Five Year Business Plan (2016-2020) 1 Hagonoy Water District
HAGONOY WATER DISTRICT FIVE YEAR
BUSINESS PLAN (2016-2020)
Five Year Business Plan (2016-2020) 2 Hagonoy Water District
INTRODUCTION
Hagonoy Water District’s business plan is created to guide and effectively plan the ongoing and
future program. It is a tool used to come out with possible solutions and means to achieve the
district’s fundamental goals. This goal is consistent with District’s mission “to provide sufficient,
safe and accessible water to least possible cost while ensuring sustainability, reliability and
preservation of the environment”. This is intended to provide a step-by-step procedure to
generate information that is vital for making rational and coordinated decisions. This paper is a
working documents that comprises the five year projects and programs expressed in strategic
goals of Hagonoy Water District.
Five Year Business Plan (2016-2020) 3 Hagonoy Water District
1. GENERAL DESCRIPTION OF THE UTILITY
1.1. Brief History of the Water Utility Hagonoy Water District (HWD) was created pursuant to Presidential Decree 198, as amended by
Presidential Decrees 768 and 1479, otherwise known as the Provincial Water Utilities Act of
1973 which was signed by President Ferdinand E. Marcos. Through Kapasiyahang Pambayan
Bilang 121-A, signed and submitted on August 26, 1976 manifesting a great need for sufficient,
safe and potable water for domestic and industrial use in Hagonoy. It affirmed that the present
funding and personnel during that time were insufficient and therefore there was a great need for
expansion and improvement.
Pursuant to the provisions of the Title II, PD No. 198 and in order to provide the much-needed
safe, sufficient and potable water supply, the body in the meeting assembled adopted and
approved Kapasiyahang Pambayan Bilang 121-A that states:
The organization of the HWD covering the following areas: all barangays accessible by
vehicular transportation;
The transfer of all existing water facilities, namely, all existing properties and/or facilities to
the jurisdiction and ownership of the Hagonoy Water District;
The creation of a Board of Directors, with five members appointed by the Municipal Mayor
as provided in PD 198;
That the HWD herein organized and formed can only be dissolved through the act of its own
Board of Directors pursuant to Sec. 45, Title II, PD No. 198;
That the HWD shall have sole powers to raise revenues and promulgate rules and
regulations to run and manage the water utility pursuant to the provisions of Sec. 26, Title II,
of PD No. 198;
That the operation of the HWD shall be in accordance with the provisions of PD No. 198,
particularly Title II, known as Local Water District Law;
The ware of the fact that the Hagonoy Waterworks system is still a non-self supporting
utility and to permit the newly formed HWD to implement and improve staffing pattern and
operational format, the Municipality of Hagonoy shall provide a monthly subsidy for a period
of time to help operate and maintain the said waterworks system or until such time as the
water district shall have been found self-sufficient by the Local Water Utilities
Administration (LWUA).
Five Year Business Plan (2016-2020) 4 Hagonoy Water District
In recognition of its having taken very significant and necessary steps and substantial commitment
to improve the domestic water service to the people of Hagonoy, as evidenced by a schedule of
improvements, submitted to and approved by LWUA, the HWD was granted a Conditional
Certificate of Conformance No. 31 with the standards of service to the public that have to be
achieved. Thus, creating HWD and becoming the first local water district in the Province of
Bulacan.
The first General Manager of HWD was Engr. Antonio Santos who after resigning from LWUA
managed the district. The first few months of operation was subsidized by the Municipality of
Hagonoy and the rehabilitation of pump stations to improve service was made from loans granted
by LWUA. In 1981, Engr. Santos migrated in USA and was replaced by then Director (Member of
the Board of Directors) Miguel Santos. During his term expansions of coverage areas were made
in the southern part of the town specifically Sta. Cruz, Sto. Rosario and Sagrada. Unfortunately,
the financial feasibility of the project was not met and the project became a dismal failure due to
the management’s inability to pay the loans granted by LWUA. As a result, the district decided to
accept a take-over management by LWUA under the interim management of Engr. Edgardo
Tolones replacing Mr. Miguel Santos. In 1987, after more than a year of take-over management,
LWUA opened the position of General Manager to the public.
Among 21 applicants vying for the position as General Manager, Engr. Celestino S. Vengco was
chosen after strict screening and testing conducted by LWUA. He is also the lone passer of the
psychological and other tests conducted.
During his first 10 years of term, HWD has emerged from losses to net income. The management
has become updated in all loan amortizations with LWUA. The improvement projects that were
abandoned by a certain contractor were continued by the management without making
additional loans from LWUA. Eighteen hours of service became 24 hours around the clock.
Expansions and improvements all over Hagonoy were successfully accomplished from the mere
operational fund of the district and also from financial assistance granted by then Senator Blas F.
Ople and some of his allies like Hipolito and Magsaysay.
HWD was originally a quasi-public corporation but performing in a private manner and without
the control of national government agencies until the Supreme Court ruling issued to Davao City
Water District vs. the Civil Service Commission (CSC), that all local water districts are now
government-owned and controlled corporations (GOCC) and under the control of national
government agencies like GSIS for membership coverage, CSC for appointments, the Department
of Budget and Management (DBM) for the plantilla and benefits and the Commission on Audit
(COA) for annual audit as to accounting procedures followed by water districts.
HWD as an entity is independent, autonomous, non-stock, self-supporting, non-profit, self-reliant
GOCC that does not receive regular subsidy, grant or budgetary allocation from any
political government subdivision. HWD is tasked to manage and operate the district in a
businesslike and proficient manner through the strict performance of its manpower and by the
appropriate allocation and timely utilization of its resources to result in the optimum benefits to
HWD and its water consuming public.
Five Year Business Plan (2016-2020) 5 Hagonoy Water District
NO. PUMPING STATION LOCATION TYPE OF MOTOR RATED CAPACITY PROD.CAPACITY WELL DEPTH WELL STW DATE INSTALLED SERVICE AREA
1 PoblacionMunicipal Compound
pathway thru H.E.S.
submersible pump
& motor15 h.p. 317 gpm 400-500 ft. 56 ft. 1976
Sto Nino ,San Agustin, San
Sebastian
2Apo Ana Production
Center
Water Tank Compoundin
front of Sta Ana church
submersible pump
& motor7.5 h.p. 115 gpm 400-500 ft. 56 ft. Aug. 2000
San Sebastian, Poblacion
Sto Nino, San Agustin
3 Sta MonicaPurok-1 near the river
side
submersible pump
& motor15 h.p. 317 gpm 383 ft. 58 ft. 1976
San Jose, Sta Monica,
Poblacion, Tampok
4 San Agustin San Agustinsubmersible pump
& motor5 h.p. 100 gpm 500 ft. 64 ft. March 2014
Sto Nino, Sta Monica, San
Agustin, Halang
5 Engr. Manuel R. Contreras memorial production cntr.in front of san pedro
church
submersible pump
& motor30 h.p. 450/500 gpm 550 ft. 65 ft. Dec. 2010
San Pedro, Abulalas,
Halang, San Agustin,
Paombong
6 San Miguel - New San Miguel side of submersible pump
& motor30 h.p. 230 gpm 550 ft. 72 ft. 1978 San Miguel, San Agustin,
7 Apo Pelis Memorial Production Centerin front of iba churchsubmersible pump
& motor30 h.p. 566 gpm 400/500 ft. 56 ft. 1997
Iba-Poblacion, iba-ibayo,
Palapat,caril lo,sn.miguel
8 Kapitan Andres Sytamco San Isidrosubmersible pump
& motor30 h.p. 600 gpm 500 ft. 62 ft. Feb. 2002
san miguel, san juan
bangkal, panducot
9 San Nicolas Production Center Well # 1 San Nicolas near
elementary school
submersible pump
& motor30 hp 550 gpm 380 ft. 54 ft. 1984
San Nicolas, Sagrada,
San Sebastian, Sta Elena,
Sto Rosario
10 Victor AguinaldoMemorial Prod. CenterSan Pascual near churchsubmersible pump
& motor30 h.p. 705 gpm 500 ft. 52 ft. May 2001
San Pascual, Sta Cruz, San
Roque, Sto Rosario
11 Kapitan Isidro Crisostomo Mercadosubmersible pump
& motor30 h.p. 529 gpm 550 ft. 65 ft. 2002
Mercado, Sto Rosario, Sta
Cruz, San Jose
12 Apo Elena Prod. Center Sta Elenasubmersible pump
& motor30 h.p. 650 gpm 500 ft. 46 ft. May 2004
Sta Elena, Sagrada, San
Pablo
13 Sto Rosario Sto Rosario near talipapasubmersible pump
& motor15 h.p. 350 gpm 400/500 ft. 58 ft. 1976
Sto Rosario, Sta Cruz, San
Nicolas
14 Old San Nicolas Salamat Compoundsubmersible pump
& motor5 h.p. 100 gpm 300/400 ft. 58 ft. 1976
Sto Rosario, Sta. Cruz,
Mercado, San Nicolas
15 San Sebastian del Pilar St.submersible pump
& motor5 h.p. 97 gpm 500 ft. 60 ft. Dec. 02, 2015 Sukol,Rizal,Mabini
HWD covers the whole town of Hagonoy, all of its 26 barangays.The table belowshows the
existing HWD water sources/pump stations, the year constructed and the barangays being served.
HWD Pump Stations and Service Areas
Five Year Business Plan (2016-2020) 6 Hagonoy Water District
At present, HWD has a total number service connection of 27,540. The average consumption per
service connection was recorded at 19.39 m3 per month or 0.65 m3 per day.
The present minimum water tariff of HWD is PhP 127.50 for the 1st 10 m3. Rates go up from PhP
14 to 17 per m3 depending on the consumption bracket. Commercial rates are double the
residential rates.
The source of water supply in the municipality is ground water. At present, HWD has a total
distribution line of 86.5 km, more or less covering all 26 barangays of the municipality and three
barangays of neighboring town of Paombong: San Isidro II, Pinalagdan and Sto. Rosario-Gusi. Pipe sizes
range from 50 mm to 200 mm diameter uPVC. It has 15 pump stations, 11 generator sets and one
storage tank at strategic locations of the municipality. The storage tank has a capacity of 100 m3
and is located at the Poblacion.There are also about 63 fire hydrants strategically located in the
whole town.
1.2. Franchise Area Profile Information
Municipality of Hagonoy is the franchise area of Hagonoy Water District located at the southwest
tip of the Province of Bulacan. It is bounded by the Municipality of Calumpit to the north, the
Municipality of Paombong to the east, the Municipality of Masantol, Pampanga to the west and
the Manila Bay to the south. The town lies at the coordinates of 14°49’55” North and 120°43’59”
East. It is approximately 54 km from Metro Manila or about an hour and a half drive. It can be
accessed via North Luzon Expressway or McArthur Highway. It is also classified as a first class
municipality.
Location Map of Hagonoy, Bulacan
Five Year Business Plan (2016-2020) 7 Hagonoy Water District
Hagonoy is composed of 26 barangays of which seven are classified as urban. The total area of
Hagonoy is about 10,310 hectares. Clearly, more than 70% of Hagonoy is occupied by the
aquaculture industry.
Barangay Map of Hagonoy
Existing Land Use
Land Use Category Area
(hectares)
Residential 470.56
Commercial/Industrial 14.37
Institutional 31.38
Agricultural 775
Fishpond 8,128.28
Open Spaces (cemeteries, plazas, roads, river, etc.) 822.44
Mangroves 75.97
Five Year Business Plan (2016-2020) 8 Hagonoy Water District
In 2015, the town had a total population of 129,807 or 29,020 households.Hagonoy’s statistical
details are shown below:
Physical/Geographic Profile
NO. BARANGAY POPULATION AS OF 2015
NO. OF HOUSEHOLD AS OF 2015
LAND AREA (has)
1 Abulalas 5,283 1,256 220
2 Carillo 1,708 419 135
3 Iba 5,321 1,585 546
4 Mercado 7,114 1,378 158
5 Palapat 2,364 519 127
6 Pugad 1,907 377 812
7 SagradaFamilia 6,569 1,417 380
8 San Agustin 10,336 2,353 265
9 San Isidro 8,102 1,802 500
10 San Jose 4,646 1,032 263
11 San Juan 3,542 859 176
12 San Miguel 5,888 1,373 213
13 San Nicolas 5,113 1,245 122
14 San Pablo 3,346 651 239
15 San Pascual 5,957 1,242 741
16 San Pedro 5,042 1,088 210
17 San Roque 4,908 1,010 2,936
18 San Sebastian 8,193 1,785 283
19 Santa Cruz 3,484 735 75
20 Santa Elena 4,918 1,113 520
21 Santa Monica 8,317 1,956 530
22 Santo Niño (Pob.) 4,415 946 65
23 Santo Rosario 5,251 1,133 45
24 Tampok 2,635 612 285
25 Tibaguin 2,884 616 162
26 Iba-Ibayo 2,564 518 302
TOTAL 129,807 29,020 10,310
Five Year Business Plan (2016-2020) 9 Hagonoy Water District
1.3. Key Performance Indicators In the past years, key performance indicators have helped interested individuals to assess and scrutinize the status of the district. Key indicators for HWD are presented on table below.
Key Performance Indicator Value
Water Coverage (% of Population in Franchise Area) 98% Metered Connections (% of total connections) 100%
Non-revenue Water (% of production) 23.75%
Collection Efficiency (% of total billings) 98.87%
Employees per 1,000 water and + Sewer connection 2.5 Average total Water Sales (liters/capita/day) 125 lpcd
Average hours of water supply per day 24 hours
Revenues/Costs 117% Direct Operating Cost Coverage – from collections
(Collections/Costs)
Direct Service Coverage Ratio
Debt Equity Ratio .18 Net Profit Margin 14.80%
Operating Margin (EBITDA/Operating Income) .77
1.4. Corporate Governance Structure
As a GOCC, Hagonoy Water District operates in a corporate and business-like manner where the policy-making functions are vested to the Board of Directors while its day to day affairs are handled by the head of the management – the General Manager. The GM is answerable to the Board of Directors while all the rest of HWD employees are answerable to the GM. Each of the personnel, may it be regular, casual or the Job Orders, has a well-defined set of tasks based from their qualification. Employees are given periodic ratings to assess their performance. The current composition of HWD Board of Directors:
POSITION NAME SECTOR
Chairman Atty. Elias M. Santos Civic Oriented
Vice-Chairman Mr. Edgardo J. Perez Educational Institution
Secretary Engr. Danilo A. Fajardo Professional Association
Member Mr. Hermogenes C. Mateo Business Organization
Member Atty. Dalisay O. San Jose Women Organization
Five Year Business Plan (2016-2020) 10 Hagonoy Water District
The HWD organization, as headed by the General Manager and has five Division Managers.
2. MISSION, VISION, CORPORATE VALUES AND KRAs As public water utility firm, the primary reason of HWD’s existence is to provide service to its franchise area. Not just ordinary service but efficient and globally standard service at that. The HWD organization had set forth clear guiding statements as to what path it will tread. Such statements guided the utility to come with a clear mission and vision that states its purpose and values. VISION STATEMENT:
To ensure an efficient, sustainable and financially viable water service and sewerage sector
delivering the highest quality service to all concessionaires.
MISSION STATEMENT:
Hagonoy Water District commits itself to be a progressive and economically viable utility
firm that provides sufficient, safe and accessible water at the least possible cost while
ensuring sustainability, reliability and preservation of the environment.
General Manager Engr. Celestino S. Vengco
Division Manager
Administrative Ma. Salvacion L. Bautista
Finance Remedios R. Osorio
Customer Accounts Ma. Socorro C. Salvacion
Customer Service Micheal M. Santos
Engineering & Production Alberto S. Lopez
Five Year Business Plan (2016-2020) 11 Hagonoy Water District
CORPORATE VALUES:
As Hagonoy Water District (HWD) employees, we dedicate ourselves to:
I. Excellence
We are committed to undertake continuing exploration and development activities, aimed
at the preservation and sustainability of our water sources. We must always adhere to
sound practices in preserving our natural environment.
II. Innovation
Our capability to provide proper service must continuously improve by designing and
managing the growth of infrastructure in an innovative, timely, safe and cost-effective
manner and conforming to internationally accepted standard.
III. Teamwork
It is then indispensable to nurture a highly motivated workforce, with a strong spirit of
collaboration, deeply committed to professionalism, and firmly focused on productivity.
IV. Customer Focus
We continuously improve quality of service, responsiveness and maintain a respectful
relation with our customers and stakeholders for their satisfaction.
V. Commitment
Our workforce shall be upheld and inspired by a competent management team dedicated
to the common good of HWD. All these tasks must be accompanied by sound and prudent
financial management with the overriding goal of providing better services to the people
of Hagonoy, Bulacan.
Five Year Business Plan (2016-2020) 12 Hagonoy Water District
KEY RESULT AREAS:
Water Safety and Accessibility
‘Water’ is looked upon as a social and environmental resource. The term ‘right to water’ does not
only refer to the rights of people but also to the needs of the environment. As a minimum, the
quantity should be sufficient to meet ‘basic human needs’ in terms of drinking, bathing, cleaning,
cooking and sanitation.
Groundwater is relatively inexpensive, but it is limited in volume and irreplaceable if depleted.
Maintaining a safe water supply means that river basins and groundwater are managed in their
entirety.
Excellent service
Excellent service is the process of consistently communicating to all customers – whether it is an
internal customer or external customer – that they are valued, and that their satisfaction is
paramount to the organization.
Community Participation
Community participation is defined as a continuous two way process which involves promoting
full public understanding of processes and mechanisms through which the community is involved
in identifying environmental problems, developing action plans, implementing the best plan and
monitoring the impact of such action.
Environmental Protection
Environmental protection is a practice of making concrete actions in addressing environmental
concerns on individual and organizational levels. Environment protection proposes to solve the
existing and potential environment problems, harmonize the relationship between human beings
and environment and ensure the sustainable development of the economy and society.
Sanitation Service
Sanitation is a basic, as well as a long-standing, public health issue. It includes the proper disposal
of human and industrial wastes and the protection of the water sources. Sanitation is directly
related to water quality and water pollution which poses potential health risks. Water sources
must be protected prior to consumption. By providing protection to the source, water is available
without much treatment.
Five Year Business Plan (2016-2020) 13 Hagonoy Water District
Resource management
Resource management is the efficient and effective utilization of an organization's resources
when they are needed. Such resources may include material and human assets.
Infrastructure and Technology Development
Infrastructure and technology are the vital underlying components in maintaining and sustaining
the quality of service of any organization. Continuous development, improvement, and acquisition
and upgrading of existing technology are vital in upholding excellent service.
3 SENIOR MANAGEMENT OVERVIEW OF THE BUSINESS PLAN
Senior management of Hagonoy Water District believes in the conscious effort to strive for
excellence in the workplace by identifying issues that need to be addressed in the most
determined and objective manner. The Business Plan is recognized by Senior Management as a
handy tool in assessing where the Water District is situated at a particular time in terms of its
goals and targets and where it ought to land.
3.1. Priority Issues for the Utility
The Water District has several priority issues that are considered very urgent in terms of
addressing them. These have been identified after thoroughly assessing the present state of utility
in all aspects. The water service of Hagonoy Water District has already covered all the barangays
of the municipality. Considering this, it is apparent that the next critical stage of utility is to sustain
the need for adequate and potable water as well as to continually protect and preserve of its
water sources.
To further reduce the percentage of non-revenue water is also one of the issues that continuously
challenge Hagonoy Water District. It is necessary that future programs be established to fully
minimized non-revenue water to generate more income.
3.2. Major Challenges Facing the Utility in Implementing the Business Plan
While the Water District Management is determined to implement the business plan, it is
oftentimes confronted with challenges that are oftentimes difficult to overcome. However the
decisiveness of the Management backed up by the support of the Board and the assurance of staff
cooperation turns these challenges to something easily surmountable.
Five Year Business Plan (2016-2020) 14 Hagonoy Water District
These challenges are identified as:
3.2.1 The Capex Requirement
The funding sources needed to implement the Performance Improvement Program
to attain the strategic goals of the Water District still have to be identified. This may be
coming in the internally generated or out-sourced funds;
3.2.2 The Water Resource Requirement
The continuously increasing of water demand amidst moderate will inevitably
necessitate tapping other water sources in the future. Although as the water resources
potential of Hagonoy is still great, the threat of water supply deficit in the future is
eminent.
3.2.3 The Manpower and Skills Requirement
Looking closely at the existing manpower of the Water District and the staff
productions index of less than 2.5 employees per 1000 service connection, it is apparent
that the existing manpower of the Water District is optimally tapped. With the adoption of
new technologies as demanded by the Performance Improvement Program, additional
manpower and skills will be needed to sustain the operation of the utility.
3.2.4 Further Reduction of the Non-Revenue Water
Amidst the intensified campaign for saturation of the service area in terms of
service connection generation, optimization of water supply is a real challenge. The
reduction of non-revenue water would mean increase in revenue generating water.
3.3. Monitoring, Reporting and Corrective Actions
The successful attainment of the goals identified in the Business Plan of Hagonoy Water District
can be ascertained with the adoption of mechanisms for the monitoring, reporting and application
of corrective actions by top management. Exercise of control over every aspect of the Business
Plan is necessary to ensure that every activity is kept on track.
Five Year Business Plan (2016-2020) 15 Hagonoy Water District
3.3.1 Monitoring
Every functional area of every division in the organizational setup of Hagonoy Water
District will be monitored by the corresponding supervisor following the principle of chain
command. Each unit will be required to submit its functional areas which will be the
subject of monitoring. These functional areas will be submitted within the last quarter of
every fiscal year. However, for the initial adoption of the Business Plan these functional
areas should be submitted on or before the last working day of July. The functional areas
should have been developed based on the identified Strategic Goals and Performance
Improvement Program. Performance indicators will have to be determined and will be
made the basis for measuring the efficiency of every team member and the team itself.
Division Manager will be responsible for monitoring the performance of every team
member.
For the purpose of ensuring that monitoring is conducted, each Division will hold meetings
at least once a month (depending on the need) and should coincide in the last week of
every month. Minutes of every meeting should be taken. Moreover, managers’ meeting
will also take place to discuss the departmental accomplishment and to discuss such issues
or matters that arises within the departments.
Staff meetings will be regularly scheduled within the first week of every month to discuss
the progress of the Business Plan implementation, based on monitoring. These staff
meetings will be attended by the General Manager and Division Managers, and when the
need arises, by other team member as may be called by the General Manager.
Every meeting should have an agenda enumerating items/issues that need to be tackled.
The agenda should contain, among others the following:
Reading of the minutes of the previous meeting
Business arising from the minutes of the previous meeting
Unresolved issues
Agenda proper (items/issues that will be taken up)
Other matters
Five Year Business Plan (2016-2020) 16 Hagonoy Water District
3.3.2 Reporting
Reporting will be in writing and should be readily available during regular meeting.
Written reports should be submitted using the standard formats and forms adopted by the
Water District. It should contain the following among others:
The SUBJECT
The BACKGROUND
The PROBLEMS/ISSUES OF CONCERN
The ACTIONS TAKEN
The RECOMMENDATIONS/CONCLUSIONS
All reports will be compiled systematically since they are important documents that will be
needed as reference materials for the periodic review and updating of the Business Plan in
the future.
3.3.3 Corrective Actions
The Manager in charge of certain activities/tasks may be encountering problems that will
be ready to propose corrective actions during meetings to eliminate the problems and to
put progress of the Business Plan back on track. In times when such problems are beyond
the Supervisors ability to resolve, such should be laid down during meetings for
deliberation by the body. Identifying and applying corrective actions are necessary
considering that every Manager and team members are riding the same boat.
4. ASSESSMENT OF CURRENT CONDITIONS AND PRIORITY ISSUES
The water supply system of Hagonoy has undergone considerable changes from the time it was
originally constructed in 1976 to the formation of Hagonoy Water District to what it is at present.
These changes are clearly presented in Chapter 1. The growth of the Water District by leaps and
bounds and coping with this has become a major challenge to Management and the Board of
Directors.
4.1. Current/Expected Conditions
The matrix on performance indicators presented in Chapter 1 will instantly reveal the very
favorable conditions in the Water District. This is despite the cramped physical
arrangement of the work areas of the Water District. For a period of four decades,
employee morale has been commendable as revealed in the figures presented in the
performance indicators.
Five Year Business Plan (2016-2020) 17 Hagonoy Water District
The improvement in the physical work environment in the Water District is expected to
further elevate morale and enhance efficiency further. This move on the part of
Management to come up with a more wholesome work environment is one of the non-
cash incentives that are implemented in recognition for the high performance levels over
the years.
4.2. Organizational Affiliations
The Management continues to collaborate with other organizations not just in the water
industry but also in civic entities so that healthy organizational alliances are maintained.
Management recognizes the importance of establishing and maintaining networking with
other organizations as this will further enhance social and political acceptability of the
Water District. Hagonoy WD is an active member of BAWD, CLAWD, PAWD, WEAP and
PWWA. Being a member of these organizations, water districts’ internal predicaments with
other government agencies such as BIR and Commission on Audit will be treated with
fairness and cordiality.
4.3. Nature of Workforce and Skills
In order to attain a high level of standard and efficiency, management has been instituting
a strict screening process in the recruitment of manpower. Only qualified people are
allowed to join the workforce as mandated by the Civil Service Commission.
Coping with the fast technological advancement is done by equipping employees with the
necessary training both in-house and in other institutions/organizations.
If there is one common characteristic that is easily noticed in the workforce, it is the high
morale and level of motivation. Employees’ motivation is the key to good performance. It
is for the this reason that HWD keeps on implementing reward programs that will uplift
employee morale and pride in being part of the organization.
4.4. Search for the Most Outstanding Performer
The management is conscious of the importance of employees’ contribution in achieving
company goals. To be able to sustain employee enthusiasm, the management has a
program on “Search for the most outstanding employee of each six division and among
then choose the top performer of the year”. This program was implemented to motivate
employees to embrace the “best-effort” attitude in work.
Five Year Business Plan (2016-2020) 18 Hagonoy Water District
An employee must have served the company for 15, 20, 25, 30, 35 years and so on without
gap. Must be chosen as the best employee of his division and be the best employee among
the best employees chosen in each division. As reward for being the Best Employee of the
Year, the awardee is entitled to cash prize and certificate of appreciation from the
Management and the Board.
4.5. Resource Management and Optimization
The district is able to maintain lower percentage of operating expenses over the total
revenue which means that the district is able to optimize use of its resources at lesser
expenditure. Attaining this does not only mean budgeting. It reflects employees’ attitude
resource use and management. The district likewise manages to have a very high staffing
ratio of 405.
4.6. High Collection Efficiency
As of the end of year 2015, the district had a 98.86% collection ratio which is a product of
HWD’s endless effort to implement and practice programs encouraging concessionaires to
pay water bills on time to prevent inconvenience. Some ingenious policies that had been
adopted to attain high collection efficiency include the following:
Disconnection Policy. The Water District religiously disconnect water service by pulling out
the water meter of concessionaires who fails to pay their two (2) consecutive months
penalized.
7:00am to 5:30pm Collection Time. For practical reasons and in order to enable
concessionaires working in the 8 a.m. to 5 p.m. shift to have time to pay their bills the 7:00
a.m. to 5:30 p.m. collection period has been adopted by Management. This schedule gives
the concessionaires the flexibility to pay water bills without necessarily sneaking out of
their jobs especially to those who are working within and outside Hagonoy. Counters for
settling water bills are likewise open on Saturdays, from 8:00 a.m. to 12:00 n.n. We also
have 5 field bill collectors ready to received payments in their house-to-house distribution
of billing notice and disconnection orders. Moreover, our disconnectors are also mandated
to receive and issue official receipts for those service connections scheduled for
disconnection.
Priority lane for PWD, pregnant, senior citizen has been set up at the ground floor of the
office.
Five Year Business Plan (2016-2020) 19 Hagonoy Water District
5. STRATEGIC GOALS
The five-year business planning period of Hagonoy Water District is formulated with its Mission
Statement in mind with serious consideration on the challenges it is presently comforted with.
These are embodied in the identified strategic goals which serve as guiding light in the attainment
of the world-class image of the Water District.
5.1. Additional water sources to cope with the growing population
To provide the water sources to cope with the 0.60% population growth per year the demand for the water safety and accessibility also increases. This is one of the major considerations of Hagonoy Water District in the establishment of this goal. At present, the existing sources of HWD are capable of meeting the water demand of 27,540 service connections. However, it is projected that within five years, number of service connections will grow. Given this scenario, HWD should address the need for additional water supply.
Groundwater exploitation through deepwells is considered the most suitable source of supply for the future needs of WD. As of December 2015, HWD has fifteen (15) deep wells with a combined discharge capacity of 300 lps.
5.2. Replacement of old existing distribution line (steel pipe to uPVC pipe line)) In line with the goal of HWD to continuously reduce the non-revenue water, HWD has come up with strategy of replacing the 35 years old steel distribution line to new uPVC pipe line. The aim of this strategy is to decrease water losses due to leakages. As the government’s road upgrading projects due to high tide progress, the agency coinciding/replaces its aging distribution line.
With the availability of this facilities and program in Hagonoy Water District within the
five-year planning period, Management is confident that a higher level of efficiency will
further be attained.
5.3. Septage Management Program
The operational objectives of the Septage Management Program are:
1. To provide septage desludging service to all customers of HWD that will reduce
pollution attributed to untreated septage discharge or overflow from households;
Five Year Business Plan (2016-2020) 20 Hagonoy Water District
2. To comply to all existing local and national environmental laws and regulations on
effluent and sludge disposal by construction and operation of efficient treatment
plants and sludge disposal facility; and
3. To improve water quality, sanitation and public health conditions to enhance
economic productivity in the general areas of Hagonoy and its neighboring
municipalities.
5.4. Acquisition of lot
Acquisition of lot adjacent the HWD office building. This lot will be allotted for the drilling of an additional well, construction of warehouse, motor pool, fabrication area, water meter calibration shop and additional parking area.
5.5. Acquisition of Mobile Truck Water tanker
Acquisition of mobile truck water tanker will be used as buck up source of water in case of water interruption. This usually happens during major breakdown of water source.
Water rationing will be very beneficial especially in times of calamities as experienced by the company during the past. This will serve as a contingency measure to augment the need for potable water in times of needs.
6. WATER DEMAND MANAGEMENT ANALYSIS AND WATER SALES FORECAST
A thorough assessment of the water demand of the Water District is a crucial step to the
formulation of the business plan of the utility. It enables Management determine the parameters
that need to be controlled or enhanced to steer the Water District to the path leading to the
attainment of its strategic goals.
6.1 Per Capita Consumption by Class of Customer
Based on the historical data of Water District, per capita consumption has a gradual but
constantly increasing trend. This may be attributed to the improvement in the standard of living in
the municipality as propelled by its rapid urbanization. One noticeable change is the advent of
washing machines which is more water intensive than a manual clothes washing. Another easily
observed development is the proliferation of carwash enterprises and water refilling station which
mushroom all over the area. These are just some of the indicators that trigger the increase in unit
water consumption in the area.
While it is easy to quantify the per capita demand for domestic connections, there is some degree
of difficulty to determine with accuracy the per capita consumption for commercial connections.
This because commercial connections do not have fixed number of people served but rather
Five Year Business Plan (2016-2020) 21 Hagonoy Water District
dependent on the clientele of every commercial enterprise. This varies widely depending on the
nature of the establishment. At any rate, the unit consumptions per use category are presented
below.
Average Unit Consumptions
Domestic
(lpcd)
Commercial
(m3/conn/month)
Bulk
(m3/conn/month)
125 24 105
6.2 Non-Revenue Water
The non-revenue water (NRW) is a major factor contributing to the inefficiency of a water utility.
Recognizing this, the Management of Hagonoy Water District is particularly and rigorously
monitoring the magnitude of its NRW. Based on the monthly data sheet of the Water District,
NRW over the past five years range of 20.97 to 23.75 of water production.
6.3 Forecast of Water Sales
Water sales analysis depend on the projected number of new connections and the demand per
capita for household, commercial entities and public institutions.
6.4 Sources of Supply for the Planning Period
HWD has ground water as possible additional water sources. However, as mentioned earlier the
well fields might approach threshold capacity and exploitation and therefore may necessitate to
obtained additional supply from raw water.
7. ORGANIZATIONAL STRUCTURE AND STAFFING PLAN
7.1 Current Organization and Staffing
Hagonoy Water District’s present category is B, with a total workforce of 68 permanent
employees out of 160 approved plantilla positions by the Department of Budget and
Management. It is comprised of four departments, namely: 1) Office of the General Manager, 2)
Administrative and Finance Department, 3) Commercial Department, and 4) Production and
Engineering Department. The Administrative and Finance Department is subdivided into the
Administrative Division and Finance Division, the Commercial Department into the Customer
Service Division and Customer Accounts Division, and the Production and Engineering Department
Five Year Business Plan (2016-2020) 22 Hagonoy Water District
into the Production Division and Engineering Division. Each of the six divisions is headed by a
Division Manager reporting directly to the Office of the General Manager.
The functional organizational chart of HWD
Engr. CELESTINO S. VENGCO General Manager
DIANNE E. MENDOZA
Admin. Service Assistant / Secretary
GENERAL MANAGER’S OFFICE
CLEMENTE C. IGNACIO
Water Maintenance Man A
DALMACIO DR. PANGANIBAN
Water Maintenace & General
Foreman
JEFFERSON FERNANDEZ Utility Worker
JULIAN P. CASTRO
Bldg. Maintenance & General
Services
Five Year Business Plan (2016-2020) 23 Hagonoy Water District
MA. SALVACION L. BAUTISTA Division Manager B
JOSEFINA L. UMALI Cashier B
MA. RAQUEL DE LEON Acting Cashier
MANUELITO L. VENGCO JR.
Admin. Service Assistant
RESA E. AGBAYANI Procurement Analyst
MARIA ELENA G. FAUSTINO
Admin. Service Assistant
JOSE N. CASTRO JR.
Liaison Officer / Utility Worker
ALEX BRIAN DC. DELA CRUZ
Utility Worker
ADMINISTRATIVE DIVISION
Five Year Business Plan (2016-2020) 24 Hagonoy Water District
REMEDIOS R. OSORIO Division Manager B
EVANGELINE DC. CASTRO Sr. Property / Supply Officer
CECILIA S. SAGUINSIN
Senior Accounting Processor A MARIA CECILIA N. SANCHEZ
Senior Accounting Processor B
FERNANDO M. DELA CRUZ
Storekeeper C
ELENITA L. REYES Senior Accounting Processor B
MARY JANE F. BUNDOC
Accounting Processor
ALBERTO S. SANTOS
Meter Mechanics
FINANCE DIVISION
Five Year Business Plan (2016-2020) 25 Hagonoy Water District
CUSTOMERS SERVICE DIVISION
MICHAEL M. SANTOS Acting Division Manager B
DAMASO P. DELA CRUZ JR. Water Maintenance General Foreman
CESAR C. DEL ROSARIO
Commercial Inspector
DONATO M. SANTOS
Commercial
Inspector
JOSELITO G. CRUZ
Commercial
Inspector
MARIO M. YAMBAO
Meter Reader
FERDINAND BALTAZAR
Meter Reader
HONEY GRACE S. SANTOS
Cusomer Service
Assistant
GEMMA B. TIGLAO
Customer Service
Assistant
MELADY DC BUENSUCESO
Cmer Service Assistant
ARNULFO M. MORALES
Meter Reader
AUGUSTO RAYMUNDO
Plumber
RODOLFO T. BALUYOT
Plumber
GLENN S. MALENAB
Meter Reader
DANILO P. SANTOS
Plumber
Five Year Business Plan (2016-2020) 26 Hagonoy Water District
MA. SOCORRO C. SALVACION Acting Division Manager
ROMEO R. MANALO Cust. Service Asst A. - Supervisor
ROMEO M. MELENDEZ Field Bill Collector
EDNA A. MORALES Supervising Data Encoder
JOSE L. VENGCO
Field Bill Collector
BENJAMIN R. BENEDICTOS
Field Bill Collector
ROMEO CERVANTES JR.
Field Bill Collector
JASON ROM C. BALATBAT
Field Discon. / Recon.
ROMMEL M. IGNACIO
Office Bill Collector
ABIGAIL U. MAGPAYO
Office Bill Collector
PRISCILLA E. URBANO
Office Bill Collector
MAYVEL N. SANTOS Office Bill Collector
MOISES E. SALVADOR Field Discon. / Recon.
JONATHAN A. ESPINOZA
Field Discon. / Recon.
RESTITUTO DJ. BALUYOT
Supervising Data Encoder
KENNETH S. SAGUINSIN
Field Bill Collector
JOSEPH L. TOLENTINO Field Discon. / Recon.
CUSTOMERS ACCOUNTS DIVISION
Five Year Business Plan (2016-2020) 27 Hagonoy Water District
ENGINEERING DIVISION
ALBERTO S. LOPEZ Division Manager
MARY ANN G. MANALO Senior Data Encoder
PETER JOHN G. PANGANIBAN Utility Worker
GREGORIO A. TEODORO
Water Maintenance Foreman
GERONIMO R. SANTOS
Water Maintenance Head
JASON Q. FELIPE
Water Maintenance Man
JAIME V. PASCUAL Water Maintenance Man
LORENZO E. BAUTISTA
Utility Worker
ARTURO PINEDA
Water Maintenance Man
RICARDO M. CASTRO JR.
Senior Water Maintenance
FELIX V. SANTOS
Senior Water Maintenance
MARIO M. RAMIREZ Water Maintenance Man
ADLER M. FAUNDO Water Maintenance Man
RONALDO M. GALANG
Water Maintenance Man
Five Year Business Plan (2016-2020) 28 Hagonoy Water District
PRODUCTION DIVISION
REYNALDO B. PAYONGAYONG Asst. Division Manager
MARY ANN G. MANALO Senior Data Encoder
IRENEO P. YONGCO
Pump Operator
JUN H. LOPEZ
Pump Operator
ALEJANDRO U. DEL ROSARIOS
Senior Pump Operator
ROLANDO F. SANTOS
Pump Operator
FRANCISCO M. ELIGIO
Senior Pump Operator
EDGARDO A. CERVANTES
Pump Operator
FELINO T. VILLANUEVA
Pump Operator
ENRIQUITO P. LIONGSON
Pump Operator
REYNALDO S. CASTRO
Senior Pump Operator
AVELINO I. DELA CRUZ
Pump Operator
ERNESTO DJ ESPINOSA
Pump Operator
ALBERTO S. LOPEZ
Division Manager
Five Year Business Plan (2016-2020) 29 Hagonoy Water District
8. PERFORMANCE IMPROVEMENT PROGRAM TO ACHIEVE STRATEGIC
HWD has its own performance standards. These standards and policies/procedures are clear and
fully understood by all employees. This system helps the district to achieve its goal accomplish its
projects and programs.
Proper human resource management and sound financial utilization is the best key of Hagonoy
Water District in making its dream turn into reality. But we never stop from there, HWD
continuously to live with its mission and that is our commitment to serve with quality and
equipped with practical modern technology in order to be of best service to our consumers. That
is why the management persistently strived to achieve our strategic goals specifically within the
coverage of the business plan. Seminars and trainings will be conducted to educate all employees
regarding our goals and we will work hand in hand for the achievement of our common objective.
9. FIVE-YEAR COST BUDGET FORECAST
9.1 Base Pay
The base pay of the HWD employees are based on the Salary Standardization Law (SSL4)
prescribed by the Department of Budget and Management. Also part of the employee
compensations are the Representation and Travelling Allowances (RATA) for general manager,
and head of division. Likewise they are also entitled to Personal and Economic Relief Allowance
(PERA), Cost of Living Allowance (COLA) and Additional Compensation (ADCOM). Mandatory
benefits such as 13th month pay and other form of monetary reward is also been given to every
employee. The district incorporated the 20% increase (spread in 4 years) provision on the
anticipated SSL4.
9.2 Other Personnel Costs
This includes the employee compensation, premium contributions to GSIS, Maxicare, Pag-IBIG and
Provident Fund. Budget for the trainings and seminar is also being charge to this account.
9.3 Contracted Services
Contracted services are the expenses incurred by the district in securing the security services and
other works which have to be contracted to others, this account also known as Other Outside
Services Employed.
Five Year Business Plan (2016-2020) 30 Hagonoy Water District
9.4 Consumable Expenditures
This expenditure category includes various line items used for operations and maintenance to
include fuels, lubricants, spare/replacement parts, chemicals, tools and other supply related items
as well as services, special repair services and equipment rentals.
9.5 Debt Service
The existing Debt Service of HWD comprises loan payables to LWUA and Land Bank of the
Philippine-Malolos Branch. For the next five (5) years specifically in year 2013, the district will start
paying the principal and interest portion of the EIGHTEEN MILLION (18M) loan from Land Bank
which financed the various water improvement projects and payment of loans from the
HWWMPCI which started 2014. Said loan will have a one year grace period on principal payment.
Principal and interest payment will commence on year 2014.
10 FIVE-YEAR CAPITAL EXPENDITURE AND INVESTMENT FORECAST
To continuously improve and develop the facilities of the district, the management has lined up various capital investments that will intensify its services to the community. Among the major projects, the water system improvements (implementation of parallel pipelines, expansion and replacement program, and replacement of old existing distribution line); acquisition of lot for the drilling of an additional well, construction of warehouse, motor pool, fabrication area, water meter and calibration shop and located at Poblacion Sto. Niño (near HWD office); acquisition of mobile truck water tanker as back up source of water in case of major water interruption; and septage management program.
11 INTERNAL GENERATED CASH
The revenue needs will be based on the collection efficiency as experienced by the district or
solely on internal generated cash (IGC).
Five Year Business Plan (2016-2020) 31 Hagonoy Water District
12 TARIFF POLICY AND STRATEGY
The current water rates of HWD were shown in the table below. Additional 10% penalty charge
will be added to all overdue accounts.
COMMODITY CHARGES
CLASSIFICATION Minimum
Charges
11-20
cum
21-30
cum
31 and up
cum
Residential 127.50 14.28 15.81 17.34
Commercial 225.00 28.56 31.62 34.68
The district also offers installment basis for new connections, wherein applicants are only required
to pay FIVE HUNDRED PESOS ONLY (P500.00) as down payment and the balance amounting to
ONE THOUSAND PESOS (P1,000.00) will be payable in three (3) consecutive months without
interest. The monthly amortization will appear in his billing notice under the account “others”.
Aside from the water sales, HWD generates revenue from other fees and charges such as
reconnection fee, water meter maintenance fee, “abang” fee, tampering penalties violations,
unbilled water fees.
One of the factors that contribute to very high collection efficiency is due to the fact that HWD is
the only local water district in the province that has field bill collector.