GUIDE TO IEEE 1547-2018 - TechAdvantage · 2019-03-21 · Defined in IEEE 1547-2018 Authority may...
Transcript of GUIDE TO IEEE 1547-2018 - TechAdvantage · 2019-03-21 · Defined in IEEE 1547-2018 Authority may...
Interconnecting Distributed Resources with Electric Power Systems (2003)
16 pp
Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power
Systems Interfaces (2018)
➢Starting Point for Applying
Standard
➢Idea From T&D MAG
➢Draft Completed in September
➢Delayed-IEEE Copyright Issues➢NRECA Guide to IEEE 1547-2018 ➢IEEE Standards: 1547-2018
➢10 MVA Limit is Gone
➢Voltage Regulation Capability
➢Interoperability Capability Required for All DER
➢Clause on Intentional Islands
➢Disturbance Performance
➢Frequency Droop Requirement
➢Ride-Through (No Trip) Requirements
➢Expanded Ranges of Adjustability
➢Voltage & Frequency Disturbances
•NERC and a few utilities began to advocate
less-sensitive setpoints for tripping:
➢Keep DERs On-Line forDisturbances on BES.
➢Still enable tripping for Safety on Distribution Systems.
Defaults and Ranges of Adjustability
For
Voltage and Frequency Tripping
Covered in Clauses 6.4 & 6.5 of Standard
•Cat I Meets most BES Security needs. Includes small synchronous machines.
•Cat II Harmonized w\NERC PRC-024 (protection settings for BES generators)
•Cat III High-Penetration levels where continued DER operation is needed for Distribution System.
Harmonized w\CA Rule 21.
Q:
A: The Authority Governing Interconnection Requirements - the AGIR
Who Or What Is That?
Well, it Depends…
Defined in IEEE 1547-2018➢Can be a:
• Regulatory Agency• Public Utility Commission• Municipality• Co-Op Board of Directors
Defined in IEEE 1547-2018➢Authority may be delegated to the Area EPS operator or bulk power system
operator.
➢Decisions made by an AGIR should consider various stakeholder interests, including but not limited to:➢Load Customers➢Area EPS operators➢DER operator➢Bulk power system operator.
➢Annex B in Standard outlines considerations for Category Selection.
Still not entirely clear, but expect other players:➢Frequency is biggest concern for BES → NERC
➢PJM already working with their members to develop settings
➢Possible that ISOs will mandate frequency settings with no guidance on voltage
➢Voltage Requirements could then fall on Co-Op Board.
Closest to Original Defaults
Condition Clause 1547-2003 Category I
Voltage Trip Pickup Time
OV2 6.4 1.2 p.u. 0.16 s
OV1 6.4 1.1 p.u. 1.00 s
UV1 6.4 0.88 p.u. 2.00 s
UV2 6.4 0.5 p.u. 0.16 s
Category III
Pickup Time
1.20 p.u. 0.16 s
1.10 p.u. 1.0 s
0.88 p.u. 21.0 s
0.50 p.u. 2.0 s
Category I Category II Category III
Pickup Time Pickup Time
1.20 p.u. 0.16 s 1.20 p.u. 0.16 s
1.10 p.u. 1.0 s 1.10 p.u. 1.0 s
0.88 p.u. 2.0 s 0.88 p.u. 2.0 s
0.50 p.u. 0.16 s 0.50 p.u. 0.16 s
Closest to Original Defaults
Condition Clause 1547-2003 Closest to 1547-2003
Frequency Trip
OF2 6.5 n/a n/a
OF1 6.5 60.5 0.16 s
* UF1 6.5 59.3 0.16 s
UF2 6.5 n/a n/a
Category I, II and III
61.8 Hz 0.16 s
61.0 Hz 180.0 s
59.0 Hz 180.0 s
57.0 Hz 0.16 s
New Default Settings
➢Voltage Trip is Different in Each Category
➢Frequency Trip Same for All Categories
➢Chosen to Support Bulk Electric System
Condition Clause 1547-2003 Category I
Voltage Trip Pickup Time
OV2 6.4 1.2 p.u. 0.16 s
OV1 6.4 1.1 p.u. 1.00 s
UV1 6.4 0.88 p.u. 2.00 s
UV2 6.4 0.5 p.u. 0.16 s
Category I Category II
Pickup Time
1.20 p.u. 0.16 s
1.10 p.u. 2.0 s
0.70 p.u. 2.0 s
0.45 p.u. 0.16 s
Category III
Pickup Time
1.20 p.u. 0.16 s
1.10 p.u. 13.0 s
0.88 p.u. 21.0 s
0.50 p.u. 2.0 s
Category II Category III
Pickup Time
1.20 p.u. 0.16 s
1.10 p.u. 2.0 s
0.70 p.u. 10.0 s
0.45 p.u. 0.16 s
Category I, II and III
62.0 Hz 0.16 s
61.2 Hz 300.0 s
58.5 Hz 300.0 s
56.5 Hz 0.16 s
Condition Clause 1547-2003
Frequency Trip
OF2 6.5 n/a n/a
OF1 6.5 60.5 0.16 s
* UF1 6.5 59.3 0.16 s
UF2 6.5 n/a n/a
New Ranges of Adjustability
➢V Can Be Set to:✓Effectively Not Trip for Undervoltage (0.0 p.u. @ 21 s); and\or✓Only Trip for Overvoltage >1.20 p.u. @ 13 s)
➢f Can Be Set to Effectively Not Trip- Period.
Question: Volunteers to test 144 V for 13 s in their house?
➢Frequency-Watt Function
➢As Frequency Drops Output Increases
➢Cannot Be Disabled
➢Pre-Set Parameters Which May be Adjusted Based on Standard.
Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with
Electric Power Systems
➢Needed to Ensure Compliance w\1547 (Base Standard)
➢First Published in 2005
➢63 pp Total
➢Now >265 pp - and Counting!
Encouraging News for Co-Ops
➢Nearly Half is For Manufacturers
➢~75 pp of Evaluation and Commissioning Tests
➢Choose Evaluation & Tests Based On Reference Point of Applicability (RPA)
➢40 pp of Annexes
Article- Overview of IEEE 1547.1
➢Type Testing
➢Production Testing
➢Design Evaluation
➢Installation Evaluation (Pre-Commissioning)
➢Commissioning Tests
➢Periodic Tests
Key Decision for Co-Op:
➢How Much of This Do We Handle In-House?➢Affects Costs in Interconnection Process
➢Borne By DER Owner\Operator?
➢Borne By Co-Op?
Also Affects Interconnection Agreements
Tentative Schedule
➢Early April Final WG Vote
➢Late April Submit Draft to IEEE Standards Assn.
➢May Form Ballot Pool (30 Days)
➢June First Vote
➢July- ? Resolution of Comments & Reballot
➢October Publish IEEE 1547.1-2019
Questions?
Robert W. Harris, PESenior Principal, Transmission & Distribution Engineering
Phone 703-907-5753Cell 571-205-3189