Gridlines-45-Financing PPP in India - CHarris SKTadimalla

download Gridlines-45-Financing PPP in India - CHarris SKTadimalla

of 4

Transcript of Gridlines-45-Financing PPP in India - CHarris SKTadimalla

  • 8/6/2019 Gridlines-45-Financing PPP in India - CHarris SKTadimalla

    1/4

    GRIDLINESSharing knowledge, experiences, and innovations in public-private partnerships in inrastructure

    PUBLIC-PRIVATE INFRASTRUCTURE ADVISORY FACILITY

    -

    - -

    Helping to eliminate poverty and achieve sustainable development

    through public-private partnerships in infrastructure

    oTE no. 45 DEc 2008

    Idia has see apid gth i ecet yeas i

    its pgam iastcte pblic-pivate

    pateships (PPPs). Despite the sge i

    demad face, lcal facial makets

    cped ell ve the peid t 2007ad eve

    eed bette tems as they became me sedt the PPP mdel. Bt aeas pssible cce

    have develped. Geaig has iceased sigif-

    catly, ad facig tems mea that PPPs

    ae me expsed t iteest ate vlatility

    cases cce i a peid isig ates

    ad edced liqidity. Fthe gth i PPPs

    ill likely eqie a badeig the sces

    facig ce the peset facial maket

    tmil has lesseed. Addessig these

    cces ill call plicy ems t capital

    makets ad ccessi ameks.

    India has seen a rapid increase in private invest-ment in inrastructure since 2003 (Harris 2008).Its PPP program has grown rapidly in the past veto six years; in 200206 more than 150 PPP dealsclosed, compared with 66 in the previous seven years (gure 1). This growth was mainly in thetransport and urban inrastructure sectors, withroad projects accounting or a large share o theincrease, particularly in the number o projects.1

    Indias government had been concerned that localnancial markets would be unable to supportcontinued large growth in investment in PPPs. The

    World Bank, with nancial support rom PPIAF,undertook a detailed review o nancing patternsand trends and the constraints to expanding PPPnancing as perceived by market participants.This exercise collected inormation on more than200 PPP projects, most o them in the transportand urban sectors, key areas or expanding PPPs.The analysis here covers a sample o 104 proj-

    ects or which detailed nancial inormation wascollected. These account or 73 percent ($11.5billion) o the total project value.

    H ee PPPs faced?

    In 19952007 senior debt accounted or 68percent o project nancing on average. The resttook the orm o equity (25 percent), subordi-nated debt (3 percent), and government grants (4percent), typically viability gap grants providedduring construction to PPPs deemed economicallydesirable but not nancially viable.

    O the senior debt, about 70 percent was providedby commercial banks, our-ths o this by publicsector banks. The rest o the total debt nanc-

    ing came rom institutional lenders (around 23percent), with 5 percent provided by the Interna-tional Finance Corporation. Bond markets wereused sparingly. The use o subordinated debtalso remains limited. Its use has become morecommon, however, particularly in the road sector,which has the largest number o projects and thegreatest acceptance by nancial markets. But mosto the subordinated debt has been provided by thesenior lenders themselves.2

    On the equity side, more than 80 percent camerom project developers, with the next largest

    contributor being the public sector. Strategicinvestors made direct equity investments in the

    Financing the boom in public-privatepartnerships in Indian infrastructureTrends and policy implications

    Clive Harris and Sri Kumar Tadimalla

    Clive Harris is the inrastructure policy advisor or East

    Asia in the World Banks Sustainable Development Vice

    Presidency, and Sri Kumar Tadimalla is a senior public-

    private partnerships specialist or the transport unit in the

    World Banks South Asia Region.

  • 8/6/2019 Gridlines-45-Financing PPP in India - CHarris SKTadimalla

    2/4

    2

    special-purpose vehicles established to implementthe PPPs or only nine projects in the sample.These investments totaled almost $167 million(6 percent o the total equity), most o it in theairport sector. Equity investments by nancialinstitutions provided the rest.

    Evlvig facial stctes

    In recent years the role o senior debt has grownwhile the share o equity has declined, leading torising debt-equity ratios (gure 2). One explana-tion or this trend is that commercial banks havebecome more comortable with PPPs, particularlyin the road sector, and are thereore willing tohave senior debt make up a larger share o projectnancing.

    There is also evidence suggesting that projects withviability gap grants have higher gearing than thosewithout them. While the evidence is inconclusive,there are some indications that lenders and devel-

    opers view grants as substituting or the equityinusion needed during construction. The ewprojects involving a negative granta payment bythe PPP to the governmentalso have a higherratio o senior debt to equity, suggesting that thesepayments are being nanced by debt borrowed bythe PPP project.

    Should high gearing and the replacement o equityby grants be a concern? Some observers (such asEhrhardt and Irwin 2004) have argued that greaterleverage means a higher likelihood o bankruptcy

    and thus a higher likelihood o government bailoutto avoid the adverse consequences o bankruptcy,both actual and perceived. In addition, lowequity contributions make it easier or develop-ers to achieve a target return rom the margin onconstruction and reduce their long-term interestin the project.

    In India the typical concession terms encour-age the use o debt over equity. In the highway

    sector, or example, the contracting agency mustcompensate the contractor i the contract endsearly, even i the termination is due to a breacho the contractors own obligations or an evento orce majeure. In these cases the compensationis partial, with lenders typically being repaid inull or in large part while shareholders get noth-ing. Linking termination payments to debt, whilecommon around the world, can encourage highergearing, which in turn may increase projectsnancial vulnerability.

    Some countries put limits on the ratio o debt

    to equity. But restricting an investors ability tochoose its capital structure can increase the costo capital, prevent companies rom reaping taxadvantages associated with particular types onancing, and impose a monitoring burden on thegovernment. Alternatively, India could consider adierent basis or termination payments, reduc-ing the incentive to use debt embedded in thetermination clauses o its model concessions. Inthe United Kingdoms PPP program the govern-ment pays the market value o the asset (see U.K.Treasury 2007, section 21.2.5).

    Debt-eqity

    atis

    Idia PPP

    pjects have

    bee isig

    FIGurE 1

    Idia has see PPP pjects climb i mbe ad valePPP projects by year of financial closure, 19952006

    Source: PricewaterhouseCoopers 2007.

    7

    6

    5

    4

    3

    2

    1

    0

    60

    50

    40

    30

    20

    10

    0

    Value (total project cost) Number of projects

    Value(US$billions)

    Numberofprojects

    1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006

  • 8/6/2019 Gridlines-45-Financing PPP in India - CHarris SKTadimalla

    3/4

    3Financing the boom in public-private partnerships in Indian inrastructure

    Idia PPP

    pjects ha

    bee assm

    me itee

    ate isk

    Debt facig became me

    cmpetitive

    Despite some volatility, average spreads on debt toPPP projects have declined signicantly in recent years (gure 3).3 This does not refect trends inIndian corporate bond spreads, which increasedin 2006 and 2007. While many actors may beinvolved, the decline in spreads is probably dueto the nancial markets growing acceptance andunderstanding o PPPs as more have come on lineand provided an operational track record, particu-larly in the road sector.

    On the negative side, the tenor o debt has increasedlittle, averaging around 1415 years in the past ewyears. In addition, loans in India have shown atrend toward shorter reset periods. Although theloans are long term, rates are reset at predenedintervals. PPP projects generally do not have reve-nues that are linked to interest rates. There are

    concerns that higher rates could aect some proj-ects, particularly those with higher gearing.

    High eqity ets expected

    Developers stated their expected equity returnsin only 22 cases. But among these, more than 70percent sought returns exceeding 16 percent. Anal-ysis suggests, as would be predicted, that projectswith higher gearing had higher expected rates oreturn. Calculations indicate that the asset beta

    or these projects was around 0.60.75, dependingon the assumed equity risk premium. This is some- what higher than other estimates; or example,Alexander, Estache, and Oliveri (1999) estimatedasset betas or road projects in Latin America andthe Caribbean to be 0.310.48.

    The dierence could refect the high-powered

    regulatory regime or Indian road projectsbutit is also consistent with the aggressive biddingor road projects in 200607. Negative grant bidswere seen or some projects, driven by huge devel-oper interest in road PPPs.

    Lesss gig ad

    The trends in PPP nancing highlight several issues with implications or nancing the large-scalePPP program envisaged by Indias government.PPPs have relied heavily on commercial banks

    or their debt nancing, and it is unclear howsustainableor how desirablethis dependence will be. Long-term nancing exposes the banksto the risk o asset-liability mismatch: the mainsource o unds or Indian banks is savings depositsand term deposits, whose maturity prole rangesrom less than six months to ve years. Over mucho the period developers were comortable withshorter reset periods, perhaps because this hadbeen a period o declining or low rates. But asinterest rates began to increase, concerns aroseabout the impact on PPPs, because the concession

    FIGurE 2

    Debt-eqity atis isig Idias PPP pjectsFinancing by type for selected PPP projects, 19982007

    Source: PricewaterhouseCoopers 2007.

    80

    70

    60

    50

    40

    30

    20

    10

    01998 1999 2000 2001 2002 2003 2004 2005 2006 2007

    Percentage

    oftotal

    Senior debt Equity Subordinated debt Government grants

  • 8/6/2019 Gridlines-45-Financing PPP in India - CHarris SKTadimalla

    4/4

    c/o The World Bank, 1818 H St., N.W., Washington, DC 20433, USA

    PHonE (+1) 202 458 5588 FAX (+1) 202 522 7466

    GEnErAL EMAIL [email protected] wEB www.ppia.org

    PUBLIC-PRIVATE INFRASTRUCTURE ADVISORY FACILITY

    4

    contracts have no provisions or passing on higherinterest charges. Continued increases in rates aswell as a tightening o credit could have adverseeects on some projects.

    An active bond market can increase the fow olong-term unds and reduce reliance on banks. TheIndian corporate bond market, though one o thelargest in Asia, is still at an early stage o develop-ment, and its growth is hampered by institutional,legal, and regulatory constraints that make bonds amore expensive way o nancing debt. These prob-lems, as well as potential solutions, are highlightedby the Patil Committee (2005), established bythe government. Following the suggestions o thecommittee, the government has set up reportingand trading platorms or corporate bonds. Manyother important suggestions still await implemen-

    tation. But implementing bond market reorms isa dicult challenge in the best o times, and inthe light o the current global nancial crisis thegovernment would have to explore other innova-tive ways to ensure adequate fows o (private)nancing to inrastructure PPPs.

    On the equity side, participation by oreign play-ers, particularly strategic investors, has been loweven though PPP projects in the sectors studied areallowed to have 100 percent oreign direct invest-ment. Foreign direct investment accounted or only11 percent ($322 million) o the total investment.

    The port sector had the largest share (51 percent)o this oreign investment, ollowed by airports(32 percent) and roads (16 percent). Only nineprojects were reported to have strategic investorparticipation: our in ports, three in airports, andone each in water supply and railways. Few pureequity providers are willing to invest directly inspecial-purpose vehicles because many concessionagreements put restrictions on the sale o develop-ers equity. Encouraging pure equity providers to

    do so will require more liberal norms allowingthem to participate at the time o bidding

    or to enter later with a majority stake.

    Notes

    This note draws on PricewaterhouseCoopers (2007) and work byIan Alexander.

    1. These gures are based on data rom PricewaterhouseCoopers(2007), which may dier rom data rom the World Bank andPPIAFs Private Participation in Inrastructure (PPI) ProjectDatabase.

    2. Discussions with nancial investors suggested that subordinateddebt is a way to help developers put less equity into the projects.In return or conserving the developers equity, the banks chargea higher rate o interest on the subordinated debt, improving theoverall yield on the project debt.

    3. The spread is measured by comparing the interest rate on the

    loan against the average yield to maturity on Indian governmentborrowing during the year in which the loan was taken and ismeasured in basis points.

    Reerences

    Alexander, Ian, Antonio Estache, and Adele Oliveri. 1999. A FewThings Transport Regulators Should Know about Risk and the Costo Capital. Policy Research Working Paper 2151, World Bank,Washington, DC.

    Ehrhardt, David, and Timothy Irwin. 2004. Avoiding Customerand Taxpayer Bailouts in Private Inrastructure Projects: Policytoward Leverage, Risk Allocation, and Bankruptcy. Policy ResearchWorking Paper 3274, World Bank, Washington, DC.

    Harris, Clive. 2008. India Leads Developing Nations in PrivateSector Investment. Gridlines series, no. 30, PPIAF, Washington,DC.

    Patil Committee. 2005.Report of the High Level Expert Committee onCorporate Bonds and Securitization. New Delhi: Ministry o Finance.http://www.sebi.gov.in/debt/expertreport.pd.

    PricewaterhouseCoopers. 2007. Inrastructure Public-PrivatePartnership (PPP) Financing in India. Drat report prepared orthe World Bank with support rom PPIAF, Washington, DC.

    U.K. Treasury. 2007. Standardisation of PFI Contracts, Version 4.London. http://www.hm-treasury.gov.uk/media/3/5/p_sopc4pu101_210307.pd.

    GRIDLINESGridlines share emerging knowledge

    on public-private partnership and give an

    overview o a wide selection o projects rom

    various regions o the world. Past notes can be

    ound at www.ppia.org/gridlines. Gridlines are a

    publication o PPIAF (Public-Private Inrastructure

    Advisory Facility), a multidonor technical assistance

    acility. Through technical assistance and knowledge

    dissemination PPIAF supports the eorts o policy

    makers, nongovernmental organizations, research

    institutions, and others in designing and implementing

    strategies to tap the ull potential o private involvement in

    inrastructure. The views are those o the authors and do

    not necessarily reect the views or the policy o PPIAF,

    the World Bank, or any other afliated organization.

    FIGurE 3

    PPP speads ell shaply ve the peid200407Average spread over government borrowing, 200207

    Source: Bloomberg; PricewaterhouseCoopers 2007.

    600

    500

    400

    300

    200

    100

    0

    Selected PPP projects AAA bonds

    AA bonds BBB bonds

    2002 2003 2004 2005 2006 2007

    Basispoints