Greenwich Pumping Station SIP

download Greenwich Pumping Station SIP

of 32

Transcript of Greenwich Pumping Station SIP

  • 8/3/2019 Greenwich Pumping Station SIP

    1/32

    Introd

    uction

    Site

    and

    introdu

    ction

    Introd

    uction

    GreenwichPumping Station

    Currently, untreated sewage regularly overows into the River Thames from Londons Victorian sewerage systemvia combined sewer overows (CSOs). The proposed Thames Tunnel would intercept these overows through theuse of a new storage and transfer tunnel, which would link west London and Abbey Mills Pumping Station. Thesewage ow would then be transferred to Beckton Sewage Treatment Works via the Lee Tunnel. The reductionin untreated sewage entering the River Thames would bring long-term benets for the environment and users of

    the River Thames. In order to deliver the project we need a number of sites along the route and this documentidenties our current preferred site at Greenwich Pumping Station.

    Thames Tunnel

    Siteinformationpaper

    1

    Key facts

    Local authority: Greenwich

    CSO name: Greenwich Pumping StationCSO spill volume in an average year: 8,300,000m (equivalent to approximately

    3,320 Olympic swimming pools)

    Site type: CSO and Greenwich connection tunnel drive site

    Duration of main construction works: Approximately ve and a half years.

  • 8/3/2019 Greenwich Pumping Station SIP

    2/32

    Greenwich Pumping Station

    2

    We are proposing to use the site of our existing pumping

    station for this construction work and to accommodatepermanent structures required to operate the main

    tunnel. The site would be used to connect the existing

    local CSO, known as the Greenwich Pumping Station CSO

    to the Greenwich connection tunnel, which would direct

    flows into the main tunnel.

    The Greenwich connection tunnel is a long connection

    tunnel which connects the CSOs at Greenwich Pumping

    Station, Deptford Church Street and Earl Pumping Stationto the main tunnel at Chambers Wharf. We also need a

    worksite from which we can build this tunnel, which we

    propose to drive from Greenwich Pumping using land

    adjacent to our pumping station at Phoenix Wharf.

    The location of the site is shown in Figure 1A and

    surrounds the existing pumping station building. Norman

    Road and Norman House are to the east of the site. To

    the south is Greenwich High Road (A206), to the southwest are recently built flats and to the west is Deptford

    Creek and the Greenwich Industrial Estate. To the north of

    Phoenix Wharf are industrial units. The elevated Dockland

    Light Railway (DLR) also crosses the site. The site is

    adjacent to the Ashburnham Triangle Conservation Area.

    Section 1: Introduction and site information

    Related documents:

    Build

    This site information paper sets out our proposals at

    Greenwich Pumping Station. We have also produced

    project information papers, which cover overarching

    topics relating to the project. Where we consider that a

    project information paper is particularly relevant, we have

    highlighted this in a related documents box. At the end

    of this site information paper is a list of other documents,

    which may be of interest and a glossary of terms.

    How we chose this site

    CSO

    What we proposed at phase one consultation

    Through our site selection process, we identified two

    possible shortlisted sites to intercept the Greenwich

    Pumping Station CSO. At phase one consultation, whichwas held between September 2010 and January 2011, we

    presented these sites:

    Foreshore (near Greenwich Foot Tunnel)

    Greenwich Pumping Station.

    Greenwich Pumping Station was identified as our

    preferred site at phase one consultation.

    What we are proposing at phase two consultation

    We have considered the comments from phase one

    consultation, feedback from ongoing engagement and

    new information; and undertaken further technical work.

    We still consider that Greenwich Pumping Station should

    be our preferred site because we own most of the siteand although the Pumping Station is a Grade II listed

    structure, the proposed location of our works (to the northof the pumping station site) greatly reduces any potential

    effect upon its setting.

  • 8/3/2019 Greenwich Pumping Station SIP

    3/32

    Introduction

    3

    Figure 1A: Greenwich Pumping Station location plan

    Greenwich PumpingStation CSO

    Norman House

    GreenwichIndustrial

    Estate

    GreenwichPumpingStation

    CSO discharge

    into River Thamesapproximately500 metres tothe north east

    Deptford

    Creek

    Creekside

    Centre

    TrinityLaban

    DLR

    WavelengthsLeisure Centre

    Low LevelSewers

    Sue GodfreyNature Reserve

    N

    Greenw

    ichHigh

    Road

    Norm

    anR

    oad

    GREENWICH

    LEWISHAM

    PhoenixWharf

    Local authority boundary

    Draft limit of land tobe acquired or used

    Proposed tunnelroute centreline

    Existing sewer

    Deptford ChurchStreet site

  • 8/3/2019 Greenwich Pumping Station SIP

    4/32

    Greenwich Pumping Station

    4

    Greenwich connection tunnel

    What we proposed at phase one consultationDue to the location of the Greenwich Pumping Station

    CSO, Deptford Storm Relief CSO and Earl Pumping Station

    CSO, the Greenwich connection tunnel, is required to

    transfer the flows from these CSOs to the main tunnel.

    At phase one consultation, we identified Kings Stairs

    Gardens as our preferred site from which to drive the

    Greenwich connection tunnel to Greenwich Pumping

    Station.

    Why we have amended our proposals

    As part of our review of the tunnelling strategy for the

    main tunnel, we have re-assessed the sites from which we

    could drive the Greenwich connection tunnel.

    Given the identification of this potential new site, in

    June 2011, we held drop-in sessions with the communityaround the site to understand any local issues they may

    have, should Greenwich Pumping Station be used to drive

    the Greenwich connection tunnel. We reviewed all the

    comments we received and took these into account as

    part of the site selection process.

    What we are proposing at phase two consultation

    Our preferred site is Greenwich Pumping Stationbecause Chambers Wharf is only large enough to

    accommodate either a main tunnel drive site or a drive

    site for the Greenwich connection tunnel, due to the

    volume of excavated material that would need to be

    treated on site prior to removal. We are proposing that

    Chambers Wharf is used as a main tunnel drive site

    therefore it could not be used as a drive site for the

    Greenwich connection tunnel.

    There is not sufficient space within the existing Greenwich

    Pumping Station site to hold and process the excavated

    material that would be generated from driving the

    Greenwich connection tunnel. Additional land is therefore

    needed and we have identified land adjacent to the

    Greenwich Pumping Station site, known as Phoenix Wharf,

    for this purpose.

    Related documents:

    Changes

    Q&A Consultation

    Site selection

    Chambers WharfCW

  • 8/3/2019 Greenwich Pumping Station SIP

    5/32

    Construction

    Construction

    5

    Section 2: Construction

    Construction activitiesConstruction activities are required to intercept the

    CSO and construct the Greenwich connection tunnel. To

    intercept the CSO, we would construct an interception

    chamber. A connection culvert would link the interception

    chamber to a drop shaft (approximately 44m deep),

    through which flows would pass into the Greenwich

    connection tunnel, before connecting into the main

    tunnel. To drive the Greenwich connection tunnel, we

    would lower a tunnel boring machine into the drop shaft

    at Greenwich Pumping Station and would drive the

    Greenwich connection tunnel north west to Chambers

    Wharf. Excavated material from the tunnel drive would

    be removed from the drop shaft and taken off site. Figure

    2A illustrates the below ground infrastructure proposed.

    These activities would take place within the area

    indicated by the red line in Figure 1A, in six main phases,

    lasting approximately five and a half years in total. The

    main construction activities associated with these phases

    are set out in Table 2.1.

    Drop shaft

    Main tunnel

    Valve chamber

    To pumping station to

    River Thames

    Interception chamber

    Existing sewer

    Connection culvert

    Figure 2A: Illustration showing typical

    elements of below ground infrastructure

  • 8/3/2019 Greenwich Pumping Station SIP

    6/32

    Greenwich Pumping Station

    6

    Advance works

    Phase 1

    Site setup

    Figure reference Figure 2C

    Typical working hours Varies Standard

    Mainconstru

    ctionactivities

    Utilities connected

    Utilities diverted or protected

    Site cleared

    Site facilities and access set up

    Drop shaft excavated and built

    Tunnel boring machine delivered to site and assembled

    Tunnel excavated and built

    Internal (secondary) tunnel lining constructed

    Above and below ground structures constructed

    Mechanical and electrical equipment installed

    Site restored and landscaped

    Temporary site facilities removed

    Table 2.1: Main activities during construction phases

    Our typical working hours are expected to be:

    Standard: 8am-6pm weekdays, 8am-1pm Saturday*

    Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays

    Continuous: 24 hours a day, seven days a week**

    Varies: Working hours for advanced works will depend on the nature of the works and will be agreed

    with the local authority

    * Standard working hours would also include, subject to agreement with the local authority:

    a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site.

    equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday.

    ** The main activities taking place 24 hours a day are below ground or within an enclosure.

  • 8/3/2019 Greenwich Pumping Station SIP

    7/32

    Construction

    7

    Phase 2

    Drop shaft

    construction

    Phase 3

    Tunnelling

    Phase 4

    Secondary

    lining

    Phase 5

    Construction of

    other structures

    Phase 6

    Completion of works

    and site restoration

    Figure 2C Figure 2D Figure 2E Figure 2E

    Standard with

    occasional extended

    standard

    Continuous Continuous Standard Standard

    Related documents:

    Build

    Managing construction

  • 8/3/2019 Greenwich Pumping Station SIP

    8/32

    Greenwich Pumping Station

    8

    Site layout and construction phases

    Figures 2C, 2D and 2E show how the site might be laid

    out during the construction phases, which are set outin Table 2.1 and Figure 2B. These layouts have been

    informed by the size of the infrastructure proposed,

    the construction methods required and the location

    of neighbouring buildings and structures. They have

    also been developed to minimise effects on the local

    community and environment. A particular factor at this

    site that has influenced the layout is as follows:

    The site layout and shaft location have beendetermined by the location of existing listed buildings,

    underground infrastructure associated with the

    pumping station and proximity to the Docklands Light

    Railway viaduct.

    P1

    P2

    P3

    P4 P6

    P5

    Year 1 Year 2 Year 3 Year 4 Year 5

    Advan

    ce

    works

    Figure 2B: Construction timeline showing approximate duration of works in phases (P)

    The site layouts are indicative only, and the contractor

    may arrange the site in a different way, depending onthe chosen construction methods, provided that any

    environmental effects are appropriately managed and

    that the main construction activities are undertaken

    within the red line shown in Figure 1A.

  • 8/3/2019 Greenwich Pumping Station SIP

    9/32

    Construction

    9

    Figure 2C: Illustrative phases 1 and 2 construction plan

    N

    Cranes

    Drop shaftPiling rig

    Maximum extent ofconstruction site for

    phases 1 and 2Site hoarding

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing footpath tobe diverted

    Footpath diversion

    GREENWICH

    LEWISHAM

    Option for contractor

    to transport materialsusing barges

  • 8/3/2019 Greenwich Pumping Station SIP

    10/32

    Greenwich Pumping Station

    10

    Option for contractorto transport materialsusing barges

    N

    Gantry crane

    Drop shaft

    GREENWICH

    LEWISHAM

    Maximum extent ofconstruction for phase 3

    Site hoarding

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing footpath tobe diverted

    Footpath diversion

    Noise enclosure overshaft and gantry crane

    Figure 2D: Illustrative phase 3 construction plan

  • 8/3/2019 Greenwich Pumping Station SIP

    11/32

    Construction

    11

    N

    Gantry craneCrane

    Option for contractorto transport materialsusing barges

    GREENWICH

    LEWISHAM

    Maximum extent ofconstruction site forphases 4 and 5

    Site hoarding

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing footpath tobe diverted

    Footpath diversion

    Noise enclosure overshaft and gantry crane

    Drop shaft

    Figure 2E: Illustrative phases 4 and 5 construction plan

  • 8/3/2019 Greenwich Pumping Station SIP

    12/32

    Greenwich Pumping Station

    12

    Additional works and activitiesThe main construction activities at this site are set out in

    Table 2.1. We would also need to undertake additionalworks and activities, some of which may be located

    outside of the area indicated by the red line in Figure 1A.

    The anticipated additional works and activities are set

    out in Table 2.2.

    When Type of works What we would do

    Required for

    construction

    phase

    Installation of equipment to

    monitor environmental matterssuch as such as noise, vibration

    and dust.

    The locations of monitoring equipment would be agreed with thelocal authority and relevant landowners.

    Protection works to third party

    structures (such as buildings,

    bridges and tunnels).

    We would undertake studies to identify any effects our construction

    work may have on third party structures. The studies may

    recommend particular construction methods or, in very limited

    instances, protection works.

    If protection works are required to the existing sewer, we wouldaccess the sewer network through existing manholes.

    Temporary connection to

    utilities (such as water, sewer,

    phone and electricity supply).

    If we are unable to make a connection to water, sewer and

    phone within the pumping station site, we would need to make a

    connection in Norman Road.

    A major new electricity supply would be required at this site to

    provide power during construction. We expect to connect to

    electricity from Stowage, running cables along Gonson Street and

    Creekside. However, we are still developing a route for electricitysupply in discussion with the utility provider.

    Traffic management works.

    These may need to extend beyond our site and could include

    relocating kerb lines, repainting road lines and modifying traffic

    signals.

    Required for

    operational

    phase

    Permanent connection to

    utilities (such as water, phone

    and electricity supply) for the

    operational tunnel.

    We expect to connect to utilities from within the pumping

    station site.

    Table 2.2: Additional works and activities

  • 8/3/2019 Greenwich Pumping Station SIP

    13/32

    Construction

    13

    Construction transport and access

    We propose to transport materials to and from the site by

    road. We have considered the use of the river to transportmaterials to and from the site; however, the tidal nature

    of Deptford Creek and bridges crossing the Creek makes

    river transport difficult, and therefore unlikely to be cost

    effective. We have therefore assumed that all materials

    would be moved by road. The contractor would however

    be given the flexibility to use river transport where they

    consider it is practical and cost effective to do so.

    Table 2.3 sets out the anticipated average daily numberof lorries visiting (ie travelling to and from) the site during

    the peak months of each phase.

    Construction traffic would access the site from

    Blackheath Road (A2), along Greenwich High Road

    (A206) and Norman Road. There would be several site

    access points along Norman Road, most making use of

    existing entrances. One new entrance would be created

    from Norman Road. Light vehicles would access the sitefrom the existing entrance on Greenwich High Road

    (A206). Traffic would leave the site via the same route.

    This access route is shown on Figure 2F. Beyond this,

    construction traffic would use the major road network to

    get to and from its final destination.

    Table 2.3: Average daily lorry visits during the peak months

    We would need to make a minor diversion to the footpath

    that runs from Norman Road to the footbridge acrossDeptford Creek, as shown in Figures 2C, 2D and 2E. By

    relocating the footpath next to the elevated railway, we

    can create a safer, more efficient working space around

    the shaft. Occasionally the footpath will be temporarily

    closed to allow construction traffic to pass under the

    railway arches between the Greenwich Pumping Station

    site and Phoenix Wharf Based on our current design, we

    do not anticipate that any road diversions, parking bay

    suspensions, bus stop relocations or junction changeswould be required.

    Phase 1

    Site setup

    Phase 2

    Drop shaftconstruction

    Phase 3

    Tunnelling

    Phase 4

    Secondarylining

    Phase 5

    Constructionof other

    structures

    Phase 6

    Completionof worksand site

    restoration

    Average

    daily lorryvisits 4 lorries 24 lorries 54 lorries 15 lorries 15 lorries 9 lorries

    Related documents:

    Transport

  • 8/3/2019 Greenwich Pumping Station SIP

    14/32

    Greenwich Pumping Station

    14

    Figure 2F: Proposed access route to the site from the nearest major road

    N

    A2

    GreenwichHigh Road

    Blackheath Road

    Norman Road

    A206Light vehicle andpedestrian access only

    Greenw

    ich

    High

    RoadNorm

    an

    Road

    Norman

    Road

    GREENWICHLEWISHAM

    Draft limit of land tobe acquired or used

    Internal site road

    Site access

    Local authority boundary

    Transport for London(TfL) road network

    Proposed lorry access toTfL road network

  • 8/3/2019 Greenwich Pumping Station SIP

    15/32

    Construction

    15

    Management of construction worksOur construction works would be managed in accordance

    with an agreed Code of construction practice (CoCP).For phase two consultation, we have produced a draft

    CoCP Part A: General requirements, informed by CoCPsfrom other major construction projects in London and

    consultation with the local authorities. Through the

    environmental impact assessment process, scheme-

    wide principles to address potential effects on the local

    environment have been identified and integrated into

    the design. The CoCP Part A sets out scheme-wide control

    measures that would be used to minimise potentialeffects during the construction process.

    Table 2.4 sets out what we consider to be the key issues

    for this site during construction, and how we are currently

    proposing to address them.

    Related documents:

    Environment

    G i h P i St ti

  • 8/3/2019 Greenwich Pumping Station SIP

    16/32

    Greenwich Pumping Station

    16

    Issue Our response

    Possible effect of constructionvehicles on the capacity and

    operation of the local road

    network.

    We have sought to minimise disruption to the local road network through our

    site layout and design. We would manage the effects of road transport through

    our traffic management plans, which will seek to limit the number of vehicle

    movements and hours of operation, identify the most suitable site access points

    and any necessary highway management arrangements.

    Possible effect of noise and

    vibration on neighbouring areas.

    The contractor would be required to implement noise and vibration control

    measures at the worksite, which will be set out in the CoCP. We need to undertake

    continuous tunnelling at this site for reasons of safety, cost and programme. While

    continuous tunnelling is taking place, the working area would be enclosed in atemporary, purpose built building which would significantly reduce noise levels.

    Materials needed to construct the tunnel at night would also be loaded into the

    building during the day, to minimise machinery and vehicle movements at night.

    Possible effects on local air

    quality and dust nuisance in

    neighbouring areas.

    Preliminary findings indicate that while there is the potential for dust nuisance

    effects, there are unlikely to be any significant local air quality effects at any

    of the sites. The contractor would put in place air and dust control measures at

    the worksite, which will be set out in the CoCP. This would include enclosing the

    working area whilst tunnelling works are carried out to limit dust leaving the site.

    Effect on the Grade II listed

    coal sheds.

    The sheds will be carefully dismantled and stored prior to construction and will be

    reinstated in their current location on completion of the works in accordance with

    a methodology agreed with London Borough of Greenwich and English Heritage.

    Table 2.4: Key issues relating to construction

    Related documents:

    Managing construction

    Transport

  • 8/3/2019 Greenwich Pumping Station SIP

    17/32

    Future

    use

    Future use

    17

    Section 3: Future use

    This section describes the site after the completion of the

    construction work, ie when the main tunnel is in use the

    operational phase.

    Design

    Since phase one consultation we have progressed the

    design for the permanent use and appearance of the

    structures at Greenwich Pumping Station. The design

    of the permanent proposals follows our scheme-wideprinciples and takes into account comments made

    and ongoing engagement with the London Borough of

    Greenwich and other technical consultees.

    Our permanent works need to incorporate functional

    elements, which are required for the operation of the

    tunnel. These include:

    Underground structures including: a CSO drop shaft

    with an internal diameter of approximately 17m,

    connection culverts, interception chamber and valve

    chamber.

    Extension of the shaft, interception chamber and valve

    chamber approximately 1m above ground level withaccess covers on top of the structures. To ensure that

    they are finished to a certain level above the tunnel

    and because the site is low lying, these structures need

    to be extended above ground level. Refurbishment of

    the former beam engine house to accommodate fans,

    filters and electrical and control equipment.

    A small diameter ventilation column to the interception

    chamber up to 6m high.Maintenance vehicle access.

    Green ich P mping Station

  • 8/3/2019 Greenwich Pumping Station SIP

    18/32

    Greenwich Pumping Station

    18

    Issue Our response

    Effect on the existing pumping

    station infrastructure and

    Dockland Light Railway viaduct

    located to the north of the site.

    We have located and designed the permanent works to avoid effects upon existing

    underground and adjacent infrastructure, and to enable the pumping station to

    remain operational during and after construction.

    Re-use of the existing Grade II

    listed beam engine house.

    Changes in the scheme-wide ventilation strategy allow the beam engine house to be

    brought back into use. The building is to be refurbished and would house ventilation

    equipment and the electrical and control kiosk, which means there is no requirement

    for a new ventilation building.

    Effect on the setting of listed

    buildings and character of

    nearby Ashburnham Triangle

    Conservation Area.

    The majority of the proposed permanent works on this site would be below or near

    ground level, with the exception of the ventilation equipment, so are unlikely to have

    any significant effect on the listed buildings or Conservation Area.

    The location of the above ground works have been designed to preserve views of the

    listed building from adjoining public footpaths.

    The Grade II listed pumping station is to be sensitively refurbished with its facade

    preserved and enhanced.

    Following completion of construction, the Grade II listed coal sheds will be restored

    to their current location.

    Table 3.1: Site specific issues that have influenced our permanent design

    Table 3.1 sets out the site specific issues that have

    influenced our permanent design proposals and how we

    have addressed them in our proposed design.

    Future use

  • 8/3/2019 Greenwich Pumping Station SIP

    19/32

    Future use

    19

    Greenwich Pumping Station

  • 8/3/2019 Greenwich Pumping Station SIP

    20/32

    Greenwich Pumping Station

    20

    Figure 3A: Photo of the site before the works

    Figures 3A, 3B, 3C and 3D show the current site and

    provide illustrations of our design proposals. Further

    information on the development of our design can be

    found in the Design development report.

    Related documents:

    Design

    Future use

  • 8/3/2019 Greenwich Pumping Station SIP

    21/32

    Future use

    21

    Figure 3B: Artists impression of the site after the works are completed

    Greenwich Pumping Station

  • 8/3/2019 Greenwich Pumping Station SIP

    22/32

    Greenwich Pumping Station

    22

    Figure 3C: Aerial view of the completed works

    Future use

  • 8/3/2019 Greenwich Pumping Station SIP

    23/32

    23

    Figure 3D: Layout of site once construction works complete

    Ventilation equipment and electricaland control equipment to be housedwithin disused beam engine house

    Pedestrianfootpath to bereinstated alongexisting route

    Proposed shaftextendingapproximately 1mabove existing groundlevel with handrail

    Maintenance accessroad to be connected toexisting roads within site

    Existing boundaryfenceline to be reinstated

    DLRvia

    duct

    Coal shed tobe reinstated

    Norm

    an

    Road

    Interceptionchamber extending

    approximately1m above existingground level

    Temporary hoardingaround site forreinstatement/made available fordevelopment (by others)

    N

    Greenwich

    Pumping Station

    Ventilationstructure

    Lowmaintenance

    grass area

    Lowmaintenance

    grass area

    Biodiverseroof to shaft

    Greenwich Pumping Station

  • 8/3/2019 Greenwich Pumping Station SIP

    24/32

    Greenwich Pumping Station

    24

    Operation and maintenanceOnce the tunnel is operational, we expect to undertake

    inspection and maintenance of the ventilation and below

    ground equipment approximately once every three to six

    months. This would be undertaken within our site and as

    part of the existing maintenance routine.

    Once every ten years, we expect to carry out a major

    internal inspection of the tunnel and underground

    structures. This is likely to involve a small team of

    inspection staff, a small team of support crew and two

    mobile cranes to lower the team and inspection vehicle

    into the shaft. This is likely to take several weeks and

    would all be undertaken within our site.

    We may also need to make visits to the site for unplanned

    maintenance or repairs, for example, if there is a

    blockage, or equipment failure. This may require the use

    of mobile cranes and vans.

    Permanent vehicular access would be from Norman Road.

    Management of operational effectsWe have undertaken technical work, including stakeholder

    engagement, to assess and identify the key issues

    associated with this site once it is operational. Table

    3.2 summarises these issues and how we are currently

    proposing to address them.

    Future use

  • 8/3/2019 Greenwich Pumping Station SIP

    25/32

    25

    Issue Our response

    Possible odour effects during

    the operation of the tunnel.

    Odour effects at this site are expected to be negligible because we have developed

    anAir management plan to minimise possible odour and air quality effects arisingfrom the operation of the tunnel. The technology we are proposing to use at this site

    includes a mechanical ventilation system that draws air through the tunnel with fans

    before cleaning the air using carbon filters that will absorb possible odour before air

    leaves the ventilation equipment.

    Disturbance from future

    maintenance access.

    The permanent access to our site would remain unchanged and visits would be

    undertaken as part of the existing maintenance routine.

    Table 3.2: Key issues relating to site operation

    Related documents:

    Odour

    Further information

  • 8/3/2019 Greenwich Pumping Station SIP

    26/32

    26

    u t e o at o

    This section sets out documents which may be of particular interest. Further information on our proposals can be

    found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre

    on 0800 0721 086).

    Phase two public consultation material

    Project information papers include general information about the Thames Tunnel project. There are 17 project

    information papers, which cover various aspects of the project. Those project information papers that may be of

    particular interest are set out below.

    Icon Title Details

    Build

    Provides information on the different types of sites required for the Thames Tunnel

    project and the typical construction activities that will be undertaken at each site.

    Changes

    Explains how the scheme has changed compared to that presented at phase one

    consultation, including changes to the tunnelling strategy for the main tunnel and

    changes to sites.

    Q&A Consultation

    Sets out the consultation we have undertaken to date on the project, the scope

    of this phase two consultation and how interested parties can respond to thisconsultation.

    DesignContains the design principles which have influenced the permanent appearance of

    our sites once construction work is complete.

    EnvironmentSets out the process the project is following to assess potential environmental effects

    of the Thames Tunnel project.

    Managing

    construction

    Includes information on what measures our contractors will put in place at our sites

    during construction.

    Odour Sets out ourAir management plan and how it will work.

    Options Outlines the various ways to deal with sewage overflows.

  • 8/3/2019 Greenwich Pumping Station SIP

    27/32

    27

    Phase two public consultation material

    Icon Title Details

    OverflowSets out how Londons sewerage system works and why the capital has an overflow

    problem.

    Route and

    tunnel

    alignment

    Sets out the preferred route of the main tunnel and the reasons for our preference.

    Site selection Sets out the process we followed to find and select our preferred sites.

    Transport Contains information on the different transport options we have considered fordelivering and removing materials from our sites.

    Site information papers provide information that relate to each preferred site along the route of the Thames Tunnel

    project. The following site information papers may be of particular interest.

    Chambers WharfCW

    Further information

  • 8/3/2019 Greenwich Pumping Station SIP

    28/32

    28

    Technical reports

    Theme Icon Title Details

    Interim

    engagement

    Interim engagement

    report

    Provides a summary of the public engagement we

    have undertaken between phase one and phase two

    consultations.

    Phase one

    consultation1

    SUMMARY

    Report on phase one

    consultation:

    summary report

    Provides a summary of the comments made at phase one

    consultation and our responses.

    Phase two

    construction

    information

    Code of construction

    practice Part A:

    General requirements

    (CoCP)

    Sets out control measures to be adopted during the project

    construction period.

    Phase twoenvironmental

    information

    Air management

    plan

    Outlines the methods which we will use to manage odour

    from the main tunnel at all our preferred sites.

    Preliminary

    environmental

    information report

    (PEIR)

    Contains initial assessments on the environmental effects of

    the Thames Tunnel project based on information collected

    to date. Please refer to volume 26 of the non-technical

    summary and volume 26 of the PEIR for more information

    on this site.

    Phase two scheme

    development

    Design development

    report

    Provides a general overview of how the scheme design at

    each site has evolved to date. Please refer to chapter 24 for

    more information on this site.

    2

    Phase two scheme

    development report

    Provides an overview of the development of the Thames

    Tunnel project and how each site was chosen. Please refer to

    Appendix J for more information on this site.

    Site glossary

  • 8/3/2019 Greenwich Pumping Station SIP

    29/32

    29

    g y

    Term Definition

    Biodiverse roof

    A roof which supports a wide variety of plant and animal species and reduces

    stormwater runoff.

    Carbon filters Filters that remove odours before the air is released from the tunnel.

    Combined sewer A single sewer system that takes both rainwater and domestic and industrial wastewater.

    Combined sewer

    overflow (CSO)

    A structure, or series of structures, that allows sewers to overflow into the river when they

    are full as a result of increased rainfall. Without the overflows, the sewers would back up and

    cause flooding in streets or houses.

    Connection tunnel A tunnel connecting a drop shaft to the main tunnel.

    Conservation areaAn area designated by the local authority or English Heritage as having special architectural

    or historical interest.

    Draft limit of land to

    be acquired or used

    The extent of land that we may need to use or acquire, or over which rights may be needed to

    carry out works that are essential to the project.

    Drop shaft

    A vertical circular concrete structure, used to drop flows from the high level of the CSO to

    the low level of the main tunnel. It would also be used to provide access to construct the

    connection tunnels.

    Foreshore Ground uncovered by the river when the tide is low.

    Interception chamberA structure, built on an existing combined sewer, which diverts stormwater overflow into the

    main tunnel.

    Main tunnel/

    connection tunnel

    drive site

    A site that would be used to construct the main tunnel or connection tunnel. The excavated

    material would be removed from the tunnel and the concrete tunnel lining segments would

    be delivered to the tunnel at the main/connection tunnel drive site.

    Main tunnel The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station.

    Operational phase After the completion of the construction work, when the main tunnel is in use.

    Secondary lining A second, internal lining to the tunnel, giving it additional strength.

    Thames Tunnel project

    The Thames Tunnel project comprises a storage and transfer tunnel, from west London to

    Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along the

    Thames Tideway.

    Transport for London

    Road Network (TLRN)

    The network of roads managed by Transport for London. These are the major or strategic

    roads, which have high capacity.

    Tunnel boring machine

    (TBM)

    A machine used to excavate tunnels through a variety of conditions, with a circular

    cross-section.

  • 8/3/2019 Greenwich Pumping Station SIP

    30/32

  • 8/3/2019 Greenwich Pumping Station SIP

    31/32

    Greenwich Pumping Station

  • 8/3/2019 Greenwich Pumping Station SIP

    32/32

    32

    Phase two consultation: Greenwich Pumping Station

    For further information or to comment on our

    proposals see our website:

    www.thamestunnelconsultation.co.uk

    110-ED-PNC-00000-000082

    Autumn 2011

    It is very important that you understand theinformation we have provided. If you needfurther information in another language,

    braille, large print or audio format pleasecontact us on 0800 0721 086.