GHD Water Systems Hydraulic Modelling
Peter Bruntph: 8687 8836
Key Personnel
Mike Woods• Over 25 years
experience
• Water Network Analysis
• Strategic Planning
Ramon Shinkfield• 9 years experience
• Water model build, calibration, analysis, planning
• Spatial Analysis & GIS
Peter Brunt• 9 years experience
• Project manages water supply network capabilities
• Water model build, calibration, analysis, planning
Scott Nicholls• 10 years experience
• Water & wastewater model build, calibration, analysis, planning
• Multiple packages; Info Works, H2OMap, SynerGee, EPANet
David Hyne• 2 years experience
• Water model build, calibration & analysis
Key Personnel
Jonathan Orr• 10 years experience
• Water and wastewater network analysis
• Strategic planning
Steven Fraraccio• 3 years experience
• Water model build, calibration & analysis
• Surge Analysis
Don Sirikhant• 4 years experience
• Water & wastewater model build, calibration, analysis
GHD Melbourne Experience
• Completed modelling projects:• 39 clients – local, interstate international• Predominantly regional water authorities
• Project experience includes• Data monitoring planning and collection• System data capture and model build• Model calibration, validation, development forecasts,
analysis, planning, PMZ, scenario management, etc.• Surge/transient wave modelling
• Multiple model packaging experience• H2OMap, WaterCAD, EPANet, InfoWorks etc etc.
Ballarat Water Supply Network Model (CHW)
Purpose:
1) Develop population forecasts
2) Planning of pressure reduction works as part of an overall program to address unaccounted water
3) Planning for population & demand growth
System Complexities:• Three sources of supply (variable WQ)• Six main pressure zones plus sub-zones• 18 No. PRV’s plus 2 No. PCV’s• 22 No. storages and 8 No. pump sets• The model was validated against SCADA.
Township Development Plans (WW)Portland, Port Fairy, Hamilton & Heywood
Purpose:
1) Strategic and capital works planning
2) Efficient servicing and operations
System Complexities :• No. pipes ranged from 300 to 2000• Calibrated to monitored flows & pressures• One town under Stage 4 restrictions• Three towns under PWSM• Developed data monitoring and collection program
Bendigo Augmentation Strategy (Coliban)
Purpose:
1) Determine most effective and efficient means of operating the system
2) Develop future system improvement options:- 5 stages over 25 years
System Complexities :• Extension of the network to 5 satellite townships• Pressure, security of supply, fire flow• Water quality calibration & modelling• Leakage reduction• Develop strategy model user manual and training
WMP Hydraulic Design Review (Coliban)Purpose:1) Independent performance review of hydraulic design and as-
built system2) Confirmation that agreed levels of service can be supplied
System Complexities:• WMP system ~10% of Victoria (2M Ha), 8000km pipeline, 53
pump stations, 71 storage facilities• Review how models were used to size pipes and
their ratings, and design pump stations & storages• Identification of shortfalls, deferral opportunities
with verified via systematic consultative process• Improvement opportunities identified, e.g. security
of supply, trigger points, modelling potential
Modelling Capability Statement
• Refer to hand-out