Guide Line for Saudi Electricity Projects

download Guide Line for Saudi Electricity Projects

of 24

Transcript of Guide Line for Saudi Electricity Projects

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    1/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    1OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    ATTACHMENT - III

    BASIC REUIREMENTS AND GUIDELINES

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    2/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    2OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    TABLE OF CONTENTS

    SECTION PAGE NO.

    I BASIC REUIREMENTS AND GUIDELINES

    1.01 GENERAL CONDITIONS

    1.02 KICK-OFF MEETING

    1.03 BASE DESIGN PHASE

    1.04 BASE DESIGN REVIEW

    1.05 PROJECT DRAWINGS

    1.06 PROGRESS REPORTING

    1.0 !"ALIT# ASS"RANCE$!"ALIT# CONTROLRE!"IREMENTS

    1.0% TEST RECORD BOOK

    1.0& CONTRACTOR$COMPAN#'S CONSTR"CTION SITEOFFICE AND FACILIT#

    1.10 LOSS PREVENTION RE!"IREMENTS

    1.11 O"TAGE SCHED"LE$SH"TDOWN COORDINATION

    1.12 COMM"NICATIONS O"TAGE RE!"IREMENTS

    BASIC REUIREMENTS AND GUIDELINES

    1.01 GENERAL CONDITIONS

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    3/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    3OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    A. A(( )*+,*/ ))* 7* /8 )*+,(/* ))7( *,/**7 /8 WORK )*9 /8 )*, *7 /8 PROJECT: /8 ,)7 /( **/: 8(( ; ,,( /(( ;< /8 CONTRACTOR )/8 /8 S)*, *7 WORK T)8)(S,)7)/* COMPAN# S/. I7 /8 ,+/ /8 *'/ )*7*+ >/8,)7)/* * */ )),/;( /* COMPAN# ; * ,/ *,/=?,)$< */8 *: /8 CONTRACTOR 8(( ,*,* (//9 ,+/7* 9> ,,*9( ;< COMPAN#. H*>9: ) *7 )*7()/ /8+/: /8 CONTRACTOR 8(( ;= /8 /* /8 ///* *7 /8 COMPAN# 8(( *;/ )8 ,,();( +/ 7* /8 PROJECT >/= 7*+ /8COMPAN#. T8 CONTRACTOR 8(( 89 * =8/ /* ) * 8 *> /8+/ ) *7 )8 )*7()/: ) *7 )8 9/(/(( ; *= * / 8 *> @ )*/ /8 COMPAN# 9/8 =8/ /* )/ < * /8 )*+,(/ ,/ *7 )8 WORK = */ *7 /8CONTRACTOR' *> )*. T8 == = WORKS /8CONTRACT 8(( ; ) */ ;< == = 7+ /8/ 8=//* /* )=: )()(/* /8/: /( = 8(( ; 7( ; * /8 ; = 9> */8 7*+/*.

    A(( *)+/: >= / /)/* ;**@ /* ; ;+// ;< /8CONTRACTOR 8(( ; >// E=(8 (== M/) "/ = 8(( ; ,*=9 ,8 /;(< 7*9< /= /* =9 77)/ 9> /+ /* COMPAN#.

    G. COMPAN#' ,,*9( *7 /8 CONTACTOR' = *'/ (9 8+ *7 < ,/ *78 *;(=/* /* +/ (( /8 +/ *7 /8 CONTRACT * /8 ,*;(/

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    4/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    !OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    7* /8 )*)/ *7 /8 = )*/)/* >= *7 /8 PROJECT.

    H. A< WORK: >8)8 8/*> *7 /+* * ;//*: 8(( ; )(*(/8 /8 COMPAN#. A(( */= 8(( ; )8( / (/ 7* 4>@ 9).

    I. T8 CONTRACTOR' *=/*( )8/ 8(( ; , CONTRACTOR' @/8 /)/* /* ;.

    J. T8 CONTRACTOR 8(( ;+/ (*= >/8 ; ,*,*( /8 +7)/)*++ *,/*( , ,/ 7* ,* *7 / 10 (( ; 8( /8 COMPAN# C*) A H/O77) 8*/(< 7/ /8 > *7 /8 CONTRACT. T8 +/= >(( )*9 PROJECT+,(+//*: /8 S)*, *7 WORK S)8(: >(( =9 /8 CONTRACTOR *,,*//< /* ) (( +// (/ /* )@ ,* *7 ,(+= /8 @)@-*77 +/=. T8 ,,* *7 ; = /*)*+,(/(< 7 /8 PROJECT /( /* /7< (( /8 COMPAN# +/.I7*+/* 9(*, = /8 ; = 8(( ; = /8*=8*/ /8

    PROJECT 8(( ; )* ;= * ;*/8 ,/: ( *,/*(77)(/ * 7(> *;9 = /( = 9> */ +/)8=. A(( ; = >= 8(( ; /+, B D= D>=.

    C**/* +/= >(( ; )*)/ >/8 /8 CONTRACTOR' COMPAN#,,*9 D= /+ * =( ; /( /8 = )*+,(/.

    B. T8 CONTACTOR 8(( ;+/ T#$%% &3' / *7 /8 ; = *)+/ / (/7* 4 >@ 8 *7 /8 ; = 9> +/= /* )(: ;/ */ (+/ /*:/8 7*((*>=

    1. M* M/( P)8 R/* P(+= */8 *)+/ , S)/* 2.03

    C. T8 ; = ;+//( 8(( ; ;+// 7((< )*+,(/: )*/= (( ),(>= )()(/* //. P/( ;+//( * ,)@= )),/;( >(( ; )/. B = 8(( )( >= /* 7 /8 ,*)/.A/*( >= 7 ,*9 >(( */ ; 9> = /8 ; = ,8.

    1.0! BASE DESIGN REVIEW

    A7/ )*+,(/= /8 B D=: /8 CONTRACTOR 8(( ,/ /8 B D=P)@= 7* /)8)( 9> (*= >/8 /8 D>= C*/*( S8/. CONTRACTOR'

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    5/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    (OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    PROJECT M=: PROJECT E= /8 D=$C*/)/* )8 7( *7,)(/* 8(( // /8 ,//* +/=. D= /8 +/=: /8COMPAN#' )*++/ * /8 ; = ,)@= >(( ; 9> ) /( /* 7( /8 ; = 7* /8 PROJECT. M/ *7 /8 +/= 8((; ,, ;< /8 CONTRACTOR /* ; )*) ;< /8 COMPAN#REPRESENTATIVE.

    CONTRACTOR +< // /8 +/( ,*)+/ WORK = /8 ; =,8 *7 /8 PROJECT ;/ /8 7( ,,*9( *7 /8 +/( 8(( ; * *(< 7/)*/* *7 )*++/ =/ = B D= P8 *(/* *7)*++/ = /8 B D= R9> +/=.

    1.0( PROJECT DRAWINGS

    A. G%)%$*+

    1. T8 CONTRACTOR 8(( ,*9 (( >= 7* /8 PROJECT)*9= /8 > /+* ( ))*) >/8 /8 +/ *7 /8COMPAN# E== D>= S/: SEEDS-II.

    T8 >= 8(( ; = >/8 >= +; ? */( /8 ;*9 ,*). A ;(*)@ *7 >= +; 8(( ; ,*9 ;< /8COMPAN# 7* (( /8 >= ; * CONTRACTOR /.

    2. D>= 8(( ; *7 7*+ )8 ),( +)8 ,*;( ISO )( 8(( ; 110: 150: 1100: 1250 12500.

    3. T8 ?/= = *7 /8 *) ;//* =((< 9(;(

    >/8 /8 COMPAN# =/( 7*+/ ?),/ )/ ) >8 / /87*+ *7 /,). C*, *7 9(;( ?/= >= 8(( ; ,*9* CONTRACTOR' >// /. H*>9: 7 < (/ 7*+/* */9(;(: /8 CONTRACTOR 8(( ; ,*;( /* 9(*, (( /8 >= /* /7< /8 PROJECT +/.

    4. T8 >= 9*(9= +*7)/*$?,* *7 /8 ?/= /8 I/=,8M)*//* CADD 9: ) *7 >= 9*(9=+*7)/* /* ?/= >=: >8)8 */ 9(;( =/( 7*+/:+( 7/ >= 9(*, 7*+ S, *7 ?/= *=(

    /,) (* )),/;(.

    B. V%),$ D$*/)

    V* >= +7)/' >=: / )8(: ,)7)/* 8/:/((/* *,/= /)/* < */8 / 7* +/( *,+/. R+/ *7 )8 7*+/* /=( ,/ *7 /8 ,)8* 8(( ; ,)7 ;< /8 CONTRACTOR.

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    6/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    6OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    A=+/ *7 9* >= +; 8(( ; ))*) >/8 COMPAN#E== D>= S/: SEEDS-II.

    A(( 9* >= 8(( ; ;)/ /* 9> ,,*9( ;< /8 COMPAN# /9* /= ;$; =$/( =$)*/)/* *7 /8 CONTRACT.

    C. B*% D%/) D$*/)

    T8 CONTRACTOR 8(( ;+/ ; = >= /* /8 COMPAN# >/8 8B D= P)@= , S)/* 2.03.

    D. F/)*+ D%*/+ D%/)C)$45/) D$*/)

    T8 CONTRACTOR 8(( ;+/ ,*/ > )*+,() //+/ /* /8 COMPAN#')*++/ 8(( *;/ ,,*9( 7* (( 7( /( = >= 7/)*,*/= COMPAN# )*++/. A(( /( = >= 8(( ; /+, D/( D= D>=. A7/ )9= /8 ,,*9(: /8 CONTRACTOR 8((;+/ /* /8 COMPAN# T8 3 )*+,(/ / *7 (( >= 7*)*/)/* * 1 ;+//(. T8 >= 8(( ; ;+// /* /8 COMPAN#/* ; /+, N%, B78 ;7* /8< /+, /*CONTRACTOR' )*/)/* /+ I F* C*/)/*: ;/ * ) (/8 7*/ 14 = ,* ;< /8 COMPAN# 7( )*/)/* >= 9(;( / WORK SITE >/8 /8 COMPAN#.

    A )*+,(/ (/ *7 >= /8 CONTRACTOR 8(( ,*9 +++ 7* /8PROJECT =9 S)/* 2.03.

    F( /( = >= 8(( ; ;+// 7((< )*+,(/: ;< ),(,/= 7((< /8 ,/ *7 /8 PROJECT /* ; )*/)/ (( /8 (/>=. P/( ;+//( */ )),/;( >(( ; )/.

    E. A-B4/+ D$*/)

    1. A /8 PROJECT )*+,(/* A-B(/ >= 8(( ; ,, ;< /8CONTRACTOR 77)/ /( /* ,/ ))/ )* 7* /8COMPAN#.

    T8 ?/= *) ;//* >= 77)/ ;< /8 PROJECT 8(( ;

    9 )*,*= ?/= >= )*/*( 8/ 8(( ; ,/ ;= 8*>= (( 7(+*7)/* /* >= ,, ;< /8 V* S"BCONTRACTORS.

    I7 /8 CONTRACTOR > =9 ?/= *=( A-B(/ >=: /8 / /8 ,*;(/< *7 /8 CONTRACTOR /* / /8 COMPAN# / (/ />*2 +*/8 ;7* /8 +)8)( )*+,(/* 7* /8 ?/= *=( A-B(/>= =/( 7*+/ TIFF-GRO"P-4 ./7 * .DGN >8)8 ) ; *,

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    7/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    9OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    /8*=8 M)*//* .DGN.

    3. A ,/ *7 A-B(/ >= ;+*: /8 CONTRACTOR 8(( (* ,*9/8 COMPAN# /8 3 /*7 7( +@-, >= 7()/= /8 A-B(/ )*/* *7 /8 ,/)( =+/ *7 WORK )*+,(/ ;< /8CONTRACTOR /;/: =9 ;(*>

    - O 1/ 8(( ; / ;< /8 COMPAN# / /8 ;//*.

    - O 1/ 8(( ; ;+// /* /8 COMPAN#.

    - O 1/ 8(( ; 7* -;(/= ;< CONTRACTOR' E== D= C*(// >8)8 8(( ; )( /8 7( ;+//(.

    4. O 1 +,( *7 *=( =/( M)*//* .DGN 7*+/ M= 8(( ; ;+///* /8 COMPAN# /* 97< /8 (/< *7 =/( M)*//* .DGN 7*+/ M8/8 /8 )*)/ 7/= ,*) *,/: * 1 +*/8;7* /( ;+* *7 A-B(/ >=.

    T8 3 )*, *7 /8 -;(/ *)+/ 8(( ; ;+// /* /8 COMPAN#7* 9> /* )= 8(( ; ;+//>/8 7* 4 >@ 7/ )*++*=. T8 3 / *7 7( A-B(/>=: * 1 / *7 =** (/< A-B(/ M* 2/ *7 A-B(/ =/( M)*//* .DGN 7*+/ >= 7 ,,();( CD 8(( ;;+// /* /8 COMPAN# 7* )*.

    5. T8 COMPAN# >(( = 7* /8 +)*7(+= *7 (( 7( A-B(/ >=

    *7 /8 PROJECT / /8 COMPAN#' H/.

    1.06 PROGRESS REPORTING

    A. T8 CONTRACTOR 8(( ;+/ B->@(< PROJECT P*= R,*/: COMPAN# ,,*9 7*+/ 7* /8 PROJECT /* /8 ,*;( COMPAN#REPRESENTATIVE. F* /8 ,,* /8 /*/( WORK 8(( ; 9 /*

    1. E== D=

    2. P*)+/: M7)/: F;)/*: I,)/* D(9< *7 M/(

    E,+/.

    3. C*/)/* I/((/*

    4. T/= C*++*=

    B. T8 7*((*>= + 7*+/* 8(( ; )( /8 P*= R,*/

    1. P)/ *7 WORK )*+,(/ )*+, /* /8 >=8/ )8( /* WORK ,*=.

    2. S//+/ *7 /+ >*@ * $* )*+,(/ = /8 (/ ,*.

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    8/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    :OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    3. S//+/ *7 /+: /* ; >*@ * $* )*+,(/ = /8 7*((*>=,*.

    4. P*;(+ : >8)8 ) 89 9 77)/ * /8 )8(.

    5. S7/< ///) +/ *7 )*/)/* 7/< +/= ,*=+/=.

    6. M,*> ,+/ 9(;(/< =/ /8 )8( +/.

    . T8 CONTRACTOR 8(( )< */ PROJECT ,(=$)8(= ;< = MSPROJECT )*+,/ *7/>. A(( PROJECT )8( 8(( ; ;+// 7(*,,< @//.

    %. B-W@(< P*= M/= 8(( ; )*)/ ;/> /8 COMPAN# /8 CONTRACTOR = /8 / CONTRACT /* *7 /8 PROJECT.O/8 )**/* /7) +/= >(( ; )*)/: . T8CONTRACTOR 8(( ,, /8 +/ *7 (( +/=. T8 /( 7/ 8((; ;+// ;< /8 CONTRACTOR /* /8 COMPAN# REPRESENTATIVE 7*9> )*)). T8 CONTRACTOR 8(( /8 )*,*/ /8 )*)/* ;+/ /* /8 COMPAN# * 1 *=( />* 2 )*,7/ /8< (< = ;< /8 /8* ,//9 *7 /8CONTRACTOR. T8 COMPAN# 8(( = * 1 )*,< )),/) 78 / /* /8 CONTRACTOR / /8 *=(.

    I /*: W@(< C*/)/* S7/< M/= 8(( ; )*)/ ;< /8CONTRACTOR' S7/< E= * PROJECT E=. M/ *7 +/=8(( ; 7*> /* /8 COMPAN#.

    1.09 UALITY ASSURANCEUALITY CONTROL REUIREMENTS

    A. 4*+/7 M*)*%;%)

    CONTRACTOR 8(( +,(+/ 77)/9 (/< +=+/: >8)8 (()/ )/ )/9/ (/ /* /8 PROJECT /* /8/ (( )*/)/()*/* +/. !(/< ,(=: (/< )*/*(: (/< ) (/8* = /8 CONTRACT.

    ;. D/( PROJECT *=/*( )8/ ,)7) ((*)/* *7,*;(/ /8*/ = /8 77/ ,8 *7 /8PROJECT.

    CONTRACTOR 8(( )( /8 PROJECT *=/*( )8/ !A$!C= ,)/* )/ /* (/< ) (/*@+/(.

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    10/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    10OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    . !(/< A/

    CONTRACTOR 8(( )*)/ / *> /( (/< 9(() /,,*,/ /= .=. =: ,*)+/: )*/)/*: /((/* )*++*= /= *7 /8 PROJECT /* /+ )*+,() /* /8 77)/9 *7 /8 PROJECT !(/< P($!(/< P*=+. E)8(+/ *7 /8 PROJECT !(/< P($!(/< P*=+ 8(( ; / (/ *) = /8 (7 *7 /8 PROJECT. T8 )8( 7)< 8*( ; / 7 * * +* *7 /8 7*((*>= )*/*?/

    . R(/ *7 ,9* 9(() )/ /* ,7*+ /8++* 7/(/8 *)+/,*) /* ,9/ / . CONTRACTOR 8(( /7/8 /8CONTRACTOR' *=/*.

    CONTRACTOR' !A$!C =$,)/* 8(( -,)/ , >*@ *-)*7*+= /+. CONTRACTOR 8(( */ /= /8 (/ *7 ,)/*: / *7 ,)/* + =/ *7 /8!A$!C =$ ,)/*. S)8 )/9/ >8 ,)/* )8)@(/ 8(( )( ;/ */ )(< (+/ /* (( ,-)*++*= )*++*= )8)@ //: +/($,+/ )9= ,)/*:)*)/ ,-,* ,)/*: ,8(/=: 8

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    14/24

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    15/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    1(OF23SAUDIELECTRICITY COMPANY-E RB

    PLANT NO. INDEX DRAWING NO. PAGE NO. REV.

    01

    ;. C*+,(/ ),/* *7 /8 ,)/ +/($,+/.

    ). R,*/ +; /.

    . P() / *7 ,)/*: )*, *7 ,)/*.

    . D*)+/ = ,)/*.7. M7)/ ,(/ (*)/* >8 /8 ,+/ > +7)/.

    =. D/( ),/* *7 /8 ,)/* //= )/9/ /8(/: 9/* /* ,)7)/*: +7)/' ?,(/* /* /89/*: 9( ,)/* (/: ,)@= +@= ,)/* (/:)*)(* )*,< *7 /8 */( >= *7 /8 ,)/+/($,+/. W/ // 9> // / 8(( ;)((< /7 /8 ,)/* ,*/.

    8. N+ *7 /8 ,)/*.

    6. CONTRACTOR 8(( 78 )*, *7 /8 7*((*>= *)+/ /* /8 !(/= /5*%

    1. R( 7* S8,+/ C/7)/ )/7)/ ;< /8 CONTRACTOR /*/8 ,,($+7)/ /* ( /8 ); +/( 7* 8,+/ 7/)*++/* ;< /8 !(/< A) !(/< C*/*( S9)CONTRACTOR ,,*9( ;< /8 COMPAN#.

    2. CONTRACTOR 8(( /8/ (( +/( = ,)/* $* (//8 /8 CONTRACT +/ ,* /* ,)/* ;/= *7 //= / / ;< COMPAN# REPRESENTATIVE8(( ; >/8 /8 =( >*@= 8* *7 /8 COMPAN#. CONTRACTOR')8( 7* ,)/* >/= *7 //= / / ;< COMPAN#REPRESENTATIVE */ *7 /8 =( COMPAN# >*@= 8* 8(( 89,* ,,*9( 7*+ /8 COMPAN# REPRESENTATIVE.

    J. COMPANY 4*+/7 A%;%) &A4,/' R/#

    1. COMPAN# 9 /8 =8/ /* )*)/ )8( $* )8( (//8 C(;/* D/. T/ R(/. C*)(* R)*++/*7. A,,?: )(= // 7*+

    B. E)8 // 7*+ >8 ,,();( 8(( )( )*(+ */= /8 )),/;(+?++ +++ (+/ *7 /8 // /+ *7 9*(/=: )/: 7)/8)< *=( *7/> .. MS O77): P*)/ S)8( /8 3 HPP/ (// * )*+,/;(

  • 8/12/2019 Guide Line for Saudi Electricity Projects

    19/24

    REVISIONS

    DRAWN BY:

    DATE:

    CHKD BY:

    APPROVED

    ENGINEERING DEPT.

    OPERATING DEPT.

    CERTIFIED

    BY:

    DATE:

    THIS DRAWING IS NOT TOBE USED FORCONSTRUCTION OR FORORDERING MATERIALS

    UNTIL CERTIFIED ANDDATED

    ATTACHMENT III

    BASIC REQUIREMENTS AND GUIDELINES

    J660 A

    PTS-12WC1066

    JOB ORDER NO.

    NO

    .3 2 1

    DESCRIPTION

    CHKD

    APPD

    CERT

    .

    1 F(= C;/ /8 3%. D@ /8 3&. S>9( C8 /8310. * 1 C*7) T;( 7* />(912 ,* >/8 )811. D>= F( R)@ /8 312. G/ C8 ?613. P//* B()@;* *114. L*=== B**@ O77) S//*15. P*/;( F E?/=8: T =/* /* +/ )*/)/*: //= )*++*= ,*> +/. H*>9: 7 ,*> ,,(< ,*/ 9(;( /8 PROJECT /: /8 /+,*< +/ ()/)/< )*)/* *)8=;( ; >(( ; ,*9 ;< /8 COMPAN# /* /8 / *77) ;< O,/=A / /8 / *7 /8 CONTRACTOR.T8 /+,*< ()/)( >= /((/* 7* /8 / *77) /* ; ,7*+ ))*) >/8 /8 +/ *7 /8 (// 9* *7 /8 N/*( E()/)( C*NEC * /8 N/*( F P*/)/* A*)/* NFPA.

    C. T%+%=#)% C))%5/)

    T8 CONTRACTOR 8(( 9( /+,*< /()*++)/* 7)(/< / /8 /*77). T8 COMPAN# + /8 CONTRACTOR /* 89/+,*< ?/* *7 /(,8* )*)/*: 7 ,*;(: 7*+ /8 ?/=/()*++)/* 7)(/< * +//) *7 /(,8* /( )8= ,COMPAN# =(/*. T(,8* / *)/ );(= >(( ; /(( ;< /8CONTRACTOR.

    T8 CONTRACTOR >(( ; ((*> /* /8 /(,8* *(< 7* +@= (*)( )((.

    D. W*%$ S4==+7 C))%5/)

    F* / *77) +/ )*/)/* ,,*: /8 CONTRACTOR 8((= / >/ ,,(< 7*+ M),(// ,,(