GMRR Bridge #114 Tropical Storm Irene Emergency Repairs
Chester, Vermont
ECI Rail Constructors, Inc. September 2011
www.eci-rail.com
![Page 2: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/2.jpg)
Tropical Storm Irene
![Page 3: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/3.jpg)
NWS Bulletin for Irene 5:00 PM on August 28, 2011
• RAINFALL...IRENE IS EXPECTED TO PRODUCE TOTAL RAINFALL ACCUMULATIONS OF 4 TO 6 INCHES...WITH ISOLATED MAXIMUM AMOUNTS OF 8 INCHES... FROM NORTHEASTERN NEW YORK STATE NORTHEASTWARD THROUGH THE NORTHERN PORTION OF NEW ENGLAND. THESE RAINS...COMBINED WITH HEAVY RAINS OVER THE PAST FEW WEEKS...COULD CAUSE WIDESPREAD FLOODING AND LIFE-THREATENING FLASH FLOODS.
![Page 4: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/4.jpg)
Initial ECI Site Visit Tuesday – August 31
![Page 5: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/5.jpg)
Mobilization & Access Construction Wed-Sat: Sept 1 to Sept 3
![Page 6: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/6.jpg)
Mobilize Cranemasters Saturday – September 3
![Page 7: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/7.jpg)
Setup Cranes Saturday – September 3
![Page 8: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/8.jpg)
Bridge Brought to Vertical & Secured Sunday – September 4
![Page 9: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/9.jpg)
Stabilize West Abutment Monday - September 5
![Page 10: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/10.jpg)
Install Pedestal at NW Bearing Tuesday – September 6
![Page 11: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/11.jpg)
Secure Work from Tropical Storm Lee Wednesday – September 7
![Page 12: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/12.jpg)
Test Borings at East Abutment Thursday – September 8
![Page 13: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/13.jpg)
Start Driving Pipe Piles Thursday – September 8
![Page 14: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/14.jpg)
Testing & Driving Pipe Piles Friday – September 9
![Page 15: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/15.jpg)
13.75-in-OD x 0.707-inch wall Pipe Pile Splicing – 2 hrs/joint
![Page 16: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/16.jpg)
Final Driving of Pipe Piles Saturday – September 10
![Page 17: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/17.jpg)
Shotcreting of West Abutment Sunday – September 10
![Page 18: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/18.jpg)
Sheet Pile Wall to Extend Damaged West Abut Sunday - September 10
![Page 19: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/19.jpg)
Temporary Bearing Pedestal Sunday - September 11
![Page 20: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/20.jpg)
Setting Bridge on Temporary Bearing Supports Sunday - September 11
![Page 21: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/21.jpg)
Pouring Concrete Backwall & Abut Extension Monday – September 11
![Page 22: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/22.jpg)
Final Welding & Bracing of Piles & Pedestal Tuesday – September 13
![Page 23: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/23.jpg)
Rebuilding Approach Embankment Tuesday – September 13
![Page 24: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/24.jpg)
West Approach Track Reconstruction Tuesday – September 13
![Page 25: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/25.jpg)
Team Photo Tuesday – September 13
![Page 26: GMRR Bridge #114 Emergency Irene Repair](https://reader033.fdocuments.in/reader033/viewer/2022042701/55a18b251a28abda418b473e/html5/thumbnails/26.jpg)
First Train Wednesday – September 14