GLAST Project Science Requirements Document (SRD) Table 3 ... · Objective For This Presentation:...
Transcript of GLAST Project Science Requirements Document (SRD) Table 3 ... · Objective For This Presentation:...
1
GLAST ProjectScience Requirements Document (SRD)
Table 3. Science Requirements on the GLAST Mission
Systems Engineering
Norman RiouxChris ConnorJulie McEnery
2
SRD In Context of Mission RequirementsGLAST
Program Plan
433-PLAN-0008
(Level I Rqmts
Document)
MOC Funct &
Perf Rqmts
492-MOC-0002
LV-OBS ICD
LEVEL 1 NASA HQ
LEVEL 4 Subsystems
GBM Inst. Ops
Center Rqmts
GBM-REQ-1021
GROUND SYSTEM REQUIREMENTS
LEVEL 2 GLAST Project
LEVEL 3 SC, Instruments, LV
NASA HQ
GLAST Project
NASA/KSC
Spectrum Astro
SLAC
NASA/MSFC
MOC
NASA HQ
GLAST Project
NASA/KSC
Spectrum Astro
SLAC
NASA/MSFC
MOC
To LAT & GBM
Level 3
Science Rqmts
Document
433-SRD-0001
Science Rqmts
Document
433-SRD-0001
Mission System
Specification
433-SPEC-0001
Mission System
Specification
433-SPEC-0001
Ops Concept
Document
433-OPS-0001
Ops Concept
Document
433-OPS-0001
LAT Mission
Assurance Rqmts
433-MAR-0001
LAT Mission
Assurance Rqmts
433-MAR-0001
EMI Rqmts
Document
433-RQMT-0005
EMI Rqmts
Document
433-RQMT-0005
SC Performance
Specification
433-SPEC-0003
SC Performance
Specification
433-SPEC-0003
LAT-SC
IRD
433-IRD-0001
LAT-SC
IRD
433-IRD-0001
GBM-SC
IRD
433-IRD-0002
GBM-SC
IRD
433-IRD-0002
SSC Functional
Rqmts Document
433-RQMT-0002
SSC Functional
Rqmts Document
433-RQMT-0002
GBM Mission
Assurance Rqmts
433-MAR-0002
GBM Mission
Assurance Rqmts
433-MAR-0002
LAT Inst. Ops
Center Spec.
LAT-SP-00015
LAT Inst. Ops
Center Spec.
LAT-SP-00015
SC Mission
Assurance Rqmts
433-MAR-0003
SC Mission
Assurance Rqmts
433-MAR-0003
LAT-SC ICD
1196 EI-
Y46311-000
LAT-SC ICD
1196 EI-
Y46311-000
Detailed SC
Rqmts Document
1196 EO-R46502
Detailed SC
Rqmts Document
1196 EO-R46502
GBM-SC ICD
1196 EI-
Y46312-000
GBM-SC ICD
1196 EI-
Y46312-000
1553 Bus Protocol
Doc. 1196 EI-
S46310-000
1553 Bus Protocol
Doc. 1196 EI-
S46310-000
SAS Subsystem Spec
LOF Subsystem Spec
SAS Subsystem Spec
LOF Subsystem Spec
SAS Subsystem Spec
LOF Subsystem Spec
- Baselined Document
- In CM Process
- Baselined Document
- In CM Process
GDS Mission
Assurance Rqmts
433-MAR-0004
GDS Mission
Assurance Rqmts
433-MAR-0004
Ground System
Rqmts Document
433-RQMT-0006
Ground System
Rqmts Document
433-RQMT-0006
GBM Rqmts
Database
GBM-REQ-1007
GBM Rqmts
Database
GBM-REQ-1007
LAT Instrument
Performance Spec.
LAT-SS-00010
LAT Environ. Spec
LAT-SS-00778
LAT Instrument
Performance Spec.
LAT-SS-00010
LAT Environ. Spec
LAT-SS-00778
LAT Instrument
Performance Spec.
LAT-SS-00010
LAT Environ. Spec
LAT-SS-00778
LAT-GBM ICDLAT-GBM ICD
Mech. Subsystem Spec
TCS Performance Spec
Power Subsystem Spec
T&D Subsystem Spec
ACD Subsystem Spec
TKR Subsystem Spec
CAL Subsystem Spec
LAT-TKR ICD
LAT-CAL ICD
LAT-ACD ICD
LAT-ELEC ICD
LAT-TKR IDD
LAT-CAL IDD
LAT-ACD IDD
LAT-ELEC IDD
LAT-RAD IDD
Mech. Subsystem SpecMech. Subsystem Spec
TCS Performance Spec
Power Subsystem SpecPower Subsystem Spec
T&D Subsystem SpecT&D Subsystem Spec
ACD Subsystem SpecACD Subsystem Spec
TKR Subsystem SpecTKR Subsystem Spec
CAL Subsystem SpecCAL Subsystem Spec
LAT-TKR ICDLAT-TKR ICD
LAT-CAL ICDLAT-CAL ICD
LAT-ACD ICDLAT-ACD ICD
LAT-ELEC ICD
LAT-TKR IDD
LAT-CAL IDDLAT-CAL IDD
LAT-ACD IDDLAT-ACD IDD
LAT-ELEC IDD
LAT-RAD IDDLAT-RAD IDD
IMU SOW
CSS SOW
GPS SOW
PROP MOD SOW
SSR PFS
PDE PFS
GPIO PFS
LGIO PFS
RAD750 CPU PFS
SW Rqmts Spec
GDE PFS
PACI PFS
UDL PFS
NVM PFS
SADA PFS
ARM PFS
ST PFS
RWA PFSTAM PFS
IPCU PFS
TIB PFS cPCI PFS
SBEAS PFS
SBTBRFD PFS
APM PFS
ETR PFS
MMT PFS
S-BAND ANT PFS
Heat Pipes PFS
Solar Cell Pnl PFS
Ku Ant PFSKu XMTR PFS
Transfer Swtch PFS
PDU PFS
PRU PFSBattery PFS
OCXO SOW
GNC Design Doc
IMU SOWIMU SOW
CSS SOWCSS SOW
GPS SOWGPS SOW
PROP MOD SOWPROP MOD SOW
SSR PFSSSR PFS
PDE PFSPDE PFS
GPIO PFSGPIO PFS
LGIO PFSLGIO PFS
RAD750 CPU PFSRAD750 CPU PFS
SW Rqmts SpecSW Rqmts Spec
GDE PFSGDE PFS
PACI PFSPACI PFS
UDL PFSUDL PFS
NVM PFSNVM PFS
SADA PFSSADA PFS
ARM PFSARM PFS
ST PFSST PFS
RWA PFSRWA PFSTAM PFSTAM PFS
IPCU PFSIPCU PFS
TIB PFS cPCI PFScPCI PFS
SBEAS PFSSBEAS PFS
SBTBRFD PFSSBTBRFD PFS
APM PFSAPM PFS
ETR PFSETR PFS
MMT PFS
S-BAND ANT PFSS-BAND ANT PFS
Heat Pipes PFSHeat Pipes PFS
Solar Cell Pnl PFSSolar Cell Pnl PFS
Ku Ant PFSKu Ant PFSKu XMTR PFSKu XMTR PFS
Transfer Swtch PFSTransfer Swtch PFS
PDU PFSPDU PFS
PRU PFSPRU PFSBattery PFSBattery PFS
OCXO SOWOCXO SOW
GNC Design DocGNC Design Doc
OBS–SN ICD
OBS–GS ICD
MOC-USN ICD
FDF-MOC ICD
Ops Products ICD
MOC-BU GS ICD
GFEP-WSC ICD
GFEP-MOC ICD
PSS Rqmts Doc
GFEP Rqmts Doc
OBS–SN ICD
OBS–GS ICD
MOC-USN ICD
FDF-MOC ICD
Ops Products ICD
MOC-BU GS ICD
GFEP-WSC ICD
GFEP-MOC ICD
PSS Rqmts Doc
GFEP Rqmts Doc
GBM DPU Sys Spec
GBM-SPEC-1008
GBM Internal ICD
GBM-ICD-1009
GBM FSW Rqmts
GBM-REQ-1019
Detector Design
Description
TN-GBM-3200-DJO
GBM-PB Design
Description
TN-GBM-6200-AEO
GBM DPU Sys Spec
GBM-SPEC-1008
GBM DPU Sys Spec
GBM-SPEC-1008
GBM Internal ICD
GBM-ICD-1009
GBM Internal ICD
GBM-ICD-1009
GBM FSW Rqmts
GBM-REQ-1019
GBM FSW Rqmts
GBM-REQ-1019
Detector Design
Description
TN-GBM-3200-DJO
Detector Design
Description
TN-GBM-3200-DJO
GBM-PB Design
Description
TN-GBM-6200-AEO
GBM-PB Design
Description
TN-GBM-6200-AEO
Sim/Detector Resp
SW Funct Spec
GBM-SPEC-1026
Inst Ops & Data
Anal Funct Spec
GBM-SPEC-1031
Sim/Detector Resp
SW Funct Spec
GBM-SPEC-1026
Sim/Detector Resp
SW Funct Spec
GBM-SPEC-1026
Inst Ops & Data
Anal Funct Spec
GBM-SPEC-1031
Inst Ops & Data
Anal Funct Spec
GBM-SPEC-1031
Comp
Verif Spec
Comp
Verif Spec
GEVS-SE Rev AGEVS-SE Rev A
3
Mission Verification Process
End-To-End Mission System Verification is the responsibility of the GLAST Project Officeand is led by Systems Engineering
Rigorous verification of engineering requirements is accomplished in the course of theintegration and verification program and reported on at formal Project life cycle reviews
– PER
– PSR
– ORR
– FRR
– LRR
Observatory Verification planning, execution, and coordination is contracted to GeneralDynamics
– Includes Observatory I&T and On-Orbit Checkout
The GLAST Systems Verification Plan (SVP) documents the methodology planned toverify system functionality and compliance with mission requirements
– 433-PLAN-0005
Acceptable verification methods used on GLAST
– Test, Analysis, Inspection, Demonstration
Verification Levels of Assembly
– Component, Subsystem, Spacecraft, Observatory, On orbit
Objective For This Presentation: Status on verification process for SRD table 3
4
SRD Table 3 Requirements Summary
< 5 arcsec< 10 arcsec3.36 Pointing Knowledge 7Footnote 7: 1 sigma radius
< 0.5 degrees< 2 degrees3.35 Pointing Accuracy Absolute 7Footnote 7: 1 sigma radius.
< 4 sec< 7 sec3.34 GRB Notification Time to Ground by Spacecraft 6Footnote 6: Time from spacecraft receipt of GRB notification from GBM orLAT to delivery to the Gamma-ray Coordinates Network (GCN) computerfor 80% of all GRBs detected by the GBM or LAT.
< 5 min< 10 min3.33 Spacecraft Repointing Times for Autonomous Slews 5Footnote 5: Time for 75° slew, to be met 100% of the time under 4reaction wheel (RWA) control and 75% of the time under 3 RWA control(single RWA failure) accounting for slew constraints (e.g. yaw flip).
< 4 hours< 6 hours3.32 Time to Respond to TOO's on Ground 4Footnote 4: Response time for the SSC and MOC to plan and send aspacecraft repointing command after the decision is made to respond to aTarget of Opportunity (TOO).
> 2 kbps> 1 kbps3.31 Telemetry Uplink Realtime 3Footnote 3: Uplink telemetry rate for at least 80% of time outside of SAA
> 2 kbps> 1 kbps3.30 Telemetry Downlink Realtime 3Footnote 3: Uplink telemetry rate for at least 80% of time outside of SAA
> 1 Mbps> 300 kbps3.29 Telemetry Downlink Orbit Average
> 10 years> 5 years3.28 Mission Lifetime (<20% degradation) 2Footnote 2: 20% degradation = no more than 20% loss of LAT sciencereturn.
Goal RequirementTable 3. Science Requirements on the GLAST Mission
5
SRD Table 3 Requirements SummaryContinued
- Rocking zenithpointing15
- Pointed mode8
3.37 Observing Modes
N/A> 30°
(adjustable)
3.45 Earth Avoidance 14Axis normal to LAT shall be capable of remaining at an angle greater thanthis above the Earth's horizon during normal operations, with the possibleexception of rapid slewing to acquire a GRB.
< 3 x 10-11
< 1 x 10-10
3.44 Data Corruption 13Footnote 13: Fraction of undetected corrupted events.
< 1%< 2 %3.43 Data Loss 12Footnote 12: Fraction of data taken by the instruments but not delivered tothe IOC. Not including SAA data loss. Not including instrument deadtime.
> 95%> 90 %3.42 Observing Efficiency 11Footnote 11: Fraction of time with data return, not including SAA effects.
< 1 km< 3.3 km3.41 Observatory Absolute Position Accuracy
< 3µsec< 10µsec3.40 Observatory Time Accuracy 10Footnote 10: Relative to Universal Time, 1 sigma r.m.s..
< ± 10%< ± 20%3.39 Uniformity of Sky Coverage during All-sky Survey 9Footnote 9: Sky coverage exposure uniformity integrating for 7 days, notincluding SAA effects
3.38 TargetingNo restrictions on Pointing 8 of axis normal to LATFootnote 8: Pointing of axis normal to LAT to within 30 degrees of source.(No science constraint on roll axis.).
Goal RequirementTable 3. Science Requirements on the GLAST Mission
6
AgendaPresenter / SRD Requirements
Norman Rioux
– 3.28, 3.29, 3.30
– 3.31, 3.40, 3.42
– 3.34
– 3.43
– 3.44
Chris Connor
– 3.33, 3.35, 3.37
– 3.38, 3.41, 3.45
– 3.36
Julie McEnery
– 3.32
– 3.39
7
SRD Table 3 Requirements3.28, 3.29, 3.30
Verified by test
Ground Selectable 1 k, 2 k, 4 k bps
Verified by CTV testing January 2007
Design provides commandable 8kbps data rate as a bonus if excess as-built margin permits
Final verification conducted in end to end testing with flight IEM and SSR
> 2kbps
> 1kbps
3.30 Telemetry DownlinkRealtime 3Footnote 3: Uplinktelemetry rate for at least80% of time outside of SAA
Verified by analysis and test
40 Mbps Ku band science downlink
80 minutes of TDRSS downlink time scheduled per day
Link verified in Compatibility Test Van (CTV) testing January 2007
Final verification conducted in end to end testing with flight IEM and SSRwith Ku downlinks schedule through the MOC
> 1Mbps
> 300kbps
3.29 Telemetry DownlinkOrbit Average
Mission design requirement verified by analysis
No consumables
Single fault tolerant redundant design meeting 85% 5 year reliabilityrequirement
Redundancy supporting graceful degradation in LAT Tracker, Calorimeterand ACD
> 10years
> 5years
3.28 Mission Lifetime(<20% degradation)
2
Footnote 2: 20%degradation = no more than20% loss of LAT sciencereturn.
Status
PerformanceGoal
PerformanceRequirement
3 Table 3. ScienceRequirements on theGLAST Mission
8
SRD Table 3 Requirements3.31, 3.40, 3.42
Mission design requirement verified by analysis
Mission is designed to collect data at all times
Routine operations enable continuous science data collection and return
LAT resets under investigation
> 95%> 90 %3.42 Observing Efficiency11Footnote 11: Fraction oftime with data return, notincluding SAA effects.
To be verified at observatory level
GPS receivers have been verifed to provide timing accurate to 1.5 microseconds
C&DH pulse per second interface has been functionally verified at componentlevel of testing with EM IEM
End to End LAT to Spacecraft test will verify observatory timing using Muontelescope EGSE. Muon telescope timing provided by independent GPS receiver
< 3µsec< 10µ
sec3.40 Observatory TimeAccuracy 10Footnote 10: Relative toUniversal Time, 1 sigmar.m.s..
Verified by test
4 kbps
Verified by CTV testing January 2007
Final verification conducted in end to end testing with flight IEM and SSR
> 2kbps
> 1kbps
3.31 Telemetry UplinkRealtime 3Footnote 3: Uplinktelemetry rate for at least80% of time outside of SAA
Status
PerformanceGoal
PerformanceRequirement
3 Table 3. ScienceRequirements on theGLAST Mission
9
SRD Requirement 3.34
3.34 GRB Notification Time to Ground by Spacecraft 6
< 7 sec
Footnote 6: Time from spacecraft receipt of GRB notification from GBM or LAT todelivery to the Gamma-ray Coordinates Network (GCN) computer for 80% ofall GRBs detected by the GBM or LAT.
To be verified during End to End Test
SC to MOC latency measured during Compatibility Test Van (CTV) testing forfour trials using a state of health message
– Averaging roughly 9 +/- 1 second SC to MOC
Contributing element: Lockup time of White Sands S-Band MA Demodulatorunit (DMU)
– Lockup time statistical in nature
– Code 450 (TDRSS Space Network) is developing improved FPGA algorithms for use in theWhite Sands DMU at 1Kbps
• May contribute reductions in latency on the order of 1 to 3 seconds
10
SRD Requirement 3.34 (con’t)3.34 GRB Notification Time to Ground by Spacecraft 6
< 7 sec
Footnote 6: Time from spacecraft receipt of GRB notification from GBM or LAT to delivery to theGamma-ray Coordinates Network (GCN) computer for 80% of all GRBs detected by the GBM orLAT.
End to End Latency – GBM to GCN
-1.5-1.5-1.5Margin against GBM first message to SC requirement
57.512.9Potential End to End latency with DMU improvement
89.513.9Potential End to End latency without DMU improvement
9.51115.4Instrument to SC interface to GCN latency Total:
.512MOC ITOS to GCN
8910SC output to MOC ITOS
113.4Instrument to SC Interface to SC antenna output
OptimisticNominalEstimate
Pessimistic
11
SRD Requirement 3.433.43 Data Loss 12
Requirement: < 2% Goal: <1%
Footnote 12: Fraction of data taken by the instruments but not delivered to theIOC. Not including SAA data loss. Not including instrument deadtime.
Verified via analysis
SC Data System is being thoroughly tested at Subsystem and ObservatoryLevels.
SC System designed to allow multiple retransmission of data
– SSR sized to provide 30 hours of science data and 36 hours of housekeeping data
• Analysis shows that 24 hrs of recorded HSK and Science data may be played back in~ 56 min at 40 Mbps.
• TDRSS Loading analysis determined that ~300 min/day of TDRSS SA contact timeavailable to support GLAST
• The FOT plans to schedule 80 to 90 minutes of contact time per day at 40 Mbps.
12
SRD Requirement 3.43 (con’t)
FOT Data Retransmission Plan
– While MOC is staffed:
• FOT monitors frame statistics and will re-transmit to recover anylost frames
• All missing/corrupted data will be retransmitted.
– During off hours and weekends:
• FOT will be paged when automated monitoring at the MOCindicates frame loss above a settable threshold (currently 99%)
• ISOC monitors event loss, and can also page FOT to request are-transmit
– FOT will re-dump missing/corrupt data twice from the SSR to ensurecomplete data capture and lower any likelihood of error during re-dumps
13
SRD Requirement 3.43 (con’t)
Ground System redundancy implemented to prevent data loss
– Data captured on multiple Front-end Processors (GFEPs) at White SandsTDRSS ground terminal (WSC)
• HSK and Science Data maintained on GFEPs for 7 days
• GFEPs are redundant with hot backups
• Use high reliability network connections between ground stations andMOC for transfer of science data.
– Network availability is 99.50%
– Network outage restored within 4 hrs
– Data archived at MOC and backed-up on separate media
14
SRD Requirement 3.44
3.44 Data Corruption 13
Footnote 13: Fraction of undetected corrupted events.
Requirement: < 1 x 10-10
Goal: < 3 x 10-11
Verified via analysis
Four categories of data coming out of the data channel:
1. Data is actually good and detected as good.
2. Data that is actually in error, detected as in error, and can be corrected based oncoding.
3. Data that is actually in error, detected as in error, but cannot be corrected with coding.
4. Data that is actually in error, but detected as being good.
This requirement is concerned with data in category 4.
Analysis of the science data return link performance including Reed Solomon coding andinterleaving shows that this requirement is easily met with margin.
15
SRD Table 3 Requirements3.33, 3.35, 3.37
Verified via analysis
Two primary observing modes provided are sky survey(zenith pointing with rocking angle) and pointedobservation mode
3.37 Observing ModesObserving Modes- Rocking zenith pointing 15- Pointed mode 8Footnote 8: Pointing of axis normal to LATto within 30 degrees of source. (Noscience constraint on roll axis.).Footnote 15: The observatory shall becapable of scanning the LAT FOV (55°
half-angle) over >90% of the celestialsphere repetitively on selectabletimescales as short as every 2 orbits.
Verified via analysis
0.8 deg
Driven by environmental disturbances and commandlatency
< 0.5degrees
< 2degrees
3.35 Pointing Accuracy Absolute 7Footnote 7: 1 sigma radius.
Verified via analysis
4 RWAs: Maximum slew time is 9 min3 RWAs: 84% of 75 degree slews are within 10 min
RWA reliability information: Ps(15 yrs)=0.9555
< 5 min< 10 min3.33 Spacecraft Repointing Times forAutonomous Slews 5Footnote 5: Time for 75° slew, to be met100% of the time under 4 reaction wheel(RWA) control and 75% of the time under3 RWA control (single RWA failure)accounting for slew constraints (e.g. yawflip).
3 Table 3. Science Requirements onthe GLAST Mission
StatusPerformance Goal
Performance
Requirement
Science Requirements extracted fromSRD descriptive module
16
SRD Table 3 Requirements3.38, 3.41, 3.45
Verified via analysis
30 deg
Keep the earth out of the sweet spot. Will slew across earthif need be, taking into consideration the sun angle(maintain sun in X-Z plane).
N/A> 30°
(adjustable)
3.45 Earth Avoidance 14Axis normal to LAT shall be capable ofremaining at an angle greater than thisabove the Earth's horizon during normaloperations, with the possible exception ofrapid slewing to acquire a GRB.
Verified via analysis
0.2 Km
GPS design and supporting GNC software algorithms areheritage from previous GD programs.
< 1 km< 3.3 km3.41 Observatory Absolute PositionAccuracy
Verified via analysis
Physical Constraints: Default is 30 deg Earth Avoidance,as per 3.18.
30 deg half-angle is the "sweet" spot of the LAT (55 degFOV).
GD provides PAPA (predict ahead planning algorithm)which utilizes ephemerides and operational constraints tocompute slew profiles.
3.38 TargetingNo restrictions on Pointing
8 of axis
normal to LATFootnote 8: Pointing of axis normal to LATto within 30 degrees of source. (Noscience constraint on roll axis.).
3 Table 3. Science Requirements onthe GLAST Mission
StatusPerformance Goal
Performance
Requirement
Science Requirements extracted fromSRD descriptive module
17
SRD Requirement 3.36
Observatory Pointing Knowledge Performance (1-sigma, radial)
– All BOL Sky Survey Cases: CBE < 10 arcsec
– All BOL Cases (Sky Survey & Pointed Obs): CBE < 15 arcsec
– All Mission Cases (BOL & EOL): CBE < 30 arcsec
All analysis performed with integrated, observatory-level thermalmechanical distortion models (spacecraft + science instruments)
– Modeling uncertainty factors (MUFs) applied to distortion results
18
SRD Requirement 3.36 (con’t)
Analysis efforts concentrated on identification of the primarydistortion terms & overall review of model fidelity
– Primary distortion sources are the optical bench skirt & star tracker to startracker distortion on the optical bench reference
– SC provider performed optical bench thermal test (Dec 2005) to help correlatemodels and refine predicted performance
LAT & SC thermal model correlation underway
– Observatory TVAC scheduled for Summer 2007
– Upon completion of these activities, we can reduce the MUFs
On-orbit GNC Kalman filter will help with some of the star tracker-to-star tracker distortion
– Cyclic thermal distortion due to day/night transitions each orbit
19
SRD Requirement 3.32
RPS
Science Community
GSSCDutyScientist
Pager Tool
MOC
ProjectScientist
EvaluationTools
ToO Approver/RejectorToO Orderer
ToO Order
ToO StatusMessages
ToO StatusWeb Page
ToO StatusDatabase
As-Flown Timeline
Timeline Comparator
ToO Request
TimelineDifferences
ToOCommands
ToO Advice
ToO Decision
ToOQueries/Responses
ToO Request
Response time for the GSSC and MOC to plan and send a repointing comandafter the decision is made to respond to a ToO: 6 hours requirement, 4hours goal, 12 hours minimum.
20
Target of Opportunity Handling
Upon receiving authorization to proceed with the ToO, the GSSC constructs the ToOOrder and forwards to the MOC
– GSSC checks for constraint violations, occultation, availability, etc.
– Approved ToO Order is sent to the MOC
MOC recognizes ToO Order and notifies appropriate FOT personnel for action
– FOT processes ToO Order and evaluates impact to current TDRSS contact schedule
– FOT schedules a forward link with TDRSS (if necessary)
– MOC transmits the ToO commands to the spacecraft as soon as the TDRSS forward link is available
Receipt of ToOs orders do not absolutely necessitate weekly ATS replans by the FOT
– Observatory autonomously returns to on-board observing schedule at completion of the ToO usingcheck-pointed commands from the ATS
– FOT will evaluate the affect of the ToO on scheduled TDRSS contacts and re-schedule additionalcontacts if necessary
GSSC will evaluate the affect of the ToO on current timeline and adjust accordingly witha re-planned timeline or adjust the upcoming planning week
SRD Requirement 3.32
21
SRD Requirement 3.32
ToO Latency - Worst case scenario
221Total
5uplink command
30SN to prep for contact
30FOT to Schedule contact
90FOT to travel to MOC
5FOT to receive email
1MOC to send email
60GSSC duty scientist to perform evaluation and send mail
Time (min)Action
22
SRD Requirement 3.39
Uniformity of sky coverage during all sky survey: +-20% (req), +-10%(goal) integrated for 7 days not including effects of the SAA.
Analysis:– Survey mode rocking 35 degrees north/south each orbit, orbit with 25.4 deg inclination.
– Convolve the pointing history with the LAT effective area as a function of inclination toobtain the exposure over the sky.
– The next two slides show the exposure from 100 MeV - 200 GeV for a 1 week and 55 daysurvey mode observation.
23
Exposure Uniformity - 7 days
Colour scale is from maxto min pixel value (so it iseasy to see smallstructure)
Histogram of exposure inbins of equal angular areaon the sky.
rms/mean = 7.3%,however there are someoutliers.
1.6% (41) of the bins liefurther than 20% from themean.
24
Exposure Uniformity - 55 days
RMS/Mean = 2.3%, all bins liewithin 20% of the mean. Thelines +-20% of the mean lie offthe scale of this plot!
25
A caveat
The LAT Aeff vs inclination angle varies with energy, thus theexposure pattern on the sky also varies depending on the energyband being considered.
26
Exposure vs energy band
27
Effect of SAA - 1 week integration
The distribution ofexposure on the sky hasbecome significantly morenon-uniform.
rms/mean = 14%
28
Effect of SAA - 55 day integration
On longer timescales, theeffect of SAA outages isto introduce a north/southasymmetry. However theoverall magnitude of thisis fairly small, all pointson the sky remain within20% of the mean.
29
GLAST Mission Systems
USN(GN)
HEASARC
DELTA2920H-10
Commands 2 kbpsTelemetry 51 kbps
2.4 Mbps SSOH - RT
White Sands (SN)
TDRSS (SN)
LAT InstrumentOperations Center
GBM InstrumentOperations Center
GRBCoordinates Network
S-Band
Alerts
Data, Command Loads
Data, Command Loads
Schedules/CMDS
ArchiveMissionOperations Center
GSFC
ScienceSupport Center GSFC
GPS Signals Provide• Time 10 µsec• Position <3.3 km
• Ku-Band Downlink: 40 Mbps forStored Science, SSOH Data, Real-Time Data
• S-Band SA Downlink:1,2,4,8 kbps for RT Data
• S-Band MA Downlink: 1 kbps forAlerts (Burst, Safe Mode)
Commands 4 kbps (S-BandSA), 250 bps (S-Band MA)
= Ku-Band Downlink = S-Band Downlink = S-Band Uplink
Schedules/CMDS