Client : Contractor : Contractor Consultant : Doc. No.: 048/2013/HFT/E/1000/01/A4
Rev O
Job Ref.
J 5259
Project Title:
RAECO TENDER No.048/2013
2X10MVA HANFEET PRIMARY SUBSTATION
Document Title:
DOCUMENT CONTROL REGISTER
Detail Engineering Progress summary
As per project schedule,
Total scheduled weightage for electrical Engg= 60%
Total scheduled weightage for Civil Engg= 40%
SL.No.
ELECTRICALELE_HFT 50.00% 100.00% #N/A #N/A
ELE_VENDOR_HFT 10.00% 100.00% #REF! #REF!
SUB TOTAL 60.00% SUB TOTAL #N/ACIVIL
1 35.00% 100.00% 0.00% 0.00%
SUB TOTAL 35.00% SUB TOTAL 0.00%
MECHANICAL & PLUMBING
5.00%SUB TOTAL 5.00% SUB TOTAL 0.00%
OVERALL 100.00%OVERALL (Electrical+Civil+ Mechanical & Plumbing)#N/A
0 May-14 NK MSR MSR
REV. DATE Prepared By Approved By
Rural Area Electricity Company S.A.O.C.
RITAJ Engineers & Consultants
Scheduled Weightage
Scheduled Progress
Actual Progress
Achieved Weightage
MECHANICAL & PLUMBING
Checked By
Page 2 of 11
DOCUMENT CONTROL SCHEDULEIssue Date : 01,MAY,2014 2X10MVA HANFEET PRIMARY SUBSTATION P = PLANNED
Revision No. : Rev-O Job No. CO-379 A = ACTUAL
F = FORECAST
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing/Document No.
Nu
mbe
r of
sh
eets
Drg
siz
e
Rev Drawing/Document Title Remarks
ELECTRICAL A) DRAWINGS 50% 75% 95% 100%
048/2013/HFT/E/1001/01/A1 1 A1 B Symbols, Abbreviations & Legends 1.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 06/May/2014 26/May/2014 04/Jun/2014 22/Jun/2014 09/Jul/2014 10/Jul/2014
F
048/2013/HFT/E/1002/01/A1 1 A1 B 33/11kV Main Single Line Diagram 3.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 06/May/2014 26/May/2014 04/Jun/2014 22/Jun/2014 09/Jul/2014 13/Jul/2014 10/Aug/2014
F
048/2013/HFT/E/1003/01/A1 1 A1 B 33kV Protection & Metering Single line Diagram 4.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 09/Jun/2014 29/Jun/2014 11/Aug/2014 17/Aug/2014 25/Aug/2014 31/Aug/2014
F
048/2013/HFT/E/1004/01/A1 1 A1 B 11kV Protection & Metering Single line Diagram 4.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 09/Jun/2014 29/Jun/2014 11/Aug/2014 17/Aug/2014 25/Aug/2014 31/Aug/2014
F
048/2013/HFT/E/1005/01/A3 4 A3 B 33kV Control & interlocking block logic diagram 4.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 09/Jun/2014 29/Jun/2014 11/Aug/2014 17/Aug/2014 25/Aug/2014 31/Aug/2014
F
048/2013/HFT/E/1006/01/A3 7 A3 B 11kV Control & interlocking block logic diagram 4.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 09/Jun/2014 29/Jun/2014 11/Aug/2014 17/Aug/2014 25/Aug/2014 31/Aug/2014
F
048/2013/HFT/E/1007/01/A1 1 A1 A 4.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 17/Jun/2014 23/Jun/2014 19/Aug/2014 26/Aug/2014
F
048/2013/HFT/E/1008/01/A1 1 A1 A 110V DC Distribution Single Line Diagram 4.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 17/Jun/2014 23/Jun/2014 19/Aug/2014 26/Aug/2014 29/Sep/2014 24/Nov/2014
F
048/2013/HFT/E/1009/01/A1 1 A1 0 SPARE
P
A
F
048/2013/HFT/E/1010/01/A1 1 A1 D Overall Equipment Layout 4.00% #N/A #N/A
P
IFCA 02/Jun/2014 24/Jun/2014 29/Jun/2014 08/Jul/2014 21/Jul/2014 23/Jul/2014 25/Dec/2014
F
048/2013/HFT/E/1011/01/A1 2 A1 0 Overall Cable Trench Layout & Sectional Details 3.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 12/Aug/2014 24/Aug/2014 23/Sep/2014 29/Sep/2014
F
048/2013/HFT/E/1012/01/A1 1 A1 0 Overall Grounding Layout 3.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 21/Aug/2014 10/Sep/2014 20/Oct/2014
F
048/2013/HFT/E/1013/01/A1 1 A1 A Standard Earthing Installation Details 2.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 13/Aug/2014 17/Aug/2014 15/Sep/2014 29/Sep/2014
F
048/2013/HFT/E/1014/01/A1 1 A1 B 4.00% #N/A #N/A
PIFC submit for approval 25.05.15A 13/Aug/2014 17/Aug/2014 23/Sep/2014 29/Sep/2014 27/Oct/2014 02/Nov/2014
F
048/2013/HFT/E/1015/01/A1 3 A1 A 2.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 12/Aug/2014 24/Aug/2014 27/Oct/2014 02/Nov/2014
F
048/2013/HFT/E/1016/01/A1 1 A1 A 2.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 13/Aug/2014 17/Aug/2014 15/Sep/2014 29/Sep/2014
F
Achieved Target Level(0= not submitted;1= Rev-0
issued comments;2=Rev-A issued approval;3= Re
issued for Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments/ Approval
received from Client
Issued for Approval
Approval/ comments
received from Client
Re-Issued for Approval
Approval received from
Client
Approved for Construction
415V AC Auxiliary Distribution - Single Line Diagram
11kV SWGR & Control Building Equipment Layout Plan & Sections
11kV SWGR & Control Building Cable Tray/Trench layout Plan & Section
11kV SWGR & Control Building Equipment Earthing Layout Plan
Page 3 of 11
DOCUMENT CONTROL SCHEDULEIssue Date : 01,MAY,2014 2X10MVA HANFEET PRIMARY SUBSTATION P = PLANNED
Revision No. : Rev-O Job No. CO-379 A = ACTUAL
F = FORECAST
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing/Document No.
Nu
mbe
r of
sh
eets
Drg
siz
e
Rev Drawing/Document Title Remarks
Achieved Target Level(0= not submitted;1= Rev-0
issued comments;2=Rev-A issued approval;3= Re
issued for Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments/ Approval
received from Client
Issued for Approval
Approval/ comments
received from Client
Re-Issued for Approval
Approval received from
Client
Approved for Construction
048/2013/HFT/E/1017/01/A1 3 A1 0 Substation Lightning Protection Layout Plan& Sections 2.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 24/Sep/2014 29/Aug/2014
F
048/2013/HFT/E/1018/01/A1 10 A1 0 Sectional Details Layout 2.00% #N/A #N/A
P
IFC submit for approval 25.05.15A 17/Nov/2014 02/Dec/2014
F
B) CALCULATIONS & DOCUMENTS
048/2013/HFT/E/1021/01/A4 A4 A 33KV CT & VT Sizing Calculation 5.00% #N/A #N/A
P
ApprovedA 13/Aug/2014 17/Aug/2014 22/Sep/2014 29/Sep/2014
F
048/2013/HFT/E/1022/01/A4 A4 A 11kV CT & VT Sizing calculation 5.00% #N/A #N/A
P
AWCA 30/Jun/2014 01/Jul/2014 08/Sep/2014 15/Sep/2014 15/Oct/2014
F
048/2013/HFT/E/1023/01/A4 A4 0 Grounding Conductor sizing 2.00% #N/A #N/A
P
ApprovedA 23/Aug/2014 10/Sep/2014 23/Sep/2014 29/Sep/2014
F
048/2013/HFT/E/1024/01/A4 A4 0 Grounding Step & Touch Potential calculations 4.00% #N/A #N/A
P
ApprovedA 26/Aug/2014 31/Aug/2014
F
048/2013/HFT/E/1025/01/A4 A4 A Sizing of MV Power Cables 3.00% #N/A #N/A
P
ApprovedA 10/Jun/2014 08/Jul/2014 03/Aug/2014 11/Aug/2014
F
048/2013/HFT/E/1026/01/A4 A4 A Sizing of LV Cables Sizing 3.00% #N/A #N/A
P
ApprovedA 01/Sep/2014 07/Sep/2014 18/Sep/2014 29/Aug/2014
F
048/2013/HFT/E/1027/01/A4 A4 0 4.00% #N/A #N/A
P
A 11/Aug/2014 17/Aug/2014 01/Sep/2014 07/Sep/2014 30/Sep/2014 21/Oct/2014
F
048/2013/HFT/E/1029/01/A4 A4 A Power Cable Schedule 2.00% #N/A #N/A
P
ApprovedA 24/Sep/2014 29/Sep/2014 27/Oct/2014 02/Nov/2014
F
048/2013/HFT/E/1030/01/A4 A4 0 Control Cable Schedule 4.00% #N/A #N/A
P
Information is noted (4)A 04/Dec/2014 25/Dec/2014
F
048/2013/HFT/E/1031/01/A4 A4 0 Control cable Interconnection chart 6.00% #N/A #N/A
P
A
F
048/2013/HFT/E/1032/01/A4 A4 0 Lightning Protection Calculation 4.00% #N/A #N/A
P
A 31/Aug/2014 04/Sep/2014
F
048/2013/HFT/E/1033/01/A4 A4 0 Relay Setting Calculations 6.00% #N/A #N/A
P
A
F
100.00% #N/A
110V Battery & 110V Battery Charger sizing calculation
Page 4 of 11
DOCUMENT CONTROL SCHEDULEIssue Date : 01,MAY,2014 2X10MVA HANFEET PRIMARY SUBSTATION P = PLANNED
Revision No. : Rev-0 Job No. CO379 A = ACTUAL
F = FORECAST
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing/Document No.
Nu
mb
er o
f sh
eets
Drg
siz
e
Rev Drawing/Document Title Remarks
VENDOR DOCUMENTSA) DRAWINGS
048/2013/HFT/E/1041/01/XX 2 10MVA TRANSFORMER
P
AWCA 01/Jul/2014 08/Jul/2014 31/Aug/2014 02/Sep/2014 23/Oct/2014 29/Oct/2014F
048/2013/HFT/E/1042/01/XX 0 33KV OUTDOOR BREAKER WITH CTS
P
AWCA 13/Oct/2014 28/Oct/2014 25/Nov/2014 16/Dec/2014F
048/2013/HFT/E/1043/01/XX 0 SPARE
P
Subject to vendor document submissionA
F
048/2013/HFT/E/1044/01/XX 0 STATION AUXILIARY TRANSFORMER
P
A 17/Jun/2014 23/Jun/2014
F
048/2013/HFT/E/1045/01/XX 0 33KV CONTROL & RELAY PANEL
P
A 28/Sep/2014 19/Oct/2014F
048/2013/HFT/E/1046/01/XX 0 11KV SWITCHGEAR
P
A 23/Sep/2014 12/Oct/2014F
048/2013/HFT/E/1047/01/XX 0 110V DC SYSTEM
P
A 13/Aug/2014 17/Aug/2015 03/Dec/2014 17/Dec/2014F
048/2013/HFT/E/1048/01/XX 0 415V AC LV SWITCHGEAR
P
A 01/Jul/2014 08/Jul/2014 04/Dec/2014 25/Dec/2014F
048/2013/HFT/E/1049/01/XX 3 1 CAPACITOR BANK
P
A 30/Jun/2014 02/Jul/2014 14/Aug/2014 24/Aug/2014 19/Oct/2014 21/Oct/2014F
048/2013/HFT/E/1049/01/XX 0 DISTRIBUTION BOARD
P
A 18/Nov/2014F
Achieved Target Level(0= not submitted;1= Rev-0
issued comments;2=Rev-A issued approval;3= Re
issued for Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments/ Approval
received from Client
Issued for Approval
Approval/ comments
received from Client
Re-Issued for Approval
Approval received from
Client
Approved for Construction
Page 5 of 11
DOCUMENT CONTROL SCHEDULE2X10MVA HANFEET PRIMARY SUBSTATION
Issue Date : 01,MAY,2014 Job No. CO379 P = PLANNED
Revision No. : Rev-0 A = ACTUAL
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing No. Dwg Size Rev Drawing Title Remarks
CIVILA) DRAWINGS
048/2013/HFT/C/1001/01/A1 01 A1 A 0 2.00% 0.00% 0%P 25-May-2014 1-Jun-2014 8-Jun-2014 15-Jun-2014 22-Jun-2014 29-Jun-2014 2-Jul-2014
ApprovedA 24-Jun-2014 1-Jul-2014 9-Jul-2014 17-Jul-2014
048/2013/HFT/C/1002/01/A1 01 A3 A 0 2.00% 0.00% 0%P 25-May-2014 1-Jun-2014 8-Jun-2014 15-Jun-2014 22-Jun-2014 29-Jun-2014 2-Jul-2014
ApprovedA 24-Jun-2014 1-Jul-2014 9-Jul-2014 17-Jul-2014
048/2013/HFT/C/1003/01/A1 01 A3 A STANDARD DWGS - CAGE LADDER 0 2.00% 0.00% 0%P 25-May-2014 1-Jun-2014 8-Jun-2014 15-Jun-2014 22-Jun-2014 29-Jun-2014 2-Jul-2014
ApprovedA 24-Jun-2014 1-Jul-2014 9-Jul-2014 17-Jul-2014
048/2013/HFT/C/1004/01/A1 01 A3 A 0 2.00% 0.00% 0%P 25-May-2014 1-Jun-2014 8-Jun-2014 15-Jun-2014 22-Jun-2014 29-Jun-2014 2-Jul-2014
ApprovedA 24-Jun-2014 1-Jul-2014 9-Jul-2014 17-Jul-2014
048/2013/HFT/C/1005/01/A1 02 A1 A 0 2.00% 0.00% 0%P 1-Jun-2014 8-Jun-2014 15-Jun-2014 22-Jun-2014 29-Jun-2014 6-Jul-2014 9-Jul-2014
ApprovedA 24-Jun-2014 1-Jul-2014 9-Jul-2014 17-Jul-2014
048/2013/HFT/C/1006/01/A1 04 A1 B 0 2.00% 0.00% 0%P 7-Sep-2014 14-Sep-2014 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 15-Oct-2014
IFCA 7-Sep-2014 17-Sep-2014 11-Oct-2014 19-Oct-2014 23-Oct-2014 2-11-204
048/2013/HFT/C/1007/01/A1 01 A1 A 0 2.00% 0.00% 0%P 10-Sep-2014 17-Sep-2014 24-Sep-2014 1-Oct-2014 8-Oct-2014 15-Oct-2014 18-Oct-2014
ApprovedA 14-Dec-2014 23-Dec-2014 29-Dec-2014
048/2013/HFT/C/1008/01/A1 02 A1 B 0 2.00% 0.00% 0%
P 20-Jun-2014 27-Jun-2014 4-Jul-2014 11-Jul-2014 18-Jul-2014 25-Jul-2014 28-Jul-2014
IFC approved not receviedA 2-Sep-2014 8-Sep-2014 24-Sep-2014 21-Oct-2014 3-Dec-2014
048/2013/HFT/C/1009/01/A1 01 A1 C SITE GRADING PLAN AND SECTIONS 0 2.00% 0.00% 0%P 25-Aug-2014 1-Sep-2014 8-Sep-2014 15-Sep-2014 22-Sep-2014 29-Sep-2014 2-Oct-2014
A 28-Aug-2014 8-Sep-2014 23-Sep-2014 30-Sep-2014 21-Oct-2014 29-Oct-2014 25-Nov-2014
048/2013/HFT/C/1010/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1011/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1012/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
No of Sheets
Achieved Target Level(0= not
submitted;1= Rev-0 issued
comments;2=Rev-A issued
approval;3= Re issued for
Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments received from
Client
Issued for Approval
Comment/approval received from Client
Re-Issued for approval
Approval received from
Client
Approved for Contruction
GENERAL NOTES AND LEGEND FOR CIVIL WORKS
STANDARD DWGS - MISCELLANEOUS FINISHES
STANDARD DWGS - BLOCKWORK MASONRY UNITS
STANDARD DRAWINGS FOR ROOF FINISHERS
COMPOUND WALL LAYOUT AND DETAILS
ROAD AND DRAINAGE LAYOUT DETAILS
SEPTIC TANK & SOAK AWAY PIT PLAN & RC DETAIL
IFC25-11-2014 ( Approved with
comment)
Page 6 of 11
DOCUMENT CONTROL SCHEDULE2X10MVA HANFEET PRIMARY SUBSTATION
Issue Date : 01,MAY,2014 Job No. CO379 P = PLANNED
Revision No. : Rev-0 A = ACTUAL
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing No. Dwg Size Rev Drawing Title RemarksNo of Sheets
Achieved Target Level(0= not
submitted;1= Rev-0 issued
comments;2=Rev-A issued
approval;3= Re issued for
Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments received from
Client
Issued for Approval
Comment/approval received from Client
Re-Issued for approval
Approval received from
Client
Approved for Contruction
33/11kV SWGR &CONTROL BUILDING (ARCHITECTURAL DRGS)
048/2013/HFT/C/1013/01/A1 06 A1 C 0 8.00% 0.00% 0%
P 21-Aug-2014 28-Aug-2014 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 28-Sep-2014
A /06-11-14 issued IFCA 19-Aug-2014 26-Aug-2014 8-Sep-2014 17-Sep-2014 21-Oct-2014 29-Oct-2014
048/2013/HFT/C/1014/01/A1 01 A1 C 0 1.00% 0.00% 0%
P 21-Aug-2014 28-Aug-2014 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 28-Sep-2014
A /06-11-14 issued IFCA 19-Aug-2014 26-Aug-2014 8-Sep-2014 17-Sep-2014 21-Oct-2014 29-Oct-2014
048/2013/HFT/C/1015/01/A1 01 A1 0 0 1.00% 0.00% 0%P 21-Aug-2014 28-Aug-2014 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 28-Sep-2014
A
048/2013/HFT/C/1016/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1017/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1018/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1019/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
33/11KV SWGR &CONTROL BUILDING (RCC DRAWINGS)
048/2013/HFT/C/1020/01/A1 01 A1 A 0 2.00% 0.00% 0%P 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 2-Oct-2014 9-Oct-2014 12-Oct-2014
IFCA 21-Oct-2014 29-Oct-2014 5-Nov-2014 16-Nov-2014
048/2013/HFT/C/1021/01/A1 01 A1 A 0 2.00% 0.00% 0%P 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 2-Oct-2014 9-Oct-2014 12-Oct-2014
AWCA 21-Oct-2014 29-Oct-2014 5-Nov-2014 16-Nov-2014
048/2013/HFT/C/1022/01/A1 01 A1 A 0 2.00% 0.00% 0%P 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 2-Oct-2014 9-Oct-2014 12-Oct-2014
IFCA 21-Oct-2014 29-Oct-2014 5-Nov-2014 16-Nov-2014
048/2013/HFT/C/1023/01/A1 01 A1 A 0 2.00% 0.00% 0%P 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 2-Oct-2014 9-Oct-2014 12-Oct-2014
IFC approved copy not recevoedA 30-Oct-2014 6-Nov-2014 18-Nov-2014
048/2013/HFT/C/1024/01/A1 01 A1 A 0 2.00% 0.00% 0%
P 11-Sep-2014 18-Sep-2014 25-Sep-2014 2-Oct-2014 9-Oct-2014 16-Oct-2014 19-Oct-2014
IFC
A 30-Oct-2014 6-Nov-2014 18-Nov-2014
33/11KV SWGR & CONTROL BUILDING : ARCHITECTURAL,SECTION & ELEVATION DRAWINGS
33/11KV SWGR & CONTROL BUILDING :DOOR AND WINDOWS IRONMONGERY DETAILS.
33/11KV SWGR & CONTROL BUILDING : STAIRCASE GA AND DETAILS
33/11kV SWGR & CONTROL BUILDING : FOUNDATION LAYOUT
33/11kV SWGR & CONTROL BUILDING : GRADE BEAM LAYOUT
33/11KV SWITCHGEAR AND CONTROL BUIILDING GRADE SLAB LAYOUT & RC DETAILS
33/11kV SWGR & CONTROL BUILDING : ROOF BEAM - LAYOUT & RC DETAILS
33/11kV SWGR & CONTROL BUILDING: ROOF SLAB LAYOUT & RC DETAILS
Page 7 of 11
DOCUMENT CONTROL SCHEDULE2X10MVA HANFEET PRIMARY SUBSTATION
Issue Date : 01,MAY,2014 Job No. CO379 P = PLANNED
Revision No. : Rev-0 A = ACTUAL
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing No. Dwg Size Rev Drawing Title RemarksNo of Sheets
Achieved Target Level(0= not
submitted;1= Rev-0 issued
comments;2=Rev-A issued
approval;3= Re issued for
Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments received from
Client
Issued for Approval
Comment/approval received from Client
Re-Issued for approval
Approval received from
Client
Approved for Contruction
048/2013/HFT/C/1025/01/A1 02 A1 0 1.00% 0.00% 0%P 11-Sep-2014 18-Sep-2014 25-Sep-2014 2-Oct-2014 9-Oct-2014 16-Oct-2014 19-Oct-2014
IFC approved copy not recevoedA 30-Oct-2014 6-Nov-2014
048/2013/HFT/C/1026/01/A1 03 A1 0 SPARE 0 1.00% 0.00% 0%
P
A
048/2013/HFT/C/1027/01/A1 01 A1 0 SPARE 0 1.00% 0.00% 0%P
A
048/2013/HFT/C/1028/01/A1 01 A1 0 SPARE 0 1.00% 0.00% 0%P
A
048/2013/HFT/C/1029/01/A1 04 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1030/01/A1 04 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1031/01/A1 04 A1 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1032/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
20MVA TRANSFORMER FOUNDATION & WORKS
048/2013/HFT/C/1033/01/A1 01 A1 B 0 2.00% 0.00% 0%P 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 19-Oct-2014 26-Oct-2014 29-Oct-2014
IFCA 15-Sep-2014 24-Sep-2014 11-Oct-2014 19-Oct-2014 23-Oct-2014 2-Nov-2014
048/2013/HFT/C/1034/01/A1 02 A1 0 0 1.00% 0.00% 0%P 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 19-Oct-2014 26-Oct-2014 29-Oct-2014
IFCA 15-Sep-2014 24-Sep-2014 11-Oct-2014 19-Oct-2014 23-Oct-2014 2-Nov-2014
048/2013/HFT/C/1035/01/A1 01 A1 A 0 1.00% 0.00% 0%P 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 19-Oct-2014 26-Oct-2014 29-Oct-2014
IFCA 4-Nov-2014 16-Nov-2014 3-Dec-2014
048/2013/HFT/C/1036/01/A1 01 A1 0 0 1.00% 0.00% 0%P 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 19-Oct-2014 26-Oct-2014 29-Oct-2014
ApprovedA 9-Nov-2014 2-Dec-2014
048/2013/HFT/C/1037/01/A1 02 A1 B 0 1.00% 0.00% 0%P 25-Sep-2014 2-Oct-2014 9-Oct-2014 16-Oct-2014 23-Oct-2014 30-Oct-2014 2-Nov-2014
IFCA 5-Nov-2014 16-Nov-2014 23-Nov-2014 24-Nov-2014 25-Dec-2014
HVAC FOUNDATION LAYOUT AND RC DETAILS
10MVA TRANSFORMER FOUNDATION - MASONRY DETAILS
10MVA TRANSFORMER FOUNDATION - RC DETAILS
10MVA TRANSFORMER FOUNDATION GRATING PLATFORM DETAILS
10MVA TRANSFORMER FIRE BARRIER WALL RC DETAILS
REMOVABLE FENCING LAYOUT &DETAILS
Page 8 of 11
DOCUMENT CONTROL SCHEDULE2X10MVA HANFEET PRIMARY SUBSTATION
Issue Date : 01,MAY,2014 Job No. CO379 P = PLANNED
Revision No. : Rev-0 A = ACTUAL
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing No. Dwg Size Rev Drawing Title RemarksNo of Sheets
Achieved Target Level(0= not
submitted;1= Rev-0 issued
comments;2=Rev-A issued
approval;3= Re issued for
Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments received from
Client
Issued for Approval
Comment/approval received from Client
Re-Issued for approval
Approval received from
Client
Approved for Contruction
048/2013/HFT/C/1038/01/A1 01 A1 0 SPARE 0 0.00% 0.00% 0%P
A
MISCELLANEOUS FOUNDATIONS & WORKS
048/2013/HFT/C/1039/01/A1 01 A1 B 0 1.00% 0.00% 0%P 27-Sep-2014 4-Oct-2014 11-Oct-2014 18-Oct-2014 25-Oct-2014 1-Nov-2014 4-Nov-2014
ApprovedA 24-Sep-2014 21-Oct-2014 2-Dec-2014 14-Dec-2014 29-Dec-2014
048/2013/HFT/C/1040/01/A1 01 A1 0 0 1.00% 0.00% 0%P 29-Sep-2014 6-Oct-2014 13-Oct-2014 20-Oct-2014 27-Oct-2014 3-Nov-2014 6-Nov-2014
ApprovedA 15-Sep-2014 24-Sep-2014 11-Oct-2014 19-Oct-2014 23-Oct-2014 2-Nov-2014
048/2013/HFT/C/1041/01/A1 02 A1 0 SPARE 0 1.00% 0.00% 0%P
A
048/2013/HFT/C/1042/01/A1 02 A1 B 0 1.00% 0.00% 0%P 10-Oct-2014 17-Oct-2014 24-Oct-2014 31-Oct-2014 7-Nov-2014 14-Nov-2014 17-Nov-2014
IFCA 11-Nov-2014 2-Dec-2014 23-Dec-2014 28-Dec-2014 8-Jan-2015 13-Jan-2015
048/2013/HFT/C/1043/01/A1 03 A1 0 0 0.00% 0.00% 0%
P
AWC
A 27-Dec-2014 29-Dec-2014
33 KV SWITCHYARD STRUCTURE
048/2013/HFT/C/1044/01/A1 01 A1 A 0 2.00% 0.00% 0%P 13-Oct-2014 20-Oct-2014 27-Oct-2014 3-Nov-2014 10-Nov-2014 17-Nov-2014 20-Nov-2014
A 18-Dec-2014 23-Dec-2014 29-Dec-2014 29-Dec-2014 11-Jan-2015 Approved
048/2013/HFT/C/1045/01/A1 01 A1 A 0 1.00% 0.00% 0%P 13-Oct-2014 20-Oct-2014 27-Oct-2014 3-Nov-2014 10-Nov-2014 17-Nov-2014 20-Nov-2014
A 18-Dec-2014 23-Dec-2014 29-Dec-2014 29-Dec-2014 11-Jan-2015 Approved
048/2013/HFT/C/1046/01/A1 05 A1 A 0 1.00% 0.00% 0%P 13-Oct-2014 20-Oct-2014 27-Oct-2014 3-Nov-2014 10-Nov-2014 17-Nov-2014 20-Nov-2014
A 18-Dec-2014 23-Dec-2014 29-Dec-2014 29-Dec-2014 11-Jan-2015 Approved
048/2013/HFT/C/1047/01/A1 06 A1 0 0 2.00% 0.00% 0%P 16-Oct-2014 23-Oct-2014 30-Oct-2014 6-Nov-2014 13-Nov-2014 20-Nov-2014 23-Nov-2014
A
AUXILARY TRANSFORMER GA & RC DETAILS
CAPACITOR BANK FOUNDATION LAYOUT AND DETAILS
OUTDOOR CABLE TRENCH - LAYOUT AND DETAILS
11KV SWGR & CONTROL BUILDING INDOOR CABLE TRENCH LAYOUT AND DETAILS
SWITCHYARD FOUNDATION LAYOUT
SWITCHYARD FOUNDATION GA AND RCC DETAILS
SWITCHYARD PEDESTAL LAYOUT AND RC DETAILS
SWITCHYARD STEEL SUPPORTING STRUCTURE
Page 9 of 11
DOCUMENT CONTROL SCHEDULE2X10MVA HANFEET PRIMARY SUBSTATION
Issue Date : 01,MAY,2014 Job No. CO379 P = PLANNED
Revision No. : Rev-0 A = ACTUAL
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing No. Dwg Size Rev Drawing Title RemarksNo of Sheets
Achieved Target Level(0= not
submitted;1= Rev-0 issued
comments;2=Rev-A issued
approval;3= Re issued for
Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments received from
Client
Issued for Approval
Comment/approval received from Client
Re-Issued for approval
Approval received from
Client
Approved for Contruction
048/2013/HFT/C/1048/01/A1 01 A4 0 SPARE 0 2.00% 0.00% 0%P
A
048/2013/HFT/C/1049/01/A1 01 A4 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1050/01/A1 01 A4 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1051/01/A1 01 A4 0 SPARE 0 0.00% 0.00% 0%P
A
B) CALCULATIONS & DOCUMENTS
048/2013/HFT/C/1051/01/A4 01 A4 0 0 3.00% 0.00% 0%
P 25-May-2014 1-Jun-2014 8-Jun-2014 15-Jun-2014 22-Jun-2014 29-Jun-2014 2-Jul-2014
ApprovedA 24-Jun-2014 1-Jul-2014
048/2013/HFT/C/1052/01/A4 01 A4 0 0 7.00% 0.00% 0%P 4-Sep-2014 11-Sep-2014 18-Sep-2014 25-Sep-2014 2-Oct-2014 9-Oct-2014 12-Oct-2014
ApprovedA 21-Oct-2014 29-Oct-2014
048/2013/HFT/C/1053/01/A4 01 A4 0 0 3.00% 0.00% 0%P 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 19-Oct-2014 26-Oct-2014 29-Oct-2014
ApprovedA 15-Sep-2014 24-Sep-2014 11-Oct-2014
048/2013/HFT/C/1054/01/A4 01 A4 0 0 2.00% 0.00% 0%P 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 19-Oct-2014 26-Oct-2014 29-Oct-2014
ApprovedA 11-Nov-2014 2-Dec-2014
048/2013/HFT/C/1055/01/A4 01 A4 0 0 3.00% 0.00% 0%P 29-Sep-2014 6-Oct-2014 13-Oct-2014 20-Oct-2014 27-Oct-2014 3-Nov-2014 6-Nov-2014
ApprovedA 15-Sep-2014 21-Oct-2014
048/2013/HFT/C/1056/01/A4 01 A4 0 SPARE 0 3.00% 0.00% 0%P
A
048/2013/HFT/C/1057/01/A4 01 A4 0 0 3.00% 0.00% 0%P 27-Sep-2014 4-Oct-2014 11-Oct-2014 18-Oct-2014 25-Oct-2014 1-Nov-2014 4-Nov-2014
A 24-Sep-2014 21-Oct-2014
048/2013/HFT/C/1058/01/A4 01 A4 0 SPARE 0 3.00% 0.00% 0%P
A
048/2013/HFT/C/1059/01/A4 01 A4 0 0 3.00% 0.00% 0%P 7-Sep-2014 14-Sep-2014 21-Sep-2014 28-Sep-2014 5-Oct-2014 12-Oct-2014 15-Oct-2014
A 7-Sep-2014 17-Sep-2014 11-Oct-2014
048/2013/HFT/C/1060/01/A4 01 A4 0 0 5.00% 0.00% 0%P 13-Oct-2014 20-Oct-2014 27-Oct-2014 3-Nov-2014 10-Nov-2014 17-Nov-2014 20-Nov-2014
A 18-Dec-2014 23-Dec-2014
DESIGN BASIS REPORT FOR CIVIL WORKS
33/11kV SWGR & CONTROL BUILDING: DESIGN CALCULATION
20MVA TX. FOUNDATION & GRATING - DESIGN CALCULATION
20MVA TRANSFORMER FIRE BARRIER WALL - DESIGN CALCULATIONS
CAPACITOR BANK DESIGN CALCULATION
AUX.TRANSFORMER FOUNDATION DESIGN CALCULATION
COMPOUND WALL: DESIGN CALCULATION
DESIGN CALCULATION OF SWITCHYRAD STRUCTURE
Page 10 of 11
DOCUMENT CONTROL SCHEDULE2X10MVA HANFEET PRIMARY SUBSTATION
Issue Date : 01,MAY,2014 Job No. CO379 P = PLANNED
Revision No. : Rev-0 A = ACTUAL
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing No. Dwg Size Rev Drawing Title RemarksNo of Sheets
Achieved Target Level(0= not
submitted;1= Rev-0 issued
comments;2=Rev-A issued
approval;3= Re issued for
Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments received from
Client
Issued for Approval
Comment/approval received from Client
Re-Issued for approval
Approval received from
Client
Approved for Contruction
048/2013/HFT/C/1061/01/A4 01 A4 0 SPARE 0 5.00% 0.00% 0%P
A
048/2013/HFT/C/1062/01/A4 01 A4 0 SPARE 0 0.00% 0.00% 0%P
A
048/2013/HFT/C/1063/01/A4 01 A4 0 SPARE 0 0.00% 0.00% 0%P
A
DOCUMENT CONTROL SCHEDULEIssue Date : 01,MAY,2014 2X10MVA HANFEET PRIMARY SUBSTATION P = PLANNED
Revision No. : Rev-O Job No. CO-379 A = ACTUAL
F = FORECAST
Numbering system Drawing /Document description Progress Measurement Rev 0 Rev A Rev B AFC
Drawing/Document No.
Num
ber
of s
heet
s
Drg
siz
e
Rev Drawing/Document Title Remarks
MEP DRAWINGSA) DRAWINGS 50% 75% 95% 100%
048/2013/HFT/SFO/CO379/MEP/01/A1 1 A1 2
P
ApprovedA 04/Nov/2014 10/Nov/14 23/Nov/2014 11/Dec/2014 08/Jan/2015 12/Jan/2015
F
048/2013/HFT/SFO/CO379/MEP/02/A1 1 A1 2
P
ApprovedA 04/Nov/2014 10/Nov/14 23/Nov/2014 11/Dec/2014 08/Jan/2015 12/Jan/2015
F
048/2013/HFT/SFO/CO379/MEP/03/A1 1 A1 2
P
ApprovedA 04/Nov/2014 10/Nov/14 23/Nov/2014 11/Dec/2014 08/Jan/2015 12/Jan/2015
F
048/2013/HFT/SFO/CO379/MEP/04/A1 1 A1 2
P
ApprovedA 04/Nov/2014 10/Nov/14 23/Nov/2014 11/Dec/2014 08/Jan/2015 12/Jan/2015
F
048/2013/HFT/SFO/CO379/MEP/05/A1 1 A1 2
P
ApprovedA 04/Nov/2014 10/Nov/14 23/Nov/2014 11/Dec/2014 08/Jan/2015 12/Jan/2015
F
048/2013/HFT/SFO/CO379/MEP/06/A1 1 A1 2
P
ApprovedA 04/Nov/2014 10/Nov/14 23/Nov/2014 11/Dec/2014 08/Jan/2015 12/Jan/2015
F
048/2013/HFT/SFO/CO379/MEP/07/A1 1 A1 2
P
ApprovedA 04/Nov/2014 10/Nov/14 23/Nov/2014 11/Dec/2014 08/Jan/2015 12/Jan/2015
F
048/2013/HFT/SFO/CO379/MEP/08/A1 1 A3 A
P
ApprovedA 10.12.2014 17.12.2014
F
048/2013/HFT/SFO/CO379/MEP/09/A1 1 A3 A
P
ApprovedA 10.12.2014 17.12.2014
F
048/2013/HFT/SFO/ACDB/1 1 A3 AIR CONDITIONING DB
P
ApprovedA 19/Nov/2014 24/Nov/14 10/Dec/2014F
048/2013/HFT/SFO/ILDB/1 1 A3 INDOOR LIGHTING CONTROL PANEL
P
ApprovedA 19/Nov/2014 24/Nov/14 10/Dec/2014F
048/2013/HFT/SFO/EXDB/1 1 A3 EXTERNAL LIGHTING CONTROL PANEL
P
ApprovedA 19/Nov/2014 24/Nov/14 10/Dec/2014F
048/2013/HFT/SFO/ELDB/1 1 A3 110 V ELDB
P
ApprovedA 19/Nov/2014 24/Nov/14 10/Dec/2014F
Achieved Target Level(0= not submitted;1= Rev-0 issued
comments;2=Rev-A issued
approval;3= Re issued for
Approval after Rev-A;4= AFC)
Weightage assigned
Weightage achieved
Drawing/ Document Progress
status
Issued for Comments
Comments/ Approval
received from Client
Issued for Approval
Approval/ comments
received from Client
Re-Issued for Approval
Approval received from
Client
Approved for Construction
11KV SWITCHGEAR BUILDING LIGHTING LAYOUT
11KV SUBSTATION BUILDING DB SCHEDULE (LDB & ELDB)
11KV SWITCHGEAR BUILDING FIRE ALARM & FIRE FIGHTING LAYOUT
11KV SWITCHGEAR BUILDING SPLIT A/C INDOOR LAYOUT
11KV SWITCHGEAR BUILDING SPLIT A/C OUTDOOR LAYOUT
11KV SWITCHGEAR BULDING INDOOR SMALL POWER & TELEPHONE LAYOUT
33/11 KV SUBSTATION BUILDING OUTDOOR LIGHTING LAYOUT
33/11 KV SUBSTATION BUILDING DRAINAGE & WATER SUPPLY LAYOUT- INTERNAL
33/11 KV SUBSTATION BUILDING DRAINAGE & WATER SUPPLY LAYOUT- EXTERNAL