Handling Out of Tolerance Strand Elongations_tcm77 1306091
-
Upload
wenix-oniralco -
Category
Documents
-
view
219 -
download
0
Transcript of Handling Out of Tolerance Strand Elongations_tcm77 1306091
-
8/12/2019 Handling Out of Tolerance Strand Elongations_tcm77 1306091
1/3
D
uring pretensioning operations
for prestressed concrete, its
standard practice to measure
force in the strand by two inde-
pendent methods.
After ini tially tensioning the strand to re-
move slack, an operator applies the final
prestressing force, which is read from a hy-
draulic gauge mounted on the tensioning
jack . T he force i s then checked by measur-
ing strand elongation and comparing this
measured value wi th a theoretical (calculat-
ed) value. M easured and theoretical elon-
gation must agree within 5% . A lso, i f the
gauge force is higher than the specified
force, the combined percentage deviation
of elongation and force measurements cant
exceed 5% ( see box on page 776).
I n a well-run plant, the measurements
usually fall within the 5% tolerance. Signif-
icant elongation variations are relatively
rare, especially for straight strands, says
John K ime, vice president of operations at
D ukane Precast Inc. in Aurora, I ll. Well
investigate our system i f theres any appre-
ciable difference in measured and theoreti-
cal elongation, even i f its less than 5% .
What should you look for when investi-
gating the system? T he Precast/PrestressedConcrete Institutes quali ty control manual
( M NL-116) describes some of the conditions
that might lead to differences between mea-
sured and theoretical elongation values.
Check the jacking systemA malfunctioni ng hydraulic gauge is one
possible source of jack ing pressure error.
G auges, jacks, and pumps should be cali-
brated as a system in the same way that
theyre used in the tensioning operations.
M NL-116 requires calibration at least yearly
and any time a tensioning system yields er-ratic results.
Some producers who use multiple-strand
tensioning devices may initially calibrate
the total system, then use a master gauge
for check ing the production gauges. When
this is done, production gauges must be
checked against the master gauge at least
every six months and the master gauge
must also be i ndependently calibrated at a
six-month frequency.
Load cells can also be installed in front of
the stressing ram as a means of checking
gauge accuracy. Prestress Supply I nc. ( PSI) ,
in Lakeland, Fla., mark ets a single-strand
tensioning jack wi th a load cell between
the jack ing box and cylinder head in the
stressing ram. A ccording to PSI V ice Presi-
dent Gaylan Leeman, this load cell mak es
the hydraulic gauge redundant, providing a
double-check for jack ing force. H e adds
that the load cell i s less susceptible to dam-
age than one mounted in front of the ram.
Elongation di screpancies may also be
due to a scored hydraulic cylinder, says
James Simms, president of Simms Engineer-
ing Co. in Elk G rove Village, I ll. I n such
cases, the hydraulic cylinder would have to
be replaced.
I f there are friction forces wi thin the
jack ing system, the gauge reading reflects
those forces as well as the forces in the
Measuredandtheoreticalstrandelongationsdont agreewi thin 5%.Now what?
By Kaushal
Gupta
Handling out-of-tolerance strandelongations
During prestressing, force in the strand is measured by pressure gauge. T he gaugereading i s checked by comparing measured and theoretical strand elongation values.
KaushalGupta
-
8/12/2019 Handling Out of Tolerance Strand Elongations_tcm77 1306091
2/3
-
8/12/2019 Handling Out of Tolerance Strand Elongations_tcm77 1306091
3/3
strands at one or two points near
mi dspan. Since the stressing ram has
been disconnected when the strands
are deflected, gauges in the jack ing
system cant be used to verify the fi-
nal force. Instead, when a new bed
is set up, or deflection procedures
change, stress measurements are
made on strands at each anchorage
at each end of the bed.
Stressing deflected strands. If final
stressing is done wi th strands in a
draped position, friction at the de-
flecting devices resists some of the
force applied by the jacki ng system.
T hus, force in the strand decreases
at each successive deflection point
away from the jack ing source.
H old-up or hold-down devices
should be equipped with low-fric-
tion pin-and-roller assemblies or
other means for minimizing friction.
H owever, actual elongation may
not be wi thin 5% of theoretical
elongation or the combined percent
deviation for elongation and gauge
pressure may exceed 5% .
I f the measurements dont agree
within 5% , the jack or a load cell
may be used at the dead end to
check force in the strand at that loca-
tion. I f force measurements from the
gauge at the live end and the jack or
load cell at the dead end agree with-
in 5% , the requirement for elonga-
tion agreement can be waived.
When draped strands are jacked
from one end of the bed, M NL-116
requires measuring force on at least
two strands at the far end of the
bed, even when actual elongation
is wi thin 5% of theoretical elonga-
tion. T his can be done with dead-
end load cells or by moving the
jack to the dead end and just barely
lifting off the chuck from the abut-
ment. T he measured force must not
be below the theoretical values by
more than 5% . I f it is, force may be
added from the dead end and the
chucks reset. Elongation from this
added force must be recorded and
added to that measured at the live
end to check tolerances.
If the theoretical strand elongation
isnt attained when the gauge read-
ing exceeds specified force by 5% ,
strand must be jacked to theoretical
elongation from the other end of the
bed. I f this requires an overstress ex-
ceeding 5% , friction-reducing modi -
fications of the hold-up or hold-
down hardware may be needed.
Alternatively, deflectors can be re-
moved at some locations until the
required elongation can beachieved with not more than a 5%
overstress. Strand is then lifted or
depressed at these locations to pro-
duce final deflection.
When a bed with draped strands
is initially set up, or when changes
are made in the deflecting equip-
ment, its a good idea to determine
distribution of strand stress along
the bed. T his is done by mark ing off
a 10-foot or greater length of strand
after the ini tial stress has been ap-
plied. After final tensioning, the dis-tance between marks is remeasured.
Forces calculated from these elonga-
tion measurements must be within
5% of specified values.
Casting bed movementand strand slippage
Bed movements caused by abut-
ment rotation, anchorage move-
ment, or elongation of anchoring in
abutment beds are sometimes small
enough to be ignored. H owever, if
needed, movements can be checked
by setting stringlines parallel to and
some distance away from both abut-
ments, then measuring the distances
before and after stressing strands.
T he procedure is to check move-
ment periodically, preferably when
members with the maximum num-
ber of strands (highest prestressing
force) are produced.
Seating in the gripping devices
duri ng strand stressing can also af-
fect measured elongation, requiring
a small correction. G enerally, the
seating corrections are very consis-
tent, says John D ick, di rector of
certification programs at PC I . Peri-
odically, though, quality control
personnel need to go out and mea-
sure the amount of seating that oc-
curs in the chucks.
Keep accurate recordsT ensioning records are an invalu-
able resource when measured elon-
gations dont fall within allowable
tolerances. For all pretensioning,
M N L-116 requires quali ty control
personnel to record:
Required total load per strand
Initial tension
Anticipated and actual gauge pres-
sure for each strand or group ofstrands stressed in one operation
Anticipated elongation for each
different jack ing load
D ifferences in measured and theo-
retical elongation values, if recorded
daily, can give an early warning
when the 5% tolerance is being ap-
proached. Recording these differ-
ences also increases awareness of
the tolerances for plant personnel.
Reference
Manual for Quality Control forPlants and Production of Precast
and Prestressed Concrete Prod-ucts, MNL-116-85, Precast/ Pre-
stressed Concrete Institute, 1985.
In addition to their quality con-
trol manual, PCI offers two useful
training manuals for technicians.
TM -101, Qua lity Control Tech-
n ic i an / In spec to r Level I & I I
Tra in in g Manual , provides in-
formation on common plant pro-
cedures, including the tensioning
of straight strands.
TM -103, Qua lity Control Tech-ni cian /In spector Level III Man u -
al , is a continuation of topics
presented i n T M -103 and in-
cludes information on prestress-
ing deflected strands.
T hese manuals can be pur-
chased from Precast/Prestressed
Concrete Institute, 175 W. Jack-
son Blvd. , Chicago, I L 60604.
Training aidsfor prestressed
concrete producers
PUBLICATION #J960775Copyright 1996, The Aberdeen GroupAll rights reserved