Grant Projects UpdateJanuary 9, 2017
Goals for Presentation
Provide the current status of grant funded projects Focus on infrastructure projects
Not inclusive of all county grants
Provide general information about specific grant programs
Provide insight for planning and budgeting decisions
To answer questions related to projects
1/5/2017
2
Information to be presented
Current status/phase of project
Anticipated timeline for project completion
Budget planning considerations
Historical information if relevant
Other significant information of interest
Grants & Special Programs
Program Summary Awarded
Hazard Mitigation Grant Program (HMGP) drainage projects
$ 443,963
Flood Mitigation Assistance Program (FMA)private property mitigation
$ 939,900
Parks & Recreation (FRDAP & CPI) $ 130,000
Natural Resource Damage Assessment (NRDA)* $ 3,423,355
Community Development Block Grant (CDBG) $ 750,000
FDOT Landscape Projects $ 450,000
FWC Derelict Vessel Removal Program $ 4,125
Total $ 6,141,343
1/5/2017
3
Engineering Department
Program Summary Awarded
Local Agency Program (LAP) sidewalk projects $ 159,341
FDOT Aviation Grants $ 1,149,411
FAA Aviation Grants $ 130,000
State appropriation – Camden Drive Drainage (HBTS) $ 650,000
State appropriation – I-10 Industrial Park $ 1,000,000
Total $ 3,088,752
Hazard Mitigation Grant Program (HMGP)
Funds allocated to county following a major disaster declaration for implementation of long-term hazard mitigation measures
Typical Federal share of 75%, local match 25%
County’s focus historically on stormwater drainage projects with recurring flooding concerns
Private property and public infrastructure wind mitigation projects Partnership with Rebuild Northwest Florida
Five open projects
1/5/2017
4
Settlers Colony Rescopement / Expansion
HMGP funds post TS Debby (2012)
Original Settler’s Colony drainage project completed in 2016
DEM encouraged the county to expand project in Jan 2016 with leftover disaster funding
Proposed expansion project would improve drainage in the areas of Gondolier Boulevard and Coronado Drive and the arterial roadways including Aquamarine Drive, Bay Street, Grand Canal Street, Settlers Colony Blvd, Silver Strand Court, Venetian Way, Vestavia Way and Wild Roost Road.
Requested water quality components
Requested federal share of $4,671,172 committing local share of $1,557,058
Settlers Colony Rescopement / Expansion
Project expansion activities were expedited with deliverables submitted in February 2016 and subsequently revised in April 2016
In FEMA Environmental and Historic Preservation review since May 2016
Current projected review completion is Jan 31, 2017
Pending grant agreement issuance in early 2017, design would commence immediately.
Atkins & BDI selected as Phase I design engineers
Project will be expedited to the extent practical for completion by April 2018 (FEMA’s requested deadline).
Archeological monitoring may be a requirement of construction
1/5/2017
5
Cost Estimate Line ItemCost Estimate
Amount
Construction Cost => $5,234,394
Pre-Award Cost => $39,530
Engineering Design and Permitting => $554,306
Project Management => $60,000
Post Design Services (CEI Services) => $225,000
Archaeological Monitoring Services => $115,000
Grand Total => $6,228,230
Settlers Colony Rescopement / Expansion
Ranchettes Subdivision Drainage (Gulf Breeze) HMGP funds post 2014 Flood event
Proposed expansion project would improve drainage in the areas of the Gulf Power Ditch, Ranchettes North, Ranchettes South, Rosa Del Villa East, Rosa Del Villa West, Rancho Villa Drive, Whisper Bay Blvd, Coral Strip Pkwy and Bay Heather Drive (acquisition of property required).
Requesting federal share of $1,243,230 committing local share of $414,410 for Phase II construction costs
Design & permitting complete (American Consulting Engineers)
Phase I deliverables by DEM was recently completed
Review of Phase I deliverables by FEMA to commence in January 2017
Phase II Construction funding award – TBD (2017?)
April 2018 – FEMA’s desired completion date
1/5/2017
6
Pace Lane/Patterson Lane Drainage (Pace)
HMGP funds post 2014 Flood event
Proposed expansion project would improve drainage in the areas of Pace Lane, Patterson Lane, Faircloth Street, Matthew Road and Overlook Circle (acquisition of property required)
Requesting federal share of $1,059,022 committing local share of $353,007 for Phase II construction costs
Design & permitting complete (Atkins)
Phase I deliverables by DEM was recently completed
Review of Phase I deliverables by FEMA to commence in January 2017
Phase II Construction funding award – TBD (2017?)
April 2018 – FEMA’s desired completion date
Maranatha Way/Chipper Lane Drainage (Pace)
HMGP funds post 2014 Flood event
Proposed expansion project would improve drainage in the areas of the Maranatha Way, Chipper Lane, and Millie Lane (acquisition of property required).
Requesting federal share of $891,821 committing local share of $297,274 for Phase II construction costs
Design & permitting complete (Baskerville Donovan)
Phase I deliverables currently under review by DEM
Phase II Construction funding award – TBD (2017?)
April 2018 – FEMA’s desired completion date
1/5/2017
7
Venetian Way/Coronado Drive Drainage (Gulf Breeze)
HMGP funds post 2014 Flood event
Proposed expansion project would improve drainage in the general areas of Venetian Way, Lido Boulevard, Lido Gardens, Venetian Court, Venetian Gardens, and Villa Venyce Court
Requesting federal share of $1,790,433 committing local share of $596,811 for Phase II construction costs
Design & permitting 90% (Southern Site & Utility Design)
Phase I deliverable submittal – January 2017
Phase II Construction funding award – TBD (2017?)
April 2018 – FEMA’s desired completion date
Open HMGP Budget SummaryF/Y Project Name Status
Total or Estimated Costs Federal Share Local Share
FY 16FY 17
Ranchettes/Whisper Bay Phase I $132,490 $99,368 $33,123
Patterson/Pace Ln Phase I $114,990 $86,243 $28,748
Venetian Way/Coronado Dr Phase I $215,000 $161,250 $53,750
Maranatha/Chipper Phase I $129,470 $97,103 $32,368
Total Underway & Budgeted $591,950 $443,963 $147,988
2017 Settlers Colony Expansion ‐ Design Pending $614,306 $460,730 $153,577
2018 Settlers Colony Expansion ‐ Construction** Pending $5,574,394 $4,180,796 $1,393,599
2017 Ranchettes/Whisper Bay Phase II $1,657,640 $1,243,230 $414,410
2017 Patterson/Pace Ln Phase II $1,412,029 $1,059,022 $353,007
2017 Maranatha/Chipper Phase II $1,189,095 $891,821 $297,274
2017 Venetian Way/Coronado Dr Phase II $2,387,244 $1,790,433 $596,811
Total Upcoming & Not Budgeted $12,834,708 $9,626,031 $3,208,677
*Local Match greater than 25% due to property purchase
** Budget includes water quality improvements
TOTALS FY 2017 $7,260,314 $5,445,236 $1,815,079
TOTALS FY 2018 $5,574,394 $4,180,796 $1,393,599
Needed:$1,815,079
for FY17
$1,393,599for FY18
1/5/2017
8
Proposed Land Acquisitions (HMGP Projects)
Each of the four projects in design phase will require acquisition of land and/or easements
Pace & Patterson Lane property acquisitions have been approved by the Board.
Negotiations between property owners and county are underway for three other projects
Land acquisitions need to be completed by the issuance of Phase II agreement with DEM (expected sometime in 2017)
In order to maintain cost effectiveness requirements and/or stay within grant budget restraints, the Board may be required to fully fund the acquisition of necessary property, resulting in additional local share costs
Major drainage projects completed with HMGP (past ten years)
Project Name StatusTotal or Estimated
Costs Federal Share Local Share
Ramblewood (Gulf Breeze)* Complete $1,236,234 $810,926 $425,308
Greenbriar (Gulf Breeze) Complete $900,395 $675,296 $225,099
Orion Lake (Navarre) Complete $682,344 $511,758 $170,586
Harrison Avenue (Gulf Breeze) Complete $1,296,083 $972,063 $324,021
Villa Venyce (Gulf Breeze) Complete $524,063 $393,047 $131,016
Sabertooth (Gulf Breeze) Complete $823,172 $617,379 $205,793
Ganges and Madura (Gulf Breeze) Complete $799,686 $599,764 $199,921
Settlers Colony Phase I (Gulf Breeze) Complete $65,950 $49,463 $16,488
Settlers Colony Phase II (Gulf Breeze) Complete $415,479 $311,609 $103,870
Total Complete $6,743,406 $4,941,305 $1,802,102
Gain to SRC Cost to SRC
1/5/2017
9
Flood Mitigation Assistance Program (FMA)
Federal mitigation funding to reduce the risk of flood damage to repetitively flooded NFIP insured structures
Competitive funding
Federal share ranges from 75-100%, local match met by willing and eligible homeowners
County’s focus on elevation of properties (as opposed to other types of mitigation)
12 properties mitigated since 2010
4 properties approved for mitigation in 2017
Awards totaling $939,900 pending BOCC approval 3951 West Madura Rd, Gulf Breeze(100% funded)
2960 Coral Strip Pkwy, Gulf Breeze (90% funded)
2954 Coral Strip Pkwy, Gulf Breeze (90% funded)
1432 Alabama St, Navarre Beach (90% funded)
Elevation projects will be completed in 2017
Flood Mitigation Assistance Program (FMA)
1/5/2017
10
Completed FMA Projects
Year
Complete Address City Mitigation Type Project Cost Grant
Homeowner
Match
2010 2956 Coral Strip Pkwy Gulf Breeze Elevation 159,111.13$ 143,200.02$ 15,911.11$
2011 6025 Saddle Club Rd Pace Acquisition 427,104.00$ 384,393.60$ 42,710.40$
2012 2932 Coral Strip Pkwy Gulf Breeze Acquisition 504,718.30$ 454,246.47$ 50,471.83$
2013 2928 Coral Strip Pkwy Gulf Breeze Elevation 215,001.58$ 193,501.42$ 21,500.16$
2012 2958 Coral Strip Pkwy Gulf Breeze Elevation 149,583.85$ 134,625.47$ 14,958.38$
2012 1644 Stanford Rd Gulf Breeze Elevation 149,026.00$ 134,123.40$ 14,902.60$
2012 3148 Coquina Way* Gulf Breeze Elevation 230,706.31$ 207,706.31$ 23,070.63$
2012 3845 Sabertooth Cir* Gulf Breeze Elevation 252,196.33$ 226,976.68$ 25,219.65$
2015 3135 Harrison St Milton Elevation 170,700.00$ 170,700.00$ $0.00
2015 1690 College Pkwy Gulf Breeze Elevation 90,833.00$ 90,833.00$ $0.00
2015 8120 Glennview Rd Milton Elevation 174,158.00$ 174,158.00$ $0.00
2015 6036 Saddle Club Rd Pace Elevation 253,690.19$ 253,690.19$ $0.00
Totals 2,776,828.69$ 2,568,154.56$ 208,744.76$
*Homeowner match reimbursed through Increased Cost of Compliance Program (ICC)
Parks & Recreation
Outstanding CPI application for Sandpiper Park Pier & Seawall – notifications in Spring 2017
Grant Project Amount Status Completion
FRDAP Floridatown Park Improvements
$ 50,000 Awarded – pending grant agreement
TBD2017
FRDAP Navarre Park Improvements
$ 50,000 Awarded – Master Planning / Design (Genesis Engineering)
TBDApril 2018 grant deadline
CPI Bagdad Mill Site Park Bathroom
$ 30,000 Awarded – Bidding Phase Fall 2017
1/5/2017
11
Bagdad Mill Site Park Recap (Special Project of Grants Dept)
Long term project – 2005
Phase I complete in 2016 – Grand opening in May
Grant Funds totaling $329,960 were spent on development of the park Grant funds represented 1/3rd of total project cost
Grant funded tree planting project recently completed 147 trees of ten different species
Educational components ongoing
Permanent restroom construction completion in 2017
Requested NRDA funding under the recreation/public access category to build permitted floating bock dock with connector dock to existing T fishing pier including a handicap ramp from fishing pier to dock (estimate $600,000)
Bagdad Mill Site Park Pictures
1/5/2017
12
Natural Resources Damage Assessment (NRDA) Early restoration funding as a result of the Deep Water Horizon Oil Spill
Project AwardAmount
Status of project Construction /Completion
Navarre Beach Park Gulfside Walkover Complex
$ 1,221,847 Managed by DEP - Design complete, permittingnearing completion (Genesis Engineering)Bidding Spring 2017
Summer/Fall 2017
Navarre Beach Park Coastal Access and Dune Restoration Improvements
$ 614,630 Managed by DEP - Design complete, permitting nearing completion (Genesis Engineering)Bidding Spring 2017
Summer/Fall 2017
Artificial Reef Construction (Snorkel and Fish/Dive)
$ 1,469,817 Design Phase (Taylor Engineering) (2017-2018)
Sea Turtle Lighting Retrofits
$ 117,061 Project Underway Summer 2017
Community Development Block Grant (CDBG)
Grant Awarded – pending grant agreement issuance
Sewer line extension and septic tank abatement in Legend Creek area of Pace (low to moderate income requirement)
Service approximately 100 households
Partnership with Pace Water System for implementation ($730,000 matching commitments)
Project construction TBD (2017-2018)
1/5/2017
13
FDOT Landscape Projects
Pace US 90 (Woodbine Rd to Chumuckla Hwy) $200,000 awarded for construction
Genesis Engineering commencing design phase in Jan 2017
Construction in Fall 2017
Navarre SR 87 (US 98 to High School Blvd) $250,000 approved for construction
Pending grant agreement issuance
Landscape architect selection – early 2017
Design phase – mid 2017
Construction TBD
Derelict Vessel Removal Grant
Derelict Vessel Removal Grant awarded
Solicitation of quotes from qualified marine contracts expected in March 2017
Removal of Vessel will occur in spring/summer 2017
1/5/2017
14
Local Agency Participation (LAP)
Project AwardAmount
Status of project Construction /Completion
King Middle SchoolSidewalk Project
$ 42,022 Design funding only. Design underway.Construction funding programmed in 2018.
TBD – 2019
Glover Lane Sidewalk (west side of Glover from
Hamilton Bridge Rd to Hobbs Middle)
$ 33,612 Design funding only. Design underway. Construction funding programmed in 2018.
TBD – 2019
Hamilton Bridge Rd Sidewalk
$ 23,306 Design funding only. Design start in 2017. Construction funding programmed in 2019.
TBD – 2020
Spring Street (Jay) Sidewalk
$ 60,401 Design funding only. Design start in 2017. Construction funding programmed in 2019.
TBD – 2020
FDOT Aviation Development Grants
Project AwardAmount
Local Match
Status of project Construction /Completion
Construct 12 T-Hangar units $ 480,000 $ 120,000 Design phase (Mott McDonald) Late 2017 or 2018
Two entrance/exit taxiways on south side of airfield
$ 129,000 $ 32,250 Scheduled FDOT funding in 2017 2019-2020
Construct east T-Hangaraccess taxilanes to support additional T-Hangar construction
$ 227,200 $ 56,800 Scheduled FDOT funding in 2017 2019-2020
1/5/2017
15
FAA Aviation Grants
Project AwardAmount
Local Match
Status of project Construction /Completion
Runway overlay / pavement rehabilitation & maintenance
$ 1,149,411 $ 127,712 Recently completed (First quarter of FY 2017)
Camden Drive Drainage Water Project Appropriation
Funds in the amount of $650,000 awarded
Project includes improvements to the existing drainage way along with proposed infrastructure improvements
County funds in the amount of $850,000 obligated as matching
Design underway by Baskerville Donovan
Anticipated construction in late 2017 or 2018
Additional funding will be requested for the state’s 2018 budget
1/5/2017
16
I-10 Industrial Park Appropriation
Funds in the amount of $1,000,000 awarded, pending grant issuance
Funds will be used for second park entrance and 1400 LF of industrial roadway with water, sewer and stormwater infrastructure
County funds in the amount of $270,000 obligated as matching
Design will be completed by Engineering Department by mid January
Anticipated construction in 2017
Moving Forward Absent a new federally declared disaster, HMGP funds will be
exhausted after completion of current projects (2018)
No other substantial grant opportunity to continue the stormwater drainage improvements program
Increased focus on Environmental/water quality grant funding
Greenways and Trails - extension of Blackwater Heritage Trail north to Blackwater River State Forest / Wolfe Creek
Funding for projects associated with long term planning efforts
Pace/Gulf Breeze Pedestrian Plans
LOST planning
Other Board priorities
1/5/2017
17
Questions?