Haida Energy, Inc. Presentation
Reynolds Creek Hydroelectric Project Corry Hildenbrand – Project Manager
Hildenbrand Associates LLC
1
PROJECTLOCATION
Loca1on:PrinceofWalesIsland,AlaskaWaterbody:LakeMellen(Rich’sPond)andReynoldsCreek;HeHaInlet
ProjectFeaturesDAM:A20‐foot‐long,6‐foot‐high,concretediversiondam,withan
uncontrolledspillway,neartheoutletofRich’sPondateleva1on870feetmeansealevel.
INTAKE:Asmallconcretebox‐typeintakestructurewithfishrackslocatedontheleZsideofthediversiondam;
PENSTOCK:A42‐inch‐diameter,3,200‐foot‐long,steelpenstock;POWERHOUSE:A40‐foot‐wide,100‐foot‐long,pre‐engineering
insulatedmetalpowerhouseonaconcreteslabcontainingonegenera1ngunitswithatotalinstalledcapacityof5MW;
TAILRACE:An80‐foot‐longtailracechannelconsis1ngdischargingintoReynoldsCreek;
SWITCHYARD/SUBSTATION:Aswitchyard/substa1on,locatednexttothepowerhouse.
TRANSMISSIONLINE:Anoverhead34.5kV,12‐mile‐longtransmissionlineinterconnec1ngtoPOWTransmissionline;
ProjectTeam(todate)Phase1Construc1on
AlaskaEnergyAuthority(AEA)
ProjectManager
HildenbrandAssociatesLLC
CorryHildenbrand
AP&T/HDREngineering
EngineeringSupport
GlassmanAssociatesLLC
SteveGlassman
CivilEngineering
MooreEngineering
TracyMoore
PhaseIAccessImprovements
DuReHeConstruc1on
EnvironmentalControl
Monitor
JeaneHeBrucker
FisheriesConsultant
Dr.PaulRusanowki
ShipleyGroup
SafetyConsultant
JerryLemm
ElectricalSafetyConsultantsInterna1onal,Inc.
HaidaEnergyCorp.
Administra1veSupport
AllisonGrant
Administra1veSupport,FERCCompliance
andFinancialTracking
S.TinneyAssociates,Inc.
SusanTinney
HaidaEnergyCorp.
Financial
ToddTew,CPA
HaidaEnergyCorpora1on
PhaseIAccessImprovements
• ContractAwardedto:DuReHeConstruc1on
• Schedule:– 9/6/11:ContractAwardLeHer– 9/20/11:MaterialsandEquipmentarriveinThorneBay– 9/24/11:ProposedbargedateintoCopperHarbor– 9/26/11:SetupFuelContainmentareaatCopperHarbor;setuparea
forExplosivesProductMagazines;setupErosion/Controlmeasures– 10/1/11:BeginProjectwork–NTPissued
• 11Weekstoperformonsite–Weatherdependent.• December31,2011‐AllPhaseIworktobecompleted