GOLDFINCH ENGINEERING -...
Transcript of GOLDFINCH ENGINEERING -...
COMPANY PROFILE
GOLDFINCH ENGINEERING
SYSTEMSTM
PRIVATE LIMITED.
(Formerly Waste Encare (India) Pvt. Ltd.)
An ISO 9001:2008 certified Company, BS OHSAS 18001: 2007 for Laboratory,
Approved as Standard Laboratory from (MoEF) QCI – NABET Accredited EIA Consultant Organization
Plot No. A – 288, Road No. 16 Z, Thane Industrial Area,
MIDC (Wagle Estate), Thane (W) - 400 604. MAHARASHTRA, INDIA.
Tel.: 91-22-2580 1529/1521/1546/1555
E-mail: [email protected]; [email protected];
Website: www.goldfinchengg.com
INDEX
Sr. No.
Description Page No.
1 QUALITY POLICY 1 - 2
2 INTRODUCTION 3 – 9
3 LIST OF DIRECTORS AT GOLDFINCH 10
4 ACHIEVEMENTS / ACCREDITATIONS CERTIFICATES
11
5 CLIENT LIST 12 – 24
6 SOME OF OUR PRESTIGIOUS PROJECTS 25 – 33
Quality Policy
We, at Goldfinch, will provide products and services in environmental
engineering and management that meet or exceed the customer expectations.
Satisfaction of identified customer requirements shall be achieved through our
total commitment to continual improvement in everything we do, effective use
of quality management system, review, realignment & up-gradation of
resources, training of employees and offering better & different technologies. It
will be confirmed that the Quality Policy is understood by all employees through
effective communication.
Our Vision
Goldfinch considers that fighting pollution is not merely a commercial venture;
in fact it serves to fulfill a social obligation. Goldfinch has spread far and wide
to include big corporate names into its Clients list. Well defined working
philosophy, is the backbone of Goldfinch’s growth.
4.0 ACHIEVEMENTS / ACCREDITATIONS
ISO 9001:2008 Certified Organization.
OHSAS 18001: 2007 Certified Organization for Laboratory.
Approved as Standard Laboratory from (MoEF)
QCI - NABET Accreditation as EIA Consultant Organization
4
Contact Details
Company Details & Organization of Company
a) Name : Goldfinch Engineering Systems Private Limited. (Formerly Waste Encare (India) Pvt. Ltd) b) Address : Plot No. A – 288, Road No. 16 Z,
Thane Industrial Area, MIDC, (Wagle Estate), Thane (W) - 400 604. ,
Maharashta, India. c) Telephone : 91- 022 - 2580 1529 / 46 / 21/ 55 d) Fax : 91- 022 - 2583 1533
Email : [email protected], [email protected] Visit us on : www.goldfinchengg.com
e) Constitution of
Company : Private Limited
f) Year of Establishment : October 1983
5
1. INTRODUCTION
World's advance into 21st century is marked, inevitably, by technical progress and industrial
growth, at a rapid rate. Also inevitable are various "side effects" of this rapid industrial growth,
the most significant of these being environmental pollution. The alarming rate of increase in
pollution would pose a threat to healthy living and is viewed as a gigantic problem painting
with certainly a foggy picture of the future unless measures to control it are taken immediately.
Goldfinch has been providing solutions for Environmental Problems since 1983; and
Goldfinch considers that fighting pollution is not merely a commercial venture; in fact it serves
to fulfill a social obligation. Goldfinch is a well-knit family of highly qualified personnel working
under its wings, which have spread far and wide to include big corporate names into its
Clients list. Well defined working philosophy, is the backbone of Goldfinch's growth.
2.1 Working Philosophy.
Services
Identification of industrial pollution problems & environmental concerns and
providing precise solutions, forms the core of our activities.
Quality
Results oriented services to the best satisfaction of the customer.
Integrity
Nothing can be as valuable as Customer Relationship. Towards this end we strive
our best by performance that far exceeds mere promises.
Self-Reliance
Over the years, the firm has achieved self-reliance in all the aspects of
management skills, technical competence, application of sophisticated tolls in
project execution and report presentation, etc.
6
2.2 History
• Goldfinch was started as a partnership company by the name of M/s Perfect Labs in
1983. The company was chiefly promoted by Mr. Anand Apte who is a qualified
Chemical Engineer from Laxminarayan Institute of Technology (LIT – Batch 1974).
The company was converted to M/s Perfect Labs Pvt. Ltd. in 1988. The company latter
grew steadily in resources, Services, Volumes & Revenues. The name of Perfect Labs
Pvt. Ltd. was changed to M/s Waste Encare India Pvt. Ltd.(WEIPL) in year 1998 with
Mr. Anand Apte as its Managing Director. The company changed it’s name to
Goldfinch Engineering Systems Private Limited in the year 2012.
Goldfinch’s professional, ethical, technical & flexible approach to troubleshooting &
service providing helped it to win over clients from all sectors of industry.
Goldfinch has spread its wings & network to incorporate a variety of services like
Turnkey Projects, Detail Engineering & Project Management Services, Operation &
Maintenance of ETP's & STP's, Environmental studies & preparation of EIA, carrying
capacity reports etc. & Environmental Analysis. Goldfinch has developed a full- fledged
MoEF approved laboratory for its Analysis & Research & Development Activities.
Goldfinch since inception has given priority to quality & customer service and is a
noted service provider in the field of Environmental Engineering. Goldfinch's list of
clients given on the website is only a glimpse of the Company's achievements.
Goldfinch has grown into a truly professional company which is spearheaded by
technocrats like Mr. Anand Apte.
Currently Goldfinch is catering all industrial sectors like Pharma & API’s,
Agrochemical, FMCG’s, Foods, Textiles, Speciality Chemicals & Organics,
Construction, Engineering etc.
7
2.3 Capabilities and services provided by Goldfinch include;
1) Environmental Management
Pollution Monitoring/ Waste Inventory
Waste Minimization and Treatment
Environmental Impact Assessment and Environmental Clearance
Treatability Studies and Project Feasibility Reports
Environmental Statement
Disaster Management
Health Impacts
Monitoring and Compliance Guidance
Operation and Control of Treatment Plants
Training of personnel for Waste Treatment Plant Operation
Detailed Engineering
Project Management and Turnkey Execution
Traffic Management
Green Belt / Afforestation
Hazardous, Solid , Biomedical & E- Waste Management
Storm Water Management
2) Environmental Analysis and Compliance Monitoring Services
Water and Wastewater Analysis
Air Pollution Surveys
Noise Level Monitoring
Workroom Environment Monitoring
8
3) Operation of Water, Wastewater and Sewage Treatment Plants on a
contract basis by providing
Technical Support
Manpower
Consumables
Meeting Compliance to Norms
4) Project Management
For your engineering project Goldfinch can offer
Basic and Detailed Engineering
Project Management and Monitoring Service
Turnkey Execution Solution
(Engineering, Procurement, Construction and Commissioning)
2.4 Infrastructure
Over the years Goldfinch has acquired an operational infrastructure which provides a
strong base to the services provided. Outline of the infrastructure which is specifically
developed to meet services oriented work is given below.
2.4.1 Technical Expertise
Human resources are obviously at the heart of any successful organization. Our
dedicated personnel consist of highly qualified, result-oriented, experienced people.
Goldfinch employs about 70 technical people apart from the administration, accounts
and other support staff.
9
2.4.2 Office
Goldfinch has a comfortable, centrally located 15000 square feet office in Thane. The
office is equipped with all modern amenities and gadgets to complete any design,
drafting, publishing work in-house. In addition the state-of-art communication system
facilitates immediate contact, interactions and data communication either from field to
office or with any client around the globe.
2.4.3 Laboratory
Our well-equipped State of Art laboratory is capable of conducting all major analytical
tests on air, water or solid samples. This laboratory also consists of bench scale
equipment to carry out treatability studies like physical separations, biological oxidation
(aerobic and anaerobic), chlorination, filtration etc. to evaluate the design parameters.
Laboratory also possesses small pilot plants which can be transported to field to
corroborate the suitability of selected treatment scheme and design parameters before
executing the full scale plant.
13
2.4.4 Manufacturing Facility
Our state of art manufacturing facility is well equipped to manufacture a range of units
required for pollution control e.g. Pressure Vessels, Settling tanks, Heat Exchangers,
piping and electricals etc.
2.4.5 Reference Library
Our reference library consists of reference books, journals, papers, articles, publishers,
reports and other such comprehensive study material. Excellent references for
environmental, chemical, civil, mechanical, electrical engineering as well as on legal,
management, communication and computers are available here.
14
3.0 LIST OF DIRECTORS AT GOLDFINCH
Sr. No.
Name Qualification Designation Work Experience
1. Mr. Anand Apte
B. Tech. (Chem. Engg.)
Managing Director
37 years experience in all kinds of environmental monitoring/projects and industrial safety.
2. Mr. Santosh V. Bhide
L.E.E (Power) Director– Projects
28 years experience in air & water pollution monitoring, detailed engineering & Project management.
3. Mrs. Shubhangi A. Apte
B Sc. (Stat.) Director – Finance 25 years in administration and accounting.
4. Mrs. Pradnya S. Bhide
B.Sc. (Microbiology)
Director -Analytical Laboratory
20 years in Wastewater, soil, Air emissions monitoring & analysis
5. Mr. Harshad A. Apte
B.E.(Electrical) Director-
Manufacturing & Supply Chain
5 years in in planning, design, fabrication and quality manufacturing of ETP related equipments.
6. Mr. Shardul A. Apte
B.E.(Chem. Engg.)
Director - Operations
10 Years Experience in all kinds of environmental projects, designs and industrial safety.
15
5. CLIENT LIST Representative Project Details for design, engineering, procurement, supply,
erection, installation, construction, start-up and commissioning of ETP, STP, CETP,
ZLD EXECUTIONS
Sr. No.
Client Name & Location Type Scope of Work Year Plant
Capacity (m
3/ day)
Value of
Project (Rs.
Lacs)
Value of Project
Including Civil (Rs.
Lacs)
1. Indofil Industries Ltd., Dahej
Agro Chemical Upgradation of ETP
2010 400 90.0 150.0
2. PI industries- Jambusor Pesticides Greenfield ETP Project
2010 600 252.0 450.0
3. Astec Lifesciences, Mahad
Agro Chemical Multiple Effect Evaporator
2012 40 112.0 130.0
4. Indofil Industries Ltd., Thane
Agro Chemical Upgradation of ETP
2013 200 52.0 90.0
5. Indofil Industries Ltd., Dahej
Agro Chemical Zero Liquid Discharge
2015 500 1220.0 1220.0
6. Nicholas Piramal Ltd. Thane
Bulk Drug ETP Upgradation 2005 500 50.00 50.0
7. Sekhsaria Chemicals Ltd., Dombivli
Bulk Drug ETP Upgradation 2007 100 95.0 95.0
8. Lupin Research park Pune
R & D Centre and Pilot Plants
ETP Up-gradation 2008 250 125.0 125.0
9. Lupin Tarapur Bulk Drug ETP Up-gradation 2009 1100 65.0 150.0
10. Harman finochem – Aurangabad
Bulk Drug Multiple Effect Evaporator
2010 30 67.0 80.0
11. Arch Pharma, Taloja Pharmaceutical Intermediates
ETP Upgradation 2011 8 37.0 40.0
12. Dr. Acharya Laboratories API Greenfield ETP 2011 100 125.0 125.0
13. BEC Chemicals Pvt. Ltd. Bulk Drug ETP Upgradation 2013 100 65.0 110.0
14. Anthem Biosciences, Bangalore
API Greenfield ETP 2014 150 310.0 500.0
15. Harman finochem – Aurangabad
Bulk Drug ETP Upgradation 2010 200 12.0 100.0
16. Aurolabs Pvt. Ltd. Bulk Drug Zero Liquid Discharge
2015 50 300.0 300.0
16
Sr. No.
Client Name & Location Type Scope of Work Year Plant
Capacity (m
3/ day)
Value of
Project (Rs.
Lacs)
Value of Project
Including Civil (Rs.
Lacs)
17. Dombivli CETP – Phase II, Dombivli
Chemical CETP Greenfield Project including DPR and Approvals
1998 1500 275.0 275.0
18.
Dombivli Better Environment System Association – Phase I, Dombivli
Textile CETP Greenfield Project including DPR and Approvals
1999 14000 600.0 600.0
19. Dombivli Better Environment System Association, Dombivli
Textile CETP CETP Upgradation including DPR and Approvals
2005 14000 600.0 600.0
20. Lote – CETP Chemical CETP DPR, Approvals, Design & Detailed Engineering
2009 10000 64.0 2000.0
21. Kores India Ltd. Roha Speciality Chemicals
ETP Upgradation 2003 115 35.00 35.0
22. Heavy Water Board, Talcher – Orissa
Solvents Multiple Effect Evarporator & Scrubber
2007 8 199.80 250.0
23. Heavy Water Board, Manuguru – Andhra Pradesh
Atomic Plant Greenfield ETP 2007 7 224.0 275.0
24. Innovassynth, Khopoli Chemical ETP Upgradation 2011 600 122.0 122.0
25. Innovasynth Technologies Ltd., Khopoli
Chemical Multiple Effect Evaporator
2012 10 88.0 88.0
26. Reliance Chemical Products Ltd., Nigeria
Chemical Multiple Effect Evaporator
2015 10 24.0 40.0
27. Fine Organics Industries Pvt Ltd., Ambernath
Food Additives and fatty acids
ETP upgradation 2015 85 72.5 115.0
28. Lona Industries Ltd., Rasayani
CPC Blue ETP Upgradation 1998 1200 80.00 80.0
29. DCW Ltd., Sahupuram, Tamilnadu
Ore Enriching ETP Upgradation 1999 6000 50.00 50.0
30. Reckit Benckiser, Uttarakhand
Disinfectants ETP Upgradation 2011 100 150.0 150.0
31. P Z Cussons, Ikorodu, Nigeria
Greenfield ETP 2014 400 80.0 150.0
32. Lever Gist Brocades Pvt. Ltd., Lote, Chiplun
Yeast Turnkey 1998 200 98.00 98.0
33. Parle Biscuits Pvt. Ltd., Nashik
Chips ETP Turnkey excluding Civil
2007 - 70.0 100.0
34. Parle Candy, Nirmrana, Rajasthan
Confectioneries ETP Up-radation 2011 80 90 125.0
17
Sr. No.
Client Name & Location Type Scope of Work Year Plant
Capacity (m
3/ day)
Value of
Project (Rs.
Lacs)
Value of Project
Including Civil (Rs.
Lacs)
35. Parle Biscuits Pvt. Ltd., Khopoli
Biscuits Upgradation of ETP
2014 36.35 157.10 157.1
36. Parle Biscuits Pvt. Ltd., Neemrana
Confectionaries Upgradation of ETP
2014 160 137.80 137.8
37. Liberty Oil Mills Ltd. Oil Industry Design & Detailed Engineering
1999 350 55.00 55.0
38. Frito Lay India, Ranjangaon
Chips Design & Detailed Engineering
2000 500 185.00 185.0
39. State Bank of India, Nerul Housing Solar Water Heating System & STP
2007 - 150.0 150.0
40. Kansai Nerolac Paints Ltd., Jainpur
Paints ETP Up-gradation 2008 160 30.0 40.0
41. Kansai Nerolac Paints Ltd., Lote
Paints ETP 2013 20 117.32 117.32
42. Pawan Hans Helicopters Ltd. Santacruz
Helicopter Company
Greenfield STP 2002 180 32.0 32.0
43. B.G. Shirke Construction Technology Ltd. Mumbai
Construction Co Greenfield STP 2006 2000 100.0 100.0
44. State Bank of India, Nerul Housing Greenfield STP 2007 140 45.0 45.0
TOTAL NO. OF PROJECTS FOR ALL CATAGORIES: Over 400
18
Partial Reference List for Treatment Plant Operation & Maintenance Services.
Sr. No.
Client Type of Industry Plant Type Period Capacity (m3/day)
Outside Maharashtra Region
1 Hyderabad Urban Development Authority
Urban Area STP 2005 - 07 2500
Mumbai Region
2 Pawan Hans Helicopters Ltd., Juhu Helicopter Services
STP 2002 – 2012
180
Taloja Region
3 Resins & Plastics Ltd., Taloja Resins ETP 1986 -10 60
4 Arch Pharma, Taloja Pharmaceuticals ETP 2012 8
Shahapur Region
5 Liberty Oil Mills, Shahapur Edible Oil ETP 1984 ….. 250
Khopoli Region
6 Innovasynth Technologies Ltd., Khopoli Multi Organics ETP 1984 … 1000
7 Musco Ltd., Khopoli Steel STP 1983 –
2005 3000
8 Alkyl Amines Chemicals Ltd., Patalganga
Organic Chemicals ETP 1995 ….. 200
Roha Region
9 BEC Chemicals Pvt. Ltd., Roha Bulk Drug ETP 2015 …. 200
10 Kores (I) Ltd., Roha Bulk Drug ETP 1995 –
2005 110
Pune Region
11 Alkyl Amines Chemicals Ltd., Kurkumbh
Organic Chemicals ETP 1996 …. 100
Nashik Region
12 Parle Biscuits., Nashik Foods ETP 2007 –
2012 200
Dombivli Region
13 Dombivli CETP – Dombivli – Phase II -- CETP 1998 …. 1500
14 DBESA – Dombivli – Phase I -- CETP 1999 ….. 14000
19
Sr. No.
Client Type of Industry Plant Type Period Capacity (m3/day)
15 Arch Pharma, Dombivli Pharmaceutical ETP 2008 –
2012 150
Ambernath Region
16 Watson Pharma Pharmaceutical ETP 2012…… 150
17 Dr. Acharya Lab Pharmaceutical ETP 2014….. 60
Tarapur Region
18 Lupin Ltd., Tarapur Bulk Drug ETP 1998 …. 300
Chiplun / Ratnagiri Region
19 A.B. Mauri Yeast ETP 1998 –
2014 500
20 JK Files & Tools, Chiplun Engineering ETP & STP 1996 - 98 100
21 Lote CETP (Lote) -- CETP 2006…. 4500
22 Nicholas Piramal (Mahad) Bulk Drug ETP 2007-09 75
23 Privi Organics Organic Chemical ETP 2008….. 300
24 Rallis (India) Ltd. Chemical ETP 2009…. 75
Uran Region
25 Skol Brewerries Ltd., Uran Bear ETP 2001- 05 400
Navi Mumbai Region
26 Sandoz Private Ltd., Turbhe Bulk Drug ETP 2000 - 07 220
27 Hindustan Lever Ltd. TTC Fast Food Ingredients
ETP 2000-11 75
28 Sandoz Private Ltd., Kalwa Pharmaceutical
Formulation ETP 2003 - 08 180
Thane Region
29 Nicholas Piramal India Limited, Thane Bulk Drug ETP 2002 - 08 350
30 Indofil Chemicals Co. Fungicide Mfg. ETP 2004 …. 125
20
ASSIGNMENENTS COMPLETED DURING LAST TWENTY YEARS
Environmental Impact Assessment / Environmental Clearance
S. No. Name of Project Type of project Date of
Commencement Date of
Completion
1. Alkyl Amines Chemicals Pvt.Ltd. Kurkumbh
Chemicals & Speciality
Intermediates Feb. 2013 In Progress
2. Srikrishna Pharmaceuticals, Solapur (B-14 Expansion)
Bulk Drug Feb.2013 In Progress
3. Srikrishna Pharmaceuticals, Solapur (F-1 Green Field)
Bulk Drug May 2012 In Progress
4. Harman Finochem, Shendra, Aurangabad
Bulk Drug May 2012 In Progress
5. Lupin Research Park, Pune R & D Building Construction
Dec. 2010 15th Nov. 2012
6. Dr. Acharya Laboratories Pvt. Ltd., Dombivli
Bulk Drugs Intermediates &
Specialty Chemicals
May 2010 January 2013
7. Alkyl Amines Chemicals Ltd Kurkumbh
Chemicals Feb 2010 24,Feb 2011
8. Polypeptides Laboratories, Ambernath
API Sept 09 Sept. 2011
9. Galaxy Surfactants Ltd Navi Mumbai Surfactants/
Specialty Chemicals
Nov 09 3, Dec.2010
10. B.G. Shirke Construction Tech. Pvt. Ltd (Mhada Malavani)
Building Construction
Oct 09 25, April 2011
11. Lupin Ltd, Tarapur. Bulk Drugs April 09 29,Nov2010
12. Specialty Molecule Ltd, Ambernath Industrial
Chemicals Feb 09 25, May 2010
13. Indofil Chemicals Company
Dahej, Gujarat
Pesticide
Industry Jan 08 July 08
14. United Spirits Ltd, Nasik Malt Spirit
Distillery May 08 June 09
15. United Spirits Ltd.
Aurangabad
Extra Neutral Alcohol from
Molasses Nov 07 July 08
16. Brihan Mumbai Mahanagarpalika (Mcgm)
Beautification project for Haji Ali
promonade Sep 07 April 08
21
S. No. Name of Project Type of project Date of
Commencement Date of
Completion
17. B. G. Shirke
(Mhada Dahisar)
New Construction
project June 07 May 08
18. Kansai Nerolac Paints Ltd,
Lote Parashuram Paint Industry March 2007 Oct.2007
19. M/S. Shriram Mills Ltd., Mumbai New Construction
project 2005 Aug. 06
20. Mhada For Dharavi Site New Construction
project 2005 2006
21. Mhada For Malwani Site New Construction
project 2005 Oct.2006
22. M/S. Albright & Wilson Ltd., Roha Surfactants 2006 April 2008
23. Lupin Ltd., Tarapur Bulk Drugs 2004 Sept. 2005
24. Environmental Monitoring Of mass Rapid Transit Systems(Mrts) For Thane City
Infrastructure May, 2000 Sept, 2000
25. Bhart Petroleum Corporation Ltd., Mumbai
Petroleum Feb, 1998 Feb, 1999
26. Sudharshan Chemicals Ltd., Mahad Pigment Chemical
Jan, 1998 Dec, 1998
27. JK Files & Tools, Ratnagiri Engineering Dec,1997 June, 1998
28. Japan Port Consultants- Jica Infrastructure Oct, 1997 Nov, 1997
29. Rashtriya Chemicals & Fertilizers, Alibaug
Chemicals & Fertilizer
Aug, 1997 Sept, 1997
30. Lupin Chemicals Ltd., Tarapur Bulk drug Mar, 1994 Dec, 1994
31.
Integrated Urban Environmental Management (State Of Maharashtra For Thane Belapur Road, And Chembur Area World Bank Funded)
MEIP Project
International collaboration
Jan, 1993 Dec, 1994
32. The Dharmasi Morarji Chemicals Co. Ltd., Roha
Heavy Chemical Sept, 1992 July, 1993
33. Amar Dye Chem. Ltd., Kalyan Dyes &
Chemicals Sept, 1991 July, 1992
22
S. No. Name of Project Type of project Date of
Commencement Date of
Completion
34. Rama Krishi Rasayan Ltd. Pune Sulfuric Acid and
Fertilizer Mar, 1992 Jan, 1993
35. Hikal Chemical Ind. Ltd.
Mahad Chemicals Feb, 1992 April, 1993
36. Borax Morarji Ltd Ambernath Inorganic Chemicals
Sept, 1991 April,1992
37. Unichem Lab Ltd., Roha Bulk drugs Jan, 1991 Nov, 1991
38. German Remedies Ltd.,
Patalganga, Raigad Bulk drugs Oct, 1991 Aug,1992
Note : Total Environmental Clearances obtained from 1990 to date- Over 50 nos.
23
CARRYING CAPACITY REPORT
S. No. Name of Project Type of project Date of
Commencement Date of
Completion
1. Infrastructure Logistics Iron ore Mining at Reddi -- March 09
2. Infrastructure Logistics Iron ore Mining at Tiroda -- April 09
3. New India Mining Corporation Pvt Ltd.
Iron ore Mining at Sindhudurg
-- April 09
4. New India Mining Corporation Pvt Ltd.
Iron ore Mining at Sindhudurg
-- April 12
TREATABILITY STUDIES
Sr. No.
Name of Project Type of project Date of
Commencement Date of
Completion
Indofil Chemicals Company
MEE August 2005 September 2005
Dombivli CETP, Phase I Biodegradability studies
& ETP scheme September 2005 October 2005
Sekhsaria Chemicals Ltd, Dombivli
Biodegradability studies & ETP scheme
May 2006 June 2006
Heavy Water Board, Talcher
Scrubber, MEE & ETP scheme
August 2007 December 2007
Mahad CETP Biodegradability studies September 2007 September 2007
Lote CETP Biodegradability studies September 2009 September 2009
Alkyl Amines, Kurkumbh Biodegradability studies July 2010 July 2010
BEC Chemicals Pvt. Ltd., Roha
Biodegradability studies & ETP scheme
November 2010 January 2011
Dr. Acharya Laboratories, Ambernath
Biodegradability studies January 2013 January 2013
Dombivli CETP, Phase II Biodegradability studies
& ETP scheme January 2013 February 2013
Astec Lifescience Ltd., Mahad
MEE & ETP Biodegradability studies
April 2013 May 2013
Amoli Organics Pvt. Ltd., Vapi
MEE & ETP Biodegradability studies
June 2013 July 2013
Metropolitan Eximchem, Dombivali
Zero liquid discharge July-2014 Continued
Fine Organics, Ambernath
Primary, Secondary and Tertiary Treatment
July-2014 October-2014
24
6. SOME OF OUR PRESTIGIOUS PROJECTS
1. ETP for Lupin, Tarapur, Maharashtra – 1000 m3 / day
The ETP was designed with two stage aerobic system using state of art aeration
technology. The outlet water of the ETP is fed to the R.O and then the R.O reject is
evaporated to the achieve Zero Discharge. The permeate of R.O is recycled for process.
26
2. ETP for Parle, Bahadurgarh, Haryana – 200 m3 / day
This ETP is designed to treat 200 m3 / day of wastewater. It has anaerobic followed
by aerobic technology. The gas generated from the anaerobic digestor is used as
fuel. The treated water from aerobic system is used for gardening.
27
3. Common Effluent Treatment Plant for M/s. Dombivli Better Environmental
Systems Association.
M/s. Dombivli Better Environmental Systems Association (DBESA) is working for the group
of Textile processing industries in the Dombivli MIDC area. DBESA has installed a full-
fledged Common Effluent Treatment Plant (ETP) to cater the needs of effluent generated
from the Textile processing. The CETP is treating 16000 m3 / day of wastewater to the
MPCB standards.
28
4. Zero Discharge Project for Heavy Water Board, Talcher
The Zero Discharge project was designed to treat the wastewater from manufacturing
facility. The project included the design & installation of scrubber system, followed by
Rotary Vaccum Dryer and followed by evaporator plant. The project was executed on
Turnkey basis.
29
5. ETP for Indofil, Dahej, Gujarat – 500 m3 / day
This ETP was designed for treating agrochemical waste. The total wastewater was 500 m3 /
day. The bioreactor is operating and working successfully at a TDS of around 70000 ppm.
30
6. INTEGRATED URBAN ENVIRONMENTAL MANAGEMENT (IUEM)
Thane-Belapur Industrial Area (TBIA) and Chembur, Maharashtra, India Goldfinch carried out the IUEM project as Indian counterpart of Ecology & Environment, Inc.,
USA. This study project is a part of The World Bank's Metropolitan Environmental Improvement
Program (MEIP), executed by The Environmental Department, Government of Maharashtra.
This study was carried out for two hot spot areas; TBIA, and Chembur, known to have
environmental problems. TBIA is the largest industrial belt in Asia, housing more than 1200
small, medium, large scale; diverse type of industries. Chembur, which is part of Greater
Bombay, houses 8 very large industries and other urban industries and other urban
development. Both these areas have become mixed use are as over the years & hence an
integrated approach program was desired. The work carried out by Goldfinch encompasses an
Environmental Assessment, Feasibility Studies, and an Integrated Plan of Action. The
environmental assessment included collection of data, preparation of computerized databases,
data assessment, identification of data gaps and determining the environmental status of the
study areas. Various databases for water contamination, air pollution, soil contamination, micro-
meteorological parameters etc. were prepared. Also an overview of current waste treatment and
disposal practices was done and pollution loads in air, water and land were estimated. Goldfinch
carried out feasibility studies on industrial waste abatement, disaster management, traffic
management, strengthening of public services and health impacts. In industrial waste
abatement, Goldfinch performed an engineering analysis of the existing pollution abatement
practices in order to develop new strategies for a more cost-effective, long-term pollution
abatement program in the study areas. Methodologies used were; industrial waste classification
/ inventory, identification of treatment methods, review of emissions and standards and
development of methods of compliance, evaluation of pollution control alternatives with an
emphasis on waste minimization, pollution load estimation, and design of pollution abatement
program. In disaster management; hazards from industrial, transportation and non-
transportation sources were considered. Methodology used included identification of disaster
scenarios using computer modeling, review of existing risk assessments and mitigation
measures and recommendations for improvement. A traffic management plan and a road
network improvement plan for Chembur was developed with an intent to reduce vehicular traffic
congestion and air pollution. Emergency escape route for use in disaster was also identified. A
review of the existing public service infrastructure was done and improvements were
recommended in the areas of solid waste management, storm water drains, green belt/
31
afforestation, sewage system, legislation and zoning policy. For evaluating the health impacts of
pollution the existing data on epidemiological studies of disease rates in the communities
surrounding study areas was sought to identity exposed and unexposed areas. A guideline for
monitoring health impacts was developed. For improving environmental conditions, an
integrated plan of action was developed, which consisted of the results of the environmental
assessment and feasibility studies and is supplemented by recommendations for policy
changes, priorities for action, potential financial sources, and institutional and manpower
requirements.
7. WASTE ANALYSIS AND DESIGN OF A WASTE TREATMENT FACILITY Chiplun, Maharashtra, India For an industry that manufactures engineers’ steel files and twist drills, Goldfinch conducted
feasibility studies and designed a waste treatment facility. The industries’ process encompasses
cropping to packing including hardening, pickling, and electro-polishing. Cyanide waste was
generated from hardening and chromium waste was generated from electro-polishing and
pickling. The industry was not allowed to discharge trade effluent in sewer and it was to be
reused/ recycled after treatment. Goldfinch completed feasibility studies to determine a suitable
cost-effective treatment scheme. Analysis of effluent samples for various parameters and pilot
plant studies were carried out for this. The scheme consisted of isolating cyanide and chromium
bearing waste and treating them separately. After chemical reaction, solids were allowed to
settle in clarifier. Clarified water, mixed with domestic effluent was oxidized by biological
oxidation on the principle of extended aeration. Goldfinch designed, fabricated, erected, and
commissioned the entire treatment facility, prepared the operating manual and trained industry
staff to operate this facility. The parameters of the treated water were within the consented
limits. For reuse/ recycle of the treated water, various alternatives were considered. Goldfinch
suggested reusing the water for gardening. Treated water was tried on different saplings for
about two months and found to have no adverse effects. An irrigation system for the entire plot
was designed. The solid waste generated was mainly iron dust produced during wet grinding.
Studies for reuse/ conversion of this waste to any other form were performed. After elaborate
studies, a process was evolved to make ferrous sulphate using this waste. For making internal
roads in the factory, this dust was used in the tar.
32
8. WASTE-WATER MANAGEMENT - Khopoli, Raigad
Client proposed to manufacture Phenyl Glycine at their plant at Khopoli. Goldfinch performed
waste-water management. The waste-water emanating from the process included various types
of streams including cyanide bearing, free chlorine bearing, high dissolved solids bearing
containing mainly inorganic solids (HDS), and low dissolved solids bearing containing high
organic load (LDS). Goldfinch developed a treatment process based upon the samples available
from the pilot plant and from the theoretical estimations. Further, Goldfinch engineered the
entire project up to the commissioning stages including the design of equipment, piping,
electrical and instrumentation. Goldfinch evaluated various options for treatment including
stripping, chlorination, evaporation, incineration, and biological oxidation; and estimated the
capital and running costs. The treatment scheme selected consisted of segregation of streams
in three main categories: cyanide, LDS, and HDS. Cyanide was destructed by chlorination using
sodium hypochlorite or free chlorine bearing stream from process when available. The free
chlorine then was removed and this stream further joined the LDS stream. LDS stream was
given primary treatment of neutralization, alum coagulation and settling followed by two stage
biological oxidation (extended aeration process), and secondary settling. The sludge generated
was dried and used as landfill or manure. The HDS stream was equalized and pumped
continuously to a multiple effect evaporation system. Here waste was concentrated to a flowable
extent and the concentrate disposed in the saline zone at a selected location. The evaporator
condensate joined the LDS stream. Various legal/ statutory requirements were fulfilled and the
necessary consents/ no objection certificates (NOCs) obtained on behalf of the industry from the
state pollution board by Goldfinch.
9. JAPAN INTERNATIONAL COOPERATION AGENCIES (JICA)
JICA has undertaken the study on the Development of Port of Mumbai in India pursuant to an
agreement between the Government of India and Japan. JICA study team has engaged M/s.
Goldfinch Engineering Systems Private Limited (Goldfinch) Formerly WEIPL to carryout the
environmental survey for the proposed development of the Port of Mumbai.
33
The scope of work consists of : 1. Survey and analysis of Air Quality
2. Survey and analysis of Water Quality
3. Sampling and analysis of Sea Bottom Materials (Sediment)
4. Survey and analysis of Noise level and Vibration.
5. Traffic volume survey and forecasting of increased air quality loads. M/s. Goldfinch Engineering Systems Private Limited (Goldfinch) Formerly WEIPL completed the
fieldwork and analytical work for the above survey and submitted final report in September 97.
10. ENVIRONMENTAL MONITORING FOR MASS RAPID TRANSIT SYSTEM
(MRTS) FOR THANE CITY
Goldfinch has worked with Consulting Engineering services, Mumbai for Environmental
Monitoring Survey in Thane City. Job includes - Air, Noise, Water & Soil sampling & analysis in
May 2000.