Global Aggregation
Mod 34.09 raised by ESB CS at Mods Meeting 24 (29.09.09)
Mods Panel recommended setting up Working Group to explore further
Working Group 1, held on 19th November 2009
SEMO & RA met December 1st to develop options paper
Options impact assessed for Working Group 2, held on 23rd February 2010
3
Global Aggregation
At Working Group 2, MRSO proposed option E
Further assessments completed
Working Group 3 held on 27th April 2010
Decision to consult on Options A+ and E
Consultation Paper issued by SEMO for response by 19th July 2010
4
Global Aggregation
Nine responses received to Consultation
Five responses favour Option E
Three responses favour Option A+
One response recommended either option
5
Global Aggregation
Of Participants who responded -
Two responses favour Option E
Three responses favour Option A+
Remaining three responses supporting Option E from service providers
6
Global Aggregation
Working Group 4 scheduled for August 2010
There is no clear consensus from the consultation responses
SEMO proposes that two T&SC modifications be drafted
One modification for each Option
7
Global Aggregation
SEMO requests approval to seek fuller impact assessments
Noting response from BGE, SEMO recommends Participants also impact
assess system changes for both Options
Working Group 4 can review and discuss both modifications and costs
If no consensus can be reached, both modifications should be submitted to
Modifications Committee in September with full Working Group report for final
decision