construction methods Perform a H & S management function Review and report on contractor's

performance Keep records

– However

Page 35: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 35

The DesignerThe Designer

Not CDM designers

– The manufacturers of standardised components

Page 36: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 36

Health and Safety in DesignHealth and Safety in Design

Designers required to– Reduce foreseeable risks

By– Identifying hazards– Identifying who may be affected– Assessing Risks– Altering the design

Page 37: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 37

Health and Safety in DesignHealth and Safety in Design

Hierarchy of Control

EliminateCombat at SourcePPE

Page 38: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 38

Health and Safety in DesignHealth and Safety in Design

Elimination

– Specify less hazardous materials– Avoid processes that create dusts

and fumes– Avoid the need to work at height– Consider prefabrication - off site

Page 39: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 39

Health and Safety in DesignHealth and Safety in Design

Combat at Source

– Specify lighter materials– Build in lifting points– Ensure weights are known– Build in edge protection– Consider maintenance– Identify hazards at demolition

Page 40: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 40

Health and Safety in DesignHealth and Safety in Design

PPE

– A last resort

 Remaining risks to be notified to

affected parties

Page 41: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 41

Health and Safety in DesignHealth and Safety in Design

Records

Notes on drawingsDesign risk assessmentConstruction sequences

Page 42: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 42

Health and Safety in DesignHealth and Safety in Design

Design Risk Assessment Hansen have a pro forma,

consistent with the requirements of the regulations

Page 43: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 43

The Planning SupervisorThe Planning Supervisor

Duties– Ensure HSE is notified– Ensure co-operation between

Designers– Ensure Designers comply with duties– Ensure a pre-tender H & S Plan is

prepared – Advise the client when requested– Ensure a H & S File is prepared and

given to the Client

Page 44: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 44

The Planning SupervisorThe Planning Supervisor

Not Duties

Provide advice– Unless requested

Approve appointmentsApprove or check designs

– Be satisfied on risk

Page 45: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 45

The Planning SupervisorThe Planning Supervisor

Not Duties

Approve the Construction Phase Health and Safety Plan– Be able to advise on its adequacy

Supervise the implementation of the Plan or monitor Construction work

Page 46: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 46

The Planning SupervisorThe Planning Supervisor

To be effective – Should be appointed as soon as

possible– When the client is in a position to

judge– The competence and resources

needed

Page 47: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 47

The Principal ContractorThe Principal Contractor

Usually the main or managing contractor

Page 48: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 48

The Principal ContractorThe Principal Contractor

Duties

Satisfy themselves– Designers and Contractors they

appoint – Competent and adequately

resourced

Page 49: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 49

The Principal ContractorThe Principal Contractor

Ensure that a suitable Construction Phase Health and Safety Plan is

– Prepared before construction begins– Implemented– Current

Page 50: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 50

The Principal ContractorThe Principal Contractor

Promote co-operation between Contractors

Ensure site boundary integrity and security

Enforce site rulesDisplay the Project Notification on

siteProvide relevant information to

Contractors

Page 51: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 51

The Principal ContractorThe Principal Contractor

Promptly, provide relevant information to – Planning Supervisor – For inclusion in the Health and

Safety FileEncourage worker participationEnsure worker consultation

Page 52: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 52

ContractorsContractors

Duties

Satisfy themselves that

– Designers and Contractors they appoint

– Competent and adequately resourced

Page 53: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 53

ContractorsContractors

Co-operate with the Principal Contractor

Provide information on the risks to the Principal Contractor– Risk Assessments– Method Statements

Comply with the Construction Phase H & S Plan

Page 54: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 54

ContractorsContractors

Monitor and manage their activities Report RIDDOR incidents to the

Principal ContractorProvide information for the H&S FileProvide information and training

– to their employees– sub contract labour

Page 55: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 55

Competence and ResourcesCompetence and Resources

All duty holders must

– Satisfy themselves– All parties – Engage or appoint– Competent and have sufficient

resources

Page 56: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 56

Competence and ResourcesCompetence and Resources

Take reasonable steps – to assess the competence of

individuals or organisations– making a judgement

This includes making enquiries or seeking advice

Page 57: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 57

Competence and ResourcesCompetence and Resources

Principles

Requirements only relate to H & S issues

Checks should be appropriate

Page 58: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 58

Competence and ResourcesCompetence and Resources

There is no need to repeat checks – if the duty holder has conducted– recent, similar work

A demonstration of a successful recent track record – should be sufficient

Page 59: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 59

AssessmentAssessment

Performance evidence

– Personal experience– References– Evidence from previous project

reviews– Evidence from site visits

Page 60: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 60

AssessmentAssessment

Evidence of individual competence

– Practical experience and knowledge– Qualifications– Membership of trade or professional

bodies– Health and safety training

Page 61: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 61

AssessmentAssessment

Availability of resources

– Appropriate, sufficient competent people

– Equipment– Facilities– Management systems– Time available

Page 62: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 62

AssessmentAssessment

Past health and safety performance

– Enforcement action– Accident statistics

Page 63: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 63

Information And TrainingInformation And Training

Under CDMRequirement to provide

information and training

Page 64: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 64

Information And TrainingInformation And Training

Key Requirements

– Provide Induction training– Not general health and safety

information or training – To enable trades to work safely

Page 65: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 65

Information and TrainingInformation and Training

Induction should includeManagement’s commitment to

safetyOutline of projectName line management and key

personnelSite specific hazardsControl measures

Page 66: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 66

Information and TrainingInformation and Training

Arrangements for housekeeping and storage

Welfare facilitiesEmergency proceduresFirst aid arrangementsAccident reportingDetails of planned training

Page 67: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 67

Information and TrainingInformation and Training

Details for worker representation Information on individuals

responsibilities

Other legislation provides greater duties

Page 68: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 68

Involving the WorkforceInvolving the Workforce

Most at risk Should be fully informed of the

risksTheir consistent involvement is

essential – Aid good communication– The development of a safety culture

Page 69: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 69

Involving the WorkforceInvolving the Workforce

A combination recommended

– Informal discussions– Meetings– Toolbox talks– Involvement in managing hazards

Page 70: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 70

Involving the WorkforceInvolving the Workforce

Consultation arrangements

– Must be in Construction Phase H & S Plan

Page 71: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 71

Involving the WorkforceInvolving the Workforce

By being involved– Benefits

The CDM regulations do not impose specific obligations– Framework

Page 72: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 72

The Health and Safety PlanThe Health and Safety Plan

Regulation 15 requires a Plan is developed in two stages

– Pre-tender– Construction phase

Page 73: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 73

The Health and Safety PlanThe Health and Safety Plan

The pre-tender plan

– Addresses the key health and safety issues

– Inform prospective contractors of hazards

– Enabling them to manage and price accordingly

Page 74: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 74

The Health and Safety PlanThe Health and Safety Plan

Construction phase

– Builds on the pre tender plan– Prepared by Principal Contractor– Must be available to all parties– Developed as construction progresses– Should be project specific– A practical aid to the management of

health and safety

Page 75: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 75

The Health and Safety PlanThe Health and Safety Plan

Provides information for

– Future work– Maintenance– Demolition– Alterations– Cleaning

Page 76: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 76

The Health and Safety FileThe Health and Safety File

Provides information to

– Clients– Future Designers and Planning Supervisors– Those preparing future pre-tender H&S

Plans– Future Contractors

Not a maintenance manual

Page 77: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 77

The Health and Safety FileThe Health and Safety File

Duties

– PS must ensure preparation– All duty holders must supply

accurate information– Clients must ensure it is available for

future use– Can be prepared by anyone

Page 78: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 78

The Health and Safety FileThe Health and Safety File

Need not include

– The health and safety plans– Risk assessments– Method statements– Accident statistics– Contract documents

Page 79: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 79

The Health and Safety FileThe Health and Safety File

No format is specified To be prepared as the

construction progressesA file is required for each

structure

Page 80: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 80

The Health and Safety FileThe Health and Safety File

Designers– expected to provide information

progressively

The principal contractor and other contractors– must provide information as required

Page 81: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 81

The Health and Safety FileThe Health and Safety File

Must be completed in good time

Handed over when the client takes responsibility for the structure 

Page 82: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 82

Managing Health and Safety in Managing Health and Safety in Construction - ACOPConstruction - ACOPBased upon experience of the last

eight yearsContains practical adviceCannot answer every query

Page 83: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 83

Managing Health and Safety in Managing Health and Safety in Construction - ACOPConstruction - ACOPContact the Health and Safety

Executive– Advice should be sought in writing– If not possible, tell the HSE what you

intend to do to comply 

Page 84: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 84

Managing Health and Safety in Managing Health and Safety in Construction - ACOPConstruction - ACOPThe purpose is to encourage

– Dialogue– Thought – Participation– Give ownership

In order to improve performance 

Page 85: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 85

Objectives Objectives

Be able to name duty holdersName the ACOPName key documentsDescribe key designer dutiesDescribe the hierarchy of controlDescribe the purpose of the

regulations

Page 86: Hansen – Managing Safely 1 CDM – An Appreciation Mark Mallen Health and Safety Manager Fenlock Hansen Ltd.

Hansen – Managing Safely 86

Managing Health and Safety in Managing Health and Safety in Construction - ACOPConstruction - ACOP

Thanks for listening– Any questions?

Don’t forget– Be safe!