    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics i

    Acknowledgement

    The report on Surveying a Building was successfully completed due to the contributions of various

    people. Therefore we would like take this opportunity to convey our heartiest gratitude to all of them.

    First of all our sincere thanks goes to Building Surveying lecturers, all other academic and non academic

    staff of the Department of Building Economics, for all the guidance and assistance provided in order to

    successfully complete this report.

    Then our special thanks go to the building owner, Mr.C.A.Perera who let us to survey his office premises

    and supported in various ways.

    Finally we would like to convey our heartiest thanks to our seniors and colleagues who helped us in

    various ways when carrying out the project and preparing the report.

  • 7/30/2019 Group 12 - Report

    2/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics ii

    Table of Content

    Acknowledgement.i

    Table of Content............................................................................................................................................ ii

    Table of Figures ........................................................................................................................................... iii

    1. Introduction ............................................................................................................................................ 1

    2. Building Surveying ................................................................................................................................ 2

    2.1 What is Building Surveying? ......................................................................................................... 2

    2.2 Building Surveying Process ........................................................................................................... 2

    3. Building Survey Report ......................................................................................................................... 4

    4. Elemental Inspection, Defects, Causes and Recommended Remedial Actions .................................... 6

    5. Defects of Building .............................................................................................................................. 11

    6. Cost Estimate for Rectification ............................................................................................................ 12

    7. Summary and Recommendation .......................................................................................................... 14

    8. Conclusion ........................................................................................................................................... 15

    9. References ............................................................................................................................................ 16

  • 7/30/2019 Group 12 - Report

    3/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics iii

    Table of Figures

    Figure 1: Cracks near beamwall connection.11

    Figure 2: Fungus attack on external wall..11

    Figure 3: Damaged ceiling11

    Figure 4: Water seepage through window beading..11

    Figure 5: Leakage in overhead water tank11

    Figure 6: Cracks on walls..11

  • 7/30/2019 Group 12 - Report

    4/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 1

    1.IntroductionNormally Buildings are designed and constructed with the expectation of existing for a long duration.

    Thus the building industry is responsible for maintaining, improving, and adapting the existing building

    in addition to the production of new building. Building surveying is a broad process which involves in

    identifying the defects in the buildings and providing necessary consultations to the clients at various

    stages of a building. The purpose of the building survey is to provide an opinion on the general condition

    of a building, advice on any urgent or future repairs and the likely consequences of non-repair. It will

    assist the buyers/ owners to have a good understanding on the condition or dilapidation of the building, as

    the building survey report provides information on building defects, building hazards and performance,

    explaining the causes of building defects and recommending the appropriate and effective remedial works

    and necessary maintenance works to maintain the life of the property.

    Building surveyors are involved in all aspects of property and construction from supervising large mixed

    use developments to planning domestic extensions. This varied workload can include everything from the

    conservation and restoration of historic buildings to contemporary new developments. Building surveyors

    work in most real estate markets including residential, commercial, retail, industrial, leisure, education

    and health. Consequently there are a wide variety of opportunities for chartered building surveyors to

    work in both the commercial, private, and public sectors.

    The preparation of a Building Survey Report provides an opportunity for the surveyor to fulfill two useful

    functions. First the client can be advised in relation to the condition of the building, the further

    investigations which may be needed and the advisability of the purchase. Secondly by encouraging timely

    and sensible repairs the nations building stock generally can be improved. Therefore this is a useful

    service and a supply of well-trained surveyors using appropriate methodology is likely to be needed for

    the foreseeable future.

    The report is emphasizing on providing consultations to the Mr. A Gunawardana who is expecting to

    purchase a building. The report comprises a summarized theoretical explanation on building surveying

    process and a detail analysis on defects identified, possible causes and necessary recommendations. This

    also provides an accurate cost proposal which would be beneficial to the client to get the correct decision

    on acquisition of the building.

  • 7/30/2019 Group 12 - Report

    5/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 2

    2.Building Surveying2.1What is Building Surveying?A building survey is an investigation or inspection of the construction and services of a property in

    sufficient detail to enable the Building Surveyor to advise what impact its condition will have upon the

    client. It can be used to identify unsatisfactory items, critical defects and their causes & making

    recommendations for repairs and identify consequences failures and future defects of a particular

    building.

    Normally building surveys are carried out prior to a construction, prior to purchasing, when there is a

    defect in the building, before the expiry of defects liability period and for the purpose of maintenance,

    budgeting, valuation and legal requirements.

    2.2Building Surveying ProcessA building surveyor should follow a methodical procedure which will often be determined by the layout

    of the site notes or field sheets being used. There arent any hard and fast rules to adhere when a building

    survey is carried out, yet it is always better to execute in a methodical approach. Steps of carrying out a

    building survey are identified below.

    Collect information prior to the survey Information of the property Information of adjoining property Extent of the survey Limitations of the site Other information such as cost estimation, lease agreement, insurance policies etc dead line

    Preliminary investigation General characteristics and description of the property

    - Layout of the property, orientation- Type of the structure- Age of the structure- Refurbishment work or any modification done to the building

    Information on adjoin properties- Condition of adjoining properties- Failures in similar properties

  • 7/30/2019 Group 12 - Report

    6/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 3

    Soil- Type of soil- History ground settlement in the area- Vegetation etc

    Grounds- Boundaries- Condition of fences, walls or other boundary demarcations

    External influences- Noise from external environment- Air quality- Relative humidity- Temperature and rain patterns

    Visual Inspection This investigation is carried out by using human sensory perceptions such as sight,

    hearing, touch and smell.

    Basic tools such as magnifying glass, measuring tape, hammer, mirrors etc can be used toinspect.

    Detailed Inspection Design detail of the building and its components Investigation of the building performance such as energy, in-door environment, space plan,

    lighting etc

    Detailed inspection of each and every building element

  • 7/30/2019 Group 12 - Report

    7/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 4

    3.Building Survey ReportSpencer & McKenzie

    Chartered Building Surveyors

    No: 7, Chatham Street, Colombo 03.

    Project Inspection of Head Office Building of Link Engineering, No 2, Park Lane,

    Rajagiriya.

    Client Mr. A. Gunawardhane

    Date of Inspection 23rd

    May 2012

    Scope of Report We have carried out a Building Survey of the above-mentioned property in

    connection with your proposed purchase. The report has been prepared in

    accordance with the signed and agreed terms and conditions of engagement.

    General Remarks This report should be construed as a comment on the overall condition of the

    property and is not an inventory of every single defect, some of which would not

    significantly affect the value of the property. For further details please refer to the

    conditions of engagement.

    At the time of inspection the weather was sunny and humid. The building was

    occupied and furnished with office equipment. There was a large quantity of

    storage and personal effects in the building which limited our access to some

    areas. Fitted floor coverings have been lifted in sample areas only in order to

    identify the nature of the construction beneath and we have not taken up fitted

    floor coverings generally. No exposure of hidden parts of the structure has been

    carried out.

    Description of

    Property

    The property is a three storied building with approximate floor area of 1200m2.

    The structure is of reinforced concrete with block masonry walls and asbestos roof

    covering on steel frame. Floor covering with semi rough tiles, roof covering with

    suspended aluminum ceiling and walls plastered with neat lime. All doors,

    windows and other fixtures are timber with brass ironmongeries.

    The building has been constructed in the year of 1985 and continued to be used as

  • 7/30/2019 Group 12 - Report

    8/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 5

    the head office building of link engineering company with minor modifications.

    Location and site

    conditions

    The site is located at park lane, rajagiriya. The extent of land is 80 perches and

    rectangular in shape. Access road is parallel to the land and building. The public

    drainage system adjacent to land is not in good condition. Apart from there isnt

    any identifiable difference in land.

    Accommodation First floor: Board Room, Stores

    Second floor: Procurement division, accounts division

    Third floor: Quantity surveying division, design division, GM/MD/Directors

    cubicles

    Tenure Freehold title

  • 7/30/2019 Group 12 - Report

    9/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 6

    4.Elemental Inspection, Defects, Causes and Recommended Remedial ActionsElement Condition Location Defect Cause

    Inspection

    Method

    Recommended

    Rectification

    Foundation Strip foundation

    made by random

    rubble work which

    in acceptable

    condition at the

    moment

    Perimeter of

    ground

    floor

    Localized

    settlements in

    the foundation

    and cracks in

    foundations as

    well as walls

    Overloading:

    Due to the modification done to the existing

    structure without a proper design and also

    overloading occurred where doors and

    windows openings have been enlarged

    Tree roots:

    Fat growing mango tree close to the building

    caused unequal settlement when active tree

    roots dry out the soil causing differential soil

    shrinkage. Shrinkage clays affect the bearing

    capacity and lead to movement in the building.

    Soil erosion:

    Due to the absence of the proper drainage

    system soil erosion occurred around building

    and therefore localized settlements can be

    occurred

    Visual

    inspection

    It should be sufficient to

    recommend that the soil

    stabilization by injecting

    the soil stabilization agent

    to the ground and increase

    the bearing capacity of the

    soil to avoid the failures

    due to the overloading

    Damage caused by the

    action of tree roots can be

    reduced by removing the

    offending trees

    To avoid the soil erosion

    we suggest constructing a

    concrete drainage system

  • 7/30/2019 Group 12 - Report

    10/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 7

    Element Condition Location Defect CauseInspection

    Method

    Recommended

    Rectification

    Exterior

    Wall

    Exterior walls are

    not in a good

    condition compare

    to the internal

    walls. External

    maintenance

    should be carried

    out to maintain the

    durability of the

    building

    Exterior of

    the building

    Cracks,

    Growth of

    biological

    agencies attack

    The roots of trees located in the vicinity of a

    wall can create cracks in walls due to growth of

    roots under foundation.

    Water penetration throughout the wall

    Visual

    inspection

    Damage caused by the

    action of tree roots can be

    reduced by removing the

    offending trees

    Apply water repellent coat

    Internal

    Wall

    It is in a good

    condition. But

    some cracks and

    paint defects are

    encountered during

    the inspection

    Office Area,

    Toilets

    Water seepage

    through joints

    between

    window frame

    and wall

    Poor tolerances of wall openings. Poor

    workmanship during grouting/ sealing of gaps

    Visual

    inspection

    Ensure correct usage of

    grout and sealant to seal the

    gaps, depending on the gap

    sizes

  • 7/30/2019 Group 12 - Report

    11/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 8

    Element Condition Location Defect CauseInspection

    Method

    Recommended

    Rectification

    Finishes Condition of wall

    paints is not very

    good and defects

    encountered in

    internal as well as

    external wall

    finishes.

    Floor tilling is

    worn out, new

    tilling required in

    all the tilled areas

    External

    wall

    Internal

    tilling

    Blistering,

    Algae/Fungus

    growth,

    Peeling in wall

    finishes

    Worn out tiles,

    slippery

    Blistering or Swelling of paint is caused due to

    the trapping of air, moisture or solvent between

    the surface and the paint film.

    Algae and fungus can grow when the surface is

    continually damp and dirty.

    Peeling is caused by moisture on the wall, poor

    surface preparation or using an incorrect

    painting system.

    Visual

    inspection

    Remove any unstable paint

    films and allow the wall to

    dry thoroughly. Then

    repaint with a

    recommended paint. Avoid

    painting under direct

    sunlight.

    Remove algae / fungus by

    high-pressure washing.

    Use an alkali-resistant

    basecoat or sealer. Patch

    surface defects with putty.

    Whole internal floor area is

    recommended to tile again

    Drainage

    system

    There is no proper

    and planed rain

    water drainage path

    Front and side

    of site is water

    logged

    Absence of a proper rain water disposal system Visual

    inspection

    We suggest repairing the

    drainage system

  • 7/30/2019 Group 12 - Report

    12/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 9

    Element Condition Location Defect CauseInspection

    Method

    Recommended

    Rectification

    Electrical Since there are

    three number of

    defects in the

    system it is not in

    good maintained

    condition

    First floor

    toilet, roof

    structure

    There was

    switch which

    was fixed

    inside wall of

    the bathroom,

    when using the

    bathroom it

    was attack by

    water

    Wiring work in

    the roof

    structure was

    not covered

    with conduit.

    Poor workmanship and design errors can be

    considered as the causes for the defects

    identified.

    Visual

    inspection

    Switch should remove

    from the current place of

    the bathroom and fixed

    at a higher level of the

    bathroom wall

    Should remove the above

    mentioned wiring part and

    should wire again with

    using conduit

    Plumbing There were some

    leakages in kitchen

    area

    First floor Joints are not

    done in a

    proper way,

    blocked s-trap

    caused bad

    This pipe takes water to kitchen sink. The

    plumbing is not directly to the tap, pipe line

    come above level to the sink and has a bend

    down ward to fit the tap

    Visual

    inspection

    Have to repair the joint as

    soon as possible. Therefore

    have to remove the

    plastering and repair the

    joint and again re - do the

  • 7/30/2019 Group 12 - Report

    13/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 10

    smell plaster.

    Element Condition Location Defect CauseInspection

    Method

    Recommended

    Rectification

    Doors and

    windows

    Need immediate

    replacement

    Ground,

    first and

    second

    floors

    Most of the

    timber doors

    and windows

    have decayed

    Heavy usage, poor quality ironmongeries,

    dampness of certain areas

    Visual

    inspection

    Recommended to install

    new aluminum doors and

    windows

    Roof

    Drainage

    system

    The roof drainage

    was in poor

    condition with

    broken and missing

    PVC sections of

    gutters.

    Front &

    Side Roof

    Broken and

    cracked gutters

    and their

    supports

    Blocked

    drainage

    The speed of the driving rain is unbearable for

    the gutters and the supports

    Lack of maintenance

    Visual

    inspection

    Replace the broken and

    cracked gutters

    Carryout proper

    maintenance procedures

  • 7/30/2019 Group 12 - Report

    14/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 11

    5.Defects of Building

    Figure 1: Cracks near beam wall connection Figure 2: Fungus attack on external wall Figure 3: Damaged ceiling

    Figure 4: Water seepage through window beading Figure 5: Leakage in overhead water tankFigure 6: Cracks on walls

  • 7/30/2019 Group 12 - Report

    15/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 12

    6.Cost Estimate for RectificationItem

    Nr Description Unit Qty Rate Rs. Amount Rs.

    1 Removal of trees

    Removal of mango tree, girth =< 1.0m

    Nr 1.00 2,000.00 2,000.00

    2 Floor Finishes

    Removal of damaged tiles and replace

    with approved manufacture, size, colour

    and design laid on and including 3/4"

    thick cement and sand 1:3 bedding and

    pointing with 1/4" tile grout to match the

    colour of tiles.

    Ft2

    1,000.00 450.00 450,000.00

    3 Refill cracks on the pavement with 1:3

    mortar, break crack around and properly

    joint

    Ft 20.00 150.00 3,000.00

    4 Wall Finishes

    Remove the existing plaster on kitchen

    wall and re-plastering with chicken mesh

    and applied the match colour C.I.C. or

    equivalent quality application of two

    coats and a primer undercoat.

    Ft2

    150.00 250.00 37,500..00

    5 Cleaning the wall surface removing

    algae, fungi and applied the match colour

    C.I.C. or equivalent quality application of

    two coats and a primer undercoat.

    Ft2

    300.00 20.00 6,000.00

    Total Carried Forward 498,500.00

  • 7/30/2019 Group 12 - Report

    16/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 13

    Item

    NrDescription Unit Qty Rate Rs. Amount Rs.

    Total Brought Forward 498,500.00

    6 Electrical Installation

    Repositioning the existing 15 A socket

    outlet in toilet

    Item 2,500.00 2,500.00

    7 Supply and installation of electrical

    wiring accessories including conduit

    insulation system with containments all

    in accordance with regulations

    Ft 60.00 500.00 30,000.00

    8 Plumbing

    Cleaning and re-fixing joints, repairing

    the leakage of water supply system in

    kitchen

    Item 10,000.00 10,000.00

    9 Doors and Windows

    Supply and install aluminium insulated

    door, Door type 2 - DG 01B as supplied

    by DAMRO, 1000 x 2200 mm size

    Nr 12.00 7,000.00 84,000.00

    10 Supply and install aluminium insulated

    window, window type 7 - DG 0SB as

    supplied by DAMRO, 1000 x 600 mm

    size

    Nr 8.00 4,000.00 32,000.00

    Total Cost of Rectification 657,000.00

  • 7/30/2019 Group 12 - Report

    17/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 14

    7.Summary and RecommendationIn the various foregoing pages of this report we have mentioned various items for repair that are

    considered necessary and advise that, prior to commitment to purchase, you obtain estimates from local

    building contractors for the works as required.

    We have not carried out tests to ascertain whether any deleterious or hazardous materials or techniques

    have been used in the construction of this building, or has been incorporated subsequently. Neither have

    we conducted tests to ascertain if the land is contaminated.

    Your legal advisers should confirm that the property is insured from the moment of exchange of contracts

    for a sufficient sum against all usual perils including fire, impact, explosion, storm, tempest, flood, burst

    pipes and tanks, subsidence, landslip and ground heave.

    Current cost of rectification = 657,000.00

    Current market value of property = 7,000,000.00

    Value after rectification = 7,657,000.00

    Cost of construction of same property = 6,000,000.00

    Current market value of land = 3,000,000.00

    Value of property if constructed = 9,000,000.00

    Note:

    This report identifies the extent of rectification required and the costs associated with it, however client

    should not your decision based solely on this report. We have valued the property in construction based

    valuation approach, it is our recommendation that this property worth to be purchased for your

    requirement. For more information it is recommended to consult a property valuer.

  • 7/30/2019 Group 12 - Report

    18/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 15

    8.ConclusionBuilding surveying is one of the widest areas of surveying practice. A building condition survey carried

    out by a Building Surveyor to assess the condition of a building, in particular, the structure, fabrics and

    components, finishes, services, safety requirements and also the general presentation of the property. A

    Building Condition Survey will let to understand the general condition of a building, including all

    building defects. A Building Defects Survey will tell the causes of building defects and how to rectify the

    building defects effectively and economically. Building surveying is carrying on the design and

    development of new buildings as well as the restoration and maintenance of existing ones. The nature of

    the surveying may range from the design of large, multimillion-pound structures to modest adaptations

    and repairs, and sometimes includes working with buildings of architectural or historic importance. This

    is a very wide field and may include advising to the owner on various aspects of buildings at different

    stages.

    Survey report intends to consult Mr. A. Gunawardana regarding the decision of acquiring the head office

    building of Link Engineering. Investigation of defects was done based on core elements of the building.

    Report is focusing to identify the major defects and causes in each and every element. Initial

    identification of the past of the building and its construction process is important to identify the most

    possible causes for the found defects. Detail analyses on defects and suitable methods of rectifications

    have been suggested in this report. Cost proposals are the most crucial factor in acquisition decision.

    Report contains precise sets of cost proposals which would be vital to the client. Report recommends

    purchasing the building where the decision was mainly influenced by the cost proposals. However it is

    important to state that for a comprehensive analysis on the value and a recommendation on purchase, the

    client should consult a property valuer. This report should not be considered as the chief consideration on

    the decision on purchase.

    The survey carried out by our group would provide a better knowledge and experience to conduct a

    proper investigation of defects in a much complicated building. Further we could identify the possible

    causes for each of such defects through a visual inspection. Though we are not the building surveyors, we

    were able to give the remedies for the inspected defects. The estimated cost proposal is given using the

    rough amounts. Preparation of the cost proposal enhances the students ability of preparing rate

    breakdowns for defects.Finally, this report helped to improve our knowledge on building surveying

    procedure, to get familiarize with different aspects of a Building Survey and to extend the understanding

    on defects associated with the selected residential building under tropical conditions.

  • 7/30/2019 Group 12 - Report

    19/19

    BE 3102Building Surveying Building Surveying Report

    Department of Building Economics 16

    9.References Glover, P., 2006,Building Surveys, Butterworth-Heinemann Publications, London. Parnham, P. and Rispin, C., 2001,Residential Property Appraisal, Spon Press, London. Royal Institute of Chartered Surveyors, 2011[online] Available from

    https://consultations.rics.org/consult.ti/buildingsurvey.pn/viewCompoundDoc?docid=2559188

    [Accessed 26 May 2012].

    https://consultations.rics.org/consult.ti/buildingsurvey.pn/viewCompoundDoc?docid=2559188https://consultations.rics.org/consult.ti/buildingsurvey.pn/viewCompoundDoc?docid=2559188