Guillermo Aranda-Mena
-
Upload
guillermo-aranda-mena -
Category
Documents
-
view
220 -
download
0
description
Transcript of Guillermo Aranda-Mena
National Guidelines for Digital Modelling
DR GUILLERMO ARANDA-MENA THE PPP CLUB - LECTURE SERIES 2012
15 MARCH 2012
Na
tion
al G
uid
elin
es fo
r Dig
ital M
od
ellin
g
ix
The project participants
Industry
Government
Research
Our thanks go to all those who attended and contributed to the success of this publication through their participation in the workshops held in Sydney, Melbourne, Brisbane and Perth.
Construction Innovation also wishes to thank and acknowledge Colleen Foelz (Construction Innovation and edenink) for managing the production of this publication, as well as Sue Ferguson (itzdesign) and Gail Cartwright (wordwright) for their design and editing respectively.
DR GUILLERMO ARANDA-MENA THE PPP CLUB - LECTURE SERIES 2012
15 MARCH 2012
Foreword
These National Guidelines and Case Studies for Digital Modelling are the outcomes from one of a number of Building Information Modelling (BIM)-related projects undertaken by the CRC for Construction Innovation. Since the CRC opened its doors in 2001, the industry has seen a rapid increase in interest in BIM, and widening adoption.
These guidelines and case studies are thus very timely, as the industry moves to model-based working and starts to share models in a new context called integrated practice. Governments, both federal and state, and in New Zealand are starting to outline the role they might take, so that in contrast to the adoption of 2D CAD in the early 90s, we ensure that a national, industry-wide benefit results from this new paradigm of working.
Section 1 of the guidelines give us an overview of BIM: how it affects our current mode of working, what we need to do to move to fully collaborative model-based facility development. The role of open standards such as IFC is described as a mechanism to support new processes, and make the extensive design and construction information available to asset operators and managers. Digital collaboration modes, types of models, levels of detail, object properties and model management complete this section. It will be relevant for owners, managers and project leaders as well as direct users of BIM.
Section 2 provides recommendations and guides for key areas of model creation and development, and the move to simulation and performance measurement. These are the more practical parts of the guidelines developed for design professionals, BIM managers, technical staff and ‘in the field’ workers.
The guidelines are supported by six case studies including a summary of lessons learnt about implementing BIM in Australian building projects.
A key aspect of these publications is the identification of a number of important industry actions: the need for BIM-compatible product information and a national context for classifying product data; the need for an industry agreement and setting process-for-process definition; and finally, the need to ensure a national standard for sharing data between all of the participants in the facility-development process.
John Mitchell David ParkenChairman, CEO,buildingSMART Australian Institute of Australasia Architects
Na
tion
al G
uid
elin
es fo
r Dig
ital M
od
ellin
g
iii
buildingSMARTInternational Alliance for Interoperability
Na
tio
na
l G
uid
elin
es f
or
Dig
ita
l M
od
elli
ng
viii
Acknowledgments
The CRC for Construction Innovation provided the major funding, industry research leadership and coordinated the development of National Guidelines for Digital Modelling and accompanying Case Studies.
The Construction Innovation project team members are:
Project Leader Tom Fussell (Project Services Queensland Department of Housing and Works)
Project Manager National Digital Modelling Guidelines — Scott Beazley (QUT)
Project Manager Case Studies — Guillermo Aranda-Mena (RMIT University)
Researchers: Guillermo Aranda-Mena, Agustin Chevez, John Crawford, Bilal Succar (RMIT University)
John Hainsworth —Arup Australasia Simon Hardy — Bovis Lend Lease Shane McAtee, Garry McCann, Richard Rizzalli — Mirvac Paul Akhurst , Chris Linning — Sydney Opera House David Marchant — Woods Bagot
Joyce Law, Phillip Lord, Dean Morse — Brisbane City Council Paul Crapper — Building Commission John Spathonis — Qld Dept of Main Roads
Scott Beazley, Robin Drogemuller, Stephan Gard, David Nielsen — Queensland University of Technology Guillermo Aranda-Mena, Ron Wakefield — RMIT
Integrated Digital Modelling Taskforce
Chair: Andrew Gutteridge (AIA)
Representatives from the following organisations served on the taskforce.
Association of Consulting Engineers AustraliaAustralian Institute of ArchitectsAustralian Institute of BuildingAustralian Institute of Quantity SurveyorsBuildingSMART Australasia Facility Management Association of Australia
THE BUSINESS VALUE OF BIMGetting Building Information Modeling to the Bottom Line
Premier Corporate PartnerGovernment PremierPartner
Corporate Contributor Sponsors
Association Premier Partners
3
Table of Contents
ImagescourtesyofMortensonConstruction
IntroductionSmartMarket Report Executive Summary .........................4
Overall Value of BIM .....................................................................6Case Study: Research 2........................................................................10Industry Issue: Impact of BIM on Productivity ..................................12
Industry Issue: Return on Investment in BIM ....................................13
Internal Business Value of BIM............................................14
Industry Issue: Impact of BIM on Marketing.....................................18
Case Study: Texas A&M Health Science Center.............................19
Project Value of BIM...................................................................20Case Study: Sutter Health Medical Center ......................................24
Industry Issue: BIM and Green Building............................................26
Case Study: Virtual Mock-Ups .............................................................27
Player Value of BIM.....................................................................28Software Industry Perspective .............................................................35
Adoption of BIM............................................................................36Case Study: Department of Energy....................................................43
Industry Issue: Opportunities and Obstacles for Engineers .........44Case Study: BIM on Heavy Civil Projects.........................................46
Conclusions.....................................................................................48
Resources ........................................................................................50
Methodology ...................................................................................50
Cover images provided byBryan Christie Design
4
Do Not Measure Measure
Negative
Break even
Less than 10%
10-25%
25-50%
50-100%
Over 100%
0
20
40
60
80
100
Perceived ROI Versus Formally Measured ROI
21%
26%
17%
17%
10%3%6%
14%
14%
15%
25%
13%
10%
9%
SmartMarket ReportExecutive Summary
Better Than Expected ValueReturn on investment can be calcu-lated in various ways, but those whotake a data-driven approach see moreupside to BIM. Users who formallymeasure their ROI report better re-turns than those who estimate ROIbased on perception.
� Seven in ten BIM users whomeasure ROI see positive returns,compared to half of those who onlygo by their perception of value.
� One in five BIM users who meas-ure ROI see returns greater than50%—double the perceived value.
Competitive AdvantageBIM is seen as a way to get a leg upon the competition. This is particularlytrue among less experienced userswho are promoting a new service.
� Marketing new business to newclients is the top rated businessbenefit of BIM.
� Half of users say offering newservices with BIM is a significantbusiness benefit.
� Two-thirds of users say BIM’s abilityto help a companymaintain repeatbusiness with past clients bringsat least a moderate level of value.
Improved ProductivityBIM creates efficiencies. Users realizesome of the greatest value of BIMthrough its potential to cut down onrework, such as rekeying informationinto models or making changes in thefield. As users become more proficient,the opportunities to improve productiv-ity are more pronounced.
� Reducing rework is the highest-rated business benefit amongexperts. Four in five experts sayit brings high to very high value,compared to 23% of beginners.
� The potential of BIM to improveproductivity is ranked by architectsas the top way to improve their returnon investment in the technology.
� Reduced conflicts and changesduring construction are amongthe top rated ways engineers sayBIM adds value to a project.
� Clash detection and avoidingrework are the top rated ways own-ers say BIM saves time and money.
BIM DefinedFor purposes of this report, McGraw-Hill Construction defines BIM as: Theprocess of creating and using digi-tal models for design, constructionand/or operations of projects.
Reaping Higher Returns During Lean TimesEven as the design and construction industry confronts a down economy, most BIM users are seeing positive payback fromtheir use of the technology, according to McGraw-Hill Construction research. Users gain bankable benefits that enhanceproductivity, improve their ability to integrate teams and give them an edge on the competition. The value from BIM growsas users gain experience, offering them an opportunity to reap greater returns even during an economic recession.
Key Findings
� Two-thirds of BIM users say they see positive ROI on their overall investment in BIM.
� 87% of expert users are experiencing positive ROI with BIM.
� 93% of BIM users believe there is potential to gain more value from BIM in the future.
Source: McGraw-Hill Construction, 2009
41
Challenges to AdoptionBeyond client demand, non-users see challenges that are of moderate to lesser con-cern when considering whether to adopt BIM. As a new technology, dealing withcosts and training issues have been the greatest hurdles on the path toadoption.
� Haven’t had sufficient time to evaluate BIM:With construction running atrecord highs in recent years, many firms had been too focused on their existingprojects to consider testing new methods. In light of the recent slowdown in newconstruction, firms may find this is not a significant issue moving forward.
� Software/hardware upgrades too expensive. Architects and engineers aremost likely to believe this, which could reflect the fact that they generally bring inlower revenues than contractors.
� Functionality doesn’t apply well enough to what we do. Engineers are mostlikely to believe this, which illustrates a belief that BIM is not addressing theirpractice-related needs.
� Insufficient BIM-compatible content available for my needs. Owners rankthis among their top reasons for not implementing BIM, which could indicate thatthey see BIM as more relevant to the work of other team members.
Most Important Obstacles to BIM Adoption
67%
49%
41%
35%
33%
Not enough demand from clientsand/or other firms on projects
Haven’t had sufficient timeto evaluate it
Software too expensive
Functionality doesn’t apply wellenough to what we do
Required hardware upgradestoo expensive
Very High/High
Issues With Little Impact on AdoptionSome issues that have been identified by users as challenging are not seen as signif-icant barriers to adoption by non-users. At least half of non-users say these factorshave little to no influence on their decision not to adopt BIM:
� Concerns about insurance/liability: 64%
� Current methods we use are better: 62%
� Poor interoperability with CAD applications: 54%
� Software too difficult to use: 51%
� Insufficient training available: 50%
Source: McGraw-Hill Construction, 2009
Importance of BIMin 5 Years
0
20
40
60
80
100
No importance
Low importance
Moderate importance
High importance
Very high importance
3%16%
39%
31%
11%
Source: McGraw-Hill Construction, 2009
Upbeat Future OutlookAbout two in five non-users (42%)believe that BIM will be highly or veryhighly important to the industry infive years. Only a small group of them(13%) say they either have no interest inusing it, or have tried it and decided notto use it again. The vast majority areopen to exploring it.
Evaluating factors that would promptnon-users to adopt, client requirementranks as the most important. Two-thirdssay they don’t see enough demand fromclients yet. However, 55% of ownerssay that BIM will be highly or very highlyimportant to the industry in five years –more than any of the other team mem-bers surveyed. If owners see BIM asimportant and can push it as a require-ment, more adoption will follow. (SeeClient Demand for BIM on page 39).
Believing in the cost effectiveness ofBIM ranked as the second most impor-tant factor that would encourage adop-tion. And when asked about reasons fordelaying adoption, concerns about BIM’scost and it’s effectiveness on smallerprojects are the top two reasons given.Six in ten (59%) non-users believe thatBIM seems less efficient for smallerprojects, while 54% list cost required asa limiting factor. Firms that focus onsmaller jobs need to understand BIM’svalue in that context in order to makethe investment.
National Guidelines for Digital Modelling
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
Dis
cip
line
mo
de
lling
, an
aly
sis
an
d s
imu
latio
n
41
- Electrical engineer: electrical pits in slabs, electrical cable ducts and conduits in slabs
- Civil engineer: retaining wall layout, set-out from architectural model, extra properties added to structural objects, structural connection rules and relationships: beam to beam, beam to column, wall to column, beam to wall, slab to wall, columns, beams, slabs, braces, walls, footings, piers, piles, trusses, loading for functions, autocheck for member support. Structural analysis model is not normally exchanged but used for investigation of structural options
Data exported to architectural model of adjusted sizes for:
- interference checking of 3D geometry
- revisions tracked
- auto connection of analytical and physical models.
Figure 3.5 Structural model of 8 Chifley Square
(Image courtesy of Arup)
Phases 4 and 5 – Contract documents and construction
- Fabrication and construction model is used for material procurement; fabrication design and details; quantity take-off and estimating; scheduling of construction sequence; tracking of elements, with use of RFID and barcoding; transportation, site handling; finishing/QA, inspections and approvals
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
Dis
cip
line
mo
de
lling
, an
aly
sis
an
d s
imu
latio
n
39
Figure 3.3 Visualisation model of 8 Chifley Square
(Image courtesy of Mirvac)
3.2.4 Phases 3 and 4 – Developed design and contract document BIM
- Material information linked to spaces through space number and name, also room painting, and other specifications
- Building elements with type information as per building specification may have specific supplier
- Each storey modelled separately, thus multi-storey walls and spaces modelled separately on each storey
Required information content:
- Elements of the building: ground gloor, ground floor slabs, structural frame, load-bearing walls, columns, beams, floor slabs, attic floor slabs, structure frame stairs, facades, external walls, windows, external doors, external decks, balconies, canopies, roofs, roof sub-
structures, roofing, glass roofs, skylights, hatches
- Elements of internal space: space dividers, partitions, glass partitions, balustrades, internal doors, specific doors, space stairs, suspended ceilings, standard fittings, specific fittings, standard machine and devices
Modelling of building objects
- Walls to be modelled using wall tool from slab to slab to storey heights, with internal and external walls distinguished. Walls and spaces to be related. Walls of multiple storey height modelled separately for each storey
- Doors and windows to be modelled using door or window tool, with type and fittings information, connected to walls. Consistent and stated dimensioning to either frames or openings. Doors and windows associated to spaces and changed when either edited
- Glass and curtain walls. Solid wall that hosts glass or curtain walls or facades must be modelled first, then doors and windows added. There should be no gaps between host wall and openings. Multiple storey height curtain walls modelled by storey with appropriate openings each storey
- Slabs (ground floor, floor and attic floor) to be modelled using slab tool. The joining of slabs to walls modelled so that slab ends on surface of load-bearing wall for consistent data for quantity take-off and cost calculation. Floors modelled to extend to the inner surface of the external wall
- Roofs, beams, stairs and columns to be modelled using correct tools
- Columns modelled by outer dimensions including surface structure
Information required by architect from other disciplines:
- Civil engineer: platforms, roadways, parking, ground levels, cut and fill, site drainage
- Mechanical engineer: plant layout outlines, vents, exhausts, plant, ductwork, air ducts, air returns, intakes, penetrations
- Electrical, fire and data engineers: cables, penetrations, external lighting, distribution points on site plan, distribution point on floor plan, electrical symbols on floor and ceiling
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
Dr. Guillermo Aranda-Mena. RMIT Melbourne. Innovation in the Built Environment Academy - LONDON - 2011
Dr Guillermo Aranda-Mena © 2011 6
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
CIFECENTER FOR INTEGRATED FACILITY ENGINEERING
Relationships Between Project Complexity and Communication
By
Reid Senescu, Guillermo Aranda-Mena, and John Haymaker
CIFE Technical Report #TR196 January 2011
STANFORD UNIVERSITY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
The Relationship Between Product Organization Process Complexity
and Communication Challenges Reid R. Senescu, Guillermo Aranda-Mena, John R. Haymaker
Dr Guillermo Aranda-Mena © 2011 12
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
217
Figure!65:!Moving!between!a!parametric!model!to!structural!analysis!and!the!comparison!
of!!performative!aspects!from!multiple!design!options,!Source:!Author!and!Arup!!
5.1.3. Optioneering across disciplines
My research in building practice with Arup specialists suggests that processes
guided though optioneering do not necessarily need to consider design-criteria
across multiple disciplines. Optioneering is well suited to address multi-criteria
optimisation within the boundaries of a single, or a selected few discipline. At the
same time, I contend that the benefits offered through optioneering in the context
of building design are particularly relevant when applied across several disciplines.
Work on the Rectangular Pitch Stadium project at Arup revealed that optioneering
can facilitate lateral thinking between design professions. In doing so, a network
of connections can be established across disciplines that is based on the specific
requirements of design performance. The configuration of the network can vary
depending on the required evaluation between a number of participants at a given
point in the collaborative effort. The scenario described in Figure 66 is an example
showing a network of collaborating professions who are laterally interconnected.
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
198
Table!1:!Summary!of!
topics!describing!
characteristics!of!
acoustic!engineering!!
topic ACOUSTIC
Primary concern in the early design stages
room sizing adjacencies noise levels type of interior finishes types of room volumes
Type of performance indicators in early design stages
reverberation times noise cancellation room acoustic targets
Measurements and units
sound intensity (W/m2) reverberation (RT60) frequency (hertz) sound pressure (dB)
Awareness of cost implications for design changes
More information desired
Feedback mostly required from others
architectural: building shape and volume façades: cladding material interior: finishes, material usage
Type of geometrical entity used for performance analysis and representation
Modeling tolerance Approximately 400mm, depending on frequency level that is investigated
Types of (geometric) modeling required
auralisation acoustic response reverberation
Ratio between group decision-making sole investigation Preferred media to pass on information to others
Auralisation reports combining text-based and visual means
Preferred media for receiving information from others
2D plans and sections charts, maps, graphs reports combining text- based and visual means verbal explanation
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
199
Table!2:!Summary!of!
topics!describing!
characteristics!of!
architectural!design!!
topic ARCHITECTURE
Primary concern in the early design stages
fulfilling the program design aesthetics functionality spatial synthesis cultural relevance ........
Type of performance indicators in early design stages
depending on local -building-codes net to gross ratio massing budget compliance
Measurements and units
Area (m2) cost per m2 ($/m2) height/length (m)
Awareness of cost implications for design changes
More information desired
Feedback mostly required from others
all/QS: basic costing structures: grid, sizing environmental: daylight mechanical: service zone requirements
Type of geometrical entity used for performance analysis and representation
Modeling tolerance Building: approx. 50 -100 mm Urban: 1000-2000 mm
Types of (geometric) modeling required
2D/3D visualisation massing, overshading surface interior/exterior
Ratio between group decision-making sole investigation Preferred media to pass on information to others
3D digital models 3D physical models hand-sketches
Preferred media for receiving information from others
charts, maps, graphs 3D digital model section with analysis results exemplary photographs 3D digital models (ideally shared)
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
200
Table!3:!Summary!of!
topics!describing!
characteristics!of!
environmental!
sustainable!design!!
topic ENVIRONMENTAL
Primary concern in the early design stages
sustainability initiatives carbon footprint / CO2 resourcefulness, lifecycle cost Green Star/LEED/BREEAM
Type of performance indicators in early design stages
Energy use, Water use Carbon output Thermal transmittance, Lighting demand
Measurements and units
Daylight (lx) skylight glare (% - index) emission (CO2) .......
Awareness of cost implications for design changes
More information desired
Feedback mostly required from others
mechanical: energy efficiency façades: glazing type fire: zoning requirements architect: massing
Type of geometrical entity used for performance analysis and representation
Modeling tolerance Walls: 500mm Small scale elements: 200mm
Types of (geometric) modeling required
life-cycle analysis lighting analysis fluid dynamics
Ratio between group decision-making sole investigation
Preferred media to pass on information to others
charts, maps, tables, 3D digital model section with analysis results mapped on graphically hand-sketches
Preferred media for
receiving information
from others:
3D digital models, 2D plans and
sections, hand-sketches, charts, maps,
graphs, reports combining text- based
and visual means
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
Dominik Holzer, PhD
Dominik Holzer, PhD
A PROPOSED FRAMEWORK TO INVESTIGATE BUILDING INFORMATION MODELLING THROUGH KNOWLEDGE ELICITATION AND VISUAL MODELS Bilal Succar, Willy Sher, University of Newcastle and Guillermo Aranda-Mena, RMIT AUBEA 2007
A PROPOSED FRAMEWORK TO INVESTIGATE BUILDING INFORMATION MODELLING THROUGH KNOWLEDGE ELICITATION AND VISUAL MODELS Bilal Succar, Willy Sher, University of Newcastle and Guillermo Aranda-Mena, RMIT AUBEA 2007
Dr. Guillermo Aranda-Mena. RMIT Melbourne. Presentation to the Faculty of Architecture, TU Delft, NL 9.Dec.2010
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS BUILDING
SOUTHERN CROSS STATION AUTHORITY
project 227 YARDMASTERS
date 31.03.2006Sketch Design
BRACED (TIED) IN ROOF PLANE
30 Panels : 3200 x 10500
Standardised fast erection sequence
Structure / Enclosure
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS BUILDING
SOUTHERN CROSS STATION AUTHORITY
project 227 YARDMASTERS
date 31.03.2006Sketch Design
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS BUILDING
SOUTHERN CROSS STATION AUTHORITY
project 227 YARDMASTERS
date 31.03.2006Sketch Design
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS BUILDING
SOUTHERN CROSS STATION AUTHORITY
project 227 YARDMASTERS
date 31.03.2006Sketch Design
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS BUILDING
SOUTHERN CROSS STATION AUTHORITY
project 227 YARDMASTERS
date 31.03.2006Sketch Design
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERSYARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERSYARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERSYARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
Thoroughly Unscientific Diagram Representing Building Costs
Budget$ Overrun
Material Labour / Process Risk / Contingency
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
Thoroughly Unscientific Diagram Representing Building Costs
Budget$ Overrun
Material Labour / Process Risk / Contingency
YARDMASTERS
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
Carlton Brewery UNITED - Consultant Brief Summary
Basement 5+
Basement 5+ Plant
Basement 4
Basement 4 Plant
Basement 3
Basement 3 Plant
Basement 2
Basement 2 Plant
Basement 1
Basement 1 Plant
Basement 1 Loading
Basement 1 Pub. Circ.
Lower Ground (Below
Ground)
Lower Ground Plant
Lower Gnd Pub. Circ.
Lower Ground (Above
Ground GFA)
Ground (GFA)
Ground (Non-GFA)
Level 1
Level 2
Level 3
Level 4
Level 5
Level 6
Level 7
Level 8
Level 9
Level 10
Level 11
Level 12
Level 13
Level 14
Level 15
Level 16
Level 17
Level 18
Level 19
Level 20
Level 21
Level 22
Level 22 Plant
Level 23
Level 24
Level 25
Level 26
Level 27
Level 28
Level 29
Level 30
Level 31
Level 32
TOTALS
Level
Apartments m2/No. 85 m2 171
Car Spaces 0
GFA % Efficiency NLA/NSA
7,234
521
542
32
85
85
85
169
177
85
85
85
1,903 85% 1,617
1,903 85% 1,617
1,903 85% 1,617
1,903 85% 1,617
1,903 85% 1,617
1,903 85% 1,617
1,903 85% 1,617
1,903 85% 1,617
1,903 85% 1,617
26,309 55% 14,556
Castlemaine (Building 1)
UNITED - Consultant Brief - Levels 9:29 AM 11/12/2008
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
THE BREWERYTHE BREWERY
IBEA LONDON 7-9 October 2011 Dr Guillermo Aranda-Mena RMIT MELBOURNE
17
Construction SegmentationKey Customers
13“MacLeamy Curve” Patrick MacLeamy CEO
Home About RMIT Contact All contacts Staff by name A
Dr Guillermo Aranda-Mena
Dr Guillermo Aranda-Mena Guillermo is currently a Senior Lecturer in Property, Construction and Project Management at RMIT University, Melbourne, Australia. He holds a PhD in Construction Management and Engineering from The University of Reading and a Masters of Science in European Construction Engineering from Loughborough University of Technology, both in the United Kingdom. In 2003 Guillermo was appointed Post Doctoral Research Fellow at the University of Newcastle, Australia, working on a Cooperative Research Centre for Construction Innovation (CRC-CI) research project in Building Information Modelling (BIM) in collaboration with the Common Wealth Scientific and Industrial Research Organisation (CSIRO), Ove Arup and Woods Bagot Architects. He has been principal investigator of four CRC-CI research projects including ‘Business Drivers for BIM’, ‘Mobilising Construction’, ‘eBusiness Adoption in Construction’ and ‘Automated BIM Estimator’. He is currently RMIT Project Leader for the CRC-CI BIM National Guidelines and Case Studies.
He is currently supervising various Masters Theses and two PhDs. Guillermo is a Conjoint Academic to the Singapore Institute of Management, Singapore and the University of Newcastle, Australia.
[Next: Publications]
Position Senior Lecturer
School / Work Unit
Property Const & Project Mgt
Contact Details +(61 3) 9925 9512
Location Building: 8 Level: 8 Room: 68
City Campus
College/Portfolio Design & Social Context
EXPLORE
Programs & courses
Future students International students How to apply Entrance requirements Fees Scholarships
Students
Login to myRMIT Study resources Administration Student services Get involved
Research
Focus areas Research Institutes Postgraduate programs Partnerships Fellowships Publications
Industry
Workforce development Work placements R & D consultancy Employing graduates
Alumni
News Events Special offers Giving to RMIT
About RMIT
Learning & teaching Colleges & schools Campuses & maps Employment News
Copyright © 2012 RMIT University Disclaimer Privacy Accessibility Website feedback ABN 49 781 030 034 CRICOS provider number: 00122A Print version Open Universities Australia
INTERACT WITH RMIT
Page 1 of 1RMIT - Aranda-Mena, Dr. Guillermo
15/03/2012http://www.rmit.edu.au/staff/guillermo