Page 1: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18
Page 2: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

Attachment 1

GU-DAR-0003(105)

Page 3: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

Activity ID Activity Name OrigDur

Activity %Complete

RemDur

Early Start Start Finish Late Finish TotalFloat

Predecessors Successors

Route 3 WRoute 3 Widening (Route 28 to Chalan Kare 619 489 23-Feb-18 16-Aug-17 A 28-Jan-20 28-Jan-20 0

Pre-ConstrPre-Construction Stage 155 25 23-Feb-18 16-Aug-17 A 29-Mar-18 28-Jan-20 464

AdministarAdministartion and Design 155 25 23-Feb-18 16-Aug-17 A 29-Mar-18 28-Jan-20 464100 Letter of Intent to Award 0 100% 0 16-Aug-17 A 150150 Contract Execution 0 100% 0 27-Dec-17 A 100 250, 300, 350, 400, 450, 500, 650200 Submit QC Plan 0 100% 0 27-Dec-17 150250 Submit APP 8 100% 0 02-Jan-18 A 11-Jan-18 150300 Submit Schedule of Values 14 100% 0 02-Jan-18 A 19-Jan-18 150350 Submit EPP/ECP/SWPPP 16 100% 0 02-Jan-18 A 23-Jan-18 150400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18 150450 Submit Traffic Control Plan 41 90% 4 23-Feb-18 02-Jan-18 A 01-Mar-18 12-Mar-18 8 150 A1070500 Submit Peliminary Schedule 40 95% 2 23-Feb-18 02-Jan-18 A 26-Feb-18 14-Jan-20 477 150 550550 Preliminary Schedule, CM Review/Approval 10 0% 10 27-Feb-18 27-Feb-18 12-Mar-18 28-Jan-20 477 500650 Building/GEPA Permits 37 100% 0 02-Jan-18 A 21-Feb-18 150 800, A1030700 Survey Encroachment Permit 10 100% 0 18-Jan-18 A 31-Jan-18 150 A1020750 Pre-Construction Conference 0 0% 0 27-Feb-18 27-Feb-18* 0 150 800800 Notice to Proceed (Section 108) 0 0% 0 28-Feb-18 28-Feb-18* 0 650, 750 850, 900, A1040, A1050850 Partnering,SCR 103.05 0 0% 0 28-Feb-18 28-Feb-18* 0 800900 Prepare and Submit Baseline Schedule 11 0% 11 01-Mar-18 01-Mar-18 15-Mar-18 14-Jan-20 464 800 950950 Baseline Sched, CM Review/Approval 10 0% 10 16-Mar-18 16-Mar-18 29-Mar-18 28-Jan-20 464 900

ConstructiConstruction Stage 527 489 23-Feb-18 02-Jan-18 A 28-Jan-20 28-Jan-20 0

ProcuremeProcurement and Engineering 146 108 23-Feb-18 02-Jan-18 A 26-Jul-18 20-Nov-19 3360100 PCMS Submittal, Review & Approval 8 100% 0 02-Jan-18 A 11-Jan-18 150 01250125 PCMS- Procurement 11 100% 0 12-Jan-18 A 26-Jan-18 0100 01500150 PCMS Production/Delivery 26 64% 9 23-Feb-18 01-Feb-18 A 08-Mar-18 12-Mar-18 3 0125 A10701100 Reinforcing Bar-Procurement 12 100% 0 02-Jan-18 A 17-Jan-18 150 11101110 Reinf. Bar-Production,Submittals 33 75% 8 23-Feb-18 18-Jan-18 A 07-Mar-18 15-Mar-18 7 1100 11251125 Reinforcing Bar-Submiital Review/Approval 10 0% 10 07-Mar-18 07-Mar-18 21-Mar-18 29-Mar-18 7 1110 11501150 Reinf. Bar-Delivery 20 0% 20 21-Mar-18 21-Mar-18 18-Apr-18 26-Apr-18 7 1125 S12101200 HDPE Drainage Pipe-Procurement, Submittal 12 100% 0 02-Jan-18 A 17-Jan-18 150 12251225 HDPE Drainage Pipe-Submittal Review/Approval 18 100% 0 18-Jan-18 A 12-Feb-18 1200 12501250 HDPE Drainage Pipe-Production,Delivery 55 15% 47 23-Feb-18 13-Feb-18 A 30-Apr-18 18-May-18 14 1225 DS11001300 Water Line-Procurement,Submittal 19 100% 0 02-Jan-18 A 26-Jan-18 150 13251325 Water Line-Submiital Review/Approval 15 0% 15 23-Feb-18 23-Feb-18 15-Mar-18 15-Mar-18 0 1300 1350, R13301350 Water Line-Production, Delivery 40 0% 40 16-Mar-18 16-Mar-18 10-May-18 10-May-18 0 1325 MW11001400 Sewer Line Matls-Procurement, Submittal 20 100% 0 02-Jan-18 A 29-Jan-18 150 14251425 Sewer Line Matls-Submittal Review/Approval 11 100% 0 30-Jan-18 A 13-Feb-18 1400 14501450 Sewer Line Matls-Production/Delivery 54 15% 46 23-Feb-18 14-Feb-18 A 27-Apr-18 19-Dec-18 163 1425 MW13101500 Elec/Comm Conduits-Procurement/Submittal 6 100% 0 02-Jan-18 A 09-Jan-18 150 15251525 Elect/Comm Conduits- Submittal Review/Approval 34 80% 7 23-Feb-18 10-Jan-18 A 05-Mar-18 06-Mar-18 1 1500 15501550 Elec/Comm Conduits-Production/Delivery 45 0% 45 05-Mar-18 05-Mar-18 07-May-18 08-May-18 1 1525 EW1100, GTA11001600 Navy PC MHs-Procurement, Submittal 31 50% 16 23-Feb-18 01-Feb-18 A 16-Mar-18 16-Mar-18 1 150 16251625 Navy PC MHs-Submittal Review/Approval 10 0% 10 16-Mar-18 16-Mar-18 30-Mar-18 30-Mar-18 1 1600 16501650 Navy PC MHs-Production, Delivery 45 0% 45 30-Mar-18 30-Mar-18 04-Jun-18 04-Jun-18 1 1625 EW11001700 Elec Cables & Appur-Procurement, Submittal 36 100% 0 02-Jan-18 A 20-Feb-18 150 17251725 Elec Cables & Appur-Submittal Review/Approval 12 5% 11 23-Feb-18 21-Feb-18 A 12-Mar-18 12-Nov-18 173 1700 17501750 Elec Cables & Appur-Production,Delivery 50 0% 50 12-Mar-18 12-Mar-18 21-May-18 25-Jan-19 173 1725 EW11101800 Power Poles-Procurement, Submittal 22 100% 0 02-Jan-18 A 31-Jan-18 150 18251825 Power Poles-Submittal Review/Approval 9 100% 0 01-Feb-18 A 13-Feb-18 1800 18501850 Power Poles-Production,Testing & Delivery 54 15% 46 23-Feb-18 14-Feb-18 A 27-Apr-18 24-May-18 19 1825 P13401900 Traffic Poles, Equip-Procurement,Submittal Prep 51 65% 18 23-Feb-18 02-Jan-18 A 20-Mar-18 16-Jul-19 336 150 19251925 Traffic Poles, Equip-Submittal Review/Approval 10 0% 10 20-Mar-18 20-Mar-18 03-Apr-18 30-Jul-19 336 1900 19501950 Traffic Poles, Eqp-Production,Delivery 80 0% 80 03-Apr-18 03-Apr-18 26-Jul-18 20-Nov-19 336 1925 R3A1802000 Chain Link Fence-Procurement, Submittal 35 100% 0 02-Jan-18 A 19-Feb-18 150 20252025 Chain Link Fence-Submittal Review/Approval 11 0% 11 01-Mar-18 01-Mar-18 15-Mar-18 27-Mar-18 8 2000 20502050 Chain Link Fence-Production, Delivery 45 0% 45 16-Mar-18 16-Mar-18 17-May-18 30-May-18 8 2025 SCF1100

General SitGeneral Site Preparation 448 411 23-Feb-18 03-Jan-18 A 04-Oct-19 24-Oct-19 14A1010 Construct Off-SiteTemp. Field Offices/Parkings 40 100% 0 03-Jan-18 A 27-Feb-18 150 A1050A1020 Survey Controls and Pre-Construction Topo Survey 26 50% 13 23-Feb-18 01-Feb-18 A 13-Mar-18 02-Apr-18 14 700 A1060A1030 Notify DPW thru CO of Excavation/Potholing 1 100% 0 21-Feb-18 A 21-Feb-18 650 A1090A1040 Biological Survey, Initial for P1-WZ1and P1-WZ2 10 0% 10 28-Feb-18 28-Feb-18 13-Mar-18 06-Apr-18 18 800 A1080A1050 Mobilize Site Set-up 22 0% 22 28-Feb-18 28-Feb-18 29-Mar-18 11-Apr-18 9 800, A1010 A1070

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2018 2019 2020

Contract ExecutionSubmit QC Plan

Submit APPSubmit Schedule of ValuesSubmit EPP/ECP/SWPPPSubmit Hazard Analysis & Critical Point

Submit Traffic Control PlanSubmit Peliminary Schedule

Preliminary Schedule, CM Review/ApprovalBuilding/GEPA Permits

Survey Encroachment PermitPre-Construction ConferenceNotice to Proceed (Section 108)Partnering,SCR 103.05

Prepare and Submit Baseline ScheduleBaseline Sched, CM Review/Approval

PCMS Submittal, Review & ApprovalPCMS- Procurement

PCMS Production/DeliveryReinforcing Bar-Procurement

Reinf. Bar-Production,SubmittalsReinforcing Bar-Submiital Review/Approval

Reinf. Bar-DeliveryHDPE Drainage Pipe-Procurement, Submittal

HDPE Drainage Pipe-Submittal Review/ApprovalHDPE Drainage Pipe-Production,Delivery

Water Line-Procurement,SubmittalWater Line-Submiital Review/Approval

Water Line-Production, DeliverySewer Line Matls-Procurement, Submittal

Sewer Line Matls-Submittal Review/ApprovalSewer Line Matls-Production/Delivery

Elec/Comm Conduits-Procurement/SubmittalElect/Comm Conduits- Submittal Review/Approval

Elec/Comm Conduits-Production/DeliveryNavy PC MHs-Procurement, Submittal

Navy PC MHs-Submittal Review/ApprovalNavy PC MHs-Production, Delivery

Elec Cables & Appur-Procurement, SubmittalElec Cables & Appur-Submittal Review/Approval

Elec Cables & Appur-Production,DeliveryPower Poles-Procurement, Submittal

Power Poles-Submittal Review/ApprovalPower Poles-Production,Testing & Delivery

Traffic Poles, Equip-Procurement,Submittal PrepTraffic Poles, Equip-Submittal Review/Approval

Traffic Poles, Eqp-Production,DeliveryChain Link Fence-Procurement, Submittal

Chain Link Fence-Submittal Review/ApprovalChain Link Fence-Production, Delivery

Construct Off-SiteTemp. Field Offices/ParkingsSurvey Controls and Pre-Construction Topo Survey

Notify DPW thru CO of Excavation/PotholingBiological Survey, Initial for P1-WZ1and P1-WZ2

Mobilize Site Set-up

PROJECT NO. GU-DAR-0003(105)ROUTE 3 WIDENING (ROUTE 28 to CHALAN KARETA)

BLACK CONSTRUCTION CORPORATION

16-Aug-1728-Jan-2023-Feb-18

30-Mar-18 15:03

Remaining Level of EffortActual Work

Remaining WorkCritical Remaining Work

Milestone Page 1 of 6BASELINE SCHEDULE

TASK filter: All Activities© Oracle Corporation

Page 4: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

Activity ID Activity Name OrigDur

Activity %Complete

RemDur

Early Start Start Finish Late Finish TotalFloat

Predecessors Successors

A1060 Survey-Establish Road Centerline 10 0% 10 14-Mar-18 14-Mar-18 27-Mar-18 16-Apr-18 14 A1020 A1065A1065 Construction Survey 396 0% 396 16-Mar-18 16-Mar-18 04-Oct-19 24-Oct-19 14 A1060 A1090A1070 Install PCMS (MEC Notification to Public) 1 0% 1 08-Mar-18 08-Mar-18 09-Mar-18 13-Mar-18 3 450, 0150, A1050 A1075, P1300, R1100A1075 Archaeological Notification of Any Excavation 3 0% 3 12-Mar-18 12-Mar-18 15-Mar-18 06-Apr-18 17 A1070 A1080A1080 Set Environmental Controls and Maintenance 391 0% 391 15-Mar-18 15-Mar-18 27-Sep-19 21-Oct-19 17 A1040, A1075 A1090A1090 Pot Holing Work 44 0% 44 20-Mar-18 20-Mar-18 18-May-18 08-Jun-18 14 A1030, A1065, A1080 DS1100, EW1100, GTA1100, MW

Phase 1 (WPhase 1 (West) 246 246 08-Mar-18 08-Mar-18 25-Feb-19 25-Feb-19 0

P1-Work ZP1-Work Zone 1, Sta. 107+34.99 to St. 136+00 141 141 09-Mar-18 09-Mar-18 26-Sep-18 25-Feb-19 104NTSC FenNTSC Fence Relocation 22 22 18-May-18 18-May-18 19-Jun-18 29-Jun-18 8SCF1100 Relocate NCTS Fence to E.G. Sta 131+50 to 138+7 17 0% 17 18-May-18 18-May-18 12-Jun-18 22-Jun-18 8 2050 SCF1125SCF1125 Remove Existing NCTS Fence 5 0% 5 13-Jun-18 13-Jun-18 19-Jun-18 29-Jun-18 8 SCF1100 NF1200

Road ConRoad Construction 132 132 09-Mar-18 09-Mar-18 13-Sep-18 13-Sep-18 0R1100 Install Temporary Traffic Control 10 0% 10 09-Mar-18 09-Mar-18 23-Mar-18 27-Mar-18 3 A1070 R1110R1110 Construct Temporary Access 2 0% 2 16-Mar-18 16-Mar-18 20-Mar-18 22-Mar-18 3 R1100 R1120R1120 Clearing and Grubbing, Haul & Dispose 30 0% 30 16-Mar-18 16-Mar-18 27-Apr-18 01-May-18 3 R1110 R1125, R1130R1125 Removal of Structures and Obstructions 15 0% 15 06-Apr-18 06-Apr-18 27-Apr-18 08-May-18 8 R1120 R1130R1130 Roadway Excavation/ Embankment 20 0% 20 06-Apr-18 06-Apr-18 04-May-18 08-May-18 3 R1120, R1125 B1100, EW1100, GTA1100, MW1R1140 Sub-base Course 5 0% 5 01-Aug-18 01-Aug-18 07-Aug-18 07-Aug-18 0 DS1130, EW1100, MW1110, GTA R1150R1150 Place Base Course 21 0% 21 08-Aug-18 08-Aug-18 06-Sep-18 06-Sep-18 0 R1140 R1155R1155 Curb & Gutter, Sta 108+94.88 to 136+00 (2,706') 21 0% 21 10-Aug-18 10-Aug-18 10-Sep-18 10-Sep-18 0 R1150 R1160R1160 Place Asphalt Concrete Pavement 3 0% 3 11-Sep-18 11-Sep-18 13-Sep-18 13-Sep-18 0 R1155 DS1140, R11A10, R1200, R12A10

BiofiltratioBiofiltration Basin (Temp Sediment Trap) 23 23 04-May-18 04-May-18 07-Jun-18 18-Jul-18 29B1100 Excavate/Load/Dispose 10 0% 10 04-May-18 04-May-18 18-May-18 28-Jun-18 29 R1130 B1125B1125 Place 24" thk. Filter Sand 3 0% 3 18-May-18 18-May-18 23-May-18 03-Jul-18 29 B1100 B1150B1150 Drain Line 4-A, CB4-A1,SDMH 4-A,headwall, riprap 10 0% 10 23-May-18 23-May-18 07-Jun-18 18-Jul-18 29 B1125 B2100, DS1130

Waterline Waterline Relocation/Adjustment 54 54 11-May-18 11-May-18 27-Jul-18 31-Jul-18 2MW1100 Relocate 10" Navy Waterline (7 loc.) 42 0% 42 11-May-18 11-May-18 11-Jul-18 11-Jul-18 0 1350, A1090, R1130 DS1100, MW1110MW1110 Relocate 20" GWA Waterline (2 loc) 12 0% 12 12-Jul-18 12-Jul-18 27-Jul-18 31-Jul-18 2 MW1100 R1140

Relocate GRelocate GTA Comminication Line 19 19 07-May-18 07-May-18 04-Jun-18 05-Jun-18 1GTA1100 Exploration 3 0% 3 07-May-18 07-May-18 10-May-18 11-May-18 1 1550, A1090, R1130 GTA1110GTA1110 Dig to expose existing GTA cable 11 0% 11 10-May-18 10-May-18 25-May-18 29-May-18 1 GTA1100 GTA1120GTA1120 Notification period prior to outage 5 0% 5 10-May-18 10-May-18 17-May-18 18-May-18 1 GTA1110 GTA1130GTA1130 Relocate GTA Comm Line and backfill 11 0% 11 17-May-18 17-May-18 04-Jun-18 05-Jun-18 1 GTA1120 DS1100, R1140

Drainage Drainage and Slope Protection Works 90 90 21-May-18 21-May-18 26-Sep-18 25-Feb-19 104DS1100 24" Drainline 1-A, 2-A, 2-B, 2-C, 2-D, 2-E&3-B 36 0% 36 21-May-18 21-May-18 11-Jul-18 11-Jul-18 0 1250, A1090, MW1100, GTA1130 DS1110, DS1120DS1110 CB1-A1, CB 2-A1,B1,C1,D1,E1, CB 3-B1 36 0% 36 21-May-18 21-May-18 11-Jul-18 11-Jul-18 0 DS1100 DS1120DS1120 Infiltration Trench, SDMH 4-A,4-B, 4-C & Chamber 12 0% 12 12-Jul-18 12-Jul-18 27-Jul-18 27-Jul-18 0 DS1100, DS1110 DS1130DS1130 24" Drainline 4 & 4-B, CB 4-A, CB 4-B1, CB 4-B 9 0% 9 19-Jul-18 19-Jul-18 31-Jul-18 31-Jul-18 0 B1150, DS1120 R1140DS1140 Gutter Outlet Riprap 8 0% 8 14-Sep-18 14-Sep-18 25-Sep-18 22-Feb-19 104 R1160 DS1150DS1150 Install Pea Gravel and Engineered Soil 1 0% 1 26-Sep-18 26-Sep-18 26-Sep-18 25-Feb-19 104 DS1140 R2300, R2100

UndergroUnderground Electrical Works 61 61 04-Jun-18 04-Jun-18 29-Aug-18 25-Feb-19 124EW1100 D/L/B U/G Navy Comm Lines & MH (7ea) 40 0% 40 04-Jun-18 04-Jun-18 31-Jul-18 31-Jul-18 1 1550, 1650, A1090, R1130 R1140, EW1110EW1110 Install Wires and Cables 6 0% 6 31-Jul-18 31-Jul-18 08-Aug-18 04-Feb-19 124 1750, EW1100 EW1120EW1120 Termination and Testing by NCTS 15 0% 15 08-Aug-18 08-Aug-18 29-Aug-18 25-Feb-19 124 EW1110 R2100, R2300

P1-Work ZP1-Work Zone 1A, Sta. 100+20 to Sta 107+35 22 22 14-Sep-18 14-Sep-18 15-Oct-18 25-Feb-19 91Road ConRoad Construction 22 22 14-Sep-18 14-Sep-18 15-Oct-18 25-Feb-19 91R11A10 Install Additional Traffic Control 4 0% 4 14-Sep-18 14-Sep-18 19-Sep-18 30-Jan-19 91 R1160 R11A20R11A20 Saw Cut, Mill Exist. Asphalt Friction Course 3 0% 3 20-Sep-18 20-Sep-18 24-Sep-18 04-Feb-19 91 R11A10 R11A30, R11A40, E11A10R11A30 Remove Exist Sign 2 0% 2 25-Sep-18 25-Sep-18 26-Sep-18 11-Feb-19 94 R11A20 R11A50R11A40 Adjust Top of Sewer Manhole to Finish Grade 5 0% 5 25-Sep-18 25-Sep-18 01-Oct-18 11-Feb-19 91 R11A20 R11A50R11A50 Roughen Existing PCC Pavement and Clean 10 0% 10 02-Oct-18 02-Oct-18 15-Oct-18 25-Feb-19 91 E11A10, R11A30, R11A40 R2100, R2300

UndergroUnderground Electrical Works 10 10 25-Sep-18 25-Sep-18 08-Oct-18 25-Feb-19 96E11A10 Install underground comm & elect traffic signal 10 0% 10 25-Sep-18 25-Sep-18 08-Oct-18 25-Feb-19 96 R11A20 R11A50

P1-Work ZP1-Work Zone 2, Sta. 136+00 to Sta 171+00 217 217 18-Apr-18 18-Apr-18 25-Feb-19 25-Feb-19 0StructuralStructural Retaining Wall 154 154 18-Apr-18 18-Apr-18 27-Nov-18 05-Dec-18 7S1210 RW-1 w/parapet, Sta 138+01.94 to 141+25.36-323L 44 0% 44 18-Apr-18 18-Apr-18 20-Jun-18 28-Jun-18 7 1150 S1220S1220 RW-2 w\conc. barrier,Sta 155+00 to 158+00-300LF 35 0% 35 20-Jun-18 20-Jun-18 09-Aug-18 17-Aug-18 7 S1210 S1230S1230 Conc. barrier w/ftg,Sta 158+00 to 161+50-350LF 25 0% 25 09-Aug-18 09-Aug-18 14-Sep-18 24-Sep-18 7 S1220 S1240S1240 RW-2 w\conc. barrier,Sta 161+50 to 166+00-450LF 50 0% 50 14-Sep-18 14-Sep-18 27-Nov-18 05-Dec-18 7 S1230 R1230

NTSC FenNTSC Fence Relocation 79 79 13-Jun-18 13-Jun-18 03-Oct-18 15-Oct-18 8NF1200 Install Temp. Construction Fence inside DOD Area 5 0% 5 13-Jun-18 13-Jun-18 19-Jun-18 29-Jun-18 8 SCF1125 NF1205NF1205 Clearing and Grading to Finish Grade 30 0% 30 13-Jun-18 13-Jun-18 25-Jul-18 06-Aug-18 8 NF1200 NF1210NF1210 Relocate Fence to FG, Sta 145+50 to 153+00 18 0% 18 05-Jul-18 05-Jul-18 30-Jul-18 09-Aug-18 8 NF1205 NF1220

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2018 2019 2020

Survey-Establish Road CenterlineConstruction Survey

Install PCMS (MEC Notification to Public)Archaeological Notification of Any Excavation

Set Environmental Controls and MaintenancePot Holing Work

Relocate NCTS Fence to E.G. Sta 131+50 to 138+70Remove Existing NCTS Fence

Install Temporary Traffic ControlConstruct Temporary Access

Clearing and Grubbing, Haul & DisposeRemoval of Structures and Obstructions

Roadway Excavation/ EmbankmentSub-base Course

Place Base CourseCurb & Gutter, Sta 108+94.88 to 136+00 (2,706')Place Asphalt Concrete Pavement

Excavate/Load/DisposePlace 24" thk. Filter Sand

Drain Line 4-A, CB4-A1,SDMH 4-A,headwall, riprap

Relocate 10" Navy Waterline (7 loc.)Relocate 20" GWA Waterline (2 loc)

ExplorationDig to expose existing GTA cable

Notification period prior to outageRelocate GTA Comm Line and backfill

24" Drainline 1-A, 2-A, 2-B, 2-C, 2-D, 2-E&3-BCB1-A1, CB 2-A1,B1,C1,D1,E1, CB 3-B1

Infiltration Trench, SDMH 4-A,4-B, 4-C & Chamber24" Drainline 4 & 4-B, CB 4-A, CB 4-B1, CB 4-B

Gutter Outlet RiprapInstall Pea Gravel and Engineered Soil

D/L/B U/G Navy Comm Lines & MH (7ea)Install Wires and Cables

Termination and Testing by NCTS

Install Additional Traffic ControlSaw Cut, Mill Exist. Asphalt Friction CourseRemove Exist SignAdjust Top of Sewer Manhole to Finish Grade

Roughen Existing PCC Pavement and Clean

Install underground comm & elect traffic signal

RW-1 w/parapet, Sta 138+01.94 to 141+25.36-323LFRW-2 w\conc. barrier,Sta 155+00 to 158+00-300LF

Conc. barrier w/ftg,Sta 158+00 to 161+50-350LFRW-2 w\conc. barrier,Sta 161+50 to 166+00-450LF

Install Temp. Construction Fence inside DOD AreaClearing and Grading to Finish GradeRelocate Fence to FG, Sta 145+50 to 153+00

PROJECT NO. GU-DAR-0003(105)ROUTE 3 WIDENING (ROUTE 28 to CHALAN KARETA)

BLACK CONSTRUCTION CORPORATION

16-Aug-1728-Jan-2023-Feb-18

30-Mar-18 15:03

Remaining Level of EffortActual Work

Remaining WorkCritical Remaining Work

Milestone Page 2 of 6BASELINE SCHEDULE

TASK filter: All Activities© Oracle Corporation

Page 5: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

Activity ID Activity Name OrigDur

Activity %Complete

RemDur

Early Start Start Finish Late Finish TotalFloat

Predecessors Successors

NF1220 Relocate NCTS Fence to E.G. Sta153+00 to 155+50 6 0% 6 31-Jul-18 31-Jul-18 07-Aug-18 17-Aug-18 8 NF1210 NF1230NF1230 Relocate Fence to F.G., Sta 155+50 to 162+00 15 0% 15 08-Aug-18 08-Aug-18 28-Aug-18 10-Sep-18 8 NF1220 NF1240NF1240 Relocate NCTS Fence to E.G. Sta 162.00 to 163+50 5 0% 5 29-Aug-18 29-Aug-18 05-Sep-18 17-Sep-18 8 NF1230 NF1250NF1250 Relocate Fence to F.G., Sta 163+50 to 167+50 10 0% 10 06-Sep-18 06-Sep-18 19-Sep-18 01-Oct-18 8 NF1240 NF1260NF1260 Relocate NCTS Fence to E.G. Sta 167+50 to 171+0 8 0% 8 20-Sep-18 20-Sep-18 01-Oct-18 11-Oct-18 8 NF1250 NF1270NF1270 Remove Existing NCTS Fence 10 0% 10 20-Sep-18 20-Sep-18 03-Oct-18 15-Oct-18 8 NF1260 R1230

Road ConRoad Construction 113 113 14-Sep-18 14-Sep-18 25-Feb-19 25-Feb-19 0R1200 Construct Temporary Access 4 0% 4 14-Sep-18 14-Sep-18 19-Sep-18 19-Sep-18 0 R1160 R1210R1210 Install Temporary Traffic Control 2 0% 2 20-Sep-18 20-Sep-18 21-Sep-18 21-Sep-18 0 R1200 R1220R1220 Clearing and Grubbing, Haul & Dispose 25 0% 25 20-Sep-18 20-Sep-18 24-Oct-18 24-Oct-18 0 R1210 R1225, R1230R1225 Removal of Structures and Obstructions 15 0% 15 11-Oct-18 11-Oct-18 31-Oct-18 05-Dec-18 23 R1220 R1230R1230 Roadway Excavation/ Embankment 45 0% 45 02-Oct-18 02-Oct-18 05-Dec-18 05-Dec-18 0 S1240, NF1270, R1220, R1225 DS1220, DS1250, EW1200, EW1R1240 Sub-base Course 5 0% 5 03-Jan-19 03-Jan-19 09-Jan-19 09-Jan-19 0 DS1215, EW1200, EW1210, MW R1250R1250 Place Base Course 30 0% 30 10-Jan-19 10-Jan-19 20-Feb-19 20-Feb-19 0 R1240 R1260R1260 Place Asphalt Concrete Pavement 3 0% 3 21-Feb-19 21-Feb-19 25-Feb-19 25-Feb-19 0 R1250 R2100, R2300

Waterline Waterline Relocation/Adjustment 14 14 23-Oct-18 23-Oct-18 09-Nov-18 09-Nov-18 0MW1200 Relocate 10" Navy Waterline, Sta 137+50 & 162+75 14 0% 14 23-Oct-18 23-Oct-18 09-Nov-18 09-Nov-18 0 R1230 DS1200, R1240

Relocate GRelocate GTA Comminication Line 9 9 23-Oct-18 23-Oct-18 02-Nov-18 02-Jan-19 39GTA1200 Exploration 1 0% 1 23-Oct-18 23-Oct-18 23-Oct-18 19-Dec-18 39 R1230 GTA1210GTA1210 Dig to expose existing GTA cable 3 0% 3 24-Oct-18 24-Oct-18 26-Oct-18 24-Dec-18 39 GTA1200 GTA1220GTA1220 Notification period prior to outage 5 0% 5 24-Oct-18 24-Oct-18 30-Oct-18 27-Dec-18 39 GTA1210 GTA1230GTA1230 Relocate GTA Comm Line and backfill 3 0% 3 31-Oct-18 31-Oct-18 02-Nov-18 02-Jan-19 39 GTA1220 R1240

Drainage Drainage and Slope Protection Works 68 68 02-Nov-18 02-Nov-18 11-Feb-19 25-Feb-19 10DS1200 24" Drainline 4, 4-C, CB-4-C & CB 4-D 12 0% 12 02-Nov-18 02-Nov-18 19-Nov-18 19-Nov-18 0 MW1200 DS1210DS1210 24" Drainline 6-A, 8A, CB 6-A1, DI 8-B 12 0% 12 20-Nov-18 20-Nov-18 07-Dec-18 07-Dec-18 0 DS1200 DS1215DS1215 Drainline 8, Grated Inlet, Sta 160+00 to165+00 16 0% 16 10-Dec-18 10-Dec-18 02-Jan-19 02-Jan-19 0 DS1210 R1240DS1220 Drainline 7, MH 7-A, HW, Riprap Apron (DOD) 15 0% 15 06-Dec-18 06-Dec-18 27-Dec-18 25-Feb-19 41 R1230 R2100, R2300DS1250 Bioswale Type 2, 3 & 4 46 0% 46 06-Dec-18 06-Dec-18 11-Feb-19 25-Feb-19 10 R1230 R2100, R2300

UndergroUnderground Electrical Works 46 46 23-Oct-18 23-Oct-18 28-Dec-18 25-Feb-19 40EW1200 D/L/B Stub-outs with caps and markers for power 7 0% 7 06-Dec-18 06-Dec-18 14-Dec-18 02-Jan-19 11 R1230 R1240EW1210 D/L/B U/G Navy Comm Lines & MH 27 0% 27 23-Oct-18 23-Oct-18 30-Nov-18 02-Jan-19 21 R1230 R1240, EW1220EW1220 Install Wires and Cables 4 0% 4 03-Dec-18 03-Dec-18 06-Dec-18 04-Feb-19 40 EW1210 EW1230EW1230 Termination and Testing by NCTS 15 0% 15 07-Dec-18 07-Dec-18 28-Dec-18 25-Feb-19 40 EW1220 R2300, R2100

P1-Work ZP1-Work Zone 2A, Bullard Avenue 73 73 14-Sep-18 14-Sep-18 28-Dec-18 25-Feb-19 40Road ConRoad Construction 73 73 14-Sep-18 14-Sep-18 28-Dec-18 25-Feb-19 40R12A10 Install Temporary Traffic Control 2 0% 2 14-Sep-18 14-Sep-18 17-Sep-18 12-Nov-18 40 R1160 R12A20R12A20 Construct Temporary Access 5 0% 5 18-Sep-18 18-Sep-18 24-Sep-18 19-Nov-18 40 R12A10 R12A30R12A30 Demolish/Relocate exist structures/utilities 25 0% 25 25-Sep-18 25-Sep-18 29-Oct-18 27-Dec-18 40 R12A20 R12A35R12A35 U/G Utility Work 25 0% 25 09-Oct-18 09-Oct-18 12-Nov-18 11-Jan-19 40 R12A30 R12A50R12A50 Place Basecourse 5 0% 5 13-Nov-18 13-Nov-18 19-Nov-18 18-Jan-19 40 R12A35 R12A55R12A55 Construct Curb and Gutter 8 0% 8 20-Nov-18 20-Nov-18 03-Dec-18 30-Jan-19 40 R12A50 R12A60R12A60 Place Asphalt Concrete Pavement 1 0% 1 04-Dec-18 04-Dec-18 04-Dec-18 31-Jan-19 40 R12A55 R12A65R12A65 Remove Dispose Temp Works 2 0% 2 05-Dec-18 05-Dec-18 06-Dec-18 04-Feb-19 40 R12A60 R12A70R12A70 Install New Street Light Pole, wirings 15 0% 15 07-Dec-18 07-Dec-18 28-Dec-18 25-Feb-19 40 R12A65 R2100, R2300

P1-Work ZP1-Work Zone 3, Sta. 171+00 to Sta 245+73 227 227 08-Mar-18 08-Mar-18 30-Jan-19 25-Feb-19 19PowerpolPowerpole and Overhead Primary Lines 115 115 08-Mar-18 08-Mar-18 20-Aug-18 14-Sep-18 19P1300 Initial Temporary Traffic Control 2 0% 2 08-Mar-18 08-Mar-18 12-Mar-18 05-Apr-18 19 A1070 P1310P1310 Construct Temporary Access Road, Screening Area 10 0% 10 12-Mar-18 12-Mar-18 26-Mar-18 19-Apr-18 19 P1300 P1320P1320 Clearing & Grubbing, Haul & Dispose 45 0% 45 12-Mar-18 12-Mar-18 14-May-18 08-Jun-18 19 P1310 P1330P1330 Excavation/Embankment, Sta 208+37 to 245+73 35 0% 35 02-Apr-18 02-Apr-18 21-May-18 15-Jun-18 19 P1320 P1332, P1340P1332 Excavation/Embankment, Sta 171+00 to 208+37 45 0% 45 21-May-18 21-May-18 25-Jul-18 30-Aug-18 27 P1330 P1342P1340 Install New Power Poles, Sta 208+37 to 245+73 28 0% 28 30-Apr-18 30-Apr-18 08-Jun-18 05-Jul-18 19 1850, P1330 P1350, P1342P1342 Install New Power Poles, Sta 171+00 to 208+37 30 0% 30 19-Jun-18 19-Jun-18 01-Aug-18 07-Sep-18 27 P1332, P1340 P1350P1350 Install Overhead Power Lines, Hook-Up/Energize 50 0% 50 08-Jun-18 08-Jun-18 20-Aug-18 14-Sep-18 19 P1340, P1342 EW1310, R1300

Road ConRoad Construction 117 117 13-Aug-18 13-Aug-18 30-Jan-19 25-Feb-19 19R1300 Initial Additional Temp. Traffic Control 5 0% 5 13-Aug-18 13-Aug-18 20-Aug-18 11-Oct-18 38 P1350 R1310, R1320R1310 Remove Exist Power Poles Sta 171+00 to 245+73 30 0% 30 20-Aug-18 20-Aug-18 02-Oct-18 26-Nov-18 38 R1300 R1330R1320 Clearing & Grubbing, Haul & Disp 15' buffer zone 15 0% 15 20-Aug-18 20-Aug-18 11-Sep-18 01-Nov-18 38 R1300 R1325, R1330R1325 Removal of Structures and Obstructions 15 0% 15 11-Sep-18 11-Sep-18 02-Oct-18 10-Dec-18 48 R1320 R1332R1330 Roadway Excav/Embank, Sta 208+37 to 245+73 B.Z 15 0% 15 04-Sep-18 04-Sep-18 25-Sep-18 15-Nov-18 38 1325, R1320, R1310 R1332, DS1340, EW1300R1332 Roadway Excav/Embak, 171+00 to 208+37 B.Z. 15 0% 15 25-Sep-18 25-Sep-18 16-Oct-18 10-Dec-18 38 R1325, R1330 MW1300, DS1342R1340 Sub-base Course, Sta 208+37 to 245+73 2 0% 2 09-Oct-18 09-Oct-18 11-Oct-18 31-Dec-18 55 EW1300, EW1310 R1350R1342 Sub-base Course, Sta 171+00 to 208+37 2 0% 2 30-Nov-18 30-Nov-18 04-Dec-18 31-Dec-18 19 EW1340, MW1310 R1352

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2018 2019 2020

Relocate NCTS Fence to E.G. Sta153+00 to 155+50Relocate Fence to F.G., Sta 155+50 to 162+00

Relocate NCTS Fence to E.G. Sta 162.00 to 163+50Relocate Fence to F.G., Sta 163+50 to 167+50

Relocate NCTS Fence to E.G. Sta 167+50 to 171+00Remove Existing NCTS Fence

Construct Temporary AccessInstall Temporary Traffic Control

Clearing and Grubbing, Haul & DisposeRemoval of Structures and Obstructions

Roadway Excavation/ EmbankmentSub-base Course

Place Base CoursePlace Asphalt Concrete Pavement

Relocate 10" Navy Waterline, Sta 137+50 & 162+75

ExplorationDig to expose existing GTA cableNotification period prior to outageRelocate GTA Comm Line and backfill

24" Drainline 4, 4-C, CB-4-C & CB 4-D24" Drainline 6-A, 8A, CB 6-A1, DI 8-B

Drainline 8, Grated Inlet, Sta 160+00 to165+00Drainline 7, MH 7-A, HW, Riprap Apron (DOD)

Bioswale Type 2, 3 & 4

D/L/B Stub-outs with caps and markers for powerD/L/B U/G Navy Comm Lines & MHInstall Wires and Cables

Termination and Testing by NCTS

Install Temporary Traffic ControlConstruct Temporary Access

Demolish/Relocate exist structures/utilitiesU/G Utility WorkPlace Basecourse

Construct Curb and GutterPlace Asphalt Concrete PavementRemove Dispose Temp Works

Install New Street Light Pole, wirings

Initial Temporary Traffic ControlConstruct Temporary Access Road, Screening Area

Clearing & Grubbing, Haul & DisposeExcavation/Embankment, Sta 208+37 to 245+73

Excavation/Embankment, Sta 171+00 to 208+37Install New Power Poles, Sta 208+37 to 245+73

Install New Power Poles, Sta 171+00 to 208+37Install Overhead Power Lines, Hook-Up/Energize

Initial Additional Temp. Traffic ControlRemove Exist Power Poles Sta 171+00 to 245+73

Clearing & Grubbing, Haul & Disp 15' buffer zoneRemoval of Structures and Obstructions

Roadway Excav/Embank, Sta 208+37 to 245+73 B.ZRoadway Excav/Embak, 171+00 to 208+37 B.Z.

Sub-base Course, Sta 208+37 to 245+73Sub-base Course, Sta 171+00 to 208+37

PROJECT NO. GU-DAR-0003(105)ROUTE 3 WIDENING (ROUTE 28 to CHALAN KARETA)

BLACK CONSTRUCTION CORPORATION

16-Aug-1728-Jan-2023-Feb-18

30-Mar-18 15:03

Remaining Level of EffortActual Work

Remaining WorkCritical Remaining Work

Milestone Page 3 of 6BASELINE SCHEDULE

TASK filter: All Activities© Oracle Corporation

Page 6: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

Activity ID Activity Name OrigDur

Activity %Complete

RemDur

Early Start Start Finish Late Finish TotalFloat

Predecessors Successors

R1350 Place Base Course, Sta 171+00 to 208+37 35 0% 35 11-Oct-18 11-Oct-18 03-Dec-18 19-Feb-19 55 R1340 R1360R1352 Place Base Course, Sta 171+00 to 208+37 35 0% 35 04-Dec-18 04-Dec-18 24-Jan-19 19-Feb-19 19 R1342 R1362R1360 Place AC Pavement, Sta 208+37 to 245+73 4 0% 4 03-Dec-18 03-Dec-18 07-Dec-18 25-Feb-19 55 R1350 R2100, R2300R1362 Place AC Pavement, Sta 171+00 to 208+37 4 0% 4 24-Jan-19 24-Jan-19 30-Jan-19 25-Feb-19 19 R1352 R2100, R2300

Waterline Waterline Relocation/Adjustment 11 11 16-Oct-18 16-Oct-18 31-Oct-18 27-Dec-18 39MW1300 Relocate 16" GWA Waterline (1 loc.), Sta 204+30 6 0% 6 16-Oct-18 16-Oct-18 24-Oct-18 19-Dec-18 39 R1332 MW1310MW1310 24" Sewerline, Sta 205+57 to Exist SMH 5 0% 5 24-Oct-18 24-Oct-18 31-Oct-18 27-Dec-18 39 1450, MW1300 R1342

Drainage Drainage and Slope Protection Works 68 68 25-Sep-18 25-Sep-18 03-Jan-19 25-Feb-19 38DS1340 Bioswale T2, 3 &, 4 & MH, Sta 208+37 to 245+73 50 0% 50 25-Sep-18 25-Sep-18 06-Dec-18 25-Feb-19 56 R1330 R2100, R2300DS1342 Bioswale T2 & 3 and MH, Sta 171+00 to 208+37 53 0% 53 16-Oct-18 16-Oct-18 03-Jan-19 25-Feb-19 38 R1332 R2100, R2300

UndergroUnderground Electrical Works 114 114 23-Jul-18 23-Jul-18 04-Jan-19 25-Feb-19 37EW1300 D/L/B Stub-outs with caps and markers for power 10 0% 10 25-Sep-18 25-Sep-18 09-Oct-18 27-Dec-18 55 R1330 R1340EW1310 D/L/B Navy Comm Lines, Sta 208+37 to 245+73 46 0% 46 23-Jul-18 23-Jul-18 26-Sep-18 22-Oct-18 19 P1350 R1340, EW1320, EW1340EW1320 Install Wires and Cables, Sta 208+37 to 245+73 8 0% 8 26-Sep-18 26-Sep-18 08-Oct-18 04-Feb-19 82 EW1310 EW1330EW1330 Termination and Testing by NCTS 15 0% 15 08-Oct-18 08-Oct-18 29-Oct-18 25-Feb-19 82 EW1320 R2100, R2300EW1340 D/L/B Navy Comm Lines, Sta 171+00 to Sta 208+37 45 0% 45 26-Sep-18 26-Sep-18 30-Nov-18 27-Dec-18 19 EW1310 R1342, EW1350EW1350 Install Wires and Cables, Sta 171+00 to Sta 208+ 8 0% 8 30-Nov-18 30-Nov-18 12-Dec-18 04-Feb-19 37 EW1340 EW1360EW1360 Termination and Testing by NCTS 15 0% 15 12-Dec-18 12-Dec-18 04-Jan-19 25-Feb-19 37 EW1350 R2100, R2300

Phase 2 (EPhase 2 (East) 194 194 26-Feb-19 26-Feb-19 29-Nov-19 07-Jan-20 25

P2-Work ZP2-Work Zone 1, Sta. 107+34.99 to St. 136+00 112 112 26-Feb-19 26-Feb-19 02-Aug-19 09-Oct-19 47Road ConRoad Construction 112 112 26-Feb-19 26-Feb-19 02-Aug-19 02-Aug-19 0R2100 Relocate Temporary Traffic Control 5 0% 5 26-Feb-19 26-Feb-19 04-Mar-19 04-Mar-19 0 DS1150, EW1120, R11A50, DS12 R2120R2120 Clearing & Grubbing, Haul & Dispose 15 0% 15 05-Mar-19 05-Mar-19 25-Mar-19 25-Mar-19 0 R2100 R2125, R2130R2125 Remove Existing Asphalt Pavement 7 0% 7 15-Mar-19 15-Mar-19 25-Mar-19 04-Apr-19 8 R2120 EW2100, GTA2100, MW2100, R2R2130 Roadway Excavation/ Embankment 15 0% 15 15-Mar-19 15-Mar-19 04-Apr-19 04-Apr-19 0 R2120 EW2100, GTA2100, MW2100, R2R2140 Sub-base Course 5 0% 5 25-Jun-19 25-Jun-19 01-Jul-19 01-Jul-19 0 DS2110, EW2100, GTA2130, MW R2150R2150 Place Base Course 20 0% 20 02-Jul-19 02-Jul-19 30-Jul-19 30-Jul-19 0 R2140 R2160R2160 Place Asphalt Concrete Pavement 3 0% 3 31-Jul-19 31-Jul-19 02-Aug-19 02-Aug-19 0 R2150 FC1000, R2A100

Waterline Waterline Relocation/Adjustment 1 1 05-Apr-19 05-Apr-19 05-Apr-19 16-Apr-19 7MW2100 Relocate 10" Navy Waterline (1 loc.), Sta 122+65 1 0% 1 05-Apr-19 05-Apr-19 05-Apr-19 16-Apr-19 7 R2130, R2125 R2140, DS2100

Relocate GRelocate GTA Comminication Line 56 56 05-Apr-19 05-Apr-19 24-Jun-19 24-Jun-19 0GTA2100 Exploration 6 0% 6 05-Apr-19 05-Apr-19 12-Apr-19 12-Apr-19 0 R2130, R2125 GTA2110GTA2110 Dig to expose existing GTA cable 45 0% 45 15-Apr-19 15-Apr-19 17-Jun-19 17-Jun-19 0 GTA2100 GTA2120GTA2120 Notification period prior to outage 5 0% 5 15-Apr-19 15-Apr-19 19-Apr-19 19-Apr-19 0 GTA2110 GTA2130GTA2130 Relocate GTA Comm Line and backfill 45 0% 45 22-Apr-19 22-Apr-19 24-Jun-19 24-Jun-19 0 GTA2120 R2140

Drainage Drainage and Slope Protection Works 52 52 18-Apr-19 18-Apr-19 01-Jul-19 09-Oct-19 70DS2100 24" Drainline 1-A, 2-A, 2-B, 2-C, 2-D, 2-E& 3-B 40 0% 40 18-Apr-19 18-Apr-19 13-Jun-19 24-Jun-19 7 MW2100 DS2110, DS2120, EW2100DS2110 CB1-A2, CB 2-A2,B2,C2,D2,E2, CB 3-B2 40 0% 40 18-Apr-19 18-Apr-19 13-Jun-19 24-Jun-19 7 DS2100 R2140, DS2120DS2120 Infiltration TrenchBioswale and Chambers 1 0% 1 14-Jun-19 14-Jun-19 14-Jun-19 24-Sep-19 70 DS2100, DS2110 DS2140DS2140 Sidewalk Culvert with Riprap Rundown 10 0% 10 17-Jun-19 17-Jun-19 28-Jun-19 08-Oct-19 70 DS2120 DS2150DS2150 Install Pea Gravel and Engineered Soil 1 0% 1 01-Jul-19 01-Jul-19 01-Jul-19 09-Oct-19 70 DS2140 FC1000

UndergroUnderground Electrical Works 12 12 09-May-19 09-May-19 24-May-19 24-Jun-19 20EW2100 D/L/B U/G Navy Power Lines & MH 12 0% 12 09-May-19 09-May-19 24-May-19 24-Jun-19 20 R2130, DS2100, R2125 R2140

P2A-Rt 28P2A-Rt 28 Int, St 100+20-105+37.9, 10+00-13+68.6 30 30 01-Aug-19 01-Aug-19 12-Sep-19 12-Sep-19 0Road ConRoad Construction 30 30 01-Aug-19 01-Aug-19 12-Sep-19 12-Sep-19 0R2A100 Install Additional Traffic Control 2 0% 2 01-Aug-19 01-Aug-19 02-Aug-19 02-Aug-19 0 R2160 R2A110, R2A120R2A110 Clearing & Grubbing 3 0% 3 05-Aug-19 05-Aug-19 07-Aug-19 07-Aug-19 0 R2A100 R2A160, R2A162, R2A170R2A120 Saw Cut, Mill Exist. Asphalt Friction Course 3 0% 3 05-Aug-19 05-Aug-19 07-Aug-19 07-Aug-19 0 R2A100 R2A130, R2A140R2A130 Remove PC Pavement, Signs, Guardrail, Comm line 10 0% 10 08-Aug-19 08-Aug-19 21-Aug-19 21-Aug-19 0 R2A120 R2A150R2A140 Install underground electrical traffic signal 10 0% 10 08-Aug-19 08-Aug-19 21-Aug-19 21-Aug-19 0 R2A120 R2A150R2A150 Roughen Existing PCC Pavement and Clean 12 0% 12 06-Aug-19 06-Aug-19 21-Aug-19 21-Aug-19 0 R2A130, R2A140 R2A180R2A160 Adjust Top of Sewer MH to FG 5 0% 5 08-Aug-19 08-Aug-19 14-Aug-19 21-Aug-19 5 R2A110 R2A180R2A162 Relocate Fiber Optic Cable (by others/MCI) 10 0% 10 08-Aug-19 08-Aug-19 21-Aug-19 21-Aug-19 0 R2A110 R2A180R2A170 Construct Bioswale Type 5 10 0% 10 08-Aug-19 08-Aug-19 21-Aug-19 21-Aug-19 0 R2A110 R2A180R2A180 Construct Curb & Gutter w/Sidewalk and Shoulder 15 0% 15 22-Aug-19 22-Aug-19 12-Sep-19 12-Sep-19 0 R2A150, R2A160, R2A162, R2A1 FC1000, R3A100

P3-Rt 28 IP3-Rt 28 Int, St 105+37.9-107+34.99, 10+00-13+68 54 54 13-Sep-19 13-Sep-19 29-Nov-19 07-Jan-20 25Road ConRoad Construction 54 54 13-Sep-19 13-Sep-19 29-Nov-19 07-Jan-20 25R3A100 Relocate Traffic Conc Barrier 1 0% 1 13-Sep-19 13-Sep-19 13-Sep-19 13-Sep-19 0 R2A180 R3A110, R3A120R3A110 Clearing & Grubbing, Haul and Dispose 3 0% 3 16-Sep-19 16-Sep-19 18-Sep-19 02-Oct-19 10 R3A100 R3A160R3A120 Saw Cut, Mill Exist. Asphalt Friction Course 3 0% 3 16-Sep-19 16-Sep-19 18-Sep-19 18-Sep-19 0 R3A100 R3A130R3A130 Remove PCC Pavement, Signs, others 5 0% 5 19-Sep-19 19-Sep-19 25-Sep-19 25-Sep-19 0 R3A120 R3A140, R3A150R3A140 Install underground electrical traffic signal 10 0% 10 23-Sep-19 23-Sep-19 04-Oct-19 04-Oct-19 0 R3A130 R3A150R3A150 Roughen Existing PCC Pavement and Clean 8 0% 8 30-Sep-19 30-Sep-19 09-Oct-19 09-Oct-19 0 R3A130, R3A140 R3A170

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2018 2019 2020

Place Base Course, Sta 171+00 to 208+37Place Base Course, Sta 171+00 to 208+37

Place AC Pavement, Sta 208+37 to 245+73Place AC Pavement, Sta 171+00 to 208+37

Relocate 16" GWA Waterline (1 loc.), Sta 204+3024" Sewerline, Sta 205+57 to Exist SMH

Bioswale T2, 3 &, 4 & MH, Sta 208+37 to 245+73Bioswale T2 & 3 and MH, Sta 171+00 to 208+37

D/L/B Stub-outs with caps and markers for powerD/L/B Navy Comm Lines, Sta 208+37 to 245+73

Install Wires and Cables, Sta 208+37 to 245+73Termination and Testing by NCTS

D/L/B Navy Comm Lines, Sta 171+00 to Sta 208+37Install Wires and Cables, Sta 171+00 to Sta 208+

Termination and Testing by NCTS

Relocate Temporary Traffic ControlClearing & Grubbing, Haul & DisposeRemove Existing Asphalt Pavement

Roadway Excavation/ EmbankmentSub-base Course

Place Base CoursePlace Asphalt Concrete Pavement

Relocate 10" Navy Waterline (1 loc.), Sta 122+65

ExplorationDig to expose existing GTA cable

Notification period prior to outageRelocate GTA Comm Line and backfill

24" Drainline 1-A, 2-A, 2-B, 2-C, 2-D, 2-E& 3-BCB1-A2, CB 2-A2,B2,C2,D2,E2, CB 3-B2Infiltration TrenchBioswale and Chambers

Sidewalk Culvert with Riprap RundownInstall Pea Gravel and Engineered Soil

D/L/B U/G Navy Power Lines & MH

Install Additional Traffic ControlClearing & GrubbingSaw Cut, Mill Exist. Asphalt Friction Course

Remove PC Pavement, Signs, Guardrail, Comm lineInstall underground electrical traffic signalRoughen Existing PCC Pavement and Clean

Adjust Top of Sewer MH to FGRelocate Fiber Optic Cable (by others/MCI)Construct Bioswale Type 5

Construct Curb & Gutter w/Sidewalk and Shoulder

Relocate Traffic Conc BarrierClearing & Grubbing, Haul and DisposeSaw Cut, Mill Exist. Asphalt Friction CourseRemove PCC Pavement, Signs, others

Install underground electrical traffic signalRoughen Existing PCC Pavement and Clean

PROJECT NO. GU-DAR-0003(105)ROUTE 3 WIDENING (ROUTE 28 to CHALAN KARETA)

BLACK CONSTRUCTION CORPORATION

16-Aug-1728-Jan-2023-Feb-18

30-Mar-18 15:03

Remaining Level of EffortActual Work

Remaining WorkCritical Remaining Work

Milestone Page 4 of 6BASELINE SCHEDULE

TASK filter: All Activities© Oracle Corporation

Page 7: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

Activity ID Activity Name OrigDur

Activity %Complete

RemDur

Early Start Start Finish Late Finish TotalFloat

Predecessors Successors

R3A160 Adjust Valve Box, Top of Sewer & Tel. MH to FG 5 0% 5 19-Sep-19 19-Sep-19 25-Sep-19 09-Oct-19 10 R3A110 R3A170R3A170 Construct Curb & Gutter and Sidewalk 15 0% 15 10-Oct-19 10-Oct-19 30-Oct-19 30-Oct-19 0 R3A150, R3A160 R3A180, FC1000R3A180 Install Complete Traffic Signal System 30 0% 30 17-Oct-19 17-Oct-19 29-Nov-19 07-Jan-20 25 1950, R3A170 C5000

P2-Work ZP2-Work Zone 2, Sta 136+00 to 171+00 128 128 15-Mar-19 15-Mar-19 13-Sep-19 30-Oct-19 33Road ConRoad Construction 103 103 15-Mar-19 15-Mar-19 08-Aug-19 13-Sep-19 25R2200 Relocate Traffic Conc Barrier 6 0% 6 15-Mar-19 15-Mar-19 22-Mar-19 26-Apr-19 25 R2130, R2125 R2220R2220 Clearing & Grubbing, Haul and Dispose 15 0% 15 25-Mar-19 25-Mar-19 12-Apr-19 17-May-19 25 R2200 R2224R2224 Remove Existing Asphalt Pavement 8 0% 8 03-Apr-19 03-Apr-19 12-Apr-19 17-May-19 25 R2220 R2230R2230 Roadway Excavation 15 0% 15 15-Apr-19 15-Apr-19 03-May-19 10-Jun-19 25 R2224 EW2200, GTA2200, MW2200R2240 Sub-base Course 5 0% 5 08-Jul-19 08-Jul-19 12-Jul-19 16-Aug-19 25 DS2210, EW2200, GTA2230, MW R2250R2250 Place Base Course 15 0% 15 15-Jul-19 15-Jul-19 02-Aug-19 09-Sep-19 25 R2240 R2260R2260 Place Asphalt Concrete Pavement 4 0% 4 05-Aug-19 05-Aug-19 08-Aug-19 13-Sep-19 25 R2250 B2100, FC1000, R3200

BiofiltratioBiofiltration Basin (Finish) 25 25 09-Aug-19 09-Aug-19 13-Sep-19 30-Oct-19 33B2100 Remove Top of 6" Filter Sand 3 0% 3 09-Aug-19 09-Aug-19 13-Aug-19 30-Sep-19 33 B1150, R2260 B2125B2125 Drill hole & Install 6' H chain link fence, gate 20 0% 20 14-Aug-19 14-Aug-19 11-Sep-19 28-Oct-19 33 B2100 B2150B2150 Place 6" thk. Top Soil and Hydroseed 2 0% 2 12-Sep-19 12-Sep-19 13-Sep-19 30-Oct-19 33 B2125 FC1000

Waterline Waterline Relocation/Adjustment 1 1 06-May-19 06-May-19 06-May-19 11-Jun-19 25MW2200 Relocate 12" GWA Waterline (2 loc.) 1 0% 1 06-May-19 06-May-19 06-May-19 11-Jun-19 25 R2230 R2240, DS2200

Relocate GRelocate GTA Communication Line 9 9 06-May-19 06-May-19 16-May-19 09-Aug-19 59GTA2200 Exploration 1 0% 1 06-May-19 06-May-19 06-May-19 30-Jul-19 59 R2230 GTA2210GTA2210 Dig to expose existing GTA cable 3 0% 3 07-May-19 07-May-19 09-May-19 02-Aug-19 59 GTA2200 GTA2220GTA2220 Notification period prior to outage 5 0% 5 07-May-19 07-May-19 13-May-19 06-Aug-19 59 GTA2210 GTA2230GTA2230 Relocate GTA Comm Line and backfill 3 0% 3 14-May-19 14-May-19 16-May-19 09-Aug-19 59 GTA2220 R2240

Drainage Drainage and Slope Protection Works 65 65 16-May-19 16-May-19 16-Aug-19 23-Sep-19 25DS2200 24" Drainline 4-C, 6-A, 8-A CB-4-C1 & CB-6A2 15 0% 15 16-May-19 16-May-19 06-Jun-19 12-Jul-19 25 MW2200 DS2210DS2210 Infiltration Trench T2&3 Bioswale T2&3, chamber 50 0% 50 07-Jun-19 07-Jun-19 16-Aug-19 23-Sep-19 25 DS2200 R2240, FC1000

UndergroUnderground Electrical Works 36 36 06-May-19 06-May-19 25-Jun-19 30-Oct-19 89EW2200 D/L/B U/G Navy Power Lines & MH 28 0% 28 06-May-19 06-May-19 13-Jun-19 09-Aug-19 40 R2230 R2240, EW2210EW2210 Install Wires and Cables 3 0% 3 14-Jun-19 14-Jun-19 18-Jun-19 23-Oct-19 89 EW2200 EW2220EW2220 Termination and Testing by NCTS 5 0% 5 19-Jun-19 19-Jun-19 25-Jun-19 30-Oct-19 89 EW2210 FC1000

P3-AreterP3-Aretero Road Intersection (Sheet 359) 19 19 09-Aug-19 09-Aug-19 05-Sep-19 10-Oct-19 25Road ConRoad Construction 19 19 09-Aug-19 09-Aug-19 05-Sep-19 10-Oct-19 25R3200 Install Traffic Control 1 0% 1 09-Aug-19 09-Aug-19 09-Aug-19 16-Sep-19 25 R2260 R3210R3210 Clearing, Remove Exist ACP, GR, Box,Headwalls 3 0% 3 12-Aug-19 12-Aug-19 14-Aug-19 19-Sep-19 25 R3200 R3220R3220 Roadway Excavation/Embankment 1 0% 1 15-Aug-19 15-Aug-19 15-Aug-19 20-Sep-19 25 R3210 R3230, R3240R3230 Install 24" Pipe Culvert (90') and Headwall 5 0% 5 16-Aug-19 16-Aug-19 22-Aug-19 27-Sep-19 25 R3220 R3250R3240 Install Underground Elect-Tel & Trafic Signal 8 0% 8 16-Aug-19 16-Aug-19 27-Aug-19 02-Oct-19 25 R3220 R3250R3250 Construct Sidewalk, Curb and Gutter 8 0% 8 23-Aug-19 23-Aug-19 04-Sep-19 09-Oct-19 25 R3230, R3240 R3260R3260 Place AC Pavement 1 0% 1 05-Sep-19 05-Sep-19 05-Sep-19 10-Oct-19 25 R3250 R4200

P4-AreterP4-Aretero Road Intersection (Sheet 363) 44 44 06-Sep-19 06-Sep-19 06-Nov-19 07-Jan-20 40Road ConRoad Construction 44 44 06-Sep-19 06-Sep-19 06-Nov-19 07-Jan-20 40R4200 Install Traffic Control 1 0% 1 06-Sep-19 06-Sep-19 06-Sep-19 11-Oct-19 25 R3260 R4210R4210 Clearing/Remove Exist ACP, Box and Headwalls 3 0% 3 09-Sep-19 09-Sep-19 11-Sep-19 16-Oct-19 25 R4200 R4220R4220 Roadway Excavation/Embankment 2 0% 2 12-Sep-19 12-Sep-19 13-Sep-19 18-Oct-19 25 R4210 R4240R4240 Install Underground Elect- Tel & Traffic Signal 8 0% 8 16-Sep-19 16-Sep-19 25-Sep-19 30-Oct-19 25 R4220 R4250R4250 Construct Paved and Gravel Shoulder 2 0% 2 23-Sep-19 23-Sep-19 24-Sep-19 29-Oct-19 25 R4240 R4260R4260 Place AC Pavement 1 0% 1 25-Sep-19 25-Sep-19 25-Sep-19 30-Oct-19 25 R4250 R4270, FC1000R4270 Install Complete Traffic Signal System 30 0% 30 26-Sep-19 26-Sep-19 06-Nov-19 07-Jan-20 40 R4260 C5000

P2-Work ZP2-Work Zone 3, Sta. 171+00 to Sta 245+73 130 130 26-Feb-19 26-Feb-19 28-Aug-19 30-Oct-19 44Road ConRoad Construction 120 120 26-Feb-19 26-Feb-19 14-Aug-19 09-Oct-19 39R2300 Relocate Temporary Traffic Control 10 0% 10 26-Feb-19 26-Feb-19 11-Mar-19 30-Apr-19 36 DS1150, EW1120, R11A50, DS12 R2320R2320 Clearing & Grubbing, Haul & Dispose 25 0% 25 05-Mar-19 05-Mar-19 08-Apr-19 29-May-19 36 R2300 R2330, R2333R2330 Roadway Excav/Embank, Sta 208+37 to 245+73 15 0% 15 19-Mar-19 19-Mar-19 08-Apr-19 29-May-19 36 R2320 R2332, R2335, MW2300, GTA23R2332 Roadway Excav/Embak, Sta 171+00 to 208+37 16 0% 16 09-Apr-19 09-Apr-19 30-Apr-19 01-Jul-19 43 R2330 R2336R2333 Remove Existg AC Pavement, Sta 208+37 to 245+73 9 0% 9 19-Mar-19 19-Mar-19 29-Mar-19 29-May-19 42 R2320 R2334, R2335R2334 Remove Existg AC Pavement, Sta 171+00 to 208+37 9 0% 9 01-Apr-19 01-Apr-19 11-Apr-19 01-Jul-19 56 R2333 R2336R2335 Install U/G Utility, Sta 208+37 to 245+73 44 0% 44 09-Apr-19 09-Apr-19 10-Jun-19 31-Jul-19 36 R2333, R2330 R2340R2336 Install U/G Utility, Sta 171+00 to 208+37 44 0% 44 01-May-19 01-May-19 02-Jul-19 03-Sep-19 43 R2332, R2334 R2342R2340 Sub-base Course, Sta 208+37 to 245+73 2 0% 2 11-Jun-19 11-Jun-19 12-Jun-19 02-Aug-19 36 GTA2330, MW2330, R2335 R2350, R2342R2342 Sub-base Course, Sta 171+00 to 208+37 2 0% 2 03-Jul-19 03-Jul-19 05-Jul-19 05-Sep-19 43 R2336, R2340 R2352R2350 Place Base Course, Sta 208+37 to 245+73 20 0% 20 13-Jun-19 13-Jun-19 11-Jul-19 30-Aug-19 36 R2340 R2360, EW2300, R2352R2352 Place Base Course, Sta 171+00 to 208+37 20 0% 20 12-Jul-19 12-Jul-19 08-Aug-19 03-Oct-19 39 R2342, R2350 R2362R2360 Place AC Pavement, Sta 208+37 to 245+73 4 0% 4 12-Jul-19 12-Jul-19 17-Jul-19 06-Sep-19 36 R2350 FC2000, R3300

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2018 2019 2020

Adjust Valve Box, Top of Sewer & Tel. MH to FGConstruct Curb & Gutter and Sidewalk

Install Complete Traffic Signal System

Relocate Traffic Conc BarrierClearing & Grubbing, Haul and DisposeRemove Existing Asphalt Pavement

Roadway ExcavationSub-base Course

Place Base CoursePlace Asphalt Concrete Pavement

Remove Top of 6" Filter SandDrill hole & Install 6' H chain link fence, gatePlace 6" thk. Top Soil and Hydroseed

Relocate 12" GWA Waterline (2 loc.)

ExplorationDig to expose existing GTA cableNotification period prior to outageRelocate GTA Comm Line and backfill

24" Drainline 4-C, 6-A, 8-A CB-4-C1 & CB-6A2Infiltration Trench T2&3 Bioswale T2&3, chamber

D/L/B U/G Navy Power Lines & MHInstall Wires and Cables

Termination and Testing by NCTS

Install Traffic ControlClearing, Remove Exist ACP, GR, Box,HeadwallsRoadway Excavation/Embankment

Install 24" Pipe Culvert (90') and HeadwallInstall Underground Elect-Tel & Trafic Signal

Construct Sidewalk, Curb and GutterPlace AC Pavement

Install Traffic ControlClearing/Remove Exist ACP, Box and HeadwallsRoadway Excavation/Embankment

Install Underground Elect- Tel & Traffic SignalConstruct Paved and Gravel ShoulderPlace AC Pavement

Install Complete Traffic Signal System

Relocate Temporary Traffic ControlClearing & Grubbing, Haul & DisposeRoadway Excav/Embank, Sta 208+37 to 245+73

Roadway Excav/Embak, Sta 171+00 to 208+37Remove Existg AC Pavement, Sta 208+37 to 245+73

Remove Existg AC Pavement, Sta 171+00 to 208+37Install U/G Utility, Sta 208+37 to 245+73

Install U/G Utility, Sta 171+00 to 208+37Sub-base Course, Sta 208+37 to 245+73

Sub-base Course, Sta 171+00 to 208+37Place Base Course, Sta 208+37 to 245+73

Place Base Course, Sta 171+00 to 208+37Place AC Pavement, Sta 208+37 to 245+73

PROJECT NO. GU-DAR-0003(105)ROUTE 3 WIDENING (ROUTE 28 to CHALAN KARETA)

BLACK CONSTRUCTION CORPORATION

16-Aug-1728-Jan-2023-Feb-18

30-Mar-18 15:03

Remaining Level of EffortActual Work

Remaining WorkCritical Remaining Work

Milestone Page 5 of 6BASELINE SCHEDULE

TASK filter: All Activities© Oracle Corporation

Page 8: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

Activity ID Activity Name OrigDur

Activity %Complete

RemDur

Early Start Start Finish Late Finish TotalFloat

Predecessors Successors

R2362 Place AC Pavement, Sta 171+00 to 208+37 4 0% 4 09-Aug-19 09-Aug-19 14-Aug-19 09-Oct-19 39 R2352 FC2000Waterline Waterline Relocation/Adjustment 18 18 09-Apr-19 09-Apr-19 02-May-19 31-Jul-19 62MW2300 Relocate 10" Navy Waterline (1 loc.), Sta 233+93 6 0% 6 09-Apr-19 09-Apr-19 16-Apr-19 15-Jul-19 62 R2330 MW2310MW2310 Relocate 16" GWA Waterline (1 loc.), Sta 233+93 6 0% 6 17-Apr-19 17-Apr-19 24-Apr-19 23-Jul-19 62 MW2300 MW2330MW2330 24" Sewerline, Connect to Exist SMH @ Sta 203+82 6 0% 6 25-Apr-19 25-Apr-19 02-May-19 31-Jul-19 62 MW2310 R2340

Relocate GRelocate GTA Communication Line 19 19 09-Apr-19 09-Apr-19 03-May-19 31-Jul-19 61GTA2300 Exploration, Sta 235+00 to 240+00 2 0% 2 09-Apr-19 09-Apr-19 10-Apr-19 08-Jul-19 61 R2330 GTA2310GTA2310 Dig to expose exist GTA cable, Sta 235+00 to 240 12 0% 12 11-Apr-19 11-Apr-19 26-Apr-19 24-Jul-19 61 GTA2300 GTA2320GTA2320 Notification Period, Sta 235+00 to 240+00 5 0% 5 11-Apr-19 11-Apr-19 17-Apr-19 15-Jul-19 61 GTA2310 GTA2330GTA2330 Relocate GTA Comm Line & backfill, Sta 2035+00 12 0% 12 18-Apr-19 18-Apr-19 03-May-19 31-Jul-19 61 GTA2320 R2340

Drainage Drainage and Slope Protection Works 100 100 09-Apr-19 09-Apr-19 28-Aug-19 30-Oct-19 44DS2340 Bioswale T2, 3 &, 4 & MH, Sta 208+37 to 245+73 60 0% 60 09-Apr-19 09-Apr-19 02-Jul-19 04-Sep-19 44 R2330 DS2350DS2350 Bioswale T2 & 3 and MH, Sta 171+00 to 208+37 40 0% 40 03-Jul-19 03-Jul-19 28-Aug-19 30-Oct-19 44 DS2340 FC2000

UndergroUnderground Electrical Works 9 9 12-Jul-19 12-Jul-19 24-Jul-19 30-Oct-19 69EW2300 D/L/B U/G Navy Power Lines & MH 3 0% 3 12-Jul-19 12-Jul-19 16-Jul-19 22-Oct-19 69 R2350 EW2310EW2310 Install Wires and Cables 1 0% 1 17-Jul-19 17-Jul-19 17-Jul-19 23-Oct-19 69 EW2300 EW2320EW2320 Termination and Testing by GPA 5 0% 5 18-Jul-19 18-Jul-19 24-Jul-19 30-Oct-19 69 EW2310 FC2000

P3-ChalanP3-Chalan Kareta Intersection (Sheet 358) 18 18 16-Jul-19 16-Jul-19 08-Aug-19 30-Sep-19 36Road ConRoad Construction 18 18 16-Jul-19 16-Jul-19 08-Aug-19 30-Sep-19 36R3300 Install Traffic Control 1 0% 1 16-Jul-19 16-Jul-19 16-Jul-19 05-Sep-19 36 R2360 R3310R3310 Clearing, Remove Existing ACP, Signs 2 0% 2 17-Jul-19 17-Jul-19 18-Jul-19 09-Sep-19 36 R3300 R3320R3320 Roadway Excavation/Embankment 1 0% 1 19-Jul-19 19-Jul-19 19-Jul-19 10-Sep-19 36 R3310 R3330, R3340R3330 Install 24" Pipe Culvert (100') 4 0% 4 22-Jul-19 22-Jul-19 25-Jul-19 17-Sep-19 37 R3320 R3350R3340 Install Underground Electrical Traffic Signal 10 0% 10 22-Jul-19 22-Jul-19 02-Aug-19 24-Sep-19 36 R3320 R3350R3350 Construct Sidewalk, Curb and Gutter 8 0% 8 29-Jul-19 29-Jul-19 07-Aug-19 27-Sep-19 36 R3340, R3330 R3360R3360 Place AC Pavement 1 0% 1 08-Aug-19 08-Aug-19 08-Aug-19 30-Sep-19 36 R3350 R4300

P3-ChalanP3-Chalan Kareta Intersection (Sheet 362) 52 52 09-Aug-19 09-Aug-19 22-Oct-19 07-Jan-20 51Road ConRoad Construction 52 52 09-Aug-19 09-Aug-19 22-Oct-19 07-Jan-20 51R4300 Relocate Traffic Control 1 0% 1 09-Aug-19 09-Aug-19 09-Aug-19 01-Oct-19 36 R3360 R4310R4310 Clearing, Remove Existing ACP, Signs 2 0% 2 12-Aug-19 12-Aug-19 13-Aug-19 03-Oct-19 36 R4300 R4320R4320 Roadway Excavation/Embankment 10 0% 10 14-Aug-19 14-Aug-19 27-Aug-19 17-Oct-19 36 R4310 R4340R4340 Install Underground Elect- Tel & Taffic Signal 8 0% 8 28-Aug-19 28-Aug-19 09-Sep-19 29-Oct-19 36 R4320 R4350R4350 Construct Paved and Gravel Shoulder 2 0% 2 06-Sep-19 06-Sep-19 09-Sep-19 29-Oct-19 36 R4340 R4360R4360 Place AC Pavement 1 0% 1 10-Sep-19 10-Sep-19 10-Sep-19 30-Oct-19 36 R4350 R4370, FC2000, PP100R4370 Install Complete Traffic Signal System 30 0% 30 11-Sep-19 11-Sep-19 22-Oct-19 07-Jan-20 51 R4360 C5000

Balance ofBalance of Work to Complete 81 81 11-Sep-19 11-Sep-19 07-Jan-20 07-Jan-20 0

Friction CFriction Course. Signs and Markings, WZ-1 & WZ-2 45 45 31-Oct-19 31-Oct-19 07-Jan-20 07-Jan-20 0FC1000 Place Friction Course 10 0% 10 31-Oct-19 31-Oct-19 13-Nov-19 13-Nov-19 0 R2160, DS2150, R2A180, R3A17 FC1050, FC1100, FC1150FC1050 Place Guard Rail, TRM Section, Structure Trans 10 0% 10 14-Nov-19 14-Nov-19 29-Nov-19 07-Jan-20 25 FC1000 C5000FC1100 Place Permanent Traffic Controls, Signs 30 0% 30 04-Nov-19 04-Nov-19 17-Dec-19 07-Jan-20 13 FC1000 C5000FC1150 Place Pavement Marking and Markers 30 0% 30 25-Nov-19 25-Nov-19 07-Jan-20 07-Jan-20 0 FC1000 C5000

Friction CFriction Course. Signs and Markings, WZ-3 45 45 11-Sep-19 11-Sep-19 12-Nov-19 07-Jan-20 36FC2000 Place Friction Course 10 0% 10 11-Sep-19 11-Sep-19 24-Sep-19 13-Nov-19 36 R2360, R2362, DS2350, EW2320 FC2100, FC2200FC2100 Place Permanent Traffic Controls, Signs 30 0% 30 13-Sep-19 13-Sep-19 24-Oct-19 07-Jan-20 49 FC2000 C5000FC2200 Place Pavement Marking and Markers 30 0% 30 02-Oct-19 02-Oct-19 12-Nov-19 07-Jan-20 36 FC2000 C5000

8" Pedest8" Pedestrian Path 13 13 11-Sep-19 11-Sep-19 27-Sep-19 07-Jan-20 68PP100 Fine Grade Re-compact Aggregate Base 6 0% 6 11-Sep-19 11-Sep-19 18-Sep-19 26-Dec-19 68 R4360 PP110PP110 4" Conc. Walk, Sta 137+29 to 141+64.47 (435LF) 1 0% 1 19-Sep-19 19-Sep-19 19-Sep-19 27-Dec-19 68 PP100 PP120PP120 2" HACP, Sta 141+64.47 to Sta 227+ (8,556LF) 6 0% 6 20-Sep-19 20-Sep-19 27-Sep-19 07-Jan-20 68 PP110 C5000

Close-outClose-out 15 15 08-Jan-20 08-Jan-20 28-Jan-20 28-Jan-20 0C5000 Pre-final Inspection/Punchlist 10 0% 10 08-Jan-20 08-Jan-20 21-Jan-20 21-Jan-20 0 R3A180, R4270, R4370, FC1050 C5030C5030 Clean-up/Demobilization 5 0% 5 22-Jan-20 22-Jan-20 28-Jan-20 28-Jan-20 0 C5000

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2018 2019 2020

Place AC Pavement, Sta 171+00 to 208+37

Relocate 10" Navy Waterline (1 loc.), Sta 233+93Relocate 16" GWA Waterline (1 loc.), Sta 233+93

24" Sewerline, Connect to Exist SMH @ Sta 203+82

Exploration, Sta 235+00 to 240+00Dig to expose exist GTA cable, Sta 235+00 to 240

Notification Period, Sta 235+00 to 240+00Relocate GTA Comm Line & backfill, Sta 2035+00

Bioswale T2, 3 &, 4 & MH, Sta 208+37 to 245+73Bioswale T2 & 3 and MH, Sta 171+00 to 208+37

D/L/B U/G Navy Power Lines & MHInstall Wires and Cables

Termination and Testing by GPA

Install Traffic ControlClearing, Remove Existing ACP, SignsRoadway Excavation/EmbankmentInstall 24" Pipe Culvert (100')

Install Underground Electrical Traffic SignalConstruct Sidewalk, Curb and GutterPlace AC Pavement

Relocate Traffic ControlClearing, Remove Existing ACP, Signs

Roadway Excavation/EmbankmentInstall Underground Elect- Tel & Taffic SignalConstruct Paved and Gravel ShoulderPlace AC Pavement

Install Complete Traffic Signal System

Place Friction CoursePlace Guard Rail, TRM Section, Structure Tra

Place Permanent Traffic Controls, SignsPlace Pavement Marking and Marker

Place Friction CoursePlace Permanent Traffic Controls, Signs

Place Pavement Marking and Markers

Fine Grade Re-compact Aggregate Base4" Conc. Walk, Sta 137+29 to 141+64.47 (435LF)

2" HACP, Sta 141+64.47 to Sta 227+ (8,556LF)

Pre-final Inspection/PunchlistClean-up/Demobilization

PROJECT NO. GU-DAR-0003(105)ROUTE 3 WIDENING (ROUTE 28 to CHALAN KARETA)

BLACK CONSTRUCTION CORPORATION

16-Aug-1728-Jan-2023-Feb-18

30-Mar-18 15:03

Remaining Level of EffortActual Work

Remaining WorkCritical Remaining Work

Milestone Page 6 of 6BASELINE SCHEDULE

TASK filter: All Activities© Oracle Corporation

Page 9: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18
Page 10: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18
Page 11: GU-DAR-0003(105) - guamwaterworks.orgguamwaterworks.org/wp-content/uploads/2018/04/Addendum-No.-7... · 400 Submit Hazard Analysis & Critical Point 19 100% 0 02-Jan-18 A 26-Jan-18

REVISIONDESCRIPTIONDATENo.BY

DESIGN:

CHECKED:

RECOMMENDED:

APPROVED:

DATE:

SCALE:

DRAWN:

7/31/2017TERRITORY

GUAM

PROJECT NAME

PROJECT NO.

DWG. NO. SHEET

NOT FOR CONSTRUCTION C-22

GWA INTERCEPTOR SEWER REFURBISHMENT PROJECT

GUAM WATERWORKS AUTHORITYGOVERNMENT OF GUAM

tmccormack
Image
tmccormack
Image
tmccormack
Image
tmccormack
Image
tmccormack
Image
tmccormack
Image
tmccormack
Image
tmccormack
Text Box
3
tmccormack
Text Box
4
tmccormack
Text Box
5
tmccormack
Text Box
6
tmccormack
Text Box
7
tmccormack
Text Box
8
tmccormack
Text Box
9
tmccormack
Image
tmccormack
Image
tmccormack
Text Box
2
tmccormack
Text Box
1
tmccormack
Text Box
DRAFT
tmccormack
Text Box
SEE C-09
tmccormack
Text Box
SEE C-12
tmccormack
Text Box
SEE C-14
tmccormack
Text Box
SEE C-14
tmccormack
Text Box
SEE C-14
tmccormack
Text Box
SEE C-16
tmccormack
Text Box
SEE C-16
tmccormack
Text Box
SEE C-21
tmccormack
Text Box
SEE C-21
LCatalano
Text Box
1
LCatalano
Text Box
4-18
LCatalano
Text Box
L
LCatalano
Text Box
Photo reference update
LCatalano
Cloud+
LCatalano
Cloud+
Rev 1
LCatalano
Polygon