H-GAC 2019 Webinar/Workshop Series
Preparedness for Debris Operations
WEBINAR DATE:MAY 15, 2019
TIME:10:00 A.M. TO 11:30 A.M.
2
H-GAC 2019 Webinar/Workshop Series
Date Event TopicsMay 15, 2019 Webinar Debris Management Preparedness.July 30, 2019 Webinar Wildfire, Tornadoes, Terrorism and
Other Debris Generating Incidents.August 16. 2019 Workshop Disaster debris affects on landfills.
Recommendations from the Governor's Commission to Rebuild Texas.Lessons learned and trends.Changes to regulations and guidance.
3
Agenda
• Identification and evaluation of debris management sites
• Identification of priority facilities and roads for road clearing
• Establishment of prepositioned contracts for debris hauling and monitoring services
• Development and maintenance of disaster debris management plans
4
Part 1: Identification and Evaluation of Temporary Debris Management Sites (DMS)
5
• Temporarily store, process, and reduce debris before it is transported to a final disposal facility.
DMS Purpose
6
• Publicly owned versus privately owned property• 5+ acres • Proximity to high population density• Ease of ingress and egress• Reduction method to be used• Proximity to natural running water or water
wells• Adherence to local, state, and federal
regulations
Considerations in Selecting a DMS
7
• Must send request for approval form to the Texas Commission on Environmental Quality (TCEQ) Regional Office prior to use of a site as a TDMS.
State Approval of DMS
8
• Prepare DMS based on concentration of debris:If necessary, get any
needed property use agreements.Get TCEQ approval.Photograph the site.Record physical features.Conduct a historical
evaluation.If necessary, collect soil
and water samples.
Preparation of a DMS
9
Reduction Methods
10
10
Reduction via Open Burning
11
11
Reduction via Air-Curtain Incineration
12
Reduction via Grinding
13
Removal of Refrigerants from White Goods Prior to Recycling
14
Construction and Demolition Storing and Reduction
15
Site Organization
1616
DMS Operations
17
17
Debris Diverted from Waste Stream
18
Restore Site to Condition Prior to Use as a DMS
• Haul out reduced and processed debris.• Remove processing equipment, storage tanks,
protection berms, and other structures built on the site.
• Take samples at the same locations as those of the initial assessment.
• Remediate any contamination that may have taken place during TDMS operations.
19
DMS Prep and Site Restoration Costs
• Understand who is responsible for the costs of DMS prep and restoration.
• Costs are reimbursable to the jurisdiction.• FEMA may not reimburse the jurisdiction if the
debris hauler contract states the debris hauler is responsible for the costs of the prep and restoration of the DMS.
20
Part 2: Creation of a Priority Facilities and Roads List
21
Purpose for the Priority Facilities and Roads List
• Serves as a tool to aid in prioritizing roads for emergency road clearing and debris collection activities following a debris-generating incident.
22
Priority Roads• Priority roads are deemed as such based on
many considerations, including:Size Proximity to adjacent citizen populations Critical facility locations Ingress/egress capabilities for the community
23
Potential Critical Facilities• Hospitals• EMS, Fire, and Police Stations• Nursing Facilities• Emergency Operations Centers• Water/Wastewater Treatment
Facilities• Electrical Utility Facilities• Communications Facilities• Public Works Facilities• Shelters
24
Maintaining the List
• Verify the list annually.• Provide the list to jurisdiction staff responsible
for road clearing and/or to the debris contractor.
• Back up the list, along with jurisdictional boundaries, to a USB drive or other portable device to ensure it will be available in the event of a disaster.
25
Part 3: Prepositioned Contracts For Debris Hauling and Monitoring Services
26
The Value of Prepositioned Contracts
• Identifying prequalified contractors and contracting needs in advance can save time and money during disaster response efforts.
• After a major disaster, multiple communities may be competing for the same resources, which may be limited.
27
Available resources
27
• FEMA Established the Procurement Disaster Assistance Team (PDAT) to provide assistance to grantees and subgrantees after disasters
• Training is available• Review of contracts may be
requested– CMAR– Cooperative Purchasing– Single Source
28
Getting Started• Applicants must comply with Federal
procurement standards as a condition of receiving Public Assistance (PA) funding for contract costs for eligible work.
• Procurement standards can be found in 2 CFR 200.
• Solicit a request for proposals for disaster debris services for specific contract provisions.
29
Solicitation for Prequalified Contractors Should Include:
• Adequately defined scope of work
• All potential debris types• Anticipated haul distances• Potential size of debris events • Hourly labor, equipment, and
material price schedule• Performance bond
requirements
30
Qualify Bidders • Licenses• Financial stability• Proof of insurance• Bonding capability• Description of related experience and capabilities,
including total verified cubic yards removed and processed
• References, including jurisdiction name, point of contact, email address, and phone number
• Description of health and safety plan, including operation plan at debris management site(s)
31
• Primary types of compensation• Unit pricing• Time & Materials• Lump Sum
• Scopes of work will dictate your contract• Must demonstrate you have control of costs
• Not to exceed• Reconciliation/Audit of documentation
• May request retainage
ContractorCompensation
31
32
Check for Disbarred Contractors
• Contractors that have been declared debarred by the Office of Federal Contract Compliance Programs (OFCCP) should not be considered.
• A complete list of federally disbarred contractors can be found in the System for Award Management (SAM) dataset at www.sam.gov.
33
Contracting Procedures
• Ensure compliance with the jurisdiction’s procurement procedures.
• Ensure compliance with applicable state and local procurement laws and regulations.
• Ensure compliance with federal procurement laws and standards identified in 2 CFR 200.
34
Contracting Procedures
• Ensure competition.• Provide a clear and definitive scope of work.• Develop a cost analysis to demonstrate cost
reasonableness for any contract or contract modification where price competition is lacking.
• For mileage based contracts evaluate contracts based on mileage categories.
35
Contracting Procedures• Ensure opportunities for minority-owned and
women-owned businesses and firms whenever possible.
• Document the process and rationale the jurisdiction followed in making procurement decisions.
36
Review and Document the Process
• Conduct a review of the procurement process and any potential contracts to be awarded to ensure compliance with all federal, state, and local requirements.
• Establish procedures to address protests and disputes related to contract awards.
• Compile all documentation related to the procurement and file in a secure location that can be accessed for future review.
37
Major Compliance Issues
• No cost or price analysis• Inadequate (or no) competition• Failure to pursue efforts re socioeconomic
contracting• Ineligible contract type• Inadequate documentation and/or contracting
documents• Missing mandatory clauses• Missing information on pricing
38
Part 4: Development and Maintenance of Disaster Debris Management Plans
39
• Provide the organizational structure, guidance, and standardized procedures for the clearance, removal, and disposal of debris caused by a major debris-generating event.
Objectives of a DDMP
40
Objectives of a DDMP
• Provide debris estimates for key hazards to aid in planning.
41
• Outline roles and responsibilities of city, county, state, federal, volunteer, and private agencies with a role in debris management operations.
Objectives of a DDMP
• Public Works• Transportation• Code Enforcement• Finance• Animal Control• Emergency
Management• Public Health
• Public Information• Parks • Administration• Debris Contractors• Debris Monitors• TDEM• TCEQ• TxDOT
• FEMA• Federal Highway
Administration• Office of
Inspector General• U.S. Army Corps
of Engineers• Natural Resources
Conservation Service
42
• Provide strategies for public information.
Objectives of a DDMP
43
• Identify health and safety processes.
Objectives of a DDMP
44
• Identify local resources that can be used in debris management operations.
Objectives of a DDMP
45
• Provide guidance for special operations, such as private property debris removal and dangerous trees, to ensure compliance with PA requirements.
Objectives of a DDMP
46
• Identify environmental and other regulations that must be considered in conducting debris management operations.
Objectives of a DDMP
• Local Regulations• National Environmental
Policy Act • Resource Conservation
and Recovery Act• National Historic
Preservation Act• Executive Order 12898,
Environmental Justice
• Endangered Species Act• Clean Water Act• Clean Air Act• National Emission Standard
for Hazardous Air Pollutants
• Executive Order 11990, Protection of Wetlands
47
• Provide direction in documenting labor hours, activities, equipment use, and expenses so the affected jurisdiction can receive the maximum reimbursement to which they are allowed. Failure to properly document costs can result in the jurisdiction being denied reimbursed for those expenses.
Objectives of a DDMP
48
• Having an approved DDMP and a pre-qualified debris removal contractor will allow for an additional 2% increase in the Federal share of debris-related recovery costs for the first 90-days of a debris removal operation following a disaster event.
Benefit of a DDMP
49
12 Key Elements of a DDMP
1. Debris Management Plan Overview2. Events and Assumptions3. Debris Collection and Removal4. Temporary Debris Management
Sites and Disposal Locations5. Debris Removal on Private Property6. Use and Procurement of Contracted
Services
50
12 Key Elements of a DDMP
7. Use of Force Account Labor8. Monitoring of Debris Operations9. Health and Safety Requirements10.Environmental Considerations and Other
Regulatory Requirements11.Public Information12.Identification of Debris Removal Contractors
51
Planning Processes• Form a planning team consisting
of departments and stakeholders with a role in debris operations.
• Assume worst-case scenario.• Identify key resources.• Examine regulatory issues and
considerations.• Review existing emergency plans.• Develop a process for maintaining
and updating the DDMP.
52
Case Study• Neither Puerto Rico nor the U.S. Virgin Islands
had comprehensive debris management plans in place before Hurricanes Irma and Maria. As a result:• Illegal dumping sites were created.• Debris accumulated in sensitive areas, such as
floodplains. • Issues with FEMA reimbursement for debris
management costs occurred.
53
Conduct Regular Reviews and Updates of the DDMP
• Update capacity information for waste management facilities, including recycling facilities.
• Verify the continued viability of pre-determined temporary debris management sites.
• Add new reuse, recycling, and composting opportunities.
• Update contact information for state, local, and federal officials and waste management facilities.
54
Conduct Regular Reviews and Updates of the DDMP
• Incorporate new contracts or agreements. • Document changes in available equipment and
other resources. • Incorporate new residential and commercial
developments. • Change debris types and quantities to
correspond to changes in the community’s character and building stock.
55
QUESTIONS?
56
Thank You!• Next Webinar – July 30th
Wildfire, Tornadoes, Terrorism and Other Debris Generating Incidents.