Glenn Highway MP 49 Blowhole Realignment - John...
Transcript of Glenn Highway MP 49 Blowhole Realignment - John...
Glenn Highway MP 49 Blowhole Realignment
By: John Fuller
David Darrington Andrew Pavey
CE 425 Highway Design
Spring 2013
Contents Introduction .................................................................................................................................................. 3
Figure 1 - Location Map ........................................................................................................................ 3
Methodology ................................................................................................................................................. 4
Design Controls and Criteria ..................................................................................................................... 4
Consideration of Alternate Routes ........................................................................................................... 5
Horizontal Alignment ................................................................................................................................ 6
Vertical Alignment .................................................................................................................................... 7
Cross Section ............................................................................................................................................. 8
Structural Section ...................................................................................................................................... 9
Earthwork Quantities .............................................................................................................................. 10
Mass Haul Diagram ................................................................................................................................. 10
Intersection Design ................................................................................................................................. 11
Analysis of Results ....................................................................................................................................... 11
Level of Service ....................................................................................................................................... 11
Cost Estimate .......................................................................................................................................... 12
Conclusions & Recommendations .............................................................................................................. 13
Appendixes .................................................................................................................................................. 14
Horizontal Alignment .............................................................................................................................. 14
Vertical Alignment .................................................................................................................................. 15
Superelevation ........................................................................................................................................ 16
Earthwork Quantities .............................................................................................................................. 18
Intersection Design ................................................................................................................................. 19
Introduction
The Glenn Highway MP 49 has a large erosion feature just east of the existing alignment. This erosion feature is threatening the road at two locations. The first location is just north of Farm Loop Road going into the horizontal curve and this erosion feature is within approximately 15 feet of the road, just off the side of the eastern shoulder.
The second erosion feature is just south of Archie Road at the scenic turnout. This erosion feature is undercutting the turnout but is still 100 feet away from the horizontal alignment and does not pose an immediate threat to the Glenn Highway.
This report will discuss Team Awesome's proposed two lane highway realignment to address these erosion problems while adhering to the appropriate design criteria.
Figure 1 - Location Map
Methodology
Design Controls and Criteria
The design controls and criteria for this project come from the Alaska Highway Preconstruction
Manual. Page 1100-14 of the manual contains the design particulars, and the Glenn Highway
MP 49 realignment falls under the rural new construction category.
The sources of the design controls for this project are as follows:
• Highway Capacity Manual 2000 (HCM)
• A Policy on the Geometric Design of Highways and Streets (The Green Book)
• Alaska Preconstruction Manual (PCM)
The specifications used from those sources are as follows:
Design Particular Source Capacity HCM2000 LOS GB Design Vehicle GB Design Speed GB Sight Distance GB Grades GB Alignment GB Roadway Cross Slope PCM Sec 1130 Superelevation Rate GB Ex 3-17, 3-22 Superelevation Transition
GB Ex 3-27,28, Eqn 3-25,26
Foreslopes PCM Sec 1130 Intersection Design GB
The values obtained from the above sources are as follows:
Criteria Value Used Design Functional Class Rural Interstate Design Year 2029
Present ADT 3870 (from
2011) Directional Split (%) 50/50 Trucks (%) 12.5 Design Vehicle Design Speed (mph) 65 Stopping Sight Distance (ft.) 645 Passing Sight Distance Not Allowed Max Allowable Grade (%) 3 Min Allowable Grade (%) 0.35 Min Radius of Curvature (ft.) 1645 Min K Value for Vertical Curves (sag) 157 Min K Value for Vertical Curves (crest) 193 Width of Traveled Way (ft.) 40 Width of Shoulders (ft.) 8 Side Slope Ratio (foreslope) 4:1 Side Slope Ratio (backslope) 2:1
Consideration of Alternate Routes
Alternate routes for this project were considered. The primary alternate considered was to the
west of the historic structures in the project area. The other alternate considered was the
existing route.
The primary reason these routes were not chosen is cost and safety. The alignment to the west
of the historic structures would require larger amounts of right-of-way and the cost would be
significantly higher due to a longer project length.
The existing alignment is unacceptable due to the risk of the erosion feature. The Glenn
Highway is the primary access to everything northeast of Anchorage and an extended closure of
the road is unacceptable.
Due to these considerations the alignment presented in this report was chosen.
Horizontal Alignment
The design of the horizontal alignment primarily came from The Green Book. The primary
design considerations were the erosion feature to the east of the existing alignment and the
historic buildings to the west. The toe of the erosion feature appears to be stable since the
railroad embankment at the bottom of the slope does not appear to have moved.
Geotechnical engineers reviewed this erosion feature and decided that the Matanuska River
does not appear to be the cause of the erosion and natural erosion due to wind and rain is the
most likely cause. This means the base of the existing slope is unlikely to move and an extent of
erosion can be determined based on the soil types in the valley and the road realignment can
be placed outside those limits.
The minimum radius of curvature for the horizontal alignment was calculated to be 1,657ft and
is based on:
• Design Speed – 65mph
• Maximum Superelevation – 0.06
• Friction Factor – 0.11
The stopping sight distance was calculated to be 645 ft. and was taken from the Green Book.
The other consideration for the horizontal alignment was the horizontal sight offset. For the
two horizontal curves used in this design the required HSO was determined to be:
• Curve 1 – 27ft
• Curve 2 – 26ft
The horizontal alignment parameters using this design criterion is presented in the following
table.
Type Length Radius Min Radius
Start Station
End Station
Delta angle
Chord length
External Tangent PI Station
Line 759.99' 5+00.00' 12+59.99' Curve 1 770.23' 1927.00' 1660.00' 12+59.99' 20+30.22' 22.9015 (d) 765.12' 390.33' 16+50.32' Line 340.83' 20+30.22' 23+71.06' Curve 2 792.05' 2023.00' 1660.00' 23+71.06' 31+63.11' 22.4327 (d) 787.01' 401.17' 27+72.22' Line 38.25' 31+63.11' 32+01.36'
The maximum superelevation was set to 6% for the two horizontal curves and the roadway was
rotated about the centerline. The superelevation design can be found in the appendices.
Vertical Alignment
The primary concerns for the vertical alignment was the minimum length of the vertical curves,
the allowable percent grade and balancing the cut and fill.
For the minimum length of curves the following criteria was checked:
• Sight Distance
• Comfort
• Appearance
• Drainage
The results of this analysis are shown below:
Required Length on Criteria (ft.)
A (Grade Change)
Curve Type SSD Comfort Appearance
Profile Curve Length (ft.)
Curve 1 2.94% Crest 567 267 294 589 Curve 2 4.37% Sag 682 397 437 691 Curve 3 2.04% Crest 394 185 204 409
For all three curves the minimum length of curve was based on sight distance criteria. After the
minimum length of curve was determined the vertical alignment was designed in AutoCAD Civil
3d with a focus on balancing the cut/fill.
The surface used for this purpose was derived from the Mat-Su boroughs 2011 LIDAR (Light
Detection and Ranging) collect that was 1’ resolution and this might account for cut/fill
differences between Team Awesome and other groups.
At this point the corridor had been constructed, the assemblies built in AutoCAD and a sight
analysis was run on the corridor to identify problem areas. While AutoCAD did not find any it is
possible that a blind corner may still exist and the vertical alignment may need to be adjusted
accordingly.
Cross Section
Typical cross sections were designed for areas of both cut and fill. The cross sections were
designed to AASHTO specifications for rural principal arterials in level terrain. 2 percent lane
slopes were used for the 12 foot lanes. Four percent cross slopes were used for the 8 foot
shoulders. This meets AASHTO standards but it was revealed to the team after the final design
that the Alaska standard is to continue the 2 percent grade through the shoulder to the edge of
pavement. In cut a 4:1 foreslope and 2:1 backslope was designed. In fill, the slopes for lanes
and shoulders were the same as in cut as well as the foreslope. No backslope was designed for
fill sections. The total right of way width totaled 102’ giving 30 feet of clear space from the edge
of pavement. (See Figure xx)
Figure xx
Using Alaska Department of Transportation standards a structural cross section was designed
for this project. The surface layer consisted of 2” of type II asphalt concrete. The base layers
consisted of 4” asphalt treaded base and 2” of D-1 base course. The final structural layer
consisted of 36” select material type A. (See Figure xx)
Structural Section
Earthwork Quantities
With the proposed alignment for the new road, we determined the amount of cut and fill
required at each station throughout the length of the project. This was done by finding the
total amount of ROW required and using our typical cross sections determining what was
needed at that particular station. At the beginning of the project after station 06+00 there is a
hill that is going to be cut into that will provide a large amount of the fill required for the
project. All of the material from the hill will fill a depression that starts between stations 13+00
and 14+00. After the depression some more cutting will be required between stations 20+00
and 21+00 and at the end of the project will have an estimated amount of 2,000 cubic yards of
material to be removed from the project site. For more details on the calculations used to
determine that amount of cut and fill at each station refer to appendix xxx.
Mass Haul Diagram
The balance points for the length of the project were determined to be at station 06+00, station
15+04, and station 30+90. From figure xx you can see the cut and fill for the whole project. For
this project the length of the project is our free haul distance, what this means is that it will not
cost the client more money to move material back and forth from part of the job to another.
This is important for this design because most of the material that will be cut will be used
further down the project. The overhaul quantity that there will be is the 2,000 cubic yards of
material that has to be removed at the end of the project. This material will be hauled away to
the nearest available dump site which was determined to be approximately 5 miles from the
beginning of the project. The total cost to remove the material came to approximately $79,000
and this was determined by the cost of the truck multiplied by half an hour for time multiplied
by the number of truck loads to remove the material.
Figure xx
Intersection Design
For our intersection design we decided to keep the existing design the same with one
modification. The only thing that was changed is just north of Palmer Fishhook Road we
changed the highway into two lanes instead of three lanes in that section of the highway. The
intersection design can be found in appendix XX.
Analysis of Results
Level of Service
Level of service for the Glenn Highway Milepost 49 project was developed using the Highway
Capacity Software. The program required several inputs to calculate the level of service for the
project. The majority of the data was obtained through Alaska Department of Transportation
resources but, due to lack of time for research, a few assumptions were needed to receive an
output. AADT, traffic distribution, and the percentage of heavy vehicles data was gained from
the AKDOT database. Lane width, shoulder width, no passing percentage, and access points per
mile were calculated from the roadway design. The percent hour factor and terrain were
assumed to be .83 and level respectively.
The HCS test was run twice. The first neglected the passing lane that extends the length of the
project, while the second included the passing lane. The results concluded that project
produced a level of service of B for the design that included the passing lane and a level of
service of a C for the design that neglected the passing lane.
Please refer to appendix XX for the entire output information from the software.
Cost Estimate
The cost estimate for this project primarily consisted of right of way acquisitions and
construction line items.
Right of way acquisitions consisted of acquiring land from two parcels for a total acquisition
area of 12 acres. Land costs in the area of the project averages $13,000 an acre. The total cost
for acquiring the land required for this project totals $156,000.
The majority of the costs for the project were from construction bid items. Accurate costs for
bid items were developed using the average of similar projects in the area and conference with
local engineers. The largest expense for this project is for unclassified excavation at $350,000
followed by asphalt treated base at $296,000. For additional line item costs please refer to
appendix XX. The total cost of line items for the project is $3.07 million.
A 15% contingency is industry standard to account for unforeseen costs. Due to the minimal
time available to prepare this cost estimate, a contingency of 20% was used.
The total for this project included ROW, line items, and the contingency. The total project cost
is estimated at $3.87 million or $7.56 million per mile.
Conclusions & Recommendations
This project needs to go forward in order to keep the Glenn Highway corridor open in the long
term. There is no doubt that this erosion feature is threatening this road and realignment
needs to take place.
There are potentially a few issues that need to be addressed in this design if it were to be used.
These issues include the following:
• A potential blind corner generated from the horizontal/vertical alignments. The grade of the
road may need to be reduced going into and out of the sag curve to eliminate the blind corner.
This would increase the required fill for the project and increase the project cost.
• There is minimal distance between the superelevated sections in this design. Either the tangent
in between the superelevated sections should be increased to 500’ or the tangent should be
removed to turn it into on continually superelevated section of road.
• While the overall cost estimate may be close some of the lump sum costs may be high.
Given the proposed design the road would operate at a level of service of C. This means that
the Glenn Highway would operate at near free flow operations. If a passing lane were to be
included then it would operate at a level of service of B, which would be desirable.
The grade should be raised in the sag curve to increase the sight distance to remove any
potential blind corner and increase the sight distance to where a passing lane is allowed. This
design would also remove the need for longer superelevated sections and remove any issues
with the superelevation. This would increase the cost of the project but make the project much
more worthwhile.
Appendixes
Horizontal Alignment
Vertical Alignment
Superelevation
Superelevation Design - Curve 1
Superelevation Curve Start Station
End Station Length
Left Outside Lane
Right Outside Lane
Transition In Region 10+92.98' 13+15.65' 222.67' Run out 10+92.98' 11+48.65' 55.67' End Normal Crown 10+92.98' -2.00% -2.00% Level Crown 11+48.65' 0.00% -2.00% Runoff 11+48.65' 13+15.65' 167.00' Level Crown 11+48.65' 0.00% -2.00% Reverse Crown 12+04.32' 2.00% -2.00% Begin Curve 12+59.99' Begin Full Super 13+15.65' 6.00% -6.00% Transition Out Region 19+74.56' 21+97.23' 222.67' Runoff 19+74.56' 21+41.56' 167.00' End Full Super 19+74.56' 6.00% -6.00% End Curve 20+30.22' Reverse Crown 20+85.90' 2.00% -2.00% Level Crown 21+41.56' 0.00% -2.00% Run out 21+41.56' 21+97.23' 55.67' Level Crown 21+41.56' 0.00% -2.00% Begin Normal Crown 21+97.23' -2.00% -2.00%
Superelevation Design - Curve 2
Superelevation Curve Start Station
End Station Length
Left Outside Lane
Right Outside Lane
Transition In Region 22+07.19' 24+25.05' 217.86' Run out 22+07.19' 22+63.05' 55.86' End Normal Crown 22+07.19' -2.00% -2.00% Level Crown 22+63.05' -2.00% 0.00% Runoff 22+63.05' 24+25.05' 162.00' Level Crown 22+63.05' -2.00% 0.00% Reverse Crown 23+18.91' -2.00% 2.00% Begin Curve 23+71.06' Begin Full Super 24+25.05' -5.80% 5.80% Transition Out Region 31+09.12' 33+26.98' 217.86' Runoff 31+09.12' 32+71.12' 162.00' End Full Super 31+09.12' -5.80% 5.80% End Curve 31+63.11' Reverse Crown 32+15.26' -2.00% 2.00% Level Crown 32+71.12' -2.00% 0.00% Run out 32+71.12' 33+26.98' 55.86' Level Crown 32+71.12' -2.00% 0.00% Begin Normal Crown 33+26.98' -2.00% -2.00%
Earthwork Quantities
ft (yd3)1 2 3 4 5 6 7 8 9 10
(5) * 10/100 (5) + (6) MassTotal Shrinkage Total Fill Cut Diagram
Station Cut Fill Cut Fill 10 Fill (-) (+) Ordinate(+) percent (-) Cum. Vol
600 473.2 20.47 - - - - - - 0700 787.3 23.89 2334.30 82.15 8.21 90.36 0.00 2243.9 2,244800 809.8 0 2957.69 44.24 4.42 48.7 0.0 2909.0 5,153900 588.5 148.59 2589.54 275.17 27.52 302.7 0.0 2286.9 7,440
1000 452.6 267.29 1928.02 770.15 77.01 847.2 0.0 1080.9 8,5211100 448.9 366.64 1669.48 1173.94 117.39 1291.3 0.0 378.1 8,8991200 791 95.44 2296.20 855.70 85.57 941.3 0.0 1354.9 10,2541300 743.8 787.32 2842.22 1634.74 163.47 1798.2 0.0 1044.0 11,2981400 0 1875.6 1377.33 4931.28 493.13 5424.4 4047.1 0.0 7,2511500 0.1 1556.5 0.19 6355.74 635.57 6991.3 6991.1 0.0 2601600 0 1344.4 0.19 5372.04 537.20 5909.2 5909.1 0.0 -5,6501700 0 1105.4 0.00 4536.59 453.66 4990.3 4990.3 0.0 -10,6401800 1.12 615.95 2.07 3187.67 318.77 3506.4 3504.4 0.0 -14,1441900 0 431.6 2.07 1939.91 193.99 2133.9 2131.8 0.0 -16,2762000 25.21 179.39 46.69 1131.46 113.15 1244.6 1197.9 0.0 -17,4742100 475 17.47 926.30 364.56 36.46 401.0 0.0 525.3 -16,9492200 666.4 0.12 2113.61 32.57 3.26 35.8 0.0 2077.8 -14,8712300 655.6 3.27 2448.00 6.28 0.63 6.9 0.0 2441.1 -12,4302400 588.8 0.24 2304.43 6.50 0.65 7.2 0.0 2297.3 -10,1322500 344.4 0.65 1728.19 1.65 0.16 1.8 0.0 1726.4 -8,4062600 304 19.37 1200.67 37.07 3.71 40.8 0.0 1159.9 -7,2462700 355.7 129.2 1221.57 275.13 27.51 302.6 0.0 918.9 -6,3272800 431.1 52.81 1456.93 337.06 33.71 370.8 0.0 1086.2 -5,2412900 515.7 6.42 1753.31 109.69 10.97 120.7 0.0 1632.7 -3,6083000 531.9 22.42 1940.00 53.41 5.34 58.7 0.0 1881.3 -1,7273100 528.5 0.3 1963.57 42.07 4.21 46.3 0.0 1917.3 1903200 457.8 0.02 1826.43 0.59 0.06 0.7 0.0 1825.8 2,016
End Area (ft2) Volume (yd3) Net Volume
(4) + (7)
Intersection Design