Operations Overview Presentation to Multi Agency Permitting Team

April 28, 2011

Gateway Pacific Terminal

Page 2: GPT Terminal Operations Overview - Wa

East Loop

Rail Access & Capacity

Railcar Unloading Station

Stockyard

Conveyance System

Shiploading

Vessel Operations

West Loop

Material Handling & Storage

Service Buildings and Terminal Support

Principal Terminal Components

Page 3: GPT Terminal Operations Overview - Wa

Pacific International Terminals, Inc. is proposing to develop the

Gateway Pacific Terminal at Cherry Point in Whatcom County,

Washington. Designed for export and import of dry bulk

commodities, the proposed terminal would include deep-draft wharf

and access trestle, dry bulk materials handling and storage facilities,

and rail transportation access.

This presentation includes a description of the terminal’s functional

layout and an introduction to its operation. To provide the viewer

with an understanding of the physical scope of the proposed project,

the presentation contains typical illustrations of the facilities,

infrastructure and equipment that would be necessary to handle dry

bulk commodities at the quantities proposed. These illustrations are

representative of those that could be employed at the terminal; actual

equipment selection and configuration will be finalized as part of the

ongoing engineering design program.

Gateway Pacific Terminal Operations Overview

Page 4: GPT Terminal Operations Overview - Wa

Rail Access and Capacity

Site Plan

Page 5: GPT Terminal Operations Overview - Wa

Rail Access and Capacity

Page 6: GPT Terminal Operations Overview - Wa

Rail Access and Capacity

East Loop

Page 7: GPT Terminal Operations Overview - Wa

Rail Access and Capacity

West Loop

Page 8: GPT Terminal Operations Overview - Wa

Rail Access and Capacity

Page 9: GPT Terminal Operations Overview - Wa

Rail Unloading Station

Page 10: GPT Terminal Operations Overview - Wa

Railcar Unloading Station

Rotary Dumper Shed and Dust Filtration System

Page 11: GPT Terminal Operations Overview - Wa

Railcar Unloading Station

Page 12: GPT Terminal Operations Overview - Wa

Railcar Unloading Station

Rail Unloading Shed and Conveyor to Stockyard (View Looking to the South)

Tandem Rotary Dumper

Hopper

Ice Crusher & Grizzly

Conveyor to Stockyard

Page 13: GPT Terminal Operations Overview - Wa

Railcar Unloading Station

Tandem Rotary Dumper(Coal within a Shed, Woodchips Outside)

Inside Rotary Dumper Shed

Page 14: GPT Terminal Operations Overview - Wa

Railcar Unloading Station

Railcar Indexer

Page 15: GPT Terminal Operations Overview - Wa

Stockyard

Page 16: GPT Terminal Operations Overview - Wa

East Loop Stockyard

Cross Section of Stockyard Showing Stacker Reclaimers and Stockpiles

Page 17: GPT Terminal Operations Overview - Wa

East Loop Stockyard

Stacker/Reclaimer

Page 18: GPT Terminal Operations Overview - Wa

East Loop Stockyard

Stacker/Reclaimers Being Commissioned

Page 19: GPT Terminal Operations Overview - Wa

Stockyard

Example of a Water Cannon (at left) and Fogging Cannon (below) Used in the Stockpiles for Dust Suppression

Page 20: GPT Terminal Operations Overview - Wa

Conveyance System

Conveyors,

Transfer Tower,

Surge Bin &

Sampler

Page 21: GPT Terminal Operations Overview - Wa

Conveyance System

Transfer Point

(material conveyed to top

of tower and dropped to lower conveyor)

Elevated Covered Conveyor

Page 22: GPT Terminal Operations Overview - Wa

Conveyance System

ABCdef

Covered Conveyor

Half Covered Conveyor (shown to illustrate the conveyor inside)

Page 23: GPT Terminal Operations Overview - Wa

Conveyance System

Enclosed Gallery (Under Construction)

Surge Bin(Under Construction)

Page 24: GPT Terminal Operations Overview - Wa

Conveyance System

Dust Suppression

Page 25: GPT Terminal Operations Overview - Wa

Shiploading

Page 26: GPT Terminal Operations Overview - Wa

Ship Loading

Shiploader with Enclosed Gallery & Enclosed Boom

Page 27: GPT Terminal Operations Overview - Wa

Ship Loading

Wharf Cross Section with Shiploader and Enclosed

Galleries

Enclosed Galleries on Access Trestle (schematic)

Page 28: GPT Terminal Operations Overview - Wa

Ship Loading

Example of Banana Spout Loading Coal Vessel

Banana Spout(schematic)

Page 29: GPT Terminal Operations Overview - Wa

Vessel Operations

Page 30: GPT Terminal Operations Overview - Wa

Cherry Point Vessel Routes

Page 31: GPT Terminal Operations Overview - Wa

Vessel Operations

Tug Assist

Page 32: GPT Terminal Operations Overview - Wa

Vessel Operations

Cape Size Vessel

Page 33: GPT Terminal Operations Overview - Wa

Vessel Operations

Quick Release Hook and Mooring Lines

Page 34: GPT Terminal Operations Overview - Wa

West Loop

Page 35: GPT Terminal Operations Overview - Wa

Gateway Pacific Terminal – West Loop

Potash Shed and Shiploading

Silo Storage

Page 36: GPT Terminal Operations Overview - Wa

Gateway Pacific Terminal – West Loop

Import Material Hopper Located on the Wharf

Self Unloading Vessel (used for import cargo)

Note that conveyor in this photo is not enclosed

Page 37: GPT Terminal Operations Overview - Wa

Gateway Pacific Terminal – West Loop

Railcar Loading with Import Material

Page 38: GPT Terminal Operations Overview - Wa