Greiman City of Boston Presentation 2013
-
Upload
public-technology-institute -
Category
Technology
-
view
305 -
download
0
description
Transcript of Greiman City of Boston Presentation 2013
![Page 1: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/1.jpg)
Managing Project Complexity
Northeast Public Sector Project Management ConferenceCity of Boston Department of Innovation and Technology and
Boston Public SchoolsMarch 20, 2013
Presented By: Professor Virginia A. GreimanV. A. Greiman Copyright © 2013
![Page 2: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/2.jpg)
What Makes a Project Complex?Size and Duration: The Big Dig, Crossrail and The English Chunnel (FHWA: More than $1Billion)
Technology: Hoover Dam and Panama Canal Extension
Untried: BP Gulf of Mexico Oil Disaster
Integration of Processes: Many Diverse and Autonomous, but interrelated and interdependent components or parts linked through many dense interconnections and interfaces.
Virginia A. Greiman © 20132
![Page 3: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/3.jpg)
Unique Characteristics of Complex Projects
Long Duration – 10 to 60 years
Extensive Public Scrutiny
Ambiguity and Uncertainty
Large Scale Policy Making
Complex Organizational and Governance Structures
Consistent Cost Underestimation
Systems Complexity
Virginia A. Greiman © 20133
![Page 4: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/4.jpg)
Linkage Between Complexity and Ambiguity
If requirements are Ambiguous, then resolving that Ambiguity will be more complex than if projects are well specified
If the deliverables are complex, then it follows that the outcomes will be less certain, especially if the plan is ambiguous about how success will be measured
Virginia A. Greiman © Copyright 2012 4
![Page 5: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/5.jpg)
Challenges of Mega ProjectsKeeping the Focus on Quality and Safety instead of Schedule and Cost
Integration of all Project Disciplines throughout the Life of the Project
Educating and Involving the Public Citizens from the Inception of the Project
Establishing a strong public owner with independent oversight
Integration does not mean sacrificing Independence!
Dynamic governance structures
Virginia A. Greiman © 2010 5
![Page 6: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/6.jpg)
Boston’s Big Dig
An Example of a Complex Project
Virginia A. Greiman © 20136
![Page 7: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/7.jpg)
Another Example
London’s Crossrail Project - 16 Billion Pounds– 42 kilometres of rail tunnels underneath London– Nine new Stations– 200 million passengers– 10% increase in rail capacity
UK’s High Speed Rail Service between London and Birmingham (HS2) - 17 Billion Pounds
Virginia A. Greiman © 20137
![Page 8: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/8.jpg)
CA/T Program
• 54 Design Packages• 132 Construction Packages• 9000 Processes & Procedures• 161 Lane Miles
• 5 Major Interchanges
• Landmark Cable-stay Bridge
• Jacked Tunnels
• Immersed Tubes
• Soil Freezing
• Deep Soil Mixing
• 8 miles of Slurry Wall
• Jet Grouting
• Excavation and Parks
CA/T Program
• 54 Design Packages• 132 Construction Packages• 9000 Processes & Procedures• 161 Lane Miles
• 5 Major Interchanges
• Landmark Cable-stay Bridge
• Jacked Tunnels
• Immersed Tubes
• Soil Freezing
• Deep Soil Mixing
• 8 miles of Slurry Wall
• Jet Grouting
• Excavation and Parks
Virginia A. Greiman © Copyright 2012
VV. A. Greiman © 2012
![Page 9: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/9.jpg)
Major Complexity Challenges on the Big Dig:
Project Integration – (150 Major Employers – One Team) 5,000 workers, thousands of complex processes
Risk Management – World’s Largest Wrap-up Program
Ambiguity and Uncertainty – Subsurface conditions
Technology Integration – Monitoring the Critical Path
Claims and Changes - Partnering
![Page 10: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/10.jpg)
Project Integration Management
Project Charter
1
CloseProject
7
Integrated Change Control
6
ProjectMgmtPlan
3
MonitorAnd Control
5
Direct and ManageExecution
4
Scope Statement
2
Project Management Institute, PMBOK, 4th ed.
![Page 11: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/11.jpg)
What is Integration?
Requires each project and product process to be appropriately aligned and connected with the other processes to facilitate their coordination. These process interactions often require tradeoffs among project requirements and objectives.
![Page 12: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/12.jpg)
Integration on Large and Complex Projects
Organizational Structure
– The People– The Processes
Community and Public Concerns
Internal and External Stakeholders
![Page 13: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/13.jpg)
First of 12 tube sections each longer than a football field arrive in Boston for the Ted Williams Tunnel
Virginia A. Greiman © Copyright 2012 13
![Page 14: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/14.jpg)
V.A. Greiman © Copyright 2012
![Page 15: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/15.jpg)
EIS = Environmental ImpactStatementICE – Interstate Cost EstimateCSU – Cost and Schedule Update
Fig. 7.1
![Page 16: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/16.jpg)
Why are Mega Projects Consistently Underestimated?
A review of large public works projects over the last century concluded that costs are consistently underestimated, a phenomenon attributed to the desire of the project advocates to have their projects approved.
(Flyvbjerg, Megaprojects and Risk: An Anatomy of Ambition, 2002)
![Page 17: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/17.jpg)
National Transportation Research Board
In 2006, the Transportation Research Board’s Final Report for Cost Estimation and Management for Highway Projects, identified eight strategies to address cost escalation, and linked these strategies to 18 different causes of cost escalation on highway projects in the United States. Notably, the research concluded that most efforts in cost estimation have focused on creating tools to improve cost estimates with less emphasis on tools for cost estimation management.
(Anderson et. al. 2006).
![Page 18: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/18.jpg)
Complexity and Project Management Trade-offs
Design, Risk, Safety, and Quality Decisions!!
![Page 19: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/19.jpg)
Big Dig’s Worst Disaster
Virginia A. Greiman © Copyright 2012 19
2006 Ted Williams Tunnel Roof CollapseSource: NTSB Report
![Page 20: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/20.jpg)
National Transportation Safety Board Findings
(1) Failure to identify potential creep by designers and contractors in the anchor adhesive as a critical long-term failure mode
(2) A general lack of understanding and knowledge in the construction community about creep in adhesive anchoring systems.
(3) Failure of the Contractor to provide the Central Artery/Tunnel project with sufficiently complete, accurate, and detailed information about the suitability of the company’s Fast Set epoxy for sustaining long‑term tensile loads.
(4) Failure of Powers Fasteners, Inc., to determine that the anchor displacement that was found in the high‑occupancy vehicle tunnel in 1999 was a result of anchor creep.
(5) Failure of Contractor, subsequent to the 1999 anchor displacement, to continue to monitor anchor performance in light of the uncertainty as to the cause of the failures.
(6) Failure of the owner to implement a timely tunnel inspection program that would likely have revealed the ongoing anchor creep.
20Virginia A. Greiman © Copyright 2012
![Page 21: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/21.jpg)
Mississippi River I-35 Bridge Collapse in Minneapolis, August 1, 2007
The National Transportation Safety Board (NTSB) determined that the probable cause of the collapse, was the inadequate load capacity, due to a design error, of the gusset plates at the U10 nodes.
Contributing to the accident was the generally accepted practice among Federal and State transportation officials of giving inadequate attention to gusset plates during inspections for conditions of distortion, such as bowing, and of excluding gusset plates in load rating analyses.
21Virginia A. Greiman © Copyright 2012
![Page 22: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/22.jpg)
What Tradeoffs Have You Made on Your Project?
Resources?
Quality?
Design?
Risk?
Time?
Cost?
Virginia A. Greiman © Copyright 2012 22
![Page 23: Greiman City of Boston Presentation 2013](https://reader033.fdocuments.in/reader033/viewer/2022061115/54642bd1af7959a2278b5195/html5/thumbnails/23.jpg)
Questions???
Virginia A. GreimanProfessor
Boston University617-353-6860
23Virginia A. Greiman © Copyright 2013