Group Meeting – Pepco Holdings, Inc. July 17, 2014
-
Upload
stanislav-nikita -
Category
Documents
-
view
19 -
download
3
description
Transcript of Group Meeting – Pepco Holdings, Inc. July 17, 2014
Group Meeting – Pepco Holdings, Inc.July 17, 2014
2
Use common model and algorithms to:– Make PV analysis a standard part of:
• Planning• Operations Monitoring
– Evaluate impact of PV/DER at feeder and transmission level
Objectives
Topic A1 60 Study Circuits
Build and major validation/correction review complete Measurement collection complete Device setting collection continuing
Completed device setting for Voltage Headroom and DA circuits
Study feeder description Short and stiff, long with high impedance, highly loaded, lightly
loaded, mix of different type customers – residential, industrial, commercial, overhead, underground, feeders with high PV saturation, feeders that are part of a Distribution Automation scheme that can’t currently operate because of a large solar farm, and then a grouping of feeders and substations where high penetration will have an impact on the transmission system.
Remaining work Compare analysis for base case and Voltage Headroom
case
1. Activities
3
1. Activities
4
Topic A2 Voltage headroom circuit selected Utilizing existing monitoring equipment and equipping a
voltage regulator bank with SCADA communications and control
Remaining Year 1 Work Complete Voltage Headroom design and define test procedure
Topic A3 Significant analysis refinement completed
Running testing analysis using study circuits Refining displays and time-series use of measurements and
load data Remaining Year 1 Work
Update and test PV interconnect criteria Compare analysis results for new and old interconnect
criteria
1. Activities
5
Topic B4 Have Forecast, Schedule, Monitor and Adjust
(FSMA) Running Conservation Voltage Reduction (CVR) using
capacitors, LTC’s and Voltage Regulators Forecasting operation Comparing against actual results Have method for defining load profile/scenarios
Have control parts of PV complete Adding PV to CVR control functionality Remaining Year 1 Work
Compare base case and controller case performance results
Accomplishments Held on site training and analysis code
feedback with PHI PV Group and Planners Completed model builds and model build
checks for 60 study circuits Collected circuit and load measurements
for analysis Time-series load measurements set for
automated attachment to all circuits Time-series circuit measurements set for
automated attachment to Voltage Headroom and Auto-reconfiguration scheme circuits
2. Accomplishments
6
3. Roadblocks
7
Model correction and validation
Critical part of making PV analysis a standard part planning and operation management
Taking more time to complete than planned
Breaking up into two parts: Initial model-build, automated
corrections Main work for this is complete. Plan to continue to
refine as this is used over the next 6 months Manual corrections
Need to simplify collection and automated use of corrections made by engineers as a part of running analysis on circuits
This will be the model build focus for the next 6 month
8
Lessons Learned Questions for the DOE
4. Lessons Learned & Questions
PV Hosting Capacity Analysis
Existing Feeder
Optimized Feeder
Analysis: Phase balance, Cap Placement, Voltage Regulator Placement & Settings, Check protection/coordination
Quantify: Improvement cost, Feeder performance impact, PV hosting impact
Run optimized feeder setup to include: Voltage Head Room ConfigurationAutonomous ControlCentral Control
Quantify: Improvement cost, Feeder performance impact, PV hosting impact
Classify circuits in terms of how much PV can be added without violating operating criteria
10
Pilot Feeder Instrumentation
PV Systems. With 480 V monitors
Pole-Mount Monitors
• Existing Monitoring
11
Pilot Feeder Instrumentation
• EPRI Pole Mount voltage and irradiance monitors installed March 2012
12
Pilot Feeder Instrumentation
INSTALLSCADA
Communications on Regulator
PV Systems. With 480 V monitors
Pole-Mount Monitors
• To be installed
13
Pilot Feeder
V. Reg.
V. Reg.
V. Reg.
Zone 1
Zone 2Zone 3
Zone 4
PV Systems.
• Voltage Regulation zones
14
PV Overvoltage at Low Load
• High voltage occurs at PV systems in Zone 2 during min load
0 5 10 15 20 25 30121122123124125126127128129
Voltage Plot to PV System #1
Distance from Substation (1,000 ft)
Volta
ge (1
20 V
Bas
e)
15
Min Load Feeder Profile
• PV penetration limited by high voltage during min load, when voltage profile is relatively flat
10 20 30 40 50 60 70120
121
122
123
124
125
126
127
128
129
Voltage Plot by Voltage Regulation Zone
Zone 1Zone 2Zone 3Zone 4
Distance from Substation (1000 ft.)
Volta
ge (1
20 V
Bas
e)
PV Site Overvoltage
16
Min Load Feeder Profile
• SCADA control of regulator allows for manual reduction of voltage for demonstration of concept
10 20 30 40 50 60 70120
121
122
123
124
125
126
Voltage Plot by Voltage Regulation Zone
Zone 1Zone 2Zone 3Zone 4
Distance from Substation (1000 ft.)
Volta
ge (1
20 V
Bas
e)
• Reducing voltage in zone 2 solves overvoltage problem without creating low voltage based on model predictions
17
PV Operations Management (FSMA)
• FSMA: Forecast, Schedule, Monitor and Adjust– Use for:
• Operations Monitoring• Planning and control simulation
– Currently running coordinated control• LTC’s, voltage regulators and capacitors• Just added PV as controllable devices
• Simulator– Separate copy of Dew that uses same
model used for control, to play the role of the system
18
Use simulator to:– See system response
to control, device state and load change
– Test & develop control– Test & develop display
User can set:– Load points/curve– Capacitor states– Voltage regulator states– PV inverter control
FSMA Control– Can be run against
simulator or real system
Model-Based Simulator
19
FSMA– Control can be run
against simulator or real system through connection to SCADA
PV Operations Management (FSMA)