Handling Out of Tolerance Strand Elongations_tcm77 1306091

download Handling Out of Tolerance Strand Elongations_tcm77 1306091

of 3

Transcript of Handling Out of Tolerance Strand Elongations_tcm77 1306091

  • 8/12/2019 Handling Out of Tolerance Strand Elongations_tcm77 1306091

    1/3

    D

    uring pretensioning operations

    for prestressed concrete, its

    standard practice to measure

    force in the strand by two inde-

    pendent methods.

    After ini tially tensioning the strand to re-

    move slack, an operator applies the final

    prestressing force, which is read from a hy-

    draulic gauge mounted on the tensioning

    jack . T he force i s then checked by measur-

    ing strand elongation and comparing this

    measured value wi th a theoretical (calculat-

    ed) value. M easured and theoretical elon-

    gation must agree within 5% . A lso, i f the

    gauge force is higher than the specified

    force, the combined percentage deviation

    of elongation and force measurements cant

    exceed 5% ( see box on page 776).

    I n a well-run plant, the measurements

    usually fall within the 5% tolerance. Signif-

    icant elongation variations are relatively

    rare, especially for straight strands, says

    John K ime, vice president of operations at

    D ukane Precast Inc. in Aurora, I ll. Well

    investigate our system i f theres any appre-

    ciable difference in measured and theoreti-

    cal elongation, even i f its less than 5% .

    What should you look for when investi-

    gating the system? T he Precast/PrestressedConcrete Institutes quali ty control manual

    ( M NL-116) describes some of the conditions

    that might lead to differences between mea-

    sured and theoretical elongation values.

    Check the jacking systemA malfunctioni ng hydraulic gauge is one

    possible source of jack ing pressure error.

    G auges, jacks, and pumps should be cali-

    brated as a system in the same way that

    theyre used in the tensioning operations.

    M NL-116 requires calibration at least yearly

    and any time a tensioning system yields er-ratic results.

    Some producers who use multiple-strand

    tensioning devices may initially calibrate

    the total system, then use a master gauge

    for check ing the production gauges. When

    this is done, production gauges must be

    checked against the master gauge at least

    every six months and the master gauge

    must also be i ndependently calibrated at a

    six-month frequency.

    Load cells can also be installed in front of

    the stressing ram as a means of checking

    gauge accuracy. Prestress Supply I nc. ( PSI) ,

    in Lakeland, Fla., mark ets a single-strand

    tensioning jack wi th a load cell between

    the jack ing box and cylinder head in the

    stressing ram. A ccording to PSI V ice Presi-

    dent Gaylan Leeman, this load cell mak es

    the hydraulic gauge redundant, providing a

    double-check for jack ing force. H e adds

    that the load cell i s less susceptible to dam-

    age than one mounted in front of the ram.

    Elongation di screpancies may also be

    due to a scored hydraulic cylinder, says

    James Simms, president of Simms Engineer-

    ing Co. in Elk G rove Village, I ll. I n such

    cases, the hydraulic cylinder would have to

    be replaced.

    I f there are friction forces wi thin the

    jack ing system, the gauge reading reflects

    those forces as well as the forces in the

    Measuredandtheoreticalstrandelongationsdont agreewi thin 5%.Now what?

    By Kaushal

    Gupta

    Handling out-of-tolerance strandelongations

    During prestressing, force in the strand is measured by pressure gauge. T he gaugereading i s checked by comparing measured and theoretical strand elongation values.

    KaushalGupta

  • 8/12/2019 Handling Out of Tolerance Strand Elongations_tcm77 1306091

    2/3

  • 8/12/2019 Handling Out of Tolerance Strand Elongations_tcm77 1306091

    3/3

    strands at one or two points near

    mi dspan. Since the stressing ram has

    been disconnected when the strands

    are deflected, gauges in the jack ing

    system cant be used to verify the fi-

    nal force. Instead, when a new bed

    is set up, or deflection procedures

    change, stress measurements are

    made on strands at each anchorage

    at each end of the bed.

    Stressing deflected strands. If final

    stressing is done wi th strands in a

    draped position, friction at the de-

    flecting devices resists some of the

    force applied by the jacki ng system.

    T hus, force in the strand decreases

    at each successive deflection point

    away from the jack ing source.

    H old-up or hold-down devices

    should be equipped with low-fric-

    tion pin-and-roller assemblies or

    other means for minimizing friction.

    H owever, actual elongation may

    not be wi thin 5% of theoretical

    elongation or the combined percent

    deviation for elongation and gauge

    pressure may exceed 5% .

    I f the measurements dont agree

    within 5% , the jack or a load cell

    may be used at the dead end to

    check force in the strand at that loca-

    tion. I f force measurements from the

    gauge at the live end and the jack or

    load cell at the dead end agree with-

    in 5% , the requirement for elonga-

    tion agreement can be waived.

    When draped strands are jacked

    from one end of the bed, M NL-116

    requires measuring force on at least

    two strands at the far end of the

    bed, even when actual elongation

    is wi thin 5% of theoretical elonga-

    tion. T his can be done with dead-

    end load cells or by moving the

    jack to the dead end and just barely

    lifting off the chuck from the abut-

    ment. T he measured force must not

    be below the theoretical values by

    more than 5% . I f it is, force may be

    added from the dead end and the

    chucks reset. Elongation from this

    added force must be recorded and

    added to that measured at the live

    end to check tolerances.

    If the theoretical strand elongation

    isnt attained when the gauge read-

    ing exceeds specified force by 5% ,

    strand must be jacked to theoretical

    elongation from the other end of the

    bed. I f this requires an overstress ex-

    ceeding 5% , friction-reducing modi -

    fications of the hold-up or hold-

    down hardware may be needed.

    Alternatively, deflectors can be re-

    moved at some locations until the

    required elongation can beachieved with not more than a 5%

    overstress. Strand is then lifted or

    depressed at these locations to pro-

    duce final deflection.

    When a bed with draped strands

    is initially set up, or when changes

    are made in the deflecting equip-

    ment, its a good idea to determine

    distribution of strand stress along

    the bed. T his is done by mark ing off

    a 10-foot or greater length of strand

    after the ini tial stress has been ap-

    plied. After final tensioning, the dis-tance between marks is remeasured.

    Forces calculated from these elonga-

    tion measurements must be within

    5% of specified values.

    Casting bed movementand strand slippage

    Bed movements caused by abut-

    ment rotation, anchorage move-

    ment, or elongation of anchoring in

    abutment beds are sometimes small

    enough to be ignored. H owever, if

    needed, movements can be checked

    by setting stringlines parallel to and

    some distance away from both abut-

    ments, then measuring the distances

    before and after stressing strands.

    T he procedure is to check move-

    ment periodically, preferably when

    members with the maximum num-

    ber of strands (highest prestressing

    force) are produced.

    Seating in the gripping devices

    duri ng strand stressing can also af-

    fect measured elongation, requiring

    a small correction. G enerally, the

    seating corrections are very consis-

    tent, says John D ick, di rector of

    certification programs at PC I . Peri-

    odically, though, quality control

    personnel need to go out and mea-

    sure the amount of seating that oc-

    curs in the chucks.

    Keep accurate recordsT ensioning records are an invalu-

    able resource when measured elon-

    gations dont fall within allowable

    tolerances. For all pretensioning,

    M N L-116 requires quali ty control

    personnel to record:

    Required total load per strand

    Initial tension

    Anticipated and actual gauge pres-

    sure for each strand or group ofstrands stressed in one operation

    Anticipated elongation for each

    different jack ing load

    D ifferences in measured and theo-

    retical elongation values, if recorded

    daily, can give an early warning

    when the 5% tolerance is being ap-

    proached. Recording these differ-

    ences also increases awareness of

    the tolerances for plant personnel.

    Reference

    Manual for Quality Control forPlants and Production of Precast

    and Prestressed Concrete Prod-ucts, MNL-116-85, Precast/ Pre-

    stressed Concrete Institute, 1985.

    In addition to their quality con-

    trol manual, PCI offers two useful

    training manuals for technicians.

    TM -101, Qua lity Control Tech-

    n ic i an / In spec to r Level I & I I

    Tra in in g Manual , provides in-

    formation on common plant pro-

    cedures, including the tensioning

    of straight strands.

    TM -103, Qua lity Control Tech-ni cian /In spector Level III Man u -

    al , is a continuation of topics

    presented i n T M -103 and in-

    cludes information on prestress-

    ing deflected strands.

    T hese manuals can be pur-

    chased from Precast/Prestressed

    Concrete Institute, 175 W. Jack-

    son Blvd. , Chicago, I L 60604.

    Training aidsfor prestressed

    concrete producers

    PUBLICATION #J960775Copyright 1996, The Aberdeen GroupAll rights reserved