GridSolar, LLC The GridSolar Project – A Different Vision for our Nation’s Electric Grid...
-
Upload
mavis-pearson -
Category
Documents
-
view
214 -
download
0
Transcript of GridSolar, LLC The GridSolar Project – A Different Vision for our Nation’s Electric Grid...
GridSolar, LLC
The GridSolar Project – A Different Vision for our Nation’s Electric Grid
Presentation – NASUCA June 15, 2010
Richard Silkman, Ph.D. - Founding Partner
2
Maine’s Energy Choice
CMP Vision in which peak load is met by large generating facilities located far from load requiring expensive transmission systems
GridSolar Vision in which peak load is met through a smart electric grid using small-scale distributed solar generation located close to load
3
CMP MPRP
4
MPRP – Proposed Solution
5
MPRP - Out-of-Date Vision of the Electric Grid
Very large Generation Stations WERE the most efficient forms of generation
6
MPRP - Out-of-Date Vision of the Electric Grid
Manufacturing – that WAS best served by Large Central Generation Stations
7
MPRP - Out-of-Date Vision of the Electric Grid
Transmission WAS easy to site and permit
8
MPRP - Out-of-Date Vision of the Electric Grid
Information WAS difficult to obtain and process
9
GridSolar Offers a Different Vision of the Electric Grid
Load growth is weather sensitive
10
GridSolar Offers a Different Vision of the Electric Grid
Generation placed near the load
11
MPRP - Out-of-Date Vision of the Electric Grid
Transmission is NOT easy to site and permit
12
GridSolar Offers a Different Vision of the Electric Grid
Information is easier to manage
13
GridSolar Vision
14
GridSolar Vision
Grid Interconnection Equipment for Distributed Solar Systems
15
GridSolar Project
Install distributed solar generation to meet actual (not projected) peak loads
When solar will not meet peak loads: Install propane/natural gas fired distributed
generation in dual role of back-up generation plus grid-tied generation
Demand-response using interruptible loads Battery backup as the technology
improves
16
Solar is the only renewable resourcethat is coincident with peak loads
0
1 0 0
2 0 0
3 0 0
4 0 0
5 0 0
6 0 0
7 0 0
8 0 0
9 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour of the Day
MW Excess Load
Solar Generation
17
Will GridSolar Work
YES - the ability of the GridSolar Project to ensure grid reliability is acknowledged by CMP.
In addition:less costly better job opportunitiesless risky less impact on the environment
18
GridSolar will Cost RatepayersLess Money than the MPRP
Cumulative Ratepayer Costs
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,00020
10
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
$00
0s MPRP
GridSolar
19
Costs of Solar PV are FallingSolar Cost Curve is expected to decline over the next 20 years due to technological improvements, manufacturing scale and new production methods
U.S. DOE PV Installed Cost Estimates Through 2015Extended to 2020 by GridSolar, LLC
0
1
2
3
4
5
6
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
20
14
20
15
20
16
20
17
20
18
20
19
20
20
No
min
al $
/Wat
t In
stal
led
Indirect
Labor
Balance of System
Inverter
Module
20
Smart Electric Grid
21
GridSolar – Next Steps
Maine – Stipulation Work with Utility to develop smart grid
plan and platform plus 2 or 3 pilot projects in Maine for implementation
Elsewhere Identify opportunities to work with
consumer advocates in other states to support the GridSolar Project as a Non-Transmission Alternative to peak load growth and ensuring grid reliability
GridSolar, LLC
Contact Informationwww.gridsolar.com(207) 772-6190