Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental...
-
Upload
elvin-green -
Category
Documents
-
view
218 -
download
0
Transcript of Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental...
Hall D Online Meeting27 June 2008
Fast Electronics R. Chris Cuevas
Jefferson LabExperimental Nuclear Physics Division
12 GeV Trigger System Status Update
-- New module design progress-- Updates to System drawings-- Testing activities
Project Status
• 15 weeks until the end of FY08• Identified FY09 PED activities are defined for the ‘Test Stand’:
• FADC250 –
-- Nine modules fully assembled and all required modifications have been added
-- 8 channel 12 bit version delivered to IU.
-- Test crate and CPU that is on loan to G. Vissar at IUCF has been moved to IU
-- LabView test routines have been completed to fully test each FADC250
-- The LabView test programs will provide a nice platform for troubleshooting and repair
-- CODA driver has been completed and is in use for testing with the Trigger Interface
-- Development to download firmware through VME has started (Hai)• Trigger Interface –
-- 4 modules fully assembled and functional
-- Successful synchronization of trigger and latency adjustment for 150m and 50m fiber
-- Plans underway to test multiple FADC250 modules in two VXS crates
- Trigger rate performance testing for FADC250
- Does FADC250 pipeline trigger readout meet specifications?
- Data throughput testing
-- Test stand software – Ben has created very useful routines to configure and display
readout data.
Signal Distribution module – -- Functional specifications completed for May Review-- Schematics are behind ‘schedule’ - New circuits to regulate power to the module - FPGA has been selected-- Must begin component placement and routing by July
Crate Trigger Processor – -- Functional specification has been completed for May Review-- Schematics are complete-- Significant progress with placement of components and routing of circuit
board-- CNU Student working with Hai on interface firmware for CTP to TI
communication
SubSystem Processor – Global Trigger Processor – Trigger Supervisor –
-- Functional specification document completed for May Review-- Design activities scheduled for FY09
Project Status
CTP Circuit Board Place & Route
2 Gigabit ‘Lanes’ from each FADC250
More updates,,
• Detailed System Drawings – -- Started converting the logical drawings to detailed rack drawings
- Include ALL equipment ‘chassis’- Drawings for each platform have been started
-- Work closely with Mechanical Engineering to identify best cable routing method for each sub-system (platform)
Tagger Area: Instrumentation Racks
Crates and other equipmentchassis shown. Need to add details to show AC mains panel assignments& Network hardware.
Testing updates,,
• Many tests are planned for multiple FADC250 boards in a crate• Must test token passing scheme, and measure any noise and jitter effects with up to 8 FADC in a crate.
• Two crate trigger latency tests have been performed, and we have the fiber optic patch panels that will be used in the final installation. The test stand is a very good platform to simulate the final configuration in the Hall and to measure total system effects on clock jitter and other critical timing parameters
• Data display and GUIs to configure the test station have been developed by Ben.