GOVERNMENT OF PAKISTAN MINISTRY OF COMMUNICATIONS ...
Transcript of GOVERNMENT OF PAKISTAN MINISTRY OF COMMUNICATIONS ...
GOVERNMENT OF PAKISTAN
MINISTRY OF COMMUNICATIONS
13th CAREC TSCC Meeting 14−15 May 2014
Action Plan on Implementing CAREC TTFS 2020
By Sabino Sikandar Jalal
CAREC Focal Person on Transport
VISION
Achieve national cohesion and regional integration through development of sustainable communication infrastructure for socio-economic uplift of the country by providing enabling environment to facilitate movement of people, goods and services in minimum time and cost.
TARGETS
Develop Pakistan as a hub of sub regional connectivity between high growth East Asia & resource rich Middle East
Improve regional connectivity (links with China, Afghanistan / CARs, Iran, India etc.)
Establish efficient and well integrated transport system to achieve competitive economy
Reduce transport costs and enhance affordability
Increase road density from 0.32 to 0.64 Km / Km2
ROAD NETWORK
Area =796,096 Sq- km
Total Road Network =260,000 Kms
National Highways & Motorways =12,131 Kms
Roads have dominant share in both transport of passengers (90%) and the Goods (95%) followed by rail.
Total Number of Vehicles more than 8 million
55.4% are two Wheelers and 44% four Wheelers (including Cars)
Annual growth rate is 9 %
PAKISTAN’S GEO-STRATEGIC SIGNIFICANCE
K A Z A K H S T A N
UZBEKISTAN
TURKMENISTAN
I R A N
C H I N A
KYRGYZSTAN
TAJIKISTAN
RUSSIA
B L A C K S E A
T U R K E Y
URALSK
GURYEV DZHURALY
ARAL SEA
JAMMU & KASHMIR
DISPUTED TERRITORY
SHEVCHENKO
ARABIAN S E A Ajmer
Amratsar
DEHLI
Persian Gulf
IRAQ
KUWAIT
OMAN UAE
QAT
AR
SAUDI ARABIA
SYRIA
PALE
STIN
E R
ED S
EA
EGYPT
MEDITERRANEAN SEA
GREECE
BULGARIA
GEORGIA
UKRAINE
MOLDAVIA
ROMANIA
AZARBIJAN
RUSSIA
I N D I A
Mumbai
DISPUTED TERRITORY
Karimabad
Chilas
Sazin
Mansehra
N-15 Malakand
Chitral
Torkham PESHAWAR
Rawalpindi ISLAMABAD
Kharian
LAHORE
Okara
Bahawalpur
Rahimyar Khan
Mastung
Kalat
Surab
Taftan
Nok Kundi Dalbandin
Nushki
QUETTA
Chaman
N-25
Dadhar
DeraMuradJamali
Shikarpur
Jacobabad
Sukkur
Kuchlak QilaSaifullah
Zhob
DI Khan
Loralai DG Khan Muzaffargarh
Skardu Dambu
Naran
Dadu
Larkana
Rajanpur
Moro
Ghotki Ubauro
Mianchannu
Mughal Kot
Retra
Parachinar
KhushalGarh
Murree Kohala N-75
M-1
M-3 Pindi Bhattian
Faisalabad
Khairpur
Sahiwal
Gujranwala
M-8 Kararo
S-2
Besima Nag
Punjgur
Kohat
S-3
Wazirabad
Khanewal
Chakothi
Kalam
Besham
Gujrat
Jhelum
Taunsa
Karakoram Pass 5575m
Abbotabad Hasanabdal
Sust
GILGIT N-35
NATIONAL HIGHWAYS & MOTORWAYS NETWORK IN PAKISTAN
Lodhran
Ratodero
Muzaffarabad
Jalkhad
Leh
Karak
Jalalabad K A S H M I R
Khuzdar
Wad
Sibi
Naushero Firoz
Chakdara
Dir
Drosh
Saidu
Multan
K2 8611m
Khunjrab Pass
Sambarial
Kotri Kabir Ranipur
J A M U &
Liari
Bela
Uthal
Ormara Kotri
Thatta ARABIAN SEA
Hoshab
Gabd Pleri
S I N D Turbat
Hyderabad
Hala
KARACHI
Pasni Gwadar Jiwani
Awaran
Duregi
Kakkar
Gharo
Keti Bandar N-110
N-120 Mirpurkhas
Umarkot
Khokhropar
ACTION PLAN - PROJECTS No. IP No. Route Cost
($ Mill) Progres Imp Period
55 101 Realignment of Karakoram Highway at Hunza – (Exim Bank of China)
275 37% Start: July 2012 End: Jan 2015
56 103 Karachi-Hub-Dureji-Sehwan (M-7) 250 Km
Funds not firmed up
Start: Jan 2015 End: Jan 2018
57 104 Sehwan-Ratodero (N-55) (Expressway -199 Km) – (JBIC & GOP)
160 54% Start: Dec 2010 End: Dec 2014
58 105 Ratodero-Dera Ghazi (DG) Khan (N-55) (Expressway - 200 Km)
Funds not firmed up
Start: Jan 2015 End: Jan 2018
59 110 Peshawar-Torkham Expressway (50 km) 255 - Funds not firmed up
Start: Jan 2015 End: Jan 2018
60 111 Gwadar-Hoshab Motorway (M-8) – (GOP)
I). Gwadar-Dasht (Section-I)
II). Dasht-Turbat (Section-II)
III). Turbat-Hoshab (Section-III)
550 60% Start: Jan 2010 End: Dec 2015
ACTION PLAN - PROJECTS No. IP No. Route Cost
($ Mill) Progres Imp Period
61 115 BCP Expansion and up-gradation at Torkham, Wagah and Chaman – (ADB Funded)
Pakistan Customs targeted to prepare Project Documents by June 2014 – ADB Loan Considerations
62 116.1 M-4 (Section 2 - Gojra-Shorkot
(4-Lane Motorway)
Funds not
firmed up
Land being
acquired
Start: Jan 2015 End: Jan 2018
63 116.2 M-4 (Section 3 – Shorkot-Khanewal (4-Lane Motorway) including bridges over Ravi and Sidhnai Rivers
Funds not
firmed up
Land being
acquired
Start: Jan 2015 End: Jan 2018
64 118 M-4 (Section 1 Faisalabad – Gojra 4-Lanes Motorway) – (ADB Funded)
170 82% Start: Feb 2010 End: Jun 2014
65 119 Lahore-Peshawar Railway Rehabilitation - - -
ACTION PLAN - PROJECTS No. IP No. Route Details Cost
($ Mill) Progress Impl Period
66 120.1 Hoshab-Sorab (National Highways N-85 & N-25) 450 Funds to be
arranged
Start: 2015 End: 2018
67 120.2 Sorab – Kalat (National Highways N-85 & N-25)
100 Funds to
be arranged
Start: 2015 End: 2018
68 121 E-35 (Section 1 Hasanabdal – Havelian) 4-Lanes Motorway –ADB Funded
150 Procurement
Start: Oct 2014 End: Jun 2016
69 122 E-35 (Section 1 Havelian – Mansehra) 4-Lanes Motorway
200 Land being
acquired
Start: 2015 End: 2018
70 123 M-4 (Section 4 Khanewal – Multan) 4-Lanes
Motorway – IDB Funded 150 38% Start: Dec
2011 End: Sep 2015
71 124 N-70 Muzaffargarh – DG Khan Section (Upgradation of existing road to 4-Lanes dual carriageway)
150 Funds to be
arranged
Start: 2015 End: 2018
KARAKORAM HIGHWAY
ISLAMABAD
ABBOTTABAD MANSEHRA
THAKOT
PATTAN
CHILAS
NANGA PARBAT(8125M)
K2(8721)
GILGIT GILGIT RIVER
RAKAPOSHI(7788M)
SKARDU
SUST
KHUNJERAB
KASHGAR
CHINA
CORRDOR
INDIA
HUNZA
TASHKURGAN
PESHAWAR
HASANABDAL
RAIKOT SAZIN
BHASHA DIAMIR DAM
Realignment of KKH at Attabad Lake – 275 Million, Exim
Bank of China, 36% Completion by Jan
2015
Khunjrab-Raikot Section (335 Km)
99% Completedj
FAISALABAD GOJRA
T T SINGH
SHORKOT
JHANG
CHINIOT
PAINSARA
SAMUNDRI
KHANEWAL
M - 4 ALIGNMENT
MULTAN
M - 3 M - 2
INTERCHANGES
ALIGNMENT OF FAISALABAD- KHANEWAL MOTORWAY (M - 4, 224 KM)
START POINT
END POINT Shorkot cantt
EXISTING ROADS
MOTORWAY ALIGNMENT
Kabirwala
Mian Chunnu
Rajhana Khiddar wala
Kamalia
PINDI BHATTIAN Bhawana
58 Km Section of Faisalabad-Khanewal
Motorway – US$ 170 M, ADB Financing, 82%
Completion by June 2014
DISPUTED TERRITORY
INDIA
CHINA
AFGHANISTAN
IRAN
ARABIAN SEA
SUST JAGLOT
MANSEHRA ABBOTABAD
HARIPUR
CHILAS
BURHAN
FATEHJHANG JAND
D.I KHAN
TAUNSA
MIANWALI
SUI DERA BUGTI
RAJANPUR
LARKANA
TALAGANG PINDIGHEB
LAYYAH
RATODERO NAG
PANJGUR
HOSHAB TURBAT
Jiwani
ATTABAD
JARANWALA SAMUNDRI PIR MEHAL
KHANEWAL
SHUJABAD
ZAHIR PIR
GHOTKI PANUAQIL
DADU
SAHIWAL OKARA
RAHIM YAR KHAN
CHAKWAL
SARGODHA
DERA MURAD JAMALI SIBI
LORALAI
YAKMUCH NOKUNDI DALBANDIN PADAG
NOSHKI
DARYA KHAN
KUNDIAN
PINDI BHATIAN
SHORKOT
LIARI
MUZAFFARABAD KOHALA BRIDGE
MANGLA / MIRPUR DINA
KHUNJERAB
GILGIT SKARDU
PESHAWAR
ISLAMABAD
LAHORE FAISALABAD
MULTAN DG KHAN QUETTA
KHUZDAR JACOBABAD
SUKKUR
HYDERABAD
KARACHI GWADAR
Boundary
Existing
• Motorways
Proposed Projects
• LKM
• Rivers
• Towns • Main Cities
• MMM
N-40
N-85
N-65 N-25
N-25
N-70
N-50
N-95
N-35
N-10 N-120
S-1
N-45
M-8
M-8
N-15
• Highways
• PCEC
National Highway Authority
Economic Corridor Roads, Rails, Ports, Energy, Special Economic Zones
-Khunjrab – Gwadar Highway (2400 Km) -Karachi-Lahore Motorway (1060 Km)
DISPUTED TERRITORY
INDIA
CHINA
AFGHANISTAN
IRAN
ARABIAN SEA
Sust Jaglot
Mansehra Abbotabad
Haripur
Chilas
Burhan
Fatehjhang Jand
Taunsa
Mianwali
Sui Dera Bugti
Rajanpur
Larkana
Talagang Pindigheb
Layyah
Ratodero Nag
Panjgur
Hoshab Turbat
Jiwani
Attabad
Jaranwala Samundri Pir mehal
Khanewal
Shujabad
Zahir Pir
Ghotki Panuaqil
Dadu
Sahiwal Okara
Rahim Yar Khan
Chakwal
Sargodha
Dera murad Jamali Sibi
Loralai
Yakmuch Nokundi Dalbandin Padag
Noshki
Darya Khan
Kundian
Pindi Bhatian
Shorkot
Liari
Muzaffarabad Kohala Bridge
Mangla / Mirpur Dina
Torkham
Sarai Gambila
Mughalkot Chaman
Besima
Awaran
KHUNJERAB
GILGIT
SKARDU PESHAWAR
LAHORE
FAISALABAD
MULTAN
KHUZDAR
N-40
N-85
N-65 N-25
N-25
N-70
N-50
N-95
N-35
N-10 N-120
S-1
N-45
M-8
M-8
N-15
Pakistan Karachi – Lahore Motorway (KLM)
DI KHAN
QUETTA
GWADAR HYDERABAD
KARACHI
ISLAMABAD
DG KHAN
SUKKUR
JACOBABAD Bahawalpur
Boundary
Existing Highways
M1,2,3&4 (633 km)
• Rivers • Towns • Main Cities
Highways
National Highway Authority
Lahore – Multan (330 Km) Est. Cost
US$ 1,57.48 Million
Multan – Sukkur (375 Km) Est. Cost US$ 257.88 Million
Sukkur – Hyderabad (345 Km) Est. Cost
US$ 2,37.25 Million
To Karachi Karachi
TO PESHAWAR TO QUETTA
IRA
N
ORMARA PASNI GAWADAR
GABD
LIARI
AWARAN
TURBAT
MAND
BUZI PASS AGHOR MALAN
JIWANI
Bela
AFGHANISTAN
Uthal SUNSTAR
M- 8
GAWADER LINKAGES
Kararo
Wad
Khuzdar
Ratodero
Khori
Wangu
Q.S.K
SK 70 km
85 km
50 km
55 km
35 km 50 km
40 km 56 km
20 km
45 km
Pleri
HOSHAB
N-10: MCHP
Completed Sections of M-8
ROUTE LENGTH A. Gawader to Hoshab (M-8) = 233 Km (Progress 68%) Hoshab to Sorab (N-85) = 454 Km (Progress 22%) Sorab to Khuzdar (N-25) = 94 Km (Completed) Khuzdar to Ratodero = 243 Km (99 km completed, 144 km in progress 73%) B. Makran Costal Highway (N-10) = 650 Km (Completed and operational)
94 km
15
KARACHI
Uthal
Bela
Khuzdar Ratodero Sukkur
Sibbi
Dalbandin Nok Kundi
Taftan
Lakpass Sariab Chowk
QUETTA
Chaman Q. Saifullah
Loralai Kuchlak
D.G.Khan
D.I.Khan
Awaran
Turbat
GWADAR
IRAN
AFGHANISTAN NWFP
PUNJAB
SINDH
Jiwani
Hub
Ormara
Pasni
Wad
Sorab
Kalat
Gabd
Dhan asar
Zhob Mughalkot
Dera Allah Yar
Basima
Nag
Panjgur
Hoshab M-7
Kakkar
-Balance works + Chaman Bypass -USAID Funding US$90 Million - To be completed by Nov 2015
136
80
72
18
KALAT-QUETTA-CHAMAN (N-25)
PAKISTAN STANCE
Sukkur-Hyderabad Section (345 Km, $237 Million) of proposed Karachi-Lahore Motorway in the list of CAREC Priority Investment Projects
Governments of Pakistan and Afghanistan have agreed to develop Peshawar-Kabul Motorway (265 Km). Technical & Financial assistance is required for the development of this vital socio-economic route which is part of CAREC Transport Corridors 5 & 6.