Group Exercise VSM Completion and Reflection - WCM...Value Stream Mapping Standard Work 4 Implement...
Transcript of Group Exercise VSM Completion and Reflection - WCM...Value Stream Mapping Standard Work 4 Implement...
Supply Chain Academy
Group Exercise – VSM Completion and Reflection
1
Supply Chain Academy 2
WCM Supplier Academy – Speaker Introduction
Eric Dvorachek – Senior Manager Supplier Development Supply Chain Operations Oshkosh Corporation
Supply Chain Academy
Supply Chain Academy
3
Supply Chain Academy4
Facilitator: CI Joe
Event: Lean Quad Production VSM Project Team Leader: Bob Bilder
Last Updated: 10/8/2020 CIE Date:
No. Opportunity Action Owner
Target
Completion
Date
Results (Estimated
Savings Expected)
%
Statu
s
Comments
1 Cut change over time in half. Organize a change over reduction project. CI Joe 10/8/202050% Reduction in
Change Over time25% 50% 75% 100%
Standard Work
5S
SMED (Not covered in this event)
2 Rebalance the line.
Line balance analysis has helped to determine the optimal
distribution of value-added work. The fender base will be
moved from Body to Chassis. The roll bar will be moved
from Body to Trim. New standard work has been developed
to reflect the move.
Bob Bilder 10/8/2020
Assembly time less than
30 seconds at all
stations.
25% 50% 75% 100%
Value Stream Mapping
Capacity Management
Standard Work
3 Implement Cellular Manufacturing.
The Body and Trim stations will swap places to create a
cellular flow through the facility and minimize material transit
time.
Bob Bilder 10/8/2020Transportation time cut to
2 seconds or less25% 50% 75% 100%
Value Stream Mapping
Standard Work
4Implement a production pull system reacting
to customer demand.
Assemblers will build assemblies based on next station
needs.Bob Bilder 10/8/2020 65% Reduction in WIP 25% 50% 75% 100%
Value Stream Mapping
5S
Capacity Management
Standard Work
5Implement a Kit and Pull strategy for raw
material.
Material will be removed from the manufacturing floor to a
common stock room. Emmet 10/8/2020
50% increase in
production floor space25% 50% 75% 100%
PFEP (See PFEP Bootcamp)
5S
Mistake Proofing
Standard Work
5.1
Material will continue to be organized by workstation.
A new team member will generate standard kits to be
delivered to the stations on a milk run.
Emmet 10/8/2020100% OTD or parts line
side.
5.22 non-standard components will be delivered via a Kanban
card at the workstation.Emmet 10/8/2020
50% reduction in on-hand
inventory of low volume
conponents
6Cut machine downtime occurance in half.
(MTBF = Mean Time Between Failure)
Improvement to our preventive maintenance strategy and
systemBob Bilder 10/8/2020
50% Reduction in
unplanned Dwontime25% 50% 75% 100%
TPM
Standard Work
7Cut average machine repair time in half.
(MTTR = Mean Time to Repair)Make improvements to our spare parts strategy Bob Bilder 10/8/2020
50% Reduction in MTTR 25% 50% 75% 100%
TPM
5S
Standard Work7.1 Develop standard repair tool kits Bob Bilder 10/8/2020
8 25% 50% 75% 100%
9 25% 50% 75% 100%
Continuous Improvement Event (CIE) Action Plan
Supply Chain Academy 5
Single Point Scheduling
Change Over Reduction
Pull System
Line Balance
Inspector Repairs
Defects?
KEEP YOUR CURRENT AND FUTURE STATE VALUE STREAM MAPS. YOU WILL NEED THEM.
Material Strategy
Supply Chain Academy
Materials Supplier
Customer
MRP
Production
Control
Future Condition Value Stream Map
Chassis Body Trim Inspect
1Associates Staff
26Cycle Time Sec
40.5 Sec
10Changeover
Loss Per ItemSec
2.5Downtime
Loss Per ItemSec
90 Sec
41 Sec 35 Sec
45 Sec
17 Sec
0 Sec45 Sec0 Sec
2Transport
TimeSec
0Queue Sec 90Queue Sec 45Queue Sec 45Queue Sec 0Queue Sec
1Associates Staff
29Cycle Time Sec
5Changeover
Loss Per ItemSec
5Downtime
Loss Per ItemSec
2Transport
TimeSec
1Associates Staff
28Cycle Time Sec
5Changeover
Loss Per ItemSec
0Downtime
Loss Per ItemSec
2Transport
TimeSec
1Associates Staff
15Cycle Time Sec
0Changeover
Loss Per ItemSec
0Downtime
Loss Per ItemSec
2Transport
TimeSec
Cycle
Tim
e (
se
c)
Station5
10
15
20
25
30
35
40
45
50
55
60
65
Chassis Body Trim Inspect
TAKT
313.5 Sec
180
133.5
Idle
Time
Station
TIme
Idle Time + Station Time = Production Lead Time =
6
Current State Results:
Product Idle Time = 765 Sec
Total Station Time = 165 Sec
Product Lead Time = 930 Sec = 15.4 Min
Supply Chain Academy
7
Let’s see what that looks like in the factory…
Supply Chain Academy8
Metrics
# Safety Incidents 1
# Defects 4
Final Ending Inventory for Chassis (from chassis sheet) $450
Final Ending Inventory for Body (from body sheet) $3,850
Final Ending Inventory for Trim (from trim sheet) $1,200
# Unsold (WIP) at Inspect/Ship 2
Unsold (WIP) Inventory Cost $2,400
# Units sold at Inspect/Ship 16
Sold Inventory Cost $19,200
# Scrap at Inspect/Ship (found at inspect/ship) 4
Scrap Inventory Cost $4,800
# Scrap (Re-inspects) (found by customer) 0
Scrap (Re-inspects) Inventory Cost $0
Total Inventory Costs $31,900
# Defective Quads Sold to Customer 0
Re-inspection Fees (# Defective Quads Sold * $1000) $0
# Customer Orders Missed 9
$ Loss for Missed Orders (# Missed Orders * $600) $5,400
Total Costs $37,300
# Units Delivered & Accepted 16
Revenue (# Good Quads Sold * Revenue) $28,800
Total Profit/Loss (Revenue - Costs) ($8,500)
On Time Delivery 64%
Pre-Event KPIs
# Safety Incidents 0
# Defects 1
Final Ending Inventory for Chassis (from chassis sheet) $500
Final Ending Inventory for Body (from body sheet) $600
Final Ending Inventory for Trim (from trim sheet) $350
# Unsold (WIP) at Inspect/Ship 0
Unsold (WIP) Inventory Cost $0
# Units sold at Inspect/Ship 24
Sold Inventory Cost $28,800
# Scrap at Inspect/Ship (found at inspect/ship) 1
Scrap Inventory Cost $1,200
# Scrap (Re-inspects) (found by customer) 0
Scrap (Re-inspects) Inventory Cost $0
Total Inventory Costs $31,450
# Defective Quads Sold to Customer 0
Re-inspection Fees (# Defective Quads Sold * $1000) $0
# Customer Orders Missed 1
$ Loss for Missed Orders (# Missed Orders * $600) $600
Total Costs $32,050
# Units Delivered & Accepted 24
Revenue (# Good Quads Sold * Revenue) $43,200
Total Profit/Loss (Revenue - Costs) $11,150
On Time Delivery 96%
Post Event KPIs
Supply Chain Academy
9
So…now what?