GO Uptown Gateway to Oakland Uptown GETTING THERE: PLAN … GO Uptown_FINAL.pdf · 2017/3/7  ·...

2
Walk 60% Bicycle 14% Bus, train, or other transit 9% Drive alone / carpool 1% Drop off / taxi / other 16% Lead Applicant Supporting Applicant GO Uptown Gateway to Oakland Uptown 2016 TIGER Grant Project Summary BROADWAY 19TH ST 17TH ST Alt. 2 Infill Alt. 1 Infill Anticipated Buildings Existing Buildings Green Space Project Description GO Uptown is a unique and transformative set of improvements to 19th St. / Oakland BART Station and the surrounding public realm that will improve access to the station, expand station capacity, and replace aging infrastructure while simultaneously reducing energy use, modernizing the appearance of the sta- tion, enhancing safety and promoting local art. The primary project components include: BART Station Modernization Projects New station elevator connecting BART with AC Transit Uptown Transit Center and other Uptown destinations Interior station upgrades including new glass railings, glass fare barriers, and new energy-efficient LED lighting throughout the station. New art features throughout the station, including three permanent illumi- nated public art installations in each of the stairwells Expanded and reconfigured fare gates to reduce crowding and anticipate re- opening of a new station entrance with the former Capwell’s/Sears building Locally Funded $17.8m (Proposition 1B) TIGER Funding $4.8m City of Oakland Public Realm Projects 20th Street BART to Lake Merritt Urban Greenway “complete streets” project New LED street lighting along 20th St. and Webster St. Extension of the City of Oakland’s pedestrian wayfinding program to a 20-block area between the 19th St. BART Station and Lake Merritt Locally Funded $4.6m (Caltrans ATP Grant) TIGER Funding $1.5m Schedule: Construction planned to begin early 2018; completion by 2020 Project Location 19th St. BART Station Profile Anticipated Growth of Surrounding Area Potential new development shown in color (from Feb. 2016 Draft Downtown Oakland Specific Plan) Total Project Funded Local Match $22.3m Total Project TIGER Funding $6.3m Total Project Cost $28.6m 13,260 entries / day (2015); projected 22,134 entries by 2040 2005-2015 growth = 4.3% per year (compared to 3.0% systemwide) Home-based trips mode (35% of all entries) Non-home based trips mode (65% of all entries) In progress Downtown Oakland Specific Plan anticipates significant growth in Lake Merritt Office and Uptown Districts: ~2,500 new residential units ~1,566,000 sq. feet new office Walk 90% Bicycle 5% Bus, train, or other transit 1% Drop off / taxi / other 4%

Transcript of GO Uptown Gateway to Oakland Uptown GETTING THERE: PLAN … GO Uptown_FINAL.pdf · 2017/3/7  ·...

Page 1: GO Uptown Gateway to Oakland Uptown GETTING THERE: PLAN … GO Uptown_FINAL.pdf · 2017/3/7  · • 13,260 entries / day (2015); projected 22,134 entries by 2040 • 2005-2015 growth

Walk60%Bicycle

14%

Bus, train, or other transit

9%

Drive alone / carpool

1% Drop off / taxi / other16%

Lead Applicant Supporting Applicant

GO Uptown Gateway to Oakland Uptown2016 TIGER Grant Project Summary

Alt. 1Infill

Anticipated Buildings

ExistingBuildings

GreenSpace

BROADWAY

19TH

ST

17TH

ST

TOTAL NEW UNITS 1,288 UNITS

TOTAL NEW COMMERCIAL, RETAIL OR SERVICES SPACE 104,512 SQUARE FEET

TOTAL NEW OFFICE SPACE 1,565,600 SQUARE FEET

TOTAL NEW PARKING AREA 188,617 SQUARE FEET

LAKE MERRITT OFFICE DISTRICT: Plan Alternative #2

Alt. 2 Infill

Alt. 1Infill

Anticipated Buildings

ExistingBuildings

GreenSpace

To meet the projected need for residents and businesses in the future, and to allow an opportunity for more affordability, new development is needed Downtown. Maintaining lower-scale development in some neighborhoods Downtown to match the existing character makes sense. However, the Lake Merritt Office District is an opportunity to intensify in an area that is already very tall.

New development should provide a variety of housing types, in-cluding one, two, and three bedroom units. An adjusted zoning ordinance that incentivizes both the inclusion of homes priced below market rate and a variety of unit types, the Lake Merritt District can offer opportunities for much needed housing supply and affordability.

Additionally, policies to incentivize shared office and commercial spaces at the ground floor should be included to implement the vision for this district. In both alternatives evaluated, the overall vision is met; however, the second alternative includes no ad-ditional parking for the added development. A lower parking requirement in this transit-rich neighborhood, gives developers more options to achieve more units with a variety of develop-ment types in the same building footprint.

GETTING THERE: PLAN CONSIDERATIONS

PLAN ALTERNAT IVES REPORT: A V I S ION FOR THE DOWNTOWN NE IGHBORHOODS 5 . 2 1

Project Description

GO Uptown is a unique and transformative set of improvements to 19th St. / Oakland BART Station and the surrounding public realm that will improve access to the station, expand station capacity, and replace aging infrastructure while simultaneously reducing energy use, modernizing the appearance of the sta-tion, enhancing safety and promoting local art. The primary project components include:

BART Station Modernization Projects• New station elevator connecting BART with AC Transit Uptown Transit Center

and other Uptown destinations• Interior station upgrades including new glass railings, glass fare barriers, and

new energy-efficient LED lighting throughout the station.• New art features throughout the station, including three permanent illumi-

nated public art installations in each of the stairwells• Expanded and reconfigured fare gates to reduce crowding and anticipate re-

opening of a new station entrance with the former Capwell’s/Sears building Locally Funded $17.8m (Proposition 1B) TIGER Funding $4.8m

City of Oakland Public Realm Projects• 20th Street BART to Lake Merritt Urban Greenway “complete streets” project• New LED street lighting along 20th St. and Webster St.• Extension of the City of Oakland’s pedestrian wayfinding program to a

20-block area between the 19th St. BART Station and Lake Merritt Locally Funded $4.6m (Caltrans ATP Grant) TIGER Funding $1.5m

Schedule: Construction planned to begin early 2018; completion by 2020

Project Location

19th St. BART Station Profile

Anticipated Growth of Surrounding Area

Potential new development shown in color (from Feb. 2016 Draft Downtown Oakland Specific Plan)

Total Project Funded Local Match $22.3mTotal Project TIGER Funding $6.3mTotal Project Cost $28.6m

• 13,260 entries / day (2015); projected 22,134 entries by 2040• 2005-2015 growth = 4.3% per year (compared to 3.0% systemwide)

Home-based trips mode (35% of all entries)

Non-home based trips mode (65% of all entries)

• In progress Downtown Oakland Specific Plan anticipates significant growth in Lake Merritt Office and Uptown Districts:• ~2,500 new residential units• ~1,566,000 sq. feet new office

Walk90%

Bicycle5%

Bus, train, or other transit

1%

Drop off / taxi / other

4%

Page 2: GO Uptown Gateway to Oakland Uptown GETTING THERE: PLAN … GO Uptown_FINAL.pdf · 2017/3/7  · • 13,260 entries / day (2015); projected 22,134 entries by 2040 • 2005-2015 growth

1

1

2

4

4

5

66

3

20th St.

(abo

ve)

Broadway (above)

19th St.

(abo

ve)

N

22

6777

Expand Station CapacityRelocate station agent booth and add fare gates to reduce crowding at north end of station

Summary of 19th St. / Oakland BART Station Modernization Improvements

Enhance Safety and Security Install new higher glass fare barriers to prevent fare evasion while maintaining sight lines

Expand Bicycle Access Install bicycle channels on 19th St. stairwell andincrease bicycle parking in station

Celebrate Community with Art Three new art pieces by local artists will be installed inthe three platform stairwells

Enhance Lighting Upgrade to energy-efficient LEDs throughout station and provide accent lighting; simultaneously reduce monthly energy use by ~30%

Improve Accessibility Provide new elevator at the north end of the station, and improve access with the AC Transit Uptown TransitCenter

Fix and Modernize Repair tiles and flooring throughout station; reopen restrooms

32

4 6 75

1

Concourse Level Plan

Future BRT Station (above)