Hampton Inn & Suites

26
Hampton Inn & Suites Productivity Study

description

Hampton Inn & Suites. Productivity Study. Agenda. Purpose & Process Project Overview**** Work Sampling Factors affecting Productivity***** 5 Min. Rating & Crew Balance Chart Process Charts & Flow Diagrams Discrete Model Simulations Safety Limitations Conclusion. Purpose & Process. - PowerPoint PPT Presentation

Transcript of Hampton Inn & Suites

Page 1: Hampton Inn & Suites

Hampton Inn & SuitesProductivity Study

Page 2: Hampton Inn & Suites

Agenda• Purpose & Process• Project Overview****• Work Sampling• Factors affecting Productivity*****• 5 Min. Rating & Crew Balance Chart• Process Charts & Flow Diagrams• Discrete Model Simulations• Safety• Limitations• Conclusion

Page 3: Hampton Inn & Suites

Purpose & Process

Discrete Model Simulation

Process Charts & Flow Diagrams

5 min. Rating & Crew Balance Chart

Work Sampling• Reason for this study• Analyze productivity• Document processes• Understand worker interaction• Identify obstacles and barriers• Provide recommendations

• Process• Study site as a whole• Identify areas of possible improvement• Analyze process in detail• Model possible solutions

Page 4: Hampton Inn & Suites

Project Overview• Construction Manager: Brinkman Partners• Client: Boulder Hospitality LLC• Design Team: Stephen Pahl Architecture• Construction Start: April 2012• Construction Finish: Summer 2013• Total Square Feet: 69,100• Location: Diagonal Highway & 63rd

• Candidate for LEED Gold Certification• Amenities:• 100 rooms, Conference Room, Board Room, Pool, Hot tub, Workout Facility, and Breakfast Area

Page 5: Hampton Inn & Suites

Project Overview• Trades on Site• Framers ~25• Plumbers ~15• Electricians ~4

• Progress to Date• 75% Frame• 30% Plumbing rough in• 15% Electrical rough

• Factors Affecting Productivity• Weather Conditions• Contract Terms• Change in Design Team• Change in Supervision• Change in Project Manager• Incomplete Construction Details• General lack of supervision• Sub-Sub Contractors

Page 6: Hampton Inn & Suites

Work Sampling

Observations Carpentry: 605 Plumbing: 471

1076

Oct. 19: Cold and DryOct. 26: Freezing & Snow

Page 7: Hampton Inn & Suites

Work Sampling22.5%

14.0%

8.7%18.2%

19.4%

13.5% 3.6%

Carpenters Average

DirectPrepTools/EquipMatlWaitingTravelPersonal

7 8 9 10 11 12 13 14 150%10%20%30%40%50%60%70%80%90%

100%Carpentry

PersonalTravelWaitingMatlTools/EquipPrep WorkDirect

Hour

Prod

ucti

vity

Page 8: Hampton Inn & Suites

Work Sampling

35.8%

35.2%

16.7%

27.4%

30.7%

20.5% 8.0%

Carpenter Max

DirectPrepTools/EquipMatlWaitingTravelPersonal

7 8 9 10 11 12 13 14 150.0%5.0%

10.0%15.0%20.0%25.0%30.0%35.0%40.0%

Carpenty

DirectPrep WorkTools/EquipMatlWaitingTravelPersonal

Hour

Prod

ucti

vity

Page 9: Hampton Inn & Suites

Work Sampling

7 8 9 10 11 12 13 14 150%10%20%30%40%50%60%70%80%90%

100%Plumbing

PersonalTravelWaitingMatlTools/EquipPrep WorkDirect

Hour

Prod

ucti

vity

25.1%

23.8%

9.1%

13.1%

6.0%

18.9%4.0%

Plumbers Average

DirectPrepTools/EquipMatlWaitingTravelPersonal

Page 10: Hampton Inn & Suites

Work Sampling

7 8 9 10 11 12 13 14 150.0%5.0%

10.0%15.0%20.0%25.0%30.0%35.0%40.0%

Plumbing

Direct WorkPrep WorkTools/EquipMatlWaitingTravelPersonal

Hour

Prod

ucti

vity

32.9%

32.9%

16.5%

19.3%

12.7%

22.0%10.7%

Plumbers Max

DirectPrepTools/EquipMatlWaitingTravelPersonal

Page 11: Hampton Inn & Suites

Activity Analysis

• Focus on a crew of 2 framers• Only crew with a repetitive task• Highly confined space

• Safety concern !!!

Trusses

Scaffold basket

Install worker

Prep worker

Page 12: Hampton Inn & Suites

5 minutes rating - observed

TimeFramer 1 Framer 2 Observation

0 I II  00:30 1 0 Framer 2 measuring

01:00 1 1  

01:30 0 1 Framer 1 waiting

02:00 1 1  

02:30 0 1 Framer 1 waiting

03:00 0 1 Framer 1 waiting

03:30 0 1 Framer 1 waiting

04:00 1 1  

04:30 1 1  

05:00 0 1 Framer 1 waiting

Total 5 9

• A lot of waiting time

• But a good effectiveness• One framer highly productive• The other one waiting

Page 13: Hampton Inn & Suites

Crew Balance chart - observed

Prep Worker Install Worker59:57

00:40

01:23

02:07

02:50

03:33

04:16

04:59

CheckPick WoodPositionPick WoodMeasureWaitMarkStackCutPick WoodRecord

• Confirms the waiting time• Only one minute of active time

for the prep worker

• Almost 40sec to record measurements !

• The two processes are not synced

Page 14: Hampton Inn & Suites

Analysis and recommendation• Only one worker really required !

• But we can’t• For safety reasons

• We have to find a way to sync the workers• Increase the prep worker productivity

Page 15: Hampton Inn & Suites

5 minutes rating & crew balance chart – Possible improvements

TimeFramer 1 Framer 2 Observation

0 I II  00:30 0 0 Framer 2 measuring01:00 0 1  01:30 1 1 Framer 1 waiting02:00 1 1  02:30 1 1 Framer 1 waiting03:00 0 1 Framer 1 waiting03:30 1 1 Framer 1 waiting04:00 1 1  04:30 1 1  05:00 1 1 Framer 1 waitingTotal 7 9

Prep Worker59:57

00:40

01:23

02:07

02:50

03:33

04:16

04:59

StackMarkStackCutPick WoodRecordPositionPick WoodCheckPositionPick Wood

Measure and record remaining braces

Page 16: Hampton Inn & Suites

Process Chart & Flow Diagram of Prep Worker

Spatial Logistics• Labor• Tools• Materials

Page 17: Hampton Inn & Suites

Process Chart & Flow Diagram of Install Worker

Page 18: Hampton Inn & Suites

Combined Analysis

x2

Page 19: Hampton Inn & Suites

Process Optimization

Page 20: Hampton Inn & Suites

Discrete Model

Observed

Minutes

Avg. 12.39

σ 1.34

Min 10.10

Max 20.74

Recommended

Minutes

Avg. 11.68

σ 1.38

Min 9.37

Max 20.18

Savings

Cycle

0.71 min

 Total

71 min

Cycle Required approx. 100 Times to complete the project

Page 21: Hampton Inn & Suites

Projected SavingsThe prep worker has 6.63 min of free time at the end of each cycle• Reassign to install 2-3 braces • Keep Clear of install worker by installing braces from H to G• Reduce Cycle time by an additional 2.16 min per cycle

No change

Prep measur

e

Prep install 2 braces

Savings

Total time (min)

1239 1168 952 28723%$ 1,858.5

01,752.00 1,428.00 430.00

Page 22: Hampton Inn & Suites

SafetyObservationso Exposure• Cold Climates• Snow & Ice• Wet Conditions

o General Working Conditions• Congestion (Layout)• Schedule Compression

o Direct Safety Violations• Lack of Railing• Toe Boards• Spotting

o Housekeeping• General Housekeeping

Recommendationso Exposure• Schedule - Coordinate with “Dry In”• Proper Work Attire

o General Working Conditions• Design Considerations• Schedule Revision

o Direct Safety Violations• On-Site Safety Manager

o Housekeeping• Labor Ready

Page 23: Hampton Inn & Suites

Limitation of the study• Only Friday work observed• (only one day, not the most productive

of the week)

• Indoor work over three floors• Low visibility

• Transition between trades• End of framing• Detail work and beginning of learning

curve

• Hawthorne effect• We explained the purpose of the study

• Interpretation of prep vs. direct • between 3 observers

• 3 observation days: Changing crews, weather,..

Page 24: Hampton Inn & Suites

Conclusion• Plumber & Framer direct work activity was LOW• Truss Bracing task could be reduced by 6-23%• Many inefficiencies throughout the jobsite• Onsite SUPERVISION would likely have the greatest

effect on productivity

Page 25: Hampton Inn & Suites

Questions?

Page 26: Hampton Inn & Suites

Factors Affecting Productivityo Weather Conditions• Cold & Wet

o Outdated plans• Revisions & Rework

o Contract changes• Uncooperative Architecture Firm• Mechanical Contracted Thru Architect

o Sub-Sub Contractor

• Framing Crew was Sub-Subo Changes in Supervision• Turnover

o Changes Project Management• New Project Manager

o Missed Scope• Storefront• HVAC Pads