GGOOVVEERRNNMMEENNTT OOFF RRAAJJAASSTTHHAANN
RRUURRAALL DDEEVVEELLOOPPMMEENNTT && PPAANNCCHHYYAATTII RRAAJJ DDEEPPAARRTTMMEENNTT
WWAATTEERRSSHHEEDD DDEEVVEELLOOPPMMEENNTT && SSOOIILL CCOONNSSEERRVVAATTIIOONN DDEEPPAARRTTMMEENNTT
RRAAJJAASSTTHHAANN,, JJAAIIPPUURR
PPRROOJJEECCTT IIMMPPLLEEMMEENNTTIINNGG AAGGEENNCCYY
AASSSSIISSTTAANNTT EENNGGIINNEEEERR
PPAANNCCHHYYAATT SSAAMMIITTII-- SSIIKKRRAAII
DETAILED PROJECT REPORT
NAME OF WASTRSHED : IWMP – I
MACRO :- 2,5 & 6
MICRO :- 10,2,3,4 & 1
TOTAL AREA :- 6130 Ha
FOREST AREA :- 622 Ha
NET AREA :- 5008 Ha.
TOTAL AMOUNT :- 600.96 LACS
PANCHAYAT SAMITI :- SIKRAI
DISTRICT :- DAUSA
IWMP-I, BLOCK-SIKRAI, DAUSA I
TABLE OF CONTENTS
TABLE OF CONTENTS .............................................................................................................
LIST OF TABLES .......................................................................................................................
ANNEXURES ...............................................................................................................................
MAPS ............................................................................................................................................
CHAPTER – I ...............................................................................................................................
1. INTRODUCTION: ..............................................................................................................
1.1.Sanction of IWMP project: ...............................................................................................
1.2. Institutional Arrangements: ........................................................................................
1.3. Details of Bank Account: .............................................................................................
CHAPTER – II .............................................................................................................................
2.1. BASIC FEATURES: ....................................................................................................
2.1.1. Present Land use: .................................................................................................
2.1.2. Live Stock Status: .................................................................................................
2.1.3. Existing Horticulture and Fodder Availability: ................................................
2.1.4. Existing Fodder Availability and Requirement: ...............................................
Milk Production: ..................................................................................................................
Demography: ........................................................................................................................
2.1.7. Infrastructure Facilities Available: ....................................................................
2.1.8. NREGA Status: ....................................................................................................
2.1.9. Land Holding Details: ..........................................................................................
2.1.10. Other Development Schemes in the Project Area:............................................
2.2. Technical Features: ......................................................................................................
2.2.1. Collection of Revenue Record: ............................................................................
2.2.2. Maps of the Area ..................................................................................................
2.2.3. Slope Details of Area:...........................................................................................
2.2.4. Water Budgeting: .................................................................................................
2.2.5. Soil Profile and Soil Fertility Status: ..................................................................
2.2.6. Climatic Details: ...................................................................................................
2.3. Problems, Demand and Scope for development: ......................................................
2.3.1. Natural Resource Management: .........................................................................
IWMP-I, BLOCK-SIKRAI, DAUSA II
2.3.2. Agriculture and Horticulture Productivity: ......................................................
2.3.3. Live Stock-gap of Fodder Availability: .............................................................
2.3.4. Livelihood and Micro enterprises: .....................................................................
CHAPTER – III ...........................................................................................................................
3.1 Preparatory Phase activities: ......................................................................................
3.1.1. Entry Point Activities: .........................................................................................
3.1.2. Capacity Building: ...............................................................................................
3.1.3. PRA Exercise: .......................................................................................................
3.2. Natural Resource Management (NRM) .....................................................................
3.2.1. Conservation measures for arable lands: ..........................................................
3.2.2. Conservation measures for non arable lands: ...................................................
3.2.3 Drainage line treatment:......................................................................................
3.3. Production System and Micro Enterprises: ..............................................................
3.3.1. Production measures for arable lands: ..............................................................
3.3.2. Production measures for non arable lands: .......................................................
3.3.3 Livelihood activities particularly for asset less person: ....................................
CHAPTER IV ...............................................................................................................................
4. Technical Designs and Estimates for Proposed Activities: ..............................................
4.1. Design of Contour Bunds: ...........................................................................................
4.2. Estimates: ......................................................................................................................
4.2.1. Estimates of Different Entry Point Activities (Estimates 1 to 7): ........................
4.2.2. Estimates of Different Activities in Arable & Non Arable: .................................
CHAPTER V ................................................................................................................................
5. Activity Wise Total Abstract of Cost through Project and Convergence: .....................
CHAPTER VI ...............................................................................................................................
6. Annual Action Plan for Project and Convergence funds: ................................................
CHAPTER VII .............................................................................................................................
7.1. Project Outcome: .................................................................................................................
IWMP-I, BLOCK-SIKRAI, DAUSA III
LIST OF TABLES
Table 1. Village Wise Land Use of Project Area ………………………………………..
Table 2. Village Wise Details of Land Holding According to Accounts (as per Revenue
Record) …………………………………………………………………………
Table 3. Village Wise Classification of Land According to Type of Land for Gram
Panchayat Thikiria (as per revenue record)……………………………….…
Table 4. Village Wise Classification of Land According to Type of Land for Gram
Panchayat Pilodi (as per revenue record)…………………………………….….
Table 5. Village Wise Classification of Land According to Type of Land for Gram
Panchayat Pancholi (as per revenue record)……………………………………..
Table 6. Village Wise Classification of Land According to Type of Land for Gram
Panchayat Pipalki(as per revenue record)………………………………………
Table 7. Village Wise Classification of Land According to Type of Land for Gram
Panchayat Kalwan (as per revenue record)……………………………………
Table 8. Village Wise Classification of Land According to Type of Land for Gram
PanchayatAchalpura(as per revenue record)………………………………………
Table 9. Village Wise Classification of Land According to Type of Land for Gram
Panchayat Geejgarh (as per revenue record)……………………………
Table 10. Village Wise Details of Irrigated, Unirrigated, Waste Land, Pasture Land……..
Table 11. Demography Information of the Project Area…………………………………….
Table 12 Villagewise Land Holding Pattern in Projet Area………………………………
Table 13 Village Wise Agriculture Production of Different Crops Grown in Kharif/Rabi
seasons ………………………………………………………………………….
IWMP-I, BLOCK-SIKRAI, DAUSA IV
FIGURES
Figure 1 Comparison of Productivity of Major Crops Grown in Kharif Season with Average
Productivity of Sikrai Block and Dausa District…………………………………….
Figure 2 Comparison of Productivity of Major Crops Grown in Rabi Season with Average
Productivity of Sikrai Block and DausaDistrict…………………………………….
IWMP-I, BLOCK-SIKRAI, DAUSA V
ANNEXURES
ANNEXURE – I. Gram Panchayat Wise Details of Various User Groups Constituted for
Development of Activities
ANNEXURE – II. Gram Panchayat wise/ Watershed Committee wise Details of Various
Self Help Groups
ANNEXURE – III. Gram Panchayat wise/ Watershed Committee wise Details of
Watershed Committee
ANNEXURE – IV. List of Beneficiaries/Cultivators selected for Horticulture Plants
IWMP-I, BLOCK-SIKRAI, DAUSA VI
MAPS
MAP 1. Sikrai Block Index Map
MAP 2. Watershed Map Showing the Slope Groups
MAP 3. Cartosat -1 Satellite Image Map of Proposed Watershed
MAP 4. Land Use Map of Proposed Watershed
MAP 5. Base Map
IWMP-I BLOCK-SIKRAI, DAUSA 1-1
CHAPTER – I
1. INTRODUCTION
Water is the basic requirement for every living life. The importance of water conservation in
the country has been recongnized since immemorial times. Over the years, watershed
approach has conventionally been applied for the purpose of arresting rainwater runoff, its
harvesting and in situ soil and moisture conservation in the country. The objective has
essentially been achieved through development of waste and degraded lands under various
Central and State Government Programmes. The Ministry of Rural Development is
implementing special area development programmes for the purpose of water harvesting in
drought prone, desert and rainfed areas. The Drought Prone Areas Programme and Desert
Development Programme were started in 1973-74 and 1977-78 respectively. The Integrated
Wastelands Development Programme was launched in 1989. On the basis of
recommendations of the Hanumantha Rao Committee (1994), in the year 2003, the Ministry
of Rural Development brought out the Guideline for Hariyali by suitably modifying the earlier
guidelines. This brought the DDP, the DPAP and IWDP under a single umbrella. In the year
2000, the Ministry of Agriculture revised its guidelines for its programme, the National
Watershed Development Project for Rainfed Areas (NWDPRA).
In order to assess the performance of various ongoing programmes of watershed development,
series of evaluation studies were conducted by Indian Council of Agricultural Research, State
Agriculture Universities, National Remote Sensing Agency etc. After series of evaluation
studies and impact assessment studies, in coordination with the Planning Commission, in the
year 2008, Common Guidelines for Watershed Development Projects was formulated in order
to have a unified perspective by all Ministries. This Common Guideline is applicable to all
Watershed Development Projects in all Departments/Ministry of Government of India
concerned with Watershed Development Projects. These guidelines coupled with the
flexibilities, would provide an enabling framework for the planning, design, management and
implementation of all watershed development projects in the country. All the watershed
projects are being implemented in accordance with these Common Guidelines with effect
from 1.4.2008. For interpretation of any of the provisions of these guidelines, the National
IWMP-I BLOCK-SIKRAI, DAUSA 1-2
Rainfed Area Authority (NRRA), which has been set up in November 2006, will be the final
authority. The common Guidelines for watershed development projects are based on equity
and gender sensitivity; decentralization; facilitating agencies; community participation;
capacity building and technology inputs; monitoring evaluation and learning and
organizational restructuring.
1.1. Sanction of IWMP project:
During the year 2009-10 under the Centrally Sponsored Scheme Integrated Watershed
Management Programme (IWMP) for implementation in accordance with the Common
Guideline for Watershed Development Projects, 2008, the 6130 ha Watershed Project IWMP-
I has been sanctioned in SIKRAI block of Dausa District. The Administrative and Financial
Sanction of the project has been issued by Rural Development & Panchayati Raj Department,
Commissionerate, Watershed Development and Soil Conservation vide letter no. F-18
(199)WDSC/PFC/2009/1822-2104, Dated 11-11-2009.
The Sikrai Block is distributed in 41 Gram Panchayat. The proposed watershed area is
covered in 25 villages of 7 Gram Panchayats. The distance/vicinity of the watershed area
from Sikrai Panchayat Samiti Headquarter is 05 to17 Km. The area includes the high hilly
and hard rocks, in which rainwater flows in Nallas/Nadi. The water level is regularly
decreasing due to increasing well/tube wells. Due to various significant problems, the area has
been selected for integrated development.
As per the social survey and by interviewing the people of the area, shows that in the area
water table is decreasing, land degradation due to soil erosion, increase in population, poor
livestock productivity, fodder shortage and marketing opportunities. Therefore the area has
been selected for integrated development with focus on integrated farming system for
increasing productivity, livelihood and regular income in a regular way. As various research
conducted for rainfed areas shows that the efficient water management through soil and water
conservation measures is the key to sustainable development. The integrated watershed
approach i.e. conserving natural resources of water, soil and vegetation has been accepted as a
major theme for development of rainfed areas.
IWMP-I BLOCK-SIKRAI, DAUSA 1-3
The introduction of MGNREGS in the area various water harvesting structures specially Farm
Ponds/Talai have been constructed. Looking to the plan of the MGNREGS the few new
water harvesting structures has been proposed. In some places only spillways have been
proposed. The main stress have been given on contour vegetative bunds with proper
outlets/wasteweirs, pasture development, loose stone check dams, small earthen bunds,
staggered box trenches in pasture areas and table land protection bunds. Also in watershed
area diversion channels from higher areas towards farm ponds have been proposed, where
water is spread and stagnated in the field.
1.2. Institutional Arrangements:
As per Common Guidelines for effective execution and management of watershed
development appropriate institutional arrangements has been made at National, State and
District levels for effective and professional management of watershed development projects.
The institutional arrangements at State, District and Project level are as follows:
a. State Level Nodal Agency (SLNA) : At State level
b. District Watershed Development Unit (DWDU) : To ensure coordination at district
level, a DWDU have been
constituted.
Executive Engineer (Land
Resources), Zila Parishad, Dausa,
(Rajasthan)
Phone No. 01427-223532
c. Project Implementing Agency (PIA) : Assistant Engineer, Panchayat
Samiti, Sikrai, District Dausa
(Rajasthan)
Phone No 01420-254204
IWMP-I BLOCK-SIKRAI, DAUSA 1-4
d. Watershed Development Team (WDT) :
The WDT is an integral part of the PIA having at least four members, broadly with the
knowledge and experience in Agriculture, Social Science, Water Management (Engineering)
and Animal Husbandry/Live Stock. Following four WDT members have been selected at PIA
level with open advertisement:
S.No. Subject Specialist Name Qualification
1. Engineering - -
2. Agriculture Sh. Mukesh Kumar Meena B.Sc. (Agriculture)
3. Animal Husbandary Sh. Santosh Kumar Trivedi LSA (2 yrs Diploma)
4. Social Science Miss Minakshi Sharma B.A. (Sociology)
e. User Groups:
As per guideline and directions given by SLNA, with the help of WDT members, for each
Gram Panchayat separate user groups have been formed for different works/ activities. The
homogeneous groups have been constituted, who may be most affected by each work/activity
and shall include the persons having land holding within the watershed areas. Each UG’s
have been formed of the persons who are likely to derive direct benefits from a particular
watershed work or activity. The representation of each village has been considered in the
formulation of groups. In each group a president has been elected. These groups have been
constituted in Gram Sabha’s. The programme of Gram Sabhas in different Gram Panchayats
was been scheduled by Block Development Officer, Panchayat Samiti, Sikrai. The Gram
Panchayat wise details of elected user groups have been enclosed at Annexure –I.
f. Self Help Groups:
In the Gram Panchayat the SHG groups have been constituted. The groups have been formed
according to interest of their work. The homogeneous groups have been formed having
common identity, who are dependent on the watershed area such as agricultural labourers,
landless persons, women, scheduled caste/scheduled tribes persons. The Gram Panchayat
wise details of elected SHG groups are enclosed at Annexure –II.
IWMP-I BLOCK-SIKRAI, DAUSA 1-5
g. Watershed Committee:
In the Gram Sabha, after constitution of UG’s and SHG’s, the watershed committee for each
gram panchayat has been formed separately. The committee comprises of 10-12members. In
the committee all the presidents of user and self help groups, representation of SC/ST, land
less persons and female representation have been considered. In the formation of committee
it was also considered that the members of all the villages of Gram Panchayat are included, so
that they can take care of work/need of their village. After constitution of watershed
committee the Chairman/President and Secretary has been selected/ elected. The Gram
Panchayat wise detail of Watershed Committee is enclosed at Annexure –III.
h. President and Secretary of Watershed Committee:
The each watershed committee has been registered under society registration act. The gram
Panchayat wise elected president and secretary are as follows:
S.N. Gram
Panchayat
Name of
Watershed
Committee
President Secretary Registration
No.
1. Thikiria Thikiria Rambharosi Meena Bharat Lal Meena
2. Pilodi Pilodi Dharmsahay Meena Ganga Sahay Meena
3. Pancholi Pancholi Badan singh gurjar Jhandu Sing Gujar
4. Pipalki Pipalki Rajendra saini Banbari lal Meena
5. Kalwan Kalwan
6. Achalpura Achalpura
7. Geejgarh Geejgarh
IWMP-I BLOCK-SIKRAI, DAUSA 1-6
1.3. Details of Bank Account:
For each Sub committee(Watershed) of gramphanchayat, the separate saving bank account
has been opened with the name of Sarpanch of concern grampanchayat,Secretary of Sub
comitee (W/s)and Junior Engineer/A.En. One separate Watershed Development Fund (WDF)
account has been opened for each committee. In the WDF Account no transaction will be
done only the contribution received from beneficiaries will be deposited.
The details of bank account for watershed committee are as follows:
S.No Watershed
Committe
Account Bank Name
Saving A/C No. WDF A/C No.
1. Thikiria 61124810681 SBBJ SIKRAI
2. Pilodi 61124754170 SBBJ SIKRAI
3. Pancholi 61124794077 SBBJ SIKRAI
4. Pipalki 61132546433 SBBJ SIKRAI
5. Kalwan .
6. Achalpura
7. Geejgarh
IWMP-I, BLOCK-SIKRAI, DAUSA 2-1
CHAPTER – II
2.1. BASIC FEATURES:
The basic features of the sanctioned watershed project:
Name of Project : IWMP – Dausa I
Local Name of Project : Achalpura
Macro/Micro No. : 5/2,5/3,5/4,6/1 & 2/10
Project Area : 5008 Ha
Cost of Project : 600.96 Lacs
Cost per hectares : Rs. 12000
Year of Sanction : 2009-10
No. Gram Panchayat : 7
No. of villages in Project area : 25
Elevation : 325 m
Major Streams : Banganga River
Latitude/Longitude : 76 o26’ to 76
o 48’ North
26 o 45’ to 26
o 59’ East
2.1.1. Present Land use:
The village wise present land use of project area with net sown area is shown in Table 1. The
village wise and Account holder wise details of land is shown in Table 2. According to
revenue record/Jamabandi the village wise classification of land for each Gram Panchayat
have been shown in Table 3 to 9. The Village wise details of Irrigated, Unirrigated, Waste
Land, Pasture Land area is shown at Table 10.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-2
2.1.2. Livestock Status:
The status of livestock i.e. Cow, Buffalo, Sheep, Camel, Pig in the area is as follows:
S.N. Name of Village Cow Buffalo Goat Sheep Camel Bull Pig
Indi. Hybrid
I. G.P. THIKRIA
1. Thikiria 50 50 1500 50 5 5 7
2. Kheda phadpur 5 15 350 10
3. Darjapur 2 8 150 15
4. Pattisalesingh 3 5 200 75 50 2 -
5. Sultanpur 4 4 40 5 4 - -
II. G.P. PILODI
1. Pilodi 80 20 1400 1000 50 5 3 15
2. Khedi 30 10 466 200 25 4
3. Heengi 30 19 500 157 30 3 2
III. G.P. PANCHOLI
1. Pancholi 60 70 1800 100 50 10
2 Kherla 25 25 700 50 10 10
3 Murlipur 10 20 1000 50 20 15
IV. G.P. PIPALKI
1. Sikri 18 4 740 480 25 2
2. Dhulkot 20 10 600 50 10 4 1
V. G.P. KALWAN
1. Kalwan 60 40 1500 1200 600 4 3 54
2. Giladi 5 2 50 40 14 1
3. Padli Barh 21 19 300 109 19 3 2
IWMP-I, BLOCK-SIKRAI, DAUSA 2-3
VI. G.P. ACHALPURA
1. Achalpura 13 24 1050 3
2. Sarundla 42 18 1300 300 150 20 20
3. Chak Sarundla 18 12 340 40
4. Chandpur 8 8 400 300 44 3 1
5 Jhangiria 28 34 1098 713 123 5
VII. G.P. GEEJGARH
1. Geejgarh 300 200 5400 300 1060 38 2 280
Total 832 617 20884 5244 2280 137 19 376
2.1.3. Existing Horticulture and Fodder Availability:
The village wise existing area under horticulture and fodder is as follow:
S.N. Name of Village Existing Area under Horticulture Existing Area
under Fodder Vegetable Orchard
I. G.P. THIKIRIA
1. Thikiria 5.0 1.50 10.00
2. Kheda phadpur 10.50 - 1.00
3. Darjapur 1.50 - 4.00
4. Pattisalesingh 2.50 1.50 5.00
5. Sultanpur 2.50 1.50 3.00
II. G.P. PILODI
1. Pilodi 7.00 1.50 10.00
2. Khedi 2.00 - 5.00
3. Heengi 10.00 - 6.00
III. G.P. PANCHOLI
1. Pancholi 3.00 - 10.00
2 Kherla 5.00 - 8.00
3 Murlipur 10.00 - 5.00
IWMP-I, BLOCK-SIKRAI, DAUSA 2-4
S.N. Name of Village Existing Area under Horticulture Existing Area
under Fodder Vegetable Orchard
IV. G.P.PIPALKI
1. Sikri 15.00 1.50 7.50
2. Dhulkot 2.00 4.00 8.00
V. G.P. KALWAN
1. Kalwan 11.50 2.00 10.00
2. Giladi 2.50 0.50 5.00
3. Padli Barh 1.50 0.50 3.00
VI. G.P. ACHALPURA
1. Achalpura 4.50 - 7.50
2. Sarundla 10.50 0.50 15.00
3. Chak Sarundla 2.00 - 4.50
4. Chandpur 3.00 1.00 3.00
5 Jhangiria 2.5 - 1.00
VII. G.P. GEEJGARH
1. Geejgarh 50.00 - 15.00
2.1.4. Existing Fodder Availability and Requirement:
The per day dry and green fodder requirement of different animals are as follows:
S.No. Animal Average Fodder Requirement per day (Kg.)
Dry Fodder Green Fodder
1. Buffalo 9 8
2. Cow (Indi.) 5 6
3. Cow (Hybrid) 7 8
4 Goat 3 4
5. Sheep 3 4
6. Camel 15 10
IWMP-I, BLOCK-SIKRAI, DAUSA 2-5
The per year requirement of green and dry fodder for different available livestock are as
follows:
S.No. Animal No. Per day requirement (Kg) Per Year requirement (Kg)
Dry
Fodder
Green Fodder Dry Fodder Green Fodder
1. Buffalo 20884 187956 167072 685453940 60981280
2. Cow
(Indi.)
832 4160 4992 1518400 1822080
3. Cow
(Hybrid)
617 4319 4936 1576435 1801640
4 Goat 5244 15732 20976 5742180 7656240
5. Sheep 2280 6840 9120 2496600 3328800
Total 219007 207096 696787555 75590040
In the project area about 60 percent of the required fodder is produced. The cultivator has to
bring 40 % of the fodder from outside. The cultivators bring only dry fodder from other area.
The green fodder gives about 30 percent of dry matter. So to calculate the net quantity of
fodder requirement, 30 % of green fodder has been added to dry fodder. The total
requirement, production and purchase quantity of fodder after converting green fodder into
dry fodder for one year are as follows:
S.No. Calculation of Requirement of Dry Fodder for one year
after converting Green Fodder into Dry Fodder
Total Production of
Dry Fodder (Kg)
Total Requirement
(Kg)
Quantity Required to be
purchased (Kg)
1. 129849170 145268595 15419425
Therefore, in the project area about 15400Ton of dry matter has to be purchased from outside
the project area.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-6
2.1.5. Milk Production:
The average Milk Production of different animals in the project area is:
Cow : 3-4 kg per Cow per day
Buffalo : 8 Kg per Buffalo per day
Goat : 2.5-4 Kg per Goat per day
2.1.6. Demography:
As per census record 2011, the village wise House Hold, Population and other details are
presented in Table 11. The Total population of the project area is 23015. The total male
population is 52 % and female Population is 48 %. The Overall SC and ST population is
19.66 % and 14.97 % respectively. The Total Household in the area is 3198.
Survey conducted in the year 2002 and subsequent orders issued by Sub Divisional Officer,
Sikrai and Chief Executive Officer, Zila Parishad, Dausa in the project area the village wise
BPL are as follows:
S.No. Gram Panchayat/Village No. of BPL
I. THIKIRIA
1. Thikiria 9
2. Kheda phadpur 31
3. Darjapur 9
4. Pattisalesingh 9
5. Sultanpur 5
II. PILODI
1. Pilodi 84
2. Khedi 16
3 Heengi 25
IWMP-I, BLOCK-SIKRAI, DAUSA 2-7
S.No. Gram Panchayat/Village No. of BPL
III. PANCHOLI
1. Pancholi 136
2. Kherla 61
3. Murlipur 66
IV. PIPALKI
1. Sikri 110
2. Dhulkot 53
V. KALWAN
1. Kalwan 175
2. Giladi 39
3. Padli Barh 35
VI. ACHALPURA
1. Achalpura 49
2. Sarundla 211
3. Chak Sarundla 21
4. Chandpur 67
5. Jheejhan 36
6. Jhangiria 29
VII GEEJGARH
1. Geejgarh 326
Total 1602
IWMP-I, BLOCK-SIKRAI, DAUSA 2-8
2.1.7. Infrastructure Facilities Available:
The Details of infrastructures in the project area are as follows:
S.No. Parameters Status
1. No. of Villages connected to the
main road
All the 28 villages of project area is connected to
main road. The nearest railway station is Bandikui.
2. No. of Villages provided with
electricity are provided with
electricity
All villages are provided with electricity
3. No. of Educational Institutions Primary/Midle
54
Secondary
2
Hr. Sec.
3
Voc.Inst.
0
4. No. of Villages with access to
primary health Centres
1,Geejgarh
5. No. of Villages with access to
Veterinary Dispensary
In 01 villages Veterinary Dispensary is available
6 No. of villages with access to post
office
All the villages are covered with PO. Main post
office is at Sikrai
7 No. of Villages with access to
Market / Mandis.
All the villages are covered with market / mandis.
The main market is at Bandikui and Dausa
8. Anganwadi Centres All the villages have Anganwadi Centres.
9. Nearest KVK DAUSA
10. No. of villages with access to Agro
Industry
-
11. Total Quantity of Surplus Milk 66800 Kg in Project Area
12 No. of Milk Collection Centres 17 No.
13. Cooperative Society
14. NGO’s
15. Credit Institutions SBBJ SIKRAI, UCOBank Manpur,
16. IT Center All the Gram Panchayat would have IT Center
(MGNREGA scheme)
IWMP-I, BLOCK-SIKRAI, DAUSA 2-9
2.1.8. Mahatma Gandhi National Rural Employment Guarantee Act Status:
In the block, MGNREGA is major scheme which is being implemented in the project area. In
the project area, Gram Panchayat wise details of number of card holder are as follows:
S.No. Gram Panchayat Village No. of Card Holders
1. THIKIRIA Thikiria 362
Kheda phadpur 136
Darjapur 57
Pattisalesingh 74
Sultanpur 21
Sub Total 650
2. PILODI Pilodi 296
Khedi 90
Heengi 105
Sub Total 491
3. PANCHOLI Pancholi 360
Kherla 165
Murlipur 183
Sub Total 708
4. PIPALKI Sikri 300
Dhulkot 222
Sub Total 522
5. KALWAN Kalwan 623
Giladi 115
Padli Barh 174
Sub Total 912
6 ACHALPURA Achalpura 168
Sarundla 444
IWMP-I, BLOCK-SIKRAI, DAUSA 2-10
S.No. Gram Panchayat Village No. of Card Holders
Chak Sarundla 63
Chandpur 138
Jhangiria 151
Sub Total 964
7. GEEJGARH Geejgarh 1686
G. Total 5933
2.1.9. Land Holding Details:
The land holding details i.e irrigated and rainfed for large, small and marginal farmers is
enclosed at Table 12.
2.1.10. Other Development Schemes in the Project Area:
The Mahatma Gandhi National Rural Employment Guarantee Act 2005 is the main scheme
which is being implemented in the project area. Other schemes are implemented through
Agriculture Department, ICDS, Animal Husbandary, PHED etc. People of the area are
benefited through these schemes.
2.2. Technical Features:
The various technical features of the area are as follows:
2.2.1. Collection of Revenue Record:
For all the villages of the project area the revenue map and details of cultivators/revenue
record/ Jamabandi have been collected from revenue department.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-11
2.2.2. Maps of the Area:
The Natural Resource Management component requires scientific and technical data. As per
Common Guidelines-2008, the detailed project report is to be prepared with complete GIS
and Remote Sensing application. Therefore, in the context the State Remote Sensing
Application Center (SRSAC), Jodhpur has been directed by department to prepare the various
thematic layers i.e. present land use, land cover, topographical details, slope groups, ground
water status, contour line, macro and micro boundary of the project area on 1:10,000 scale.
The SRSAC has submitted all the above required maps.
2.2.3. Slope Details of Area:
The proposed area includes hills. The area in various slope groups of the proposed water shed
area is as follows:
S.No. Slope Percentage Area in hectares
1. 0 to 2 % 1500
2. 3 to 6 % 3005
3. 6 to 15 % 450
4 >15 % 53
The SRSAC Jodhpur has generated the map (MAP 2), showing the slope groups 0–1 %, 1-3
%, 3–5 %, 5-10 %, 10-15 %, 15–35 %, 35–70 % and >70 %.
2.2.4. Water Budgeting:
To propose the total number of water harvesting structures, it is necessary to do water
budgeting of the area i.e. how much total run-off is available, out of which how much is being
already stored in existing structures and how much balance is available for storage. As per
guideline, maximum 75 % of balance available run-off is to be stored and 25 % of balance
available run-off is to be allowed to flow in the drainage line.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-12
In the proposed area, the various water harvesting structures have been constructed. The
surface runoff has been stored in the structures. In the area about 61 structures have been
constructed.
For water budgeting, the area is calculated and divided in following three groups:
Good Catchment : Where runoff is maximum and infiltration is minimum like hillocks,
plateau etc
Average Catchment : Cultivated land, forest land with vegetation
Bad Catchment : Where runoff is minimum and infiltration is maximum e.g. sandy soil
For estimation/water budgeting the proposed water shed area has been divided as follows:
Good Catchment : 1700 ha
Average Catchment : 2200 ha
Bad Catchment : 1014 ha
Average Annual Rainfall for the block is 515mm (20.27 inch)
By interpolation method the proportion of estimated runoff of 20.27 inch rainfall have been
calculated from Strange’s Table as follows:
Monsoon Rainfall
in inches
Yield of Runoff from Catchment (MCft/sq. mile)
Good Catchment Average Catchment Bad Catchment
21 inch 7.855 5.891 3.927
22 inch 8.842 6.631 4.421
For inch 0.987 0.740 0.494
For 0.89 inch 0.88 0.66 0.44
For 21.89 inch 8.735 6.551 4.367
Note : 1 MCft/sq. mile = 1000000 * 0.0283/258.99 = 109.271 cum /ha
(1 Cft = 0.0283 cu m, 1 sq. mile = 258.99 ha)
IWMP-I, BLOCK-SIKRAI, DAUSA 2-13
A. Calculation of Expected Yield
Type of
Water Shed
Area of Water Shed
(ha)
Factor Expected Yield
(cu m)
Good 1015 8.735 * 109.271 = 954.482 968799.23
Average 1400 6.551 * 109.271 = 715.834 1002167.600
Bad 2592 4.367 * 109.271 = 477.187 1236868.70
Total (A) 3207835.53
B. Present Storage By Existing Structure
S.No. Name of Structure No Storage Capacity
(cum)
1. Talai 65 615000
2. Anicut 8 105000
3. Local depression 25 585000
Total (B) 1305000
Balance Runoff (C) = Expected Yield – Present Storage
C = 3207835.53 – 1305000= 1902835.35 cu m
About 75 % of balance runoff may be stored by constructing new structure
0.75 * C = 1427126.647 cu m
Proposed New Structures:
S.No. Name of Structure No./length Storage Capacity
(cum)
1. Anicut/Structures 250Nos. 31135
2. Contour bunds 97687 m 1221087.5
Total 1252222.5
For Contour Bunding:
Area : ½ * 0.50 * 50 = 12.5 sqm
For 97687 m, total Quantity/capacity = 1221087.5 cum
For WHS:
Average Capacity for 67 Structures : ½ *0 50 * 20 * 65 = 325 cum (For 1 Structure)
IWMP-I, BLOCK-SIKRAI, DAUSA 2-14
For 67 Structures = 21775 cum
Average Capacity for208 Structures : ½*0.45 * 4 * 50 = 45 cum (For 1 Structure)
For 208 = 9360 cum
2.2.5. Soil Profile and Soil Fertility Status:
The major soil classes of the area are sandy loam and loam. The project area in the major soil
classes are as follows:
S.No. Major Soil Classes Area in hectares
1. Sandy Loam 2875
2. Loam 2133
The average soil fertility status i.e. N, P, K, Micronutrients in the watershed project area are:
N 50-70 Kg/ha
P 20-30 Kg/ha
K 10-15 kg/ha
Micro Nutrients PPM 100-500
2.2.5. Climatic Details:
The Agro climatic Zone of proposed watershed area is III A. The average annual rainfall of
the block is 556 mm. The Year Wise Annual Rainfall for the last 10 yr is as follows:
Year wise annual rainfall in mm
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
(upto Sept.)
585 826 695 463 385 461 388 302 839 327 366
IWMP-I, BLOCK-SIKRAI, DAUSA 2-15
The average annual rainfall of the block is693.22 mm. The average monthly rainfall of the
block is as follows:
S.No. Month Rainfall
(mm)/Duration
1. June 52 (6 days)
2. July 110 (12 days)
3. August 180 (15 days)
4. September 24 ( 4 days)
The maximum and minimum temperature of the block is as follows:
S.No. Season Maximum Minimum
1. Summer 46 oC 35
oC
2. Winter 26 oC 4
oC
3. Rainy 36 o
C 26 oC
2.3. Problems, Demand and Scope for development:
2.3.1. Natural Resource Management:
While socially surveying the area, it was realized that various water harvesting structures
mostly talai’s have been constructed in the area for storing the water. But due to non
availability of outlets/waste weirs the water was released by cutting the banks. The main
problem of the area is availability of stored water. For further development, it has been
planned that all the structures will be provided with waste weirs, so that the water can be
stored up to the design level without any fear.
During the rainy season it was found that the rain water from the higher areas flows down and
spread in the lower area and damaging the fields. As per need and suggestions given by the
beneficiaries/public representative, the diversion channels have been proposed to convey
IWMP-I, BLOCK-SIKRAI, DAUSA 2-16
water to near by tanks. This will certainly solve the problems of the area and sufficient water
will also be stored for live stock and will help in recharging the nearby wells.
The agriculture land of the area is affected by sheet erosion and forming the rills/gullies. The
problem can be solved by bunding the fields. Therefore to protect the land, the main thrust is
given on contour bunding with proper outlets.
2.3.2. Agriculture and Horticulture Productivity:
In the watershed area the production of Agriculture and Horticulture Plants are not to that
extent due to lack of improved variety and techniques. The village wise Agriculture
production of different crops grown in Kharif/Rabi seasons of the proposed watershed area is
shown in Table13. From the village wise productivity of each crop, the average productivity
of Gram Panchayat has been calculated. Comparison of Average Productivity of Gram
Panchayat with District and Block and proposed productivity for major crops of Kharif and
Rabi Seasons are shown in following tables and in Figure 1 and Figure 2 respectively.
Simultaneously the proposed productivity level of different crops is also shown. The
production will be increased by introduction of new varieties and fertilizer level of different
crops. Looking to the data it is observed that the productivity of Sikrai Block for almost all
the crops are higher than the productivity of District. The average productivity in each Gram
Panchayat is less than Block’s Productivity.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-17
Gram Panchayat wise Average Productivity (Kg/ha) for Kharif Crops:
Crops Dausa District Sikrai Block G.P. THIKIRIA Proposed
Bajra 1101 1500 1425 1600
Till 400 450 420 500
Guar 900 1050 597.5 1050
Crops Dausa District Sikrai Block G.P. Pilodi Proposed
Bajra 1101 1500 1350 1500
Till 400 450 400 1850
Guar 900 1050 672.5 1050
Crops Dausa District Sikrai Block G.P.Pancholi Proposed
Bajra 1101 1500 1362.5 1500
Till 400 450 380 1850
Guar 900 1050 687.5 1050
Crops Dausa District Sikrai Block G.P. Pipalki Proposed
Bajra 1101 1500 1425 1500
Till 400 450 390 1850
Guar 900 1050 350 1050
Crops Dausa District Sikrai Block G.P. Kalwan Proposed
Bajra 1101 1500 1416.6 1500
Till 400 450 410 1850
Guar 900 1050 758 1050
Crops Dausa District Sikrai Block G.P. Achalpura Proposed
Bajra 1101 1500 1350 1485
Till 400 450 365 1850
Guar 900 1050 800 1050
Crops Dausa District Sikrai Block G.P. Geejgarh Proposed
Bajra 1101 1500 1450 1500
Guar 900 1050 710 1050
IWMP-I, BLOCK-SIKRAI, DAUSA 2-18
Gram Panchayat wise Average Productivity (Kg/ha) for Rabi Crops:
Crops Dausa District Sikrai i Block G.P. THIKIRIA Proposed
Wheat 2815 3300 2998 3500
Barley 2433 2800 3016 3600
Mustard 809 1020 1193 1545
Crops Dausa District Sikrai Block G.P. Pilodi Proposed
Wheat 2815 3300 2800 3500
Barley 2433 2800 2950 3600
Mustard 809 1020 1170 1300
Crops Dausa District Sikrai Block G.P.Pancholi Proposed
Wheat 2815 3300 2767 3500
Barley 2433 2800 2888 3600
Mustard 809 1020 1233 1395
Crops Dausa District Sikrai Block G.P. Pipalki Proposed
Wheat 2815 3300 2800 3500
Barley 2433 2800 2937 3600
Mustard 809 1020 1083 1350
Crops Dausa District Sikrai Block G.P. Kalwan Proposed
Wheat 2815 3300 2753 3500
Barley 2433 2800 2966 3600
Mustard 809 1020 1258 1400
Crops Dausa District Sikrai Block G.P. Achalpura Proposed
Wheat 2815 3300 2790 3500
Barley 2433 2800 2895 3600
Mustard 809 1020 1257 1400
Crops Dausa District Sikrai Block G.P. Geejgarh Proposed
Wheat 2815 3300 3000 3500
Barley 2433 2800 3200 3600
Mustard 809 1020 1350 1450
IWMP-I, BLOCK-SIKRAI, DAUSA 2-19
2.3.3. Live Stock-gap of Fodder Availability:
The existing fodder area in the villages of proposed area is shown above. The availability of
fodder in the proposed watershed area is less. To meet the requirement, the farmers of the
area have to purchase from other places. The fodder area has to be increased to reduce the
demand.
2.3.4. Livelihood and Micro enterprises:
The people of the area are dependent on Agriculture. In the proposed area the landless
families are fully dependent on work. After introduction of NREGA, these families are getting
job in the area. But it is not to the extent to increase the livelihood. For development of their
livelihood, the various meetings were organized to know their interest and skills. According
to social survey conducted in different villages of the project area, different individual and
group works/activities like Ara Tari, Masala Udhyog, Tomato Sauce Preparation, Carpentry,
Mobile Repairing, Motor Cycle Repairing, Computer Hardware/ Software work and Compost
Pit/Vermi compost were identified. According to their interest homogeneous groups have
been made. The main thrust was given for land less persons.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-20
CHAPTER – III
3.1 Preparatory Phase activities:
The main objective of the preparatory phase is to create appropriate mechanism for adoption
of participatory approach with the help of watershed development team. To establish the
credibility of WDT team and to create a rappo with the villagers the entry point activities have
been executed.
3.1.1. Entry Point Activities:
To find the urgent need of the local communities, the Gram Sabhas have been conducted at
each Gram Panchayat. So that different works could be identified according to their need.
The main theme of Entry Point Activities is to establish credibility of the Watershed
Development Team and create a rapport with the village community. After identifying the
different works in Gram Sabhas, the following works were executed:
S.No. Gram Panchayat Details of works
Name of works Quantity
I. Thikiria 1 Hand Pump 1 No.
2 Water tank with Khel & Soak Pit 1 No.
II. Pilodi 1 Hand Pump 2 No.
III. Pancholi 1 Hand Pump 3 No.
IV Pipalki 1 Solar light 1 No.
2 Hand pump 3 No.
3 Hand pump with Soak Pit 2 No.
V. Kalwan 1 Solar light 30 No.
VI. Achalpura 1 Water tank with khel & Soak pit 1 No.
2 Hand pump 2 No.
3 Hand pump with Soak Pit 1 No.
VII Geejgarh 1 Boundary Wall 1 No.
2 Hand pump 2 No.
3 Khel and Soak Pit 3 No.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-21
3.1.2. Capacity Building:
Capacity building is an important aspect for the successful implementation of watershed
development programmes. The relevant training programme will be organized for all the
functionaries involved in water shed development. It will be ensured at every level that a
majority of the members of SHGs/UGs would be given basic training involving skill up
gradation and orientation on the technical and organizational aspects.. Besides training on
application on Remote Sensing Technology for generating database for watershed
development will be included in the training programme. It has been finalized that the
training will be organized by WDT members with the help of local officials of the technical
departments. SHGs & UGs would also be taken for visits to Research Stations, demonstration
of successful technologies that are relevant to them.
For participatory approach, water shed committee, user groups and self help groups have been
formed at each gram panchayat level. During the phase, the watershed development team (4
members) which is also constituted and engaged in the project earlier will facilitate. The
Gram Panchayat wise details of user groups, self help groups and water shed committee is
shown in Annexure I to III. The capacity building of these different stakeholders on
institutional and work related aspects are important part of the project.
3.1.3. PRA Exercise:
Participatory Rural Appraisal (PRA) is one of the most important exercise in Watershed
Development Projects before preparation of Action Plan.. For the preparation of detailed
project report Participatory Rural Appraisal exercise is very important part. The village wise
PRA have been conducted with the help of WDT members. For each village separate maps
have been prepared, showing all special features such as nallas, pasture land, roads, dhani’s
etc. The works have been identified according to beneficiaries need. The proposed works
have been marked on these maps.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-22
3.2. Natural Resource Management (NRM):
With the help of WDT, on the basis of the information generated from the bench mark survey
of the watershed area and detailed PRA exercise, the detailed watershed development plan for
each Gram Panchayat have been prepared. Watershed treatment/development plan have been
prepared for all the arable and non arable land including degraded lands, government and
community lands and private lands.
3.2.1. Conservation measures for arable lands:
The main problem of the area is the low and erratic rainfall. The conservation measures
meant to reduce or prevent sheet erosion. The important principles to be kept in view while
planning measures for proper conservation of water are increasing the time of concentration
and thereby allowing more runoff water to be absorbed, intercepting the long slope into short
ones and protection against damage due to excessive runoff. Bunding is the most effective
and widely practiced field measures for controlling or preventing erosion. In broader way it
can be defined as series of mechanical barriers across the land slope to break the slope length
and also to reduce the slope percentage. Different types of bunds are contour bund, side
bunds, lateral bund, graded bunds.
a. Contour Bund: Contour bunds are constructed along the contours. For the area having
slope less than 6 percent and flatter lands with scanty /erratic rainfall contour bund is
practiced to intercept the runoff by embankment whose ends may be closed or open to
conserve moisture as well as to reduce the soil erosion. As per past experience the
contour bunds can be adopted on all types of relatively permeable soils except the clayey
or deep black cotton soils. The main criterion for spacing of bunds is to intercept the
water before it reaches the erosive velocity. The most important factor of it is slope,
cropping pattern, soil and conservation practice adopted. While planning of contour bund
few things, which should be considered are: area is bifurcated according to slope, if
distance between two bunds is more than additional bund should be provided in between
IWMP-I, BLOCK-SIKRAI, DAUSA 2-23
them, lateral bunds/hooking should be extended up to the submerged length at both ends
and vertical interval may be adjusted according to field boundaries.
Side bund: bunds constructed at extreme ends of the contour bund, which are running
along the slope and up to the submerged length.
Lateral bund: bund constructed along the slope in between two side bunds, to prevent
concentration of water along one side and to break the length of contour bund.
b. Waste weirs: In order to protect the contour bunds from breaching and the standing crop
from damage, masonry outlet structures which can drain away excess water, are
constructed. The proper outlet/waste weirs are provided in the contour bunds alternate, to
avoid gully formation and also to increase the travel path. Generally waste weirs are
constructed at depressions with the crest of their body walls constructed at 0.3 m above
the contour.
c. Gully control structure: In arable lands, where small rills/gullies have been formed, then
the earthen bunds are constructed at regular intervals.
d. Diversion channels: Soil conservation measures are implemented on a whole catchment
or watershed basis. In case if the watershed area falls below the unprotected area or hilly
area from which uncertain amount of water comes and entered in the area, then the
diversion channel is excavated to intercept the runoff from the area situated above and to
conduct it safely to outlet.
3.2.2. Conservation measures for non arable lands:
The area which is unsuited to cultivation for agricultural crops and limit there use largely to
pasture, forest requires the conservation measures. These waste lands have a great potential
for producing fodder, fuel, fiber etc. To protect these lands from further degradation suitable
soil and water conservation measures supplemented with proper afforestation is required.
a. Staggered trenches: Staggered trenching is excavated trenching of shorter lengths in a
row along the contour with interspace between them. In the alternate row, the trenches
IWMP-I, BLOCK-SIKRAI, DAUSA 2-24
will be located directly below one another. The length of the staggered contour trenches
will be 3 to 3.65 m with interspaces between them in the same row of about 2.4 to 3 m.
b. Ditch cum bund: In the watershed area, the available pasture land will be protected by
ditch cum bund. From the excavate soil of the trench the bund will be prepared inside the
area along the trench, so that the animals can not step up from the trench and enter the
area. From the point of view of cost and theft, the barbed wire fencing and stone fencing
is avoided.
c. Pasture development: To mitigate the fodder requirement, in every gram panchayat of
the project area, at least one pasture development is proposed. The encroachment is the
main problem of pasture development. The pasture land will be developed by fencing the
area by ditch cum bund, constructing the staggered trenches across the slope according to
availability, gully control structures (loose stone check dam, earthen bunds), construction
of small talai/ponds, planting of different plants and grasses in between staggered
trenches. The development of grasses ultimately reflected in the runoff and soil loss. The
grass development action comprises of direct dispersion, interception, energy dissipation
and evaporation of falling rain drops.
3.2.3 Drainage line treatment:
The drainage line treatment is very important part of the project.
a. Gully control structures: Gully control structures consist of constructing bunds of
suitable dimension across the nala or gullies to hold the runoff water. Depending upon the
slope of the gully, these bunds are constructed in the series. The main thumb rule is the
bottom of the structure should coincide with the top of the downstream one. The
temporary storage of runoff against these bunds carries deposition of silt and the water is
drained off in a controlled manner. The impounding of water facilitates the percolation of
water, which otherwise will flow with intense velocity. The water released from the
bunds will be free from silt and velocity to erode. Before it can acquire erosive velocity, it
will meet the next bund below in the catchment.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-25
b. Loose stone check dam: The gully control structure will be constructed by locally
available stone without any binding material. So these structures are called Loose Stone
Check Dam. The gullies will be plugged by stone with height not more than 1 m with up
stream slope, nearly vertical and down stream slope 1.5:1. The depth of foundation will
be kept about 0.4 m and with about 0.6 m inside the natural ground on each side to
prevent flood water out flanking the structure.
c. Concrete and masonry check Dam: In some places where vegetative measures and
simple practice alone are inadequate to handle the concentration of water, permanent
masonry structures structure are provided. In the project area with the loose stone check
dam these permanent masonry gully control structures have been proposed.
d. Bank stabilization: The bank stabilization is very important part of controlling the table
lands. The water from the side area/table land comes to the gully, which widen the gully.
To protect the nalla/gully from widening and protecting the side land converting into the
gullies, the marginal bund will be made on each side of the nalla. The loose stone check
dam and masonry structures will be constructed at proper places for safe disposal of
surplus water. In some places of the side of nalla, loose stone pitching have been
provided to protect the sides from scouring.
e. Water harvesting structures Anicuts/Tanks: With the introduction of NREGA, the
ponds/ talai’s have been constructed. Therefore small thrust has been given on
construction of ponds. The village wise position of existing anicut and Talai are as
follows:
S.No. Gram Panchayat/ Village Anicut Talai
I. THIKIRIA
1. Thikiria - 1
2. Kheda phadpur - 1
3. Darjapur - 1
4. Pattisalesingh - 1
5. Sultanpur - -
IWMP-I, BLOCK-SIKRAI, DAUSA 2-26
S.No. Gram Panchayat/ Village Anicut Talai
II. Pilodi
1. Pilodi - 1
2. Khedi - 1
3 Heengi - -
III. Pancholi
1. Pancholi - 2
2. Kherla - 1
3. Murlipura - 2
IV. Pipalki
1. Sikari 1 1
2. Dhulkot - 1
V. Kalwan
1. Kalwan 1 1
2. Gilari - 2
3. PaldiBarh - 2
VI. Achalpura
1. Achalpura 1 1
2. Chak Sarundla - 2
3. Sarundla 2 2
4. Chandpur - 2
5. Jhangira 1 2
VII. Geejgarh
1. Geejgarh 2 8
Total 8 35
IWMP-I, BLOCK-SIKRAI, DAUSA 2-27
3.3. Production System and Micro Enterprises:
3.3.1. Production measures for arable lands:
To get the more benefit from agriculture crop, it is very important to decrease the cost of
cultivation and increase the production. To decrease the cost of cultivation, it is necessary to
use complete available land for cultivation, use of latest implements so that time and cost is
reduced. Good agriculture management by taking more than one crop in a year can also
increase the production. Optimum quantity of fertilizer, insecticides and pesticides should be
used. The reduction of chemical fertilizer will also increase the production.
For increasing production of crop, water management also plays an important role. The water
should be used according to its quality and also crop should be irrigated according to
need/requirement. The practice of Drip and Sprinkler irrigation will lead to optimum
utilization of water.
In the State and Centre Sector schemes, for improvement in production level of different
crops and minimize cost of cultivation, various schemes are organized by Agriculture/
Horticulture Department. The various schemes are:
a. Free seed minikit distribution: Seed minikits of newly released varieties are distributed
to small and marginal farmers for 0.1 to 0.2 hectare area with the purpose to increase in
productivity of cereals, pulses and oilseeds and to increase Seed Replacement Rate by
certified seeds. Minikits are distributed in Kharif season are improved hybrid varieties of
Bajra, Guar and Groundnut, whereas in Rabi Season are Wheat, Barley, Gram and
Mustard.
b. Crop demonstration: Crop Demonstrations are layout for adoption of full package of
technology practices in rural areas. The demonstration are organized for 0.4 hectare at
each farmers field which have adequate irrigation facilities and take interest to show all
technology practices recommended by Agriculture Department. The seed of improved
quality are provided at 50 % cost to the farmers through RSSC/NSC and other inputs like
fertilizers and plant protection chemicals are provided through KVSS or GSS on payment
IWMP-I, BLOCK-SIKRAI, DAUSA 2-28
of 50 % on total cost of all inputs up to Rs. 2000 per demonstration. In Kharif season
demonstration are taken for Guar, Bajra and in Rabi season demonstration are taken for
wheat, Barley and Mustard.
c. Certified seed distribution: Certified seed from RSSC/NSS are distributed in the area to
improve SRR and ultimately increase in productivity of crops. The main aim is to
increase in production level of different crops in scarce condition and to adopt dry farming
practices by farmers by using high yielding varieties instead of local varieties. This is
taken through KVSS/GSS and private dealers.
d. Subsidy on pipeline: Presently the irrigation methods used by farmers are not so
scientifically as flow system in which wastage of water are very high. The subsidies are
given to the farmers on purchasing ISI-approved HDPE/PVC pipe line of 63 mm to 90
mm diameter. The subsidies are given to all categories of farmers at the rate of Rs. 18.75
per meter up to 800 meter per farmer.
e. Subsidy on gypsum: To all categories of farmers, on the basis of soil testing report for
reclamation of alkaline soils, the 50 % subsidy are given on total cost of Gypsum.
Gypsum subsidy should also be given to the farmers growing Wheat, Pulses and Oilseed.
f. Establishment of farmers field school (FFS): The farmers Field School are to be
established on the compact block of 5 demonstration each of 0.4 hectare. In the FFS out
of 5 demonstration farmers 25 other farmers are to be included. The total of 30 farmers
group which have interest to learn full scientific package of practices of crop production.
Each FFS have five training days: before sowing of demonstration crop; after sowing and
germination of demonstration crops; at the time of irrigation and weed control; at grain
filling stage of crop: and at maturity stage of crop. Training is given by Agriculture
Officer, Scientist and Lecturer. Farmers problem are given to research stations and
improved practices of scientific Agriculture are given to the farmers.
g. Soil and water testing: Before every crop season like Kharif and Rabi, soil and water
testing are to be done for evaluating the actual fertility position of field and requirement of
fertilizer for irrigation. So that fertilizer quantity and quality are used as per
recommendations given by laboratory for taking maximum production level in particular
field and crop. Soil health card are given to the farmer having all recommendation of
fertilizer for a whole year as they take all crop in Kharif and Rabi season.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-29
h. Subsidy on plant protection equipments: 50 % subsidy are given to all categories of
farmers on Plant Protection equipments like Knapsack Sprayer, Dusters, Foot Sprayer and
Power Operated Sprayers of ISI mark and approved qualities.
i. Subsidy on Agricultural Implements: The subsidy are given to all categories of farmers
on purchasing improved and new Agriculture Implements, 25-50 % subsidy are given
according to quality of implement like hand operated hoeing implement, bullock drawn
bund farmer, tractor drawn seed drill machine, chaff cutter, harrows, 2 and 3 disc plow
having 25 % subsidy whereas three row bullock drawn seed drill, tractor drawn seed cum
fertilizer drill, etc have 50 % subsidy.
j. Horticulture (National Horticulture Mission): Subsidy are given on inputs like seed,
fertilizers and plant protection chemicals for growing spices and medicinal crops in the
National Horticulture Mission by Horticulture Department. Such demonstrations are
layed out in Methi, Chilli and Allovera crops. 50 % Subsidies are given on total cost of
input used in the demonstration.
k. Subsidy on sprinkler set: For the effective irrigation in the sandy soils the sprinkler
system were recommended to the farmers. From 0.5 to 5.0 hectares land holding, subsidy
of 50 % on the cost of sprinkler set are given. Sprinkler set model vary according to land
like for 1.0 hectare land there are 30 HDPE ISI approved pipe of 6 meter long and 3 meter
pipe along 5 nozzle set and other accessories. Subsidy is given on the sprinkler set is 50
% or Rs. 7150, which ever is less. For 5.0 hectare land holding farmer, can purchase 60
pipes of 6 meter and 15 nozzle set with accessories having subsidy 50 % or Rs. 15500/-
which ever is less.
l. Subsidy on drip irrigation: The drip irrigation is most effective and water saving
irrigation method. Drip irrigation system can be installed for fruit orchard and for
vegetable farming from 0.5 to 5.0 hectare land area. The subsidy is given up to 70 % of
the total cost up to Rs. 23000 per hectare in orchard plantations and Rs. 114000 per
hectares for vegetable farming.
m. Subsidy on fruit orchard plantation: Subsidy are given to the farmers for establishment
of a new orchard systematically and in scientific way. There are 6 fruit plant can be taken
in NHM, which are Anwla, Ber, Papaya, Citrus, Beel and Anar. The grafted seedlings are
provided to the farmers on 75 % subsidy after which 75 % subsidy are given for fertilizer,
IWMP-I, BLOCK-SIKRAI, DAUSA 2-30
Plant Protection Chemicals and for digging pits for planting. This subsidy varies from Rs.
22000 to 40000 per hectares for different fruit crops. Drip set subsidy is given separate
for establishment in orchard.
n. Establishment of Nursery: Subsidy is given for establishing a module nursery in
scientifically and propagation of fruit plant and sold to the farmers. 50 % on total cost,
subsidies are given, which varies from Rs. 1.5 to 9.0 lacs for 4.0 hectares land area.
o. Training for horticulture works: The training are given to youth farmers interesting to
learn horticulture works like grafting, budding and other horticulture works. Three months
to one year training programme is held, according to the farmers choice and interest. The
expenditure of the training is borne by horticulture department through National
Horticulture Mission. The Krishi Vighyan Kendra) of each district, organizes the training
programme.
p. Vermicompost: Vermicompost is an organic manure (bio-fertilizer) produced as the
vermicast by earth worm feeding on biological waste material; plant residues. This
compost is an odorless, clean, organic material containing adequate quantities of N, P, K
and several micronutrients essential for plant growth. Vermicompost is a preferred
nutrient source for organic farming. It is eco-friendly, non-toxic, consumes low energy
input for composting and is a recycled biological product. In each Gram Panchayat of the
project area, 10-12 farmers will be selected. They will be trained with installing the
vermicompost unit in their field.
During the project period the following targets of agriculture and horticulture activities have
been proposed:
S.No. Activity Unit Physical Target Financial Target
A. Agriculture
1. Free Seed Minitkit Distribuition Nos. 1000
2. Crop Demonstration Nos. 70 1.88 lac
3. Certified Seed Distribution Nos. 1560
4. Subsidy on Pipe Line Meter 14500 2.90 lac
5. Subsidy on Gypsum M.ton 500 3.40 lac
IWMP-I, BLOCK-SIKRAI, DAUSA 2-31
S.No. Activity Unit Physical Target Financial Target
6. Establishment of Farmers Field Nos. 50 2.0 lac
7. Soil and Water Testing and
Distribution of Soil Health Card
Nos. 1400
8. Subsidy on Plant Protection
Equipment
Nos. 110 0.55
9. Subsidy on Agriculture Implement No. 50 2.25
B. Horticulture
1 Medicinal Plant (Alovera) Hect. 10
2 Subsidy on Sprinkler Nos. 95 6.75 lacs
3 Subsidy on Drip Irrigation No. 30 30.00 lacs
4. Subsidy on Fruit Orchard Hect. 25 5.68 lacs
3.3.2. Production measures for non arable lands:
In government pasture land is developed by fencing the area by ditch cum bund and
constructing the staggered trenches. In between the trenches grasses are grown and on down
stream side of the trenches the forestry/fuel plants are grown. Along the ditch cum bunds the
forestry plants are also grown. In the area various plants like Khejdi, Ardoo, Shessam etc are
grown.
The fuel plants on the bunds of the private lands are also grown with the consultation of the
owner, so that cultivators can also get the fuel for his use. Similarly on the bunds the grasses
are also grown so the beneficiaries can have the fodder for the livestock.
3.3.3 Livelihood activities particularly for asset less person:
In the project area according to the interest and need livelihood activities will be followed. In
individual livelihood activity training of Masson, Motchi, Carpentry, Tailoring, Bike /Cycle
repairing etc work will be taken up so that their lives could be improved. The training
programme of computer Hardware/Software, Mobile repairing work will also be planned
according to the interest and education level of the educated young generation, so that with
IWMP-I, BLOCK-SIKRAI, DAUSA 2-32
the seasonal agriculture income of their family, they can supplement the income during non
agriculture season.
In every gram panchayat of the project area, the self help groups of land less persons have
also been formed. These groups will be trained according the their interest on different
activities like Ara Tari, Tomato Sauce Preparation, Honey Bee Production, Compost Pit,
Pottery etc, so that their livelihood can be increased.
The groups will be trained on agriculture based activities like compost pit, vermi compost,
pasture development etc according to their interest, so that they can prepare the product and
can use on their own need and can sell surplus.
At the time of PRA, the people of the area have been acquainted with livestock based
activities like milk collection booth, dairy, poultry etc.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-1
CHAPTER IV
4. Technical Designs and Estimates for Proposed Activities:
4.1. Design of Contour Bunds:
For rolling and flatter lands, with scanty or erratic rainfall contour bund is practiced to
intercept the runoff flowing down the slope, to conserve the moisture as well as to reduce soil
erosion. To remove the excessive runoff, resulting from high intensity storm, surplussing
arrangements have been provided wherever necessary.
Spacing of Contour Bunds:
Contour bunds can be adopted on all type of relatively permeable soils except the clayey or
deep black cotton soils. For planning the bunds it is necessary to know how far these bunds
should be installed. The main criterion for spacing of bunds is to intercept the water before it
attains the excessive velocity. The most important factor of it is slope, soil, rainfall, cropping
programme and conservation practices. The vertical interval between the bunds has been
calculated by following formulae:
V.I. = 0.305 (XS + Y)
Where
V. I. = Vertical Interval (m)
X = Rainfall factor (as per following table)
Y = Infiltration and Crop Cover factor (as per following table)
S = Slope (%)
Value of X, the Rainfall Factor
Rainfall Value of X Annual Rainfall (cm)
Scanty 0.8 64
Moderate 0.6 64-90
Heavy 0.4 Over 90
Source: Manual of Soil & Water Conservation Practices, Gurmel Singh, etc.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-2
Value of Y, the Infiltration and Crop Cover Factor
Intake Rate Crop Cover during
Erosive Period of Rains
Value of Y
Below Average
(e.g. black soils)
Low Coverage 1.0
Average or above Good Coverage 2.0
One of the above
factors favourable and
the other unfavourable
1.5
Source: Manual of Soil & Water Conservation Practices, Gurmel Singh, etc.
Generally the Contour Bunds are made on same elevation, i.e. on contour and therefore, the
grade is zero. Due to field boundaries, it is not possible to construct the bunds exactly on
contours. The bunds will be constructed by adjusting the field boundaries. The horizontal
interval between the bunds has been calculated by following formulae:
H.I. = V.I. X 100
Slope (%)
The height of impounding is calculated from following formulae:
He = (Re x V.I.)1/2
(50)1/2
Where
He = Depth of impounding near the bund (m)
Re = 24 hours rainfall excess (cm)
To the depth of impounding, depth of flow over the waste weir and free board is added. Then
with the help of these the cross section of bund has been calculated.
With the help of elevation data of the area, water shed area is divided into different slope
groups. The slope group wise map (Map 2), showing the different categories of slope has
been prepared by SRSAC, Jodhpur.
IWMP-I, BLOCK-SIKRAI, DAUSA 2-3
From the above formulae the Horizontal and Vertical interval and length of bunds per hectare
have been calculated for different slope groups.
Calculation of V.I. and H.I.:
X = 0.8, Y = 1.5 (From above Tables)
S.No. Slope Group
Range
Average Slope,
S (%)
V.I. (m)
0.305 (XS + Y)
H.I. (m)
V.I./S
Length per
hectare (m)
1. 0 – 1 0.50 0.60 120 80
2. 1-3 2.00 0.95 50 200
3. 3-5 4.00 1.50 40 245
4. 5-10 7.50 2.3 30 332
Generally the Contour bund is provided on land having slope up to 6 %. As per slope group
map generated by SRSAC, the area for different slope range has been calculated. As per
above calculated per hectare bund length, the total length of contour bund have been
estimated. Due to budget constraints and priority of other works, the length has been reduced.
The Gram Panchayat wise area according to the slope range and proposed length of contour
bund is calculated as follow:
S.No. Gram
Panchayat
Slope
Range (%)
Estimated
Area (ha)
Length per
hectare (m)
Length
(m)
Proposed
Length (m)
1. Thikiria 0 -1 190 80 15200 6080
1 -3 96 200 19200 7680
3 – 5 64 245 15680 6272
5 -10 36 332 11952 4780
Total 386 62032 24812
2. Pilodi 0 -1 146 80 11680 4088
1 -3 114 200 22800 7980
3 – 5 27 245 6615 2315
5 -10 14 332 4648 1630
Total 301 45743 16013
IWMP-I, BLOCK-SIKRAI, DAUSA 2-4
S.No. Gram
Panchayat
Slope
Range (%)
Estimated
Area (ha)
Length per
hectare (m)
Length
(m)
Proposed
Length (m)
3. Pancholi 0 -1 268 80 21440 7504
1 -3 178 200 35600 12460
3 – 5 79 245 19355 6775
5 -10 38 332 12616 4415
Total 563 89011 31154
4. Pipalki 0 -1 325 80 26000 9100
1 -3 243 200 48600 17010
3 – 5 78 245 19110 6690
5 -10 36 332 11952 4185
Total 682 105662 41070
5. Kalwan 0 -1 683 80 54640 19124
1 -3 421 200 84200 29470
3 – 5 145 245 35525 12434
5 -10 63 332 20916 7320
Total 1312 195101 68348
6 Achalpura 0 -1 277 80 22160 7756
1 -3 132 200 26400 9240
3 – 5 88 245 21560 7546
5 -10 41 332 13612 4764
Total 538 83732 29306
7.
Geejgarh 0 -1 467 80 37360 13076
1 -3 302 200 60400 21140
3 – 5 98 245 24010 8403
5 -10 65 332 21580 7553
Total 932 143350 50172
IWMP-I, BLOCK-SIKRAI, DAUSA 2-1
CHAPTER VII
7.1. Project Outcome:
By the end of the project, in the project area, it is expected that the water level in the wells
increases considerably and sufficient water for man and animal would be available in the
wells and ponds. The cropping intensity and productivity should be increased after the
completion of the project. Few parameters which are expected to be increased after the
completion of the project are as follow:
S.No Parameters Before Execution of
Project
Expected Increase after the
Completion of the Project
1. Availability of water
a. Average Water Table 250 -300 ft 150 – 200 ft.
b. Available Water in the Tube Wells Wells/ Tube Wells / Ponds
2. Agriculture/Horticulture
a. Net Sown Area (ha)
b. Net area sown more
than once (ha)
c. Production of Major
Crops:
Wheat
Barley
Mustard
Bajara
Groundnut
Guar
2845 Kg/ha
3003 Kg/ha
1237 Kg/ha
1397 Kg/ha
1284 Kg/ha
698 Kg/ha
4500 Kg/ha
4000 Kg/ha
2000 Kg/ha
2500 Kg/ha
2200 Kg/ha
1200 Kg/ha
d. Production of Rajka 33347 quintal 50288 quintal
e. Average Production of
Horticulture Plants
50 – 100 quintal 350-500 quintal
(Different types of fruits plants Mango,
Guava, Citrus, Ber, Papaya, etc)
IWMP-I, BLOCK-SIKRAI, DAUSA 2-2
S.No Parameters Before Execution of
Project
Expected Increase after the
Completion of the Project
3. Live Stock
a. Milk Production 3 – 7 kg/animal 7 – 12 kg/animal
b. Animal Diseases By regular camps, the various diseases will be reduced
4. Livelihood
a. Average income of
family by introduction
of other micro
enterprises
Rs. 2500-3000 per
month
Rs. 4000 – 5000 per month
b. SHG Groups 10 70
The various homogenous groups will be
constituted and the training of different
activities will be given, specially for
land less families.
During the project period (5-7 years), the various activities will be done. The natural resource
management activities will be done in between the project phase. The proposed NRM works
in arable, non arable land and drainage line treatment will increase the water table, production
of agriculture/horticulture crops. Similarly the livestock activities will increase the milk
production. The year wise various outcomes of the project are as follows:
S.
N.
Activity Unit Before
Project
During the Project Period
I Yr II Yr III Yr IV Yr V Yr VI Yr VII Yr
1. Engineering Structure
a. Contour Bund, CVH,
Restoration of Old
Structures, Gully Control
Structure
Hect. Nil 1500 2000 1000
b. Earth Bunds, WHS, Anicut No. Nil
IWMP-I, BLOCK-SIKRAI, DAUSA 2-3
S.
N.
Activity Unit Before
Project
During the Project Period
I Yr II Yr III Yr IV Yr V Yr VI Yr VII Yr
2. Increase of Agriculture
Production due to
construction of above
Engineering Structure
a. Rabi Season (Main Crops)
Wheat
Barley
Mustard
Qtl/ha 29.55
31.08
13.40
30
32
14
30
33
14
35
33
15
37
34
16
39
36
17
40
38
18
40-45
38-40
18-20
b. Kharif Season (Main
Crops)
Bajra
Guar
Til
Qtl/ha 11.02
6.27
5.84
12.5
7
6
12.5
7
6
14
8
7
15
8
7
18
9
8
20
10
8
20-25
10-12
8-10
3. Water Table Depth
May m. 65 65 60 58 57 55
September m. 58 58 58 56 55 53
December m. 60 60 60 58 57 56
4. Availability of Drinking
Water
Dec. Dec. Dec. Dec. Jan. Jan. March May
5. Survival of Plants
Horticulture Plants Nos. 1000 1000 1000 2500 5000 8000 10000 10000
Forestry Plants Nos. 450 450 450 1000 2500 4000 6000 6000
6. Milk Production per animal
Cow Kg 4.5 4.5 4.5 5.5 5.5 6 7 7
Buffalo Kg. 7.5 7.5 7.5 8 8 8 9 9
Goat Kg 2.00 2.0 2.0 2.0 2.5 3 3 3
7. Control on Migration No. Nil 10 % 30 % 40 % 70 % 80%
A. PROJECT FUND
PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN
I. ADMINISTRATIVE COST
(10%)
(Honararium of WD,Secretary of
WC, Office Expenses, Jeep Hiring
etc.)
12.019 12.019 12.019 12.019 12.019 60.096
II MONITORING (1%) 1.202 1.202 1.202 1.202 1.202 6.010
III EVALUATION (1 %) 2.003 2.003 2.003 6.010
13.221 13.22112 15.224 15.224 15.224 72.115
W/S PREPARATORY PHASE
IV ENTRY POINT ACTIVITY (4
%)
(Solar Light, Water Tank, Khel,
Soak Pit, Handpump, Plateform,
Safety Wall, Rain Water
Harvesting Structure etc.)
19.500 4.538 24.038
V TRAININGS & CAPACITY
BUILDING (ICB) 5 %
6.0096 6.0096 6.0096 6.0096 5.644 30.048
VI DETAILED PROJECT REPORT
(1 %)
3.950 1.045 1.015 6.010
29.460 11.593 7.025 6.010 5.644 60.096
WATERSHED WORK PHASE
VII NATURAL RESOURCE
MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION
WORK
CHAPTER -VI
ANNUAL ACTION PLAN
TOTAL
THIRD YEAR
2010-11 2012-13S. N. NAME OF ACTIVITY
FIRST YEAR
Unit 2011-12
SUB TOTAL (I+II+III)
SUB TOTAL (IV+V+VI)
2013-14 2014-15
SECOND YEAR FOURTH YEAR FIFTH YEAR
1 IWMP I, BLOCK SIKRAI, DAUSA
PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN
TOTAL
THIRD YEAR
2010-11 2012-13S. N. NAME OF ACTIVITY
FIRST YEAR
Unit 2011-12 2013-14 2014-15
SECOND YEAR FOURTH YEAR FIFTH YEAR
i. Earthen Bund TYPE "A"(SLOPE 0-
1%)
meter 7380 6.05201 7380 6.05201 7381 6.05201 7381 6.0520129522
24.20804
ii. Earthen Bund TYPE "B"(SLOPE 1-
3%)
meter 9158 10.62386 9158 10.62386 9159 10.62386 9159 10.6238636634
42.49544
iii. Earthen Bund TYPE "C"(SLOPE 3-
5%)
meter 4546 8.50149 4546 8.50149 4546 8.50149 4547 8.5014918185
34.00595
iv. Earthen Bund TYPE "D"(SLOPE 5-
10%)
meter 2691 6.88960 2691 6.88960 2691 6.88960 2692 6.8896010765
27.55840
v. Bund waste Weir Nos 75 4.72500 75 4.72500 75 4.72500 75 4.72500 300 18.90000
vi. Waste weir TYPE "A" Nos 34 4.59000 34 4.59000 34 4.59000 33 4.59000 135 18.36000
vii. Waste weir TYPE "B" Nos 17 4.12500 17 4.12500 16 4.12500 16 4.12500 66 16.50000
viii Gully Control Structure "A" Nos 18 1.80000 18 1.80000 18 1.80000 18 1.80000 72 7.20000
ix. Gully Control Structure "B" Nos 17 2.29425 17 2.29425 17 2.29425 18 2.29425 69 9.17700
x. Gully Control Structure "C" Nos 17 4.85750 17 4.85750 17 4.85750 16 4.85750 67 19.43000
2 NON ARABLE
CONSERVATION WORK
i. PASTURE DEVLOPMENT hectare 25 15.60000 25 15.60000 25 15.60000 29 15.60000 104 62.40000
ii. DIVERSION CHANNEL meter 840 0.44759 840 0.44759 840 0.44759 858 0.44759 3378 1.79034
iii. WHS Type "A" Nos 7 4.90825 7 4.90825 7 4.90825 8 4.90825 29 19.63300
iv. WHS Type "B" Nos 8 9.16575 8 9.16575 8 9.16575 9 9.16575 33 36.66300
v. STAGGERD TRENCHES hectare 0 0.00000 0 0.00000 0 0.00000 0 0.00000 0 0.00000
vi. LOOSE STONE CHECK DAM Nos 0 0.00000 0 0.00000 0 0.00000 0 0.00000 0 0.00000
3 DRAINAGE LINE
TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 1 0.42000 1 0.42000 1 0.42000 1 0.42000 4 1.680
ii. RETANING/SAFTY WALL 'B' Nos 0 0.43125 1 0.43125 1 0.43125 1 0.43125 3 1.725
iii. RETANING/SAFTY WALL 'C' Nos 0 0.48000 0 0.48000 1 0.48000 1 0.48000 2 1.920
iv. RETANING/SAFTY WALL 'D' Nos 0 0.00000 0 0.00000 0 0.00000 0 0.00000 0 0.000
v. RETANING/SAFTY WALL 'E' Nos 0 0.54250 0 0.54250 1 0.54250 0 0.54250 1 2.170
2 IWMP I, BLOCK SIKRAI, DAUSA
PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN
TOTAL
THIRD YEAR
2010-11 2012-13S. N. NAME OF ACTIVITY
FIRST YEAR
Unit 2011-12 2013-14 2014-15
SECOND YEAR FOURTH YEAR FIFTH YEAR
vi. MASONARY WATER
HARVESTING STRUCTURE 'A'
Nos 0 1.12500 0 1.12500 1 1.12500 1 1.125002
4.500
vii. MASONARY WATER
HARVESTING STRUCTURE 'B'
Nos 0 1.44500 0 1.44500 1 1.44500 1 1.445002
5.780
viii MASONARY WATER
HARVESTING STRUCTURE 'C'
Nos 0 1.12000 0 1.12000 1 1.12000 0 1.120001
4.480
90.144 90.144 90.144 90.144 360.576
VIII LIVELIHOOD/MICROENTERP
RISES
a. LIVELIHOOD ACTIVIVITIES
FOR ASSET LESS PERSON
(Karigar, Tailoring, white Wash
& Paint, Masala Udoyg, Bicycle,
Mobile, Pottery, Ara Tari,
Computer etc.)
b. LIVESTOCK MANAGEMENT
(A.I./ CAMP/OTHER)
c. PRODUCTION SYSTEM &
MICROENTERPRISES (For
Kharif, Rabi Season and for
Horticulture Plantation)
22.54 22.54 22.54 22.54 90.144
IX CONSOLIDATED PHASE (3 %) 18.029 18.029
TOTAL PROJECT FUND 42.681 137.494 134.929 133.914 151.577 600.96
B. CONVERGENCE FUND- WORKS TO BE DONE BY AGRICULTURE/HORTICULTURE DEPARTMENT
A.
1 Free Seed Minitkit Distribution Nos. 250 0 250 0 250 0 250 0 1000 3
2 Crop Demonstration Nos. 10 0.27 10 0.27 25 0.675 25 0.673 70 1.888
Agriculture
SUB TOTAL (VIII a,b,c) 15 %
SUB TOTAL (Natural Resource
3 IWMP I, BLOCK SIKRAI, DAUSA
PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN
TOTAL
THIRD YEAR
2010-11 2012-13S. N. NAME OF ACTIVITY
FIRST YEAR
Unit 2011-12 2013-14 2014-15
SECOND YEAR FOURTH YEAR FIFTH YEAR
3 Certified Seed Distribution Nos. 334 0 334 0 334 0 334 0 1560 0.000
4 Subsidy on Pipe Line Meter 3625 0.725 3625 0.725 3625 0.725 3625 0.725 14500 2.900
5 Subsidy on Gypsum M.ton 125 0.85 125 0.85 125 0.85 125 0.85 500 3.400
6 Establishment of Farmers field Nos. 10 0.4 10 0.4 15 0.6 15 0.6 50 2.000
7 Soil and Water Testing and
Distribution of Soil Health Card
Nos. 350 0 350 0 350 0 350 0 1400 0.000
8 Subsidy on Plant Protection
Equipment
Nos. 25 0.125 25 0.125 30 0.15 30 0.15 110 0.550
9 Subsidy on Agriculture Implements No. 10 0.45 10 0.45 15 0.675 15 0.675 50 2.250
B.
1 Medicinal Plant (Alovera) Hect. 2 0 2 0 2 0 2 0 10 0.000
2 Subsidy on Sprinkler Nos. 25 1.6875 25 1.6875 25 1.6875 25 1.6875 100 6.750
3 Subsidy on Drip Irrigation No. 5 5 5 5 10 10 10 10 30 30.000
4 Subsidy on Fruit Orchard Hect. 5 1.136 5 1.136 10 2.272 5 1.136 25 5.680
58.418
GRAND TOTAL FOR PROJECT INCLUDING CONVERGENCE 659.379
Horticulture
TOTAL CONVERGENCE FUND
4 IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY UNIT QUANTITY RATE AMOUNT REFERENCE
I. ADMINISTRATIVE COST (10%)
(Honararium of Watershed Development Team, Secretary of WC,
Office Expenses, Jeep Hiring etc.)
60.096
II MONITORING (1%) 6.010
III EVALUATION (1 %) 6.010
72.115
W/S PREPARATORY PHASE
IV ENTRY POINT ACTIVITY (4 %)
(Solar Light, Water Tank, Khel, Soak Pit, Handpump,
Plateform, Safety Wall, Rain Water Harvesting Structure etc.)
24.038 Estimate No. 1 to 7
V TRAININGS & CAPACITY BUILDING (ICB) 5 % 30.048
VI DETAILED PROJECT REPORT (1 %) 6.010
60.096
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 29522 82 2420804 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 36634 116 4249544 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 18185 187 3400595 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 10765 256 2755840 Estimate No. 11
v. Bund waste Weir Nos 300 6300 1890000 Estimate No. 12
vi. Waste weir TYPE "A" Nos 135 13600 1836000 Estimate No. 13
vii. Waste weir TYPE "B" Nos 66 25000 1650000 Estimate No. 14
viii Gully Control Structure "A" Nos 72 10000 720000 Estimate No. 15
ix. Gully Control Structure "B" Nos 69 13300 917700 Estimate No. 16
x. Gully Control Structure "C" Nos 67 29000 1943000 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
TOTAL ABSTRACT OF COST
SUB TOTAL (I+II+III)
SUB TOTAL (IV+V+VI)
IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY UNIT QUANTITY RATE AMOUNT REFERENCE
i. PASTURE DEVLOPMENT hectare 104 60000 6240000 Estimate No. 18
ii. DIVERSION CHANNEL meter 3378 53 179034 Estimate No. 19
iii. WHS Type "A" Nos 29 67700 1963300 Estimate No. 20
iv. WHS Type "B" Nos 33 111100 3666300 Estimate No. 21
v. STAGGERD TRENCHES hectare 0 22500 0 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 0 3000 0 Estimate No. 23
3 DRAINAGE LINE TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 4 42000 168000 Estimate No. 24
ii. RETANING/SAFTY WALL 'B' Nos 3 57500 172500 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 2 96000 192000 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 0 125000 0 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos 1 217000 217000 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 2 225000 450000 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos 2 289000 578000 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos 1 448000 448000 Estimate No. 31
360.576
VIII LIVELIHOOD/MICROENTERPRISES
a. LIVELIHOOD ACTIVIVITIES FOR ASSET LESS PERSON
(Karigar, Tailoring, white Wash & Paint, Masala Udoyg,
Bicycle, Mobile, Pottery, Ara Tari, Computer etc.)
b. LIVESTOCK MANAGEMENT (A.I./ CAMP/OTHER)
c. PRODUCTION SYSTEM & MICROENTERPRISES (For Kharif,
Rabi Season and for Horticulture Plantation)
90.144
IX CONSOLIDATED PHASE (3 %) 18.029
GRAND TOTAL 600.960
WORKS TO BE DONE BY AGRICULTURE/HORTICULTURE DEPARTMENT THROUGH CONVERGENCE
SUB TOTAL (VIII a,b,c) 15 %
SUB TOTAL (Natural Resource Management)
IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY UNIT QUANTITY RATE AMOUNT REFERENCE
S. No. Activity Unit Amount
A.
1 Free Seed Minitkit Distribution Nos. 3.00
2 Crop Demonstration Nos. 1.880
3 Certified Seed Distribution Nos.
4 Subsidy on Pipe Line Meter 2.900
5 Subsidy on Gypsum M.ton 3.400
6 Establishment of Farmers field Nos. 2.000
7 Soil and Water Testing and Distribution of Soil Health Card Nos.
8 Subsidy on Plant Protection Equipment Nos. 0.550
9 Subsidy on Agriculture Implements No. 2.250
B.
1 Medicinal Plant (Alovera) Hect.
2 Subsidy on Sprinkler Nos. 6.750
3 Subsidy on Drip Irrigation No. 30.000
4 Subsidy on Fruit Orchard Hect. 5.680
58.410
659.370
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
Assistant Engineer (IWMP)
PIA P.S., SIKRAI
Executive Engineer
PMDWDU Z.P., DAUSA
10
500
14500
GRAND TOTAL FOR PROJECT INCLUDING CONVERGENCE
Physical Target
1000
70
95
TOTAL
30
25
Agriculture
Horticulture
50
1400
110
50
1560
IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 2008 82 164656.00 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 2352 116 272832.00 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 1300 187 243100.00 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 1000 256 256000.00 Estimate No. 11
v. Bund waste Weir Nos 20 6300 126000.00 Estimate No. 12
vi. Waste weir TYPE "A" Nos 20 13600 272000.00 Estimate No. 13
vii. Waste weir TYPE "B" Nos 10 25000 250000.00 Estimate No. 14
viii Gully Control Structure "A" Nos 11 10000 110000.00 Estimate No. 15
ix. Gully Control Structure "B" Nos 10 13300 133000.00 Estimate No. 16
x. Gully Control Structure "C" Nos 6 29000 174000.00 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
i. PASTURE DEVELOPMENT hectare 7.00 60000 420000.00 Estimate No. 18
ii. DIVERSION CHANNEL meter 0.00 53 0.00 Estimate No. 19
iii. WHS Type "A" Nos 2 67700 135400.00 Estimate No. 20
iv. WHS Type "B" Nos 2 111100 222200.00 Estimate No. 21
v. STAGGERD TRENCHES hectare 0.00 22500 0.00 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 0 3000 0.00 Estimate No. 23
3 DRAINAGE LINE TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 42000 0.00 Estimate No. 24
A. WATERSHED COMMITTEE THIKIRIA
8 IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
ii. RETANING/SAFTY WALL 'B' Nos 0 57500 0.00 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 96000 0.00 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 125000 0.00 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos 217000 0.00 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 225000 0.00 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos289000 0.00 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos 448000 0.00 Estimate No. 31
27.792 lacs
President Secretary
Watershed Committee Thkiria Watershed Committee Thikiria
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
SUB TOTAL (Natural Resource Management)
Gram Panchayat Thikiria
Sarpanch
9 IWMP I, BLOCK SIKRAI, DAUSA
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 1285 82 105370.00 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 1800 116 208800.00 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 985 187 184195.00 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 770 256 197120.00 Estimate No. 11
v. Bund waste Weir Nos 16 6300 100800.00 Estimate No. 12
vi. Waste weir TYPE "A" Nos 15 13600 204000.00 Estimate No. 13
vii. Waste weir TYPE "B" Nos 8 25000 200000.00 Estimate No. 14
viii Gully Control Structure "A" Nos 7 10000 70000.00 Estimate No. 15
ix. Gully Control Structure "B" Nos 7 13300 93100.00 Estimate No. 16
x. Gully Control Structure "C" Nos 5 29000 145000.00 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
i. PASTURE DEVLOPMENT hectare 8.00 60000 480000.00 Estimate No. 18
ii. DIVERSION CHANNEL meter 0 53 0.00 Estimate No. 19
iii. WHS Type "A" Nos 1 67700 67700.00 Estimate No. 20
iv. WHS Type "B" Nos 1 111100 111100.00 Estimate No. 21
v. STAGGERD TRENCHES hectare 0.00 22500 0.00 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 0 3000 0.00 Estimate No. 23
3 DRAINAGE LINE TREATMENT
B. WATERSHED COMMITTEE PILODI
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
10 IWMP I, BLOCK SIKRAI, DAUSA
i. RETANING/SAFTY WALL 'A' Nos 0 42000 0.00 Estimate No. 24
ii. RETANING/SAFTY WALL 'B' Nos 0 57500 0.00 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 0 96000 0.00 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 125000 0.00 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos 217000 0.00 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 0 225000 0.00 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos289000 0.00 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos 0 448000 0.00 Estimate No. 31
21.672 lacs
President Secretary
Watershed Committee Pilodi Watershed Committee Pilodi
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
Sarpanch
Gram Panchayat Pilodi
SUB TOTAL (Natural Resource Management)
11 IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 7489 82 614098.00 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 8300 116 962800.00 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 5400 187 1009800.00 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 2950 256 755200.00 Estimate No. 11
v. Bund waste Weir Nos 76 6300 478800.00 Estimate No. 12
vi. Waste weir TYPE "A" Nos 20 13600 272000.00 Estimate No. 13
vii. Waste weir TYPE "B" Nos 6 25000 150000.00 Estimate No. 14
viii Gully Control Structure "A" Nos 15 10000 150000.00 Estimate No. 15
ix. Gully Control Structure "B" Nos 9 13300 119700.00 Estimate No. 16
x. Gully Control Structure "C" Nos 4 29000 116000.00 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
i. PASTURE DEVLOPMENT hectare 10.00 60000 600000.00 Estimate No. 18
ii. DIVERSION CHANNEL meter 53 0.00 Estimate No. 19
iii. WHS Type "A" Nos 1 67700 67700.00 Estimate No. 20
iv. WHS Type "B" Nos 1 111100 111100.00 Estimate No. 21
v. STAGGERD TRENCHES hectare 0.00 22500 0.00 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 0 3000 0.00 Estimate No. 23
3 DRAINAGE LINE TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 0 42000 0.00 Estimate No. 24
C. WATERSHED COMMITTEE PANCHOLI
12 IWMP I, BLOCK SIKRAI, DAUSA
ii. RETANING/SAFTY WALL 'B' Nos 0 57500 0.00 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 0 96000 0.00 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 125000 0.00 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos 217000 0.00 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 225000 0.00 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos289000 0.00 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos 448000 0.00 Estimate No. 31
54.072 lacs
President Secretary
Watershed Committee Pancholi Watershed Committee Pancholi
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
Sarpanch
Gram Panchayat Panchol
SUB TOTAL (Natural Resource Management)
13 IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 4219 82 345958.00 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 6200 116 719200.00 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 3300 187 617100.00 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 1100 256 281600.00 Estimate No. 11
v. Bund waste Weir Nos 70 6300 441000.00 Estimate No. 12
vi. Waste weir TYPE "A" Nos 20 13600 272000.00 Estimate No. 13
vii. Waste weir TYPE "B" Nos 15 25000 375000.00 Estimate No. 14
viii Gully Control Structure "A" Nos 10 10000 100000.00 Estimate No. 15
ix. Gully Control Structure "B" Nos 5 13300 66500.00 Estimate No. 16
x. Gully Control Structure "C" Nos 5 29000 145000.00 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
i. PASTURE DEVLOPMENT hectare 10.00 60000 600000.00 Estimate No. 18
ii. DIVERSION CHANNEL meter 1003 53 53159.00 Estimate No. 19
iii. WHS Type "A" Nos 5 67700 338500.00 Estimate No. 20
iv. WHS Type "B" Nos 5 111100 555500.00 Estimate No. 21
v. STAGGERD TRENCHES hectare 0.00 22500 0.00 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 0 3000 0.00 Estimate No. 23
3 DRAINAGE LINE TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 0 42000 0.00 Estimate No. 24
D. WATERSHED COMMITTEE PIPALKI
14 IWMP I, BLOCK SIKRAI, DAUSA
ii. RETANING/SAFTY WALL 'B' Nos 0 57500 0.00 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 96000 0.00 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 125000 0.00 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos 217000 0.00 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 0 225000 0.00 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos 0289000 0.00 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos 0 448000 0.00 Estimate No. 31
49.105 lacs
President Secretary
Watershed Committee Pipalki Watershed Committee Pipalki
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
Sarpanch
Gram Panchayat Pipalki
SUB TOTAL (Natural Resource Management)
15 IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 8816 82 722912.00 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 11392 116 1321472.00 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 3000 187 561000.00 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 3050 256 780800.00 Estimate No. 11
v. Bund waste Weir Nos 50 6300 315000.00 Estimate No. 12
vi. Waste weir TYPE "A" Nos 20 13600 272000.00 Estimate No. 13
vii. Waste weir TYPE "B" Nos 8 25000 200000.00 Estimate No. 14
viii Gully Control Structure "A" Nos 10 10000 100000.00 Estimate No. 15
ix. Gully Control Structure "B" Nos 19 13300 252700.00 Estimate No. 16
x. Gully Control Structure "C" Nos 30 29000 870000.00 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
i. PASTURE DEVLOPMENT hectare 20.00 60000 1200000.00 Estimate No. 18
ii. DIVERSION CHANNEL meter 500 53 26500.00 Estimate No. 19
iii. WHS Type "A" Nos 5 67700 338500.00 Estimate No. 20
iv. WHS Type "B" Nos 10 111100 1111000.00 Estimate No. 21
v. STAGGERD TRENCHES hectare 22500 0.00 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 0 3000 0.00 Estimate No. 23
3 DRAINAGE LINE TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 1 42000 42000.00 Estimate No. 24
E. WATERSHED COMMITTEE KALWAN
16 IWMP I, BLOCK SIKRAI, DAUSA
ii. RETANING/SAFTY WALL 'B' Nos 1 57500 57500.00 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 1 96000 96000.00 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 0 125000 0.00 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos 1 217000 217000.00 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 1 225000 225000.00 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos 1289000 289000.00 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos 1 448000 448000.00 Estimate No. 31
94.464
President Secretary
Watershed Committee Kalwan Watershed Committee Kalwan
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
Sarpanch
Gram Panchayat Kalwan
SUB TOTAL (Natural Resource Management)
17 IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 2803 82 229846.00 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 3190 116 370040.00 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 2400 187 448800.00 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 395 256 101120.00 Estimate No. 11
v. Bund waste Weir Nos 38 6300 239400.00 Estimate No. 12
vi. Waste weir TYPE "A" Nos 10 13600 136000.00 Estimate No. 13
vii. Waste weir TYPE "B" Nos 4 25000 100000.00 Estimate No. 14
viii Gully Control Structure "A" Nos 5 10000 50000.00 Estimate No. 15
ix. Gully Control Structure "B" Nos 5 13300 66500.00 Estimate No. 16
x. Gully Control Structure "C" Nos 5 29000 145000.00 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
i. PASTURE DEVLOPMENT hectare 20.00 60000 1200000.00 Estimate No. 18
ii. DIVERSION CHANNEL meter 75 53 3975.00 Estimate No. 19
iii. WHS Type "A" Nos 5 67700 338500.00 Estimate No. 20
iv. WHS Type "B" Nos 4 111100 444400.00 Estimate No. 21
v. STAGGERD TRENCHES hectare 0.00 22500 0.00 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 0 3000 0.00 Estimate No. 23
3 DRAINAGE LINE TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 0 42000 0.00 Estimate No. 24
F. WATERSHED COMMITTEE ACHALPURA
18 IWMP I, BLOCK SIKRAI, DAUSA
ii. RETANING/SAFTY WALL 'B' Nos 0 57500 0.00 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 0 96000 0.00 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 0 125000 0.00 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos 0 217000 0.00 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 225000 0.00 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos289000 0.00 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos 0 448000 0.00 Estimate No. 31
38.736 lacs
President Secretary
Watershed Committee Achalpura Watershed Committee Achalpura
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
Sarpanch
Gram Panchayat Achalpura
SUB TOTAL (Natural Resource Management)
19 IWMP I, BLOCK SIKRAI, DAUSA
S. N. NAME OF ACTIVITY Unit Qunatity Rate Amount Reference
WATERSHED WORK PHASE
VII NATURAL RESOURCE MANAGEMENT (NRM) (60 %)
1 ARABLE CONSERVATION WORK
i. Earthen Bund TYPE "A"(SLOPE 0-1%) meter 290282
237964.00 Estimate No. 8
ii. Earthen Bund TYPE "B"(SLOPE 1-3%) meter 3400116
394400.00 Estimate No. 9
iii. Earthen Bund TYPE "C"(SLOPE 3-5%) meter 1800187
336600.00 Estimate No. 10
iv. Earthen Bund TYPE "D"(SLOPE 5-10%) meter 1500256
384000.00 Estimate No. 11
v. Bund waste Weir Nos 306300
189000.00 Estimate No. 12
vi. Waste weir TYPE "A" Nos 3013600
408000.00 Estimate No. 13
vii. Waste weir TYPE "B" Nos 1525000
375000.00 Estimate No. 14
viii Gully Control Structure "A" Nos 1410000
140000.00 Estimate No. 15
ix. Gully Control Structure "B" Nos 1413300
186200.00 Estimate No. 16
x. Gully Control Structure "C" Nos 1229000
348000.00 Estimate No. 17
2 NON ARABLE CONSERVATION WORK
i. PASTURE DEVLOPMENT hectare 29.0060000
1740000.00 Estimate No. 18
ii. DIVERSION CHANNEL meter 180053
95400.00 Estimate No. 19
iii. WHS Type "A" Nos 1067700
677000.00 Estimate No. 20
iv. WHS Type "B" Nos 10111100
1111000.00 Estimate No. 21
v. STAGGERD TRENCHES hectare 0.0022500
0.00 Estimate No. 22
vi. LOOSE STONE CHECK DAM Nos 03000
0.00 Estimate No. 23
3 DRAINAGE LINE TREATMENT
i. RETANING/SAFTY WALL 'A' Nos 342000
126000.00 Estimate No. 24
G. WATERSHED COMMITTEE GEEJGARH
20 IWMP I, BLOCK SIKRAI, DAUSA
ii. RETANING/SAFTY WALL 'B' Nos 257500
115000.00 Estimate No. 25
iii. RETANING/SAFTY WALL 'C' Nos 196000
96000.00 Estimate No. 26
iv. RETANING/SAFTY WALL 'D' Nos 0125000
0.00 Estimate No. 27
v. RETANING/SAFTY WALL 'E' Nos217000
0.00 Estimate No. 28
vi. MASONARY WATER HARVESTING STRUCTURE 'A' Nos 1225000
225000.00 Estimate No. 29
vii. MASONARY WATER HARVESTING STRUCTURE 'B' Nos 1289000
289000.00 Estimate No. 30
viii MASONARY WATER HARVESTING STRUCTURE 'C' Nos448000
0.00 Estimate No. 31
74.736 lacs
President Secretary
Watershed Committee Geejgarh Watershed Committee Geejgarh
WDT WDT WDT WDT
Agriculture Engineering Animal Hubandary Social Science
Sarpanch
Gram Panchayat Geejgarh
SUB TOTAL (Natural Resource Management)
21 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Ram Bharosi Meena/Kanahiya lal Thikria President 1 Devishay Prajapat/Ramkishan Thikria President
2 Ganga Ram Meena/Giraj prasad Thikria Member 2 Ramsawroop/Ghasi Nath Thikria Member
3 Balmukund Sharma/Gosdhan das Thikria Member 3 Raghuveer Prajapat/Jagdish Thikria Member
4 Ram Khilari Meena/Ram Kishan Thikria Member 4 Laxman -do-/Kishori Thikria Member
5 Kailash Meena/Ramder Thikria Member 5 Kamlesh Meena/Mahohari Thikria Member
6 Dhasmi/Ramsi Meena Thikria Member 6 Murari Jangir/Ramji lal Thikria Member
7 Ramkesh/Ramcharan Thikria Member 7 Vijay Meena/Ramsi Thikria Member
8 Shiv ram Meena/Ramcharan Thikria Member 8 Banhori Prajapat/Ramji lal Thikria Member
9 Nisanjam Jangir/Ramjilal Thikria Member 9 Pappu/Kishori meena Thikria Member
10 Kanahiya lal/Tagolish Thikria Member 10 Jagdish/Giraj Thikria Member
1 Kistarchand Sharma/Panna lal Thikria President 1 Hajari lal Yogi/Lalluram Thikria President
2 Ram Dayal/Shivli Nath Thikria Member 2 Harkesh Meena/Ramsingh Thikria Member
3 Ravi Prajapat/Ramsawroop Thikria Member 3 Manohar Meena/Mithhu Thikria Member
4 Suresh/Giraj Meena Thikria Member 4 Mukesh Prajapat/Manohari Thikria Member
5 Sukhdev Soni/Chhagan lal Thikria Member 5 Lala Khan/Munna Thikria Member
6 Lallu Bairwa/Chhutan Thikria Member 6 Ramsawroop/Tejram Prajapat Thikria Member
7 Bhagirath/Chanda Bairwa Thikria Member 7 Chota Ram/Rampal Meena Thikria Member
8 Rajendra Meena/Giraj prasad Thikria Member 8 Hari Ram/Girraj Meena Thikria Member
9 Jagdish Soni/Chiranji lal Thikria Member 9 Hajari/Ramphoool Thikria Member
10 Hari Singh/Parsadi lal Thikria Member 10 Rajesndra Yogi/Vshram Thikria Member
1 Ram Kishan Meena/Bhambhala Thikria President 1 President
2 Ram Pyari/Ramsawroop Thikria Member 2 Member
3 Natholi Meena/Mulya Thikria Member 3 Member
4 Ramji lal/Mangi lal Thikria Member 4 Member
5 Thadi Ram/Mulya Meena Thikria Member 5 Member
6 Jagan bairwa/Hari lal Thikria Member 6 Member
7 Kamlesh Soni/Girraj Thikria Member 7 Member
8 Ramkhilari/Ramkishan Thikria Member 8 Member
9 Munsi khan/Asheem Thikria Member 9 Member
10 Bharat lal Meena/Ram Kishan Thikria Member 10 Member
WHS/Anicut User Group Animal Husbandary Development User Group
Landless Peoples User GroupPasture Development User Group
ANNEXURE - I
Gram Panchayat Wise Details of Various User Groups Constituted for Development of Activities
Gram Panchayat: Thikiria
Contour /Med Bandi User Group Horticulture/Nursery User Group
1 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Ramesh/Bharat lal Meena Pilodi President 1 Kailash/ Khyali Ram Meena Pilodi President
2 Madan/Kilan Sain Pilodi Member 2 Phyare lal/Ghamandi Meena Pilodi Member
3 Satish/Giraj Meena Pilodi Member 3 Ratan/Harshyay Pilodi Member
4 Babulal/Shiv lal Pilodi Member 4 Yad Ram/Ram lal Meena Pilodi Member
5 Harkesh/Lohra Pilodi Member 5 Amar singh/Bharat lal Pilodi Member
6 Jagram/Amarchand Pilodi Member 6 Mansingh/Dhansi Meena Pilodi Member
7 Manoj/Thandi Ram Pilodi Member 7 Jagram/Mangalram Pilodi Member
8 Ramshyai/Sanwal Ram Pilodi Member 8 Jeetram/bharosi Pilodi Member
9 Ramkesh/Harshyay Meena Pilodi Member 9 Ghamandi/Dhanna ram Pilodi Member
10 Kailash/Chamaiya Meena Pilodi Member 10 Balram/Rang lal Pilodi Member
1 Vinod/Puranmal Meena Pilodi President 1 Shiv Ram/ Heera lal Pilodi President
2 Jhaloo Ram/Moolchand Pilodi Member 2 Umedi/Ramhet Pilodi Member
3 Pratap/Kajod Pilodi Member 3 Kallu/Jailal Pilodi Member
4 Ramsingh/Mulya Pilodi Member 4 Bharosi/Sukhlal Pilodi Member
5 Sampat/Sukhha Meena Pilodi Member 5 Dhansoo//Chiranji Pilodi Member
6 Santosh/ Umrab meena Pilodi Member 6 Kailash/ Sanwal Ram Pilodi Member
7 Amit/Gopi shyay Pilodi Member 7 Rajesh/Kamal Pilodi Member
8 Ganga/Sanwal Ram Pilodi Member 8 Mahenra/Kailash Pilodi Member
9 Gopal/Johari Meena Pilodi Member 9 Praladh/Moolchand Pilodi Member
10 Rajendra/Pratap Pilodi Member 10 Raja Ram/ Ram khilari Pilodi Member
1 Dharam shay/ Rattiram Heengi President 1 Jagdish/ Ramji lal Heengi President
2 Shiv charan/ Ramdhan Heengi Member 2 Rajesh/Giraj Heengi Member
3 Ramkishaori/manohar Heengi Member 3 Jugal/ Ram kishan Heengi Member
4 Praladh/Vishram Heengi Member 4 Ramphal/ Pyare lal Heengi Member
5 Tooda/ Parsadi Heengi Member 5 Ramu/ Hulya ram Heengi Member
6 Ramji lal/ Ramdev Heengi Member 6 Suresh/Manohari Heengi Member
7 Ramroop/Bachoo Heengi Member 7 Murari/ Today Ram Heengi Member
8 Dheer singh/Rambharosi Heengi Member 8 Naharsingh/Harlal Heengi Member
9 Suresh/ Ratan lal Heengi Member 9 Pappu/Suwa lal Heengi Member
10 Vinod/Giraj Heengi Member Member
1 Babulal/Bansidhar Bairwa Pilodi President
2 Net Ram/ Shamboo Dayal Pilodi Member
3 Vishnya/Ghudya Ram Pilodi Member
4 Bodya Ram/Beerbal Pilodi Member
5 Kedar/Boolya Pilodi Member
6 Bhagwan shay/ Prabhati Pilodi Member
7 Ramji lal/Narayan Pilodi Member
WHS/Anicut User Group Livestock Development User Group
Pasture Development User Group Landless Peoples User Group
Gram Panchayat: Pilodi
Contour /Med Bandi User Group Horticulture/Nursery User Group
Agriculture Development/Production User Group
2 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Kailash / Saravan singh Gurjar Murlipur President 1 Sardar / Laxman Murlipur President
2 Sumer singh / Giraj singh Gurjar Murlipur Member 2 Raja ram / kanahiya lal Murlipur Member
3 Bhawani / Ram shyay Murlipur Member 3 Jagdish / Ramphal Murlipur Member
4 Bane singh / Ghori ram Murlipur Member 4 Jwan singh / Ramji lal Murlipur Member
5 Vijay singh / Ramphool Murlipur Member 5 Gurjarmal / Ishwar mal Murlipur Member
6 Siya ram / kanji Murlipur Member 6 Shree chand / Ram shyay Murlipur Member
7 Raja ram / Moolchand Murlipur Member 7 Devkaran / Rameshwar Murlipur Member
8 Lakhan singh /shreechand Murlipur Member 8 Rajendra / Ramsingh Murlipur Member
9 Nathu lal / Chhaju lal Murlipur Member 9 Raghuveer / Ramshyay Murlipur Member
10 Mahendra / Ranglal Murlipur Member 10 Hukum / Ram kishor Murlipur Member
1 Ishwar mal / Ramdhan Khedla President 1 Bhajan / Ramhet bairwa Pancholi President
2 Rakesh / Jaisingh Khedla Member 2 Bholu ram / Ramgopal Pancholi Member
3 Rajendra / Nathulal Khedla Member 3 Brijlal / Jagdev Pancholi Member
4 Balveer / Kanihiya Khedla Member 4 Mohar singh / Kishan lal Pancholi Member
5 Bachoo singh / Ram kishor Khedla Member 5 Nihal singh / Mohan lal Pancholi Member
6 Gulab / Meetha lal Khedla Member 6 Panchu ram / Ramniwas Pancholi Member
7 Ramnath / Bhori lal Khedla Member 7 Sumer / Laxminarayan Pancholi Member
8 Hajari / Ramdhan Khedla Member 8 Ramsingh / Rampratap Pancholi Member
9 Jagdish Moolchand Khedla Member 9 Shivcharan / Ramhans bairwa Pancholi Member
10 Kailash /Beerwal Khedla Member 10 Dharm singh / Nathulal Pancholi Member
1 Badan singh / Ramhans Pancholi President 1 Ramsingh / Ramhans Pancholi President
2 Madho singh / Mohan lal Pancholi Member 2 Pukrraj / Mohan lal Pancholi Member
3 Nathu ram / Hargovind Pancholi Member 3 Pooran /Jagdev Pancholi Member
4 Jwan singh / Kanihiya lal Pancholi Member 4 Shish ram / Kishan lal Pancholi Member
5 Jagdish / Dhannal lal Pancholi Member 5 Kailash / Laxman Pancholi Member
6 Giraj / Shrii narayan Pancholi Member 6 Nehru / Harlal Pancholi Member
7 Harshyay / Prasadi lal Pancholi Member 7 Rameshwar / Shri kishan Pancholi Member
8 Mansingh / Girdhari Pancholi Member 8 Bhagchand / Suraj mal Pancholi Member
9 Pralad / Brijmohan mahant Pancholi Member 9 Kedar / Ramsingh Pancholi Member
10 Babu Kilan rana Pancholi Member 10 Ramji lal chand lal Pancholi Member
11 Kamal / Chhaju ram Pancholi Member
1 Nathu lal / Mool chand Murlipur President
2 Vijay singh / Bhoma Ram Gurjar Murlipur Member
3 Bhola ram / Pyarsingh Murlipur Member
4 Hukam singh / Rameshwar Murlipur Member
5 Surednra / Ratan singh Murlipur Member
6 Jitendra / Man singh Murlipur Member
7 Udai singh / Harisingh Murlipur Member
8 Ranjeet / Birwal singh Murlipur Member
9 Dharm singh / Kishan lal Gurjar Murlipur Member
10 Nanu lal / Hukum singh Murlipur Member
Agriculture Development/Production User Group
Horticulture/Nursery User Group
WHS/Anicut User Group
Pasture Development User Group Landless Peoples User Group
Livestock Development User Group
Gram Panchayat: Pancholi
Contour /Med Bandi User Group
3 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Pappu ram / Ram lal saini Dhulkot President 1 Ramdhan / Roopa ram saini Dhulkot President
2 Jagdish / Nanag ram saini Dhulkot Member 2 Ramsingh / Kanahiya lal Dhulkot Member
3 Lallu ram / Gopal ram Dhulkot Member 3 Pappu ram /Pannya ram saini Dhulkot Member
4 Ramsawroop / Ganga dhar Dhulkot Member 4 Khiladi / Nathu ram saini Dhulkot Member
5 Mahendra / Shri Narayan Dhulkot Member 5 Parmal Ram / Tite ram Dhulkot Member
6 Heera lal Gordhan saini Dhulkot Member 6 Mangi lal /Ramdev saini Dhulkot Member
7 Hari ram / Ramlya saini Dhulkot Member 7 Raju / Lallu ram saini Dhulkot Member
8 Murari / Ramdev saini Dhulkot Member 8 Mukesh / Ramdhan saini\ Dhulkot Member
9 Kailash / Puna Ram Dhulkot Member 9 Mahendra / Sohan lal\ Dhulkot Member
10 Shambhoo / Ramdhan Dhulkot Member 10 Buli chand / Ghammand ram saini Dhulkot Member
1 Ashok / Kana ram bairwa Dhulkot President 1 Munna lal / Rewarmal Gurjar Dhulkot President
2 Jagdish / Prabhati ram bairwa Dhulkot Member 2 Raghuveer / Ghasi lal Dhulkot Member
3 Gopal / Kojar mal bairwa Dhulkot Member 3 Moharpal / Jagdeva Dhulkot Member
4 Raju lal / Bansi ram Bairwa Dhulkot Member 4 Mool chand / Dhanna ram Dhulkot Member
5 Shyam lal / Badari prasad Dhulkot Member 5 Malkhan Ramdhan Dhulkot Member
6 Sohan lal / Lohari ram Dhulkot Member 6 Kishori / Arjun Dhulkot Member
7 Mahendra / Raghunath\ Dhulkot Member 7 Jwan /Ganga Shyay Dhulkot Member
8 Satish / Tejram Dhulkot Member 8 Ram karan / Rewarmal Dhulkot Member
9 Manphool / Ramdhan bairwa Dhulkot Member 9 Ramawtar / Sariya ram Dhulkot Member
10 Madan / Kishan lal Dhulkot Member 10 Giraj / Basnti lal Bairwa Dhulkot Member
1 Chote lal / Sukh lal mahawar Seekri President 1 Dinesh / Ganga Bishan Meena Seekri President
2 Dodha ram / Kanihya lal Seekri Member 2 Narsi ram / Ramshyay meena Seekri Member
3 Ram babu / Pooran Seekri Member 3 Vijay / Narsi ram meena Seekri Member
4 Girraj / Ramchand Seekri Member 4 Krishan mohan / Ramdev Seekri Member
5 Narayan / Badri Seekri Member 5 Vinod / kanni ram meena Seekri Member
6 Mool chand / Bhouri lal Seekri Member 6 Praladh / Holya ram meena Seekri Member
7 Omprakash / Mool chand Seekri Member 7 Chandra mohan / Ramjilal Seekri Member
8 Ramchand / Bhouri lal Seekri Member 8 Kedar / Rameshwar prasad Seekri Member
9 Badari / Bhansi lal Seekri Member 9 Hari kishan / Badri prasad Seekri Member
10 10 Shiv ram / Mola ram Seekri Member
1 Lala ram / Gyarsha Koli Seekri President
2 Sanjay / Lala ram Seekri Member
3 Nanag ram / Patya ram Seekri Member
4 Bablu / Kishya ram Seekri Member
5 Kanji / Ramshyay kumhar Seekri Member
6 Sugan lal / Ramshyay Seekri Member
7 Birju / Kajool Seekri Member
8 Tapkya / Badri nath Seekri Member
9 Pyar singh / Papaya ram sain Seekri Member
10 Bhadur singh/ Nahar singh Seekri Member
WHS/Anicut User Group Livestock Development User Group
Pasture Development User Group Landless Peoples User Group
Agriculture Development/Production User Group
Contour /Med Bandi User Group Horticulture/Nursery User Group
Gram Panchayat: Pipalki
4 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Kailash / Kanahiya lal bairwa Giladi President 1 Hemant / Jagdish Prasad mishra Kalwan President
2 Ramkishan / Sariya bairwa Giladi Member 2 Banbari lal / Babulal bairwa Kalwan Member
3 Omprakash / Kanahiya lal Giladi Member 3 Kajok mal / Jhonth ram Kalwan Member
4 Heera lal / Swjan Giladi Member 4 Bhagchand / Nathu lal sain Kalwan Member
5 Rasal singh / sultan singh Giladi Member 5 Moolchand / Harinarayan kharwal Kalwan Member
6 Kishan lal / Bhoora bairwa Giladi Member 6 Lalit kumar/ Kajod mal bairwa Kalwan Member
7 Suesh / Kailash chand Giladi Member 7 Kishor / Ram ratan bairwa Kalwan Member
8 Nathu lal / Kishori lal Giladi Member 8 Ramesh / Shedu ram bairwa Kalwan Member
9 Ramsawroop / Bhoora ram Giladi Member 9 Hatila / Ramdhan bairwa Kalwan Member
10 Krishan lal / Ramshyay Giladi Member 10 Hari ram /Ganga dhar bairwa Kalwan Member
1 Mangal ram / Harji ram Meena Giladi President 1 Harkesh / Ramphool meena Kalwan President
2 Bhansi ram / Moolchand meena Giladi Member 2 Amersingh /Gordhan meena Kalwan Member
3 Vishram / Ratan lal kumhar Giladi Member 3 Siyaram /Gokul meena Kalwan Member
4 Ghasi ram / Kalu ram Giladi Member 4 Pyare lal /Syonarayan Kalwan Member
5 Dhasrath / Ram kishan mahaver Giladi Member 5 Ramprasad / Kishori meena Kalwan Member
6 Chote lal / Shatraghan das Giladi Member 6 Mishri lal /Chote lal meena Kalwan Member
7 Giraj /Bhoriya kumhar Giladi Member 7 Narsi / Kilan meena Kalwan Member
8 Ramshawroop / Sariya Meena Giladi Member 8 Battu ram /Ratan meena Kalwan Member
9 Kailash / Gokul meena Giladi Member 9 Bansi / Hatya ram Kalwan Member
10 Vijendra / Ramhet meena Giladi Member 10 Nathu /Jaila ram Kalwan Member
1 Bhagat Ram / Raghunath bairwa Kalwan President 1 Kishan lal /Srawan lal bairwa Padli President
2 Jagdish / Kajod Bairwa Kalwan Member 2 Rajul kankhalal bairwa Padli Member
3 Bansi /Nathya bairwa Kalwan Member 3 Sohanlal / Kishan lal bairwa Padli Member
4 Kishan lal / Ramshyay Bairwa Kalwan Member 4 Ramesh / Shriya Bairwa Padli Member
5 Kishor /Ccajoo ram bairwa Kalwan Member 5 Bardoochand /Narayan bairwa Padli Member
6 Jeetram /Bhambhola bairwa Kalwan Member 6 Ramjilal / Prabhat Bairwa Padli Member
7 Phoolchand / Babu lal bairwa Kalwan Member 7 Ramswaroop / Bhoori lal Padli Member
8 Ratan lal / Bhoriya bairwa Kalwan Member 8 Radhe Shyam / Banna ram bairwa Padli Member
9 Kandhiya / Mulya ram Kalwan Member 9 Giraj / shri Kishan Bairwa Padli Member
10 Bhagwanshyay / Ramshyay bairwa Kalwan Member 10 Bhagwan shyay /Bhansi lal bairwa Padli Member
1 Jamna lal / Gordhan Meena Kalwan President
2 Dharm Singh / Sukharam Meena Kalwan Member
3 Banwari / Ramji Lal Meena Kalwan Member
4 Bhagwan Sahay / Kanaram Kalwan Member
5 Omprakash /Ram Kishor Kalwan Member
6 Surajmal /Beerwal Kalwan Member
7 Ram Prasad / Kajodmal meena Kalwan Member
8 Amar Singh / Kalyan Sahay Meena Kalwan Member
9 Chote Lal /Mulyaram Meena Kalwan Member
10 Lohra Ram / Goverdhan Meena Kalwan Member
WHS/Anicut User Group Livestock Development User Group
Agriculture Development/Production User Group
Gram Panchayat: Kalwan
Contour /Med Bandi User Group Horticulture/Nursery User Group
Pasture Development User Group Landless Peoples User Group
5 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Sawai Singh / Devi Singh Sarundla President 1 Chandar Lal / Banshidhar Saini Sarundla President
2 Jor Singh /Ram Singh Sarundla Member 2 Laxmi Narayan / Baldev Saini Sarundla Member
3 Pushpendra / Radheyshyam Jangir Sarundla Member 3 Gopal Lal / Dolat Ram Saini Sarundla Member
4 Prabhoo Singh /Sodan Singh Sarundla Member 4 Badri Prasad / Ganga Sahay Sarundla Member
5 Vijay Singh / Sardar Singh Sarundla Member 5 Arjun Lal / Bhorya Ram Saini Sarundla Member
6 Sawai Singh /Hari Singh Sarundla Member 6 Ramesh Chand /Partya Ram Saini Sarundla Member
7 Bhagwan Sahay / Ramniwas Sharma Sarundla Member 7 Khemraj / Chitarmal Saini Sarundla Member
8 Dinesh / Ramjilal Agarwal Sarundla Member 8 Jairam / Rampal Saini Sarundla Member
9 Babu Lal / Kishor Jangir Sarundla Member 9 Hari Mohan / Ram Prasad Saini Sarundla Member
10 Santosh / Chiranji Lal Sharma Sarundla Member 10 Tulsiram / Kurilal Saini Sarundla Member
1 Jagdish / Bholaram Gurjar Achalpura President 1 Deep Chand / Paluram Bairwa Achalpura President
2 Girraj Prasad / Phool Chand Sharma Achalpura Member 2 Raghunath ? Moolchand Bairwa Achalpura Member
3 Laxman / Ramkishan Gurjar Achalpura Member 3 Ramlya / Sonya Bairwa Achalpura Member
4 Ramawatar / Bhori Prasad Achalpura Member 4 Ramji Lal /Ram Sahay Bairwa Achalpura Member
5 Satya Narayan / Chiranji Lal Achalpura Member 5 Kanchan / Mangilal Bairwa Achalpura Member
6 Gopal / Bhudram Saini Achalpura Member 6 Babu Lal / Prabati Lal Bairwa Achalpura Member
7 Aklesh / Banshidhar Sharma Achalpura Member 7 Rajesh /Babulal Sharma Achalpura Member
8 Shyam Lal / Jagdish Prasad Achalpura Member 8 Bhagwan Sahay / Ram Kishan Achalpura Member
9 Babu Lal / Ramphool Saini Achalpura Member 9 Pappu Ram /Kaluram Bairwa Achalpura Member
10 Amar Singh / Ramji Lal Gurjar Achalpura Member 10 Narsiram / Johri Lal Sharma Achalpura Member
1 Laxmi Chand / Sarjan Ram Meena Chandpur President 1 Jai Singh / Kalyan Sahay Gurjar Jhangiria President
2 Vishram /Raghunath Meena Chandpur Member 2 Ram Kishor /Shriram Gurjar Jhangiria Member
3 Rambhorishi / Hari Ram Meena Chandpur Member 3 Har Bhajan / Gordhan Gurjar Jhangiria Member
4 Makkhan / Girraj Prasad Meena Chandpur Member 4 Dayaram / Hiralal Jhangiria Member
5 Chetram / Gyarsi Ram Chandpur Member 5 Prabhati / Rewar Jhangiria Member
6 Man Singh / Meetha Ram Meena Chandpur Member 6 Raghunath / Ramdhan Jhangiria Member
7 Rajaram / Moolchand Chandpur Member 7 Ramhet / Amar Singh Jhangiria Member
8 Banwari / Jainarayan Chandpur Member 8 Munshi / Rampratap Gurjar Jhangiria Member
9 Rajendra / Jagdish Prasad Chandpur Member 9 Kamal Singh/Bhagwan Sahay Jhangiria Member
10 Banwari / Kaluram Meena Chandpur Member 10 Ram Kishan /Ram Niwash Jhangiria Member
1 Girraj / Pannalal Saini Sarundla President
2 Ram karan / Gokul Ram Saini Sarundla Member
3 Kishan Lal / Gangadhar Saini Sarundla Member
4 Bhole Ram /Chaju Ram Sarundla Member
5 Rewar / Amar Chand Sarundla Member
6 Pahlad / Ram Sahay Saini Sarundla Member
7 Ram Bhajan / Bhori Lal Saini Sarundla Member
8 Kana Ram / Ramdhan Saini Sarundla Member
9 Chiranji Lal / Ramjilal Saini Sarundla Member
10 Chote Lal / Mulchand Saini Sarundla Member
Pasture Development User Group Landless Peoples User Group
Agriculture Development/Production User Group
Gram Panchayat: Achalpura
Contour /Med Bandi User Group Horticulture/Nursery User Group
WHS/Anicut User Group Livestock Development User Group
6 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Vinod Kumar /Kanchan Lal Saini Geejgarh President 1 Banwari Lal /Jainarayan Saini Geejgarh President
2 Ravindra /Govind Sahay Saini Geejgarh Member 2 Bheemsen /Jagdish Pd. Saini Geejgarh Member
3 Rajendra /Ramdhan Saini Geejgarh Member 3 Babu lal /Laxman Lal Saini Geejgarh Member
4 Mohan Lal /Chotte Lal Saini Geejgarh Member 4 Girraj /Sukkaram Saini Geejgarh Member
5 Naresh Kumar /Shimbhoo Dayal Geejgarh Member 5 Pappu /Girraj Saini Geejgarh Member
6 Mahesh /Kanhaiya Lal Saini Geejgarh Member 6 Dayaram /Kajodmal Saini Geejgarh Member
7 Vishram /Kishan Lal Saini Geejgarh Member 7 Ramphool /Gangaram Saini Geejgarh Member
8 Kamlesh /Prabhu Dayal Saini Geejgarh Member 8 Ramesh /Lalluram Saini Geejgarh Member
9 Babu Lal /Moti Lal Saini Geejgarh Member 9 Suresh /Goverdhan Saini Geejgarh Member
10 Hariram /Manohari Lal Saini Geejgarh Member 10 Mangilal /Jamna Lal Saini Geejgarh Member
11 Jaiphool /Mevaram Saini Geejgarh Member 11 Ramji Lal /BhagwanSahay Saini Geejgarh Member
12 Basanti Lal/Chandar Lal Saini Geejgarh Member 12 Jamnalal /Mangal Ram Saini Geejgarh Member
13 Sukkaram /Jhuta ram Saini Geejgarh Member
1 Lilyaram /Prasadi Meena Geejgarh President 1 Hanuman Sahay/ Laxminarayan Geejgarh President
2 Pintu/Ramswaroop Meena Geejgarh Member 2 Gajanand/Ramswroop Sharma Geejgarh President
3 Rinku /Nathu Lal Meena Geejgarh Member 3 KedarPrasad /Mohan Lal Sharma Geejgarh Member
4 Banwari /Ramji Lal Meena Geejgarh Member 4 Chitarmal /Govind Sahay Gurjar Geejgarh Member
5 Jwala /Somotya Meena Geejgarh Member 5 Babu Lal/ Kalyan Sahay Gurjar Geejgarh Member
6 Ramji Lal /Mahadewa Meena Geejgarh Member 6 Ramawtar /Ganpatlal Sharma Geejgarh Member
7 Gaindaram /Tejaram Meena Geejgarh Member 7 Narendra /Devi Singh Rajpoot Geejgarh Member
8 Pintu /Ramdhan Meena Geejgarh Member 8 Chunni Lal/Sonpal Saini Geejgarh Member
9 Shimbhu Dayal /Motiram Meena Geejgarh Member 9 Hajari Lal/ Laxman Prasad Saini Geejgarh Member
10 Laturmal/Kishori Lal Meena Geejgarh Member 10 Somotya /Kailash Dhobi Geejgarh Member
11 Banwari Lal /Mishri Lal Meena Geejgarh Member 11 Prahlad /Jagmohan Sharma Geejgarh Member
12 Geelaram /Kanchan ram Meena Geejgarh
1 Khilariram /Mishri Lal Meena Geejgarh President 1 Ramjilal /Bheru Lal Bairwa Geejgarh President
2 Bablu/Lilyaram Meena Geejgarh Member 2 Mahesh /Ramji Lal Bairwa Geejgarh Member
3 Chiranjilal/ Bhorilal Meena Geejgarh Member 3 Mukesh BhagwanSahay Bairwa Geejgarh Member
4 Babulal/ Moolchand Meena Geejgarh Member 4 Mohanlal /Ramswroop Bairwa Geejgarh Member
5 Ghamanram/Sharwan Lal Meena Geejgarh Member 5 Surajmal /Ramkishan Bairwa Geejgarh Member
6 Bharosi Lal /Ramsahay Meena Geejgarh Member 6 Duli Chand/Kaluram Bairwa Geejgarh Member
7 Girraj /Prasadi Meena Geejgarh Member 7 Ramdeva /Khairati Bairwa Geejgarh Member
8 Harsahay/Jangliram Meena Geejgarh Member 8 Yadram /Babulal Bairwa Geejgarh Member
9 Ramswroop /Phool Chand Meena Geejgarh Member 9 Bhagwansahay/Bhori lal Bairwa Geejgarh Member
10 Somotya Lal /Moti Lal Meena Geejgarh Member 10 Dhanna Lal/Mangi Lal Bairwa Geejgarh Member
11 Suresh Kumar/ Kanaram Meena Geejgarh Member 11 Nathu Lal/Jamna Lal Bairwa Geejgarh Member
12 Pappuram /Mool Chand Meena Geejgarh Member
1 Hajari /Bisnya ram Saini Geejgarh President
2 Suresh /Bhagwan Sahay Saini Geejgarh Member
3 Rajesh /Ganga Sahay Saini Geejgarh Member
4 Mahendra /Hajari Lal Saini Geejgarh Member
5 Banwari /Hariram Saini Geejgarh Member
6 Sushil /Ramdhan Saini Geejgarh Member
7 Kamlesh /Mithuram Saini Geejgarh Member
8 Mukesh /Prabhu Ram Saini Geejgarh Member
9 Kanchan /MoolChand Saini Geejgarh Member
10 Khemraj /Ramphool Saini Geejgarh Member
11 Rewadmal /Hukmoram Saini Geejgarh Member
12 Ram Sahay /Ghasiram Saini Geejgarh Member
13 Bacchu /Govind Sahay Saini Geejgarh Member
14 Bhuraram/Ramsahay Saini Geejgarh Member
WHS/Anicut User Group Livestock Development User Group
Horticulture/Nursery User Group
Gram Panchayat: Geejgarh
Agriculture Development/Production User Group
Pasture Development User Group Landless Peoples User Group
Contour /Med Bandi User Group
7 IWMP I, BLOCK SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Prem Devi / Shambhoo Dayal Jangir President 1 Prem Devi Prajapat/ Ratan President
2 Puspa Devi / Balmukund Sharma Secreatary 2 Lali Devi / Rajendra yogi Treasurer
3 Prakashi / Jagdish Meena Member 3 Kesanti / Raghuveer Prajapat Secreatary
4 Prem Devi / Rajendra prasad Member 4 Sheela / Devi shyay Member
5 Kamla Bai / Hari prasad Member 5 Chando / Ram Dayal Yogi Member
6 Savitree /Bharat lal Member 6 Geeta / Hajari Yogi Member
7 Urmila / Murari lal Jangir Member 7 Keshanti / Om Prakash Member
8 Sushila / Ramkesh Meena Member 8 Hukum Bai / Kamlesh Meena Member
9 Sampati / Vishram Member 9 Kala Devi / Jagdish Member
10 Neha / Bansi Soni Member 10 Prem / Asheem khan Member
11 Puspa / Kanahiya lal Soni Member
12 Bhagwati / Ramkhilari Meena Member
13 Mori / Kailash Meena Member
1 Manju / Babu Sharma President 1 Meera / Dharmi Meena President
2 Laxmi / Narsi Sain Secreatary 2 Kamli / Hari Meena Secreatary
3 Meera / Nanak Sain Member 3 Seema / Kilan shyay Bairwa Member
4 Nirmla / Suresh Member 4 Bhawati / Hetram Bairwa Member
5 Kala / Jagdish Member 5 Puspa / Balmukund Sharma Member
6 Prem Lata / Tara chand Member 6 Meera / Nanag ram Member
7 Narangi / Suresh Meena Member 7 Lali / Lohra Meena Member
8 Santi / Kanihya lal Member 8 Suren / Vijay Meena Member
9 Saino / Harkesh Member 9 Heera / Lokesh Meena Member
10 Rameshwari / Jagdish Member 10 Papli / Jagram Meeena Member
Gram Panchayat: Thikiria
1. Jai Ambhe SHG 2. Jwala Mata SHG
3. Adarsh SHG 4. Anupurna SHg
ANNEXURE - II
Gram Panchayat wise/ Watershed Committee wise Details of Various Self Help Groups
8 IWMP I, BLOCK- SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Barphi / Vinod Meena President 1 Madan lal / Kilyan Sain President
2 Magani / Hajari Meena Secreatary 2 Suresh / Moolchand yogi Treasurer
3 Dhaphi / Mishri lal Meena Member 3 Rameshwar / Shri chandra Yogi Secreatary
4 Mosham / Dinesh Meena Member 4 Tara chand / Moolchand Member
5 Shanti / Kailash Meena Member 5 Pralad / Nanag ram Member
6 Rajanti / Rameshwar Meena Member 6 Babulal / Latoor Member
7 Dholi / Ramkesh Meena Member 7 Geeta / Vishanya Member
8 Kamlesh / Suresh Meena Member 8 Laxminarayan / Banbari Member
9 Kalawati / Prabhoo Meena\ Member 9 Satya narayan / Kilan Member
10 Gjari / Bharat lal Meena Member
1 Jagani / Vishnya Bairwa President 1 Beena / Ramphal President
2 Chameli / Babu Bairwa Secreatary 2 Moti / Badri Yogi Secreatary
3 Prem /Murari Member 3 Govind / Gulab Member
4 Koshalya / Nahar singh Member 4 Ram dayal / Narayan Member
5 Vimla / Kheraj Member 5 Bharosi / today Yogi Member
6 Meera / Puran Member 6 Bhajan / Jagan Member
7 Durga / Pappu Member 7 Moharsingh / Kanchan Member
8 Koshalya / Natram Member 8 Murari / Kishan lal Member
9 Koshalya / Bablu Member 9 Girdhari / Bahu nath Member
10 Angoori / Bodaya Member 10
11 Kamla / Bhagwan shay Member
S.No. Name/Fathers Name Village Postion
1 Urmila / Sant Ram Meena President
2 Chet ram / Chhote lal Koli Secreatary
3 Mangal / Ghudmal Treasurer
4 Mool chand / Ramshay Member
5 Satish /Giraj Member
6 Mithan / Lohra Member
7 Giraj / Reware Member
8 Giraj / Lohra Member
9 Jagan /Chhudmal Member
Gram Panchayat: Pilodi
3. Chamunda Mata SHG 4. Jai Ganesh SHG
5. Shri Ram SHG
1. Ganga SHG 2. Bajrang SHG
9 IWMP I, BLOCK- SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Muli /Rajaram Gurjar President 1 Ramko /Ram Singh Gurjar President
2 Pinki /Man Singh Secreatary 2 Neelam /Vijay Singh Treasurer
3 Choti /Jwan Singh Member 3 Mmta /Vinod Secreatary
4 Nathi / Bhadur Singh Member 4 Dhan Bai /Ram Prasad Member
5 Santi / Sumer Singh Member 5 Koshlya /Ram Singh Member
6 Prem /Baney Singh Member 6 Rampyari /Kishan Lal Member
7 Jasoda /Shri Chand Member 7 Sukhbai / Kailsh Member
8 Dhan Bai /Ramawtar Member 8 Rajanti /Raju Member
9 Suraj /Rajendra Gurjar Member 9 Geeta /Hari Singh Member
10 Anita /Gulab Singh Member Maya / Ramawtar
1 Nathi /NanagRam Bairwa President 1 Jagni / Girraj Bairwa President
2 Sheela /Bhudda Yogi Secreatary 2 Meera / Harkesh Secreatary
3 Meera /Narendra Member 3 Keshi / Kailash Member
4 Urmila /Todarmal Member 4 Meera / Suresh Member
5 Sushila / Rameshwar Member 5 Papita /Lekhraj Member
6 Lali /Mahesh Member 6 Roshan /Rakesh Member
7 Rekha /Jitendar Member 7 Rampati /Santosh Member
8 Laxma /Bholu Ram Member 8 Alka /Ravindra Member
9 Pinki /Bhagwan Sahay Member 9 Naresh /Rakesh Member
10 Kamla /Sheesh Ram Member 10 Rumali /Shambhoo Member
S.No. Name/Fathers Name Village Postion
1 Asha /Vijay Singh President
2 Phooli /Ram Singh Secreatary
3 Geeta /Murari Lal Treasurer
4 Badam /Harsahay Member
5 Bhoti /Kishor Member
6 Guddi /Banwari Member
7 Kanta /Hukum Singh Member
8 Sunita /Parsadi Member
9 Geeta /Suya Lal Member
10 Meera /Sita Ram Member
Gram Panchayat: Pancholi
1. Sarswati SHG 2. Murlipur SHG
10 IWMP I, BLOCK- SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Ladbai /Rakesh Bairwa President 1 Manju / Manish President
2 Meera /Malkhan Bairwa Secreatary 2 Meera / Kailashi Treasurer
3 Saroj /Girraj Member 3 Jairam /Lallu Saini Secreatary
4 Sona /Rajendra Member 4 Ujanti /Ram Singh Member
5 Heera /Suresh Member 5 Lali / Shiv Lal Saini Member
6 Kantha /Daya Ram Member 6 Kamphori /Rajendra Member
7 Vimla /Prahalad Member 7 Bholi /Brij Lal Member
8 Anguri /Ramji Lal Member 8 Sushila / Santosh Member
9 Rameshi /Karan Singh Member 9 Sharda /Hari Ram Member
10 Bhori /Kishan Lal Member 10 Chota /Kanhaiya Lal
1 Manohar /Mukesh President 1 Rajanti /Somati Lal President
2 Tofli Devi /Panchuram Secreatary 2 Pramila /Rajendra Secreatary
3 Sundar /Jagdish Member 3 Keshanta /Kailash Bairwa Member
4 Soni /Jagdish Member 4 Choti /Jagdish Bairwa Member
5 Santra /Karnphool Member 5 Sakunta /Shambhoo Dayal Member
6 Pushpa /Ramji Lal Member 6 Kamla /Hariprasad Member
7 Sunita /Mohanlal Member 7 Geeta /Ramawtar Member
8 Lali /Ramphool Member 8 Choti /Chote Lal Member
9 Rajanti /Karan Singh Member 9 Bhori /Gopal Lal Member
10 Manohari /Pemaram Member 10 Gulli /Prabhati Lal Member
S.No. Name/Fathers Name Village Postion
1 Meena /Mukesh Meena President
2 Wishbai /Ramdeen Secreatary
3 Lahadsi / Khilari Meena Treasurer
4 Munna Devi /Jagdish Member
5 Bhori /Mahesh Meena Member
6 Mukshi /Rajendra Member
7 Kali /Jagdish Prasad Member
8 Lakhana /Mohan Lal Member
9 Muthari /Sugan Lal Member
10 Mojanti /Rajendra Member
Gram Panchayat: Pipalki
11 IWMP I, BLOCK- SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Ramoti /Kajod Mal Bairwa President 1 Koshyla /Jagdish President
2 Santosh /Lalit Bairwa Secreatary 2 Chanchal /Mukesh Treasurer
3 Badami /Hatila Bairwa Member 3 Premi /Mool Chand Secreatary
4 Rajanti /Ram Singh Bairwa Member 4 Meera /Bhagchand Member
5 Samoti /Sheduram Member 5 Sona /Ramesh Member
6 Rajanti /Banshilal Member 6 Shanti /Kailash Chand Member
7 Geeta /Babulal Member 7 Meera /Vijendra Singh Member
8 Janki /Kishor Bairwa Member 8 Suraj /Ramphool Member
9 Rajanti /Vishram Bairwa Member 9 Dhapa /Kaluram Member
10 Lali /Radheshyam Bairwa Member 10 Jagni /Ramsahay
1 Manju /Santosh Jangir Geladi President 1 Sunita /Mukesh Meena Padli President
2 Laxmi /Babulal Sharma Secreatary 2 Deepika /Pawan Kr. Meena Secreatary
3 Sunita /Mukesh Jangir Member 3 Anokhi /Ratan Lal Meena Member
4 Chotti /Samoti Lal Bairwa Member 4 Lalit /Devraj Meena Member
5 Saroj /Mukesh Bairwa Member 5 Shanti /Vinod Kr. Meena Member
6 Kamla /Madan Mahawar Member 6 Manphooli /Mangiram Meena Member
7 Sajan /Dilip Singh Rajpoot Member 7 Kamod /Suresh /Meena Member
8 Pinki /Ramraj Singh Rajpoot Member 8 Meera /SatyaNarayan Meena Member
9 Sapna /Bhawani Singh Rajpoot Member 9 Kamla /Ashok Kr. Meena Member
10 Radha /RamBharosi Jangir Member 10 Sundri /Shri Kishan Meena Member
1 Seeta /Ramesh Meena President
2 Anita /Pappu Lal Meena Secreatary
3 Kamli /Surajmal Meena Member
4 Mangi /Kishan Lal Meena Member
5 Lali /Sher Singh Meena Member
6 Prem /Jagdish Meena Member
7 Geeta /Seetaram Meena Member
8 Seeta /Ramesh Chand Meena Member
9 Sheela /Hanuman Meena Member
10 Geeta /Sohan Lal Meena Member
Gram Panchayat: Kalwan
12 IWMP I, BLOCK- SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Shanti /Kedar Prasad Yogi President 1 Kamal Bai /Murari Lal President
2 Sarla /Babu Lal Secreatary 2 Seema /Harkesh Treasurer
3 Uganti /Manohar Lal Member 3 Indra /Makkhan Meena Secreatary
4 Shanti /Murari Lal Member 4 Muneshi /Ramkishor Member
5 Rajanti /Vinod Member 5 Manohari /Ram Singh Member
6 Rekha /Ghasi Ram Member 6 Mosam /Shiv Lahri Member
7 Parwati /Girdhari Lal Member 7 Sanjan /Shivram Member
8 Indu /Dheeraj Sharma Member 8 Basanti /Laxman Member
9 Manju /Mahendra Member 9 Mooli /Kishan Lal Member
10 Birma /Banwari Member 10 Guddi /Ram Kishan Member
1 Mukeshi /Surendra Chand Yogi President 1 President
2 Guddi /Rajesh Saini Secreatary 2 Secreatary
3 Mojanti Devi /Ramprasad Saini Member 3 Member
4 Meera Devi /Chotelal Saini Member 4 Member
5 Muli Devi /Ratan Lal Member 5 Member
6 Gulab Devi /Laxman Saini Member 6 Member
7 Soma Devi /Rewar Ram Saini Member 7 Member
8 Chemeli Devi / Ramhet Saini Member 8 Member
9 Rasal Devi /Ramesh Saini Member 9 Member
10 Badam /Munna Ram Saini Member 10 Member
Gram Panchayat: Achalpura
13 IWMP I, BLOCK- SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Savitri /Mukesh Mahawar President 1 Kanta /Mukesh Saini President
2 Rumali /Mahendra Saini Secreatary 2 Dmarti /Kamlesh Saini Treasurer
3 Anguri /Rajendra Kr. Saini Member 3 Seeta /Kamlesh Saini Secreatary
4 Vimla /Vinod Kr. Saini Member 4 Rambai /Ramawtar Saini Member
5 Rumali /Mukesh Kr. Saini Member 5 Urmila /Bheemsen Saini Member
6 Rajjo /Ramesh Chand Saini Member 6 Sushila /Pushpendra Saini Member
7 Pinkki /Vijendra Saini Member 7 Lali /Raju Saini Member
8 Bandana /Ashok Saini Member 8 Phooli /Rang Lal Saini Member
9 Virma /Khildi Saini Member 9 Galli /Rattiram Saini Member
10 Amarti /Babulal Saini Member 10 Meera /Ramji Lal Saini Member
1 Geeta /Rajkumar Bairwa President 1 Nahni /Vishram Mahawar President
2 Kamli /Babu Lal Bairwa Secreatary 2 Maya /Mithu Ram Saini Secreatary
3 Santosh /Dinesh Bairwa Member 3 Lali /Prem Chand Saini Member
4 Inder /Bhagwan Sahay Bairwa Member 4 Uganti /Mohan Lal Saini Member
5 Sushila /Hajari Lal Bairwa Member 5 Roshani /Dimesh Chand Saini Member
6 Munna /Shambhu Dayal Bairwa Member 6 Gulab Lallu Ram Saini Member
7 Meera /Laxman Lal Bairwa Member 7 Singari /Kishan Lal Saini Member
8 Guddi /Mahesh Kr. Bairwa Member 8 Kamla /Kailash Chand Saini Member
9 Shakuntala /Ghanshyam Bairwa Member 9 Vidha /Ramkishor Saini Member
10 Dhapa /Ramswaroop Bairwa Member 10 Kisturi /Prabhoo Dayal Member
1 Anita /Sushil Kr. Saini President
2 Guddi /Gilya ram Saini Secreatary
3 Keshanta /Bhooriya Lal Saini Member
4 Vimla /Bacchu Lal Saini Member
5 Bhagwati /Pappu Ram Saini Member
6 Kali /Govind Sahay Saini Member
7 Mankali /Banwari Member
8 Guddi /Suresh Saini Member
9 Bhonti /Mithya Ram Member
10 Prem /Hari Ram Saini Member
Gram Panchayat: Geejgarh
14 IWMP I, BLOCK- SIKRAI, DAUSA
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Rambharosi / Kaniahiya lal meena President 1 Dharm shyay / Ratti ram meena President
2 Bharat lal / Ramkishan meena Secreatary 2 Ganga shay / sanwal Ram meena Secreatary
3 Kistoor chand / Panna lal sharma Member 3 Madan / Kilan sain Member
4 Devishyay / Ram kishan prajapat Member 4 Kailash /khyali meena Member
5 Chota Ram / Ramphal meena Member 5 Babulal / Bansi bairwa Member
6 Ramkishan / Bhambhola meena Member 6 Vinod kumar/ Puran mal meena Member
7 Meera Devi / Dharmi meena Member 7 Jagani /Vishnya Bairwa Member
8 Manju / Babulal sahram Member 8 Beena / Ramphal meena Member
9 Prem Devi / Ratan kumar prajapat Member 9 Urmila / Sant ram meena Member
10 Prem Devi / Shambhoo Dayal Jangir Member 10 Bharphi / Vinod meena Member
11 Mangi Devi / Punya Bairwa Member 11 Rambharosi / Dhanna Ram meena Member
S.No. Name/Fathers Name Village Postion S.No. Name/Fathers Name Village Postion
1 Badan singh / Ramhans Gurjar President 1 Rajendra /Budharam Saini President
2 Jhandoo singh / Ram singh Gurjar Secreatary 2 Banwari Lal /Ram Sahay Meena Secreatary
3 Kailash / shavan singh Member 3 Bhambhu Nath /Ghashi Nath Member
4 Sardar /Laxman Singh Member 4 Murari Lal /Bhori Lal Bairwa Member
5 Ishwar mal /Ramdhan Gurjar Member 5 Mahesh Kumar /.Lalaram Meena Member
6 Bhajan Lal /Ramhet Bairwa Member 6 Chote lal /Sukhlal Mahawar Member
7 Muli Devi /Rajaram Gurjar Member 7 Somotya /Habbu Ram Member
8 Dhan Kanwar /Bhawani Singh Member 8 Bhaoti Devi /Girraj Bairwa Member
9 Nathi Devi /Nanagram Bairwa Member 9 Lad Bai//Rakesh Bairwa Member
10 Jagni Devi /Girraj Bairwa Member 10 Meena Devi /Mukesh Meena Member
11 Radha Kishan /Ramdhan Bairwa Member 11 Gulab Devi /Pappu Ram Saini Member
ANNEXURE - III
Gram Panchayat wise/ Watershed Committee wise Details of Watershed Committee
Watershed Committe Thikiria Watershed Committee Pilodi
Watershed Committe Pancholi Watershed Committe Pipalki
15 IWMP I, BLOCK- SIKRAI, DAUSA
Gram Panchayat: Thikiria
S.No. Name/Father's Name Caste Village No. of Plants Varieties of Plants Area (Bigha)
1 Kailash / Malya Meena Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
2 Ramesh /Lohadya Meena Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
3 Khirari /Kanhaiya Meena Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
4 Mangal Ram /Kajodya Meena Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
5 Prahalad /Hajari Meena Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
6 Sukhram /Kaluram Bairwa Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
7 Ramdhan /Murli Bairwa Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
8 Mool Chand /Kanhaiya Bairwa Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
9 Girraj /Kalya Bairwa Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
10 Gabdu /Ramshi Bairwa Darjapur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
11 Harish /Birbal Meena Thikria 250 Anar, Niboo, Anwala, Amrood 1 Bigha
12 Fulya /Prabhu Meena Thikria 250 Anar, Niboo, Anwala, Amrood 1 Bigha
13 Hariram /Ummedi Meena Thikria 250 Anar, Niboo, Anwala, Amrood 1 Bigha
14 Hari Kishan /Pratap Meena Thikria 250 Anar, Niboo, Anwala, Amrood 1 Bigha
15 Ramkesh /Raju Meena Thikria 250 Anar, Niboo, Anwala, Amrood 1 Bigha
16 Rameshwar /Sarju Sharma Thikria 250 Anar, Niboo, Anwala, Amrood 1 Bigha
17 Ramswroop /Chanda Meena Thikria 250 Anar, Niboo, Anwala, Amrood 1 Bigha
18 Hajari /Bansi Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
19 Tejram /Prabhudayal Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
20 Shivlal /Bhura Ram Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
21 Rajpal /Ramjilal Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
22 Prabhu /Ramdhan Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
23 Girraj /Johri Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
24 Ramesh /Meetha ram Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
25 Kalu /Kalyan Meena Patti Salesingh 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
26 Pappu /Bharoshi Meena
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
27 Gopal /Ghashi Meena
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
28 Kishan /Hariya Mali Mali
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
29 Ramkishor /Ramdhan Meena
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
30 Ramotar /Kanhaiya ram Sharma
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
31 Ramkhilari /Ghantoli Bairwa
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
32 Harmukh /Harsahay Meena
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
33 Ganga Ram /Ramswaroop Meena
Kheda
Pahadpur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
ANNEXURE - IVList of Beneficiaries/Cultivators selected for Horticulture Plants
IWMP I, BLOCK SIKRAI, DAUSA
34 Bachan Singh /Bahadur Singh Rajpoot Sultan pur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
35 Balveer Singh /Mohan Singh Rajpoot Sultan pur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
36 Kamla /Babulal Bairwa Sultan pur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
37 Faili /Ghisya Bairwa Sultan pur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
38 Chota /Chaina Bairwa Sultan pur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
39 Kalu /Kalyan Meena Sultan pur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
40 Ramkhilari / Sawaria Meena Sultan pur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
6550Total
IWMP I, BLOCK SIKRAI, DAUSA
Gram Panchayat: Pilodi
S.No. Name/Father's Name Caste Village No. of Plants Varieties of Plants Area (Bigha)
1 Dhapuram /Chiranji Lal Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
2 Kuldeep /Kailash Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
3 Shivlal /Moharpal Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
4 Kanchan /Ram Sahay Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
5 Bacchu /Ramdhan Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
6 Prahlad /Mulya Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
7 Bharatlal /Hira Lal Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
8 Kishor /Manohari Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
9 Shri Man /Dharmsahay Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
10 Surajmal /Rewad Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
11 Ramdhan /Chiranji Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
12 Shri phool /Dhanna Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
13 Pratap /Kajodya Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
14 Ramprasad /Harchanda Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
15 Ummedi /Ramhet Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
16 Thandi /Sawalram Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
17 Jhalu /Mangya Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
18 Shivram/ Harsahay Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
19 Prahlad /Parsadi Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
20 Kedar /Jainarayan Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
21 Prahlad /Nanagram Saini Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
22 Mahesh /Parmatya Saini Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
23 Ramesh /Vishram Sharma Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
24 Kilan /Omkar Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
25 Mitthan /Lohadya Koli Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
26 Bharosi /Suklya Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
27 Pooran /Meva Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
28 Kedar /Ramswaroop Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
29 Lohadya /Kajod Meena Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
30 Jagram /Omkar Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
31 Mohan /Jagdeva Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
32 Raji Devi /Charan Meena Pilodi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
IWMP I, BLOCK SIKRAI, DAUSA
33 Ramdhan /Sulya Meena Heengi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
34 Dharm Sahay/Sitaram Meena Heengi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
35 Pooran /Jainarayan Meena Heengi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
36 Raghunath /Ghasi Meena Heengi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
37 Jaldhari /Jairam Meena Heengi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
38 Ghanshayam/Kalu Meena Heengi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
39 Pyarelal /Ghisya Meena Heengi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
40 Ratanlal /Radha Kishan Meena Heengi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
41 Bhagwan Sahay /Siyaram Meena Heengi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
42 Harsahay /Jainarayan Meena Khedi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
43 Girwar /Gordhan Meena Khedi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
44 Lakhan /Kishanlal Meena Khedi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
45 Ramkishor /Balu Meena Khedi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
46 Badri /Ramsahay Meena Khedi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
47 Rameshwar /Gabdu Meena Khedi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
48 Madan /Kilan Sain Pilodi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
8700Total
IWMP I, BLOCK SIKRAI, DAUSA
Gram Panchayat: Pancholi
S.No. Name/Father's Name Caste Village No. of Plants Varieties of Plants Area (Bigha)
1 Rajaram /Mindya ram Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
2 Murari /Moolchand Sain Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
3 Jairam /Shyobaksh Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
4 Dharm Singh/Nathu Lal Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
5 Mohar Singh/Kishanlal Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
6 Savitri Devi/ Dharm Singh Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
7 Kamal /Chajulal Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
8 Sardar /Kajod Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
9 Brij Lal /Jagdeva Gurjar Pancholi 250 Anar, Niboo, Anwala, Amrood 1 Bigha
10 Jawaan Singh/ Kanhaiya Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
11 Nathu Lal /Hargovind Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
12 Pukhraj /Mohanlal Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
13 Harkesh /Jagdish Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
14 Ramotar /Harbaan Singh Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
15 Badan Singh /Ramhans Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
16 Nihal Singh /Mohan singh Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
17 Meetha lal /Kishanlal Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
18 Madho Singh /Mohan Lal Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
19 Bholu Ram /Ram Gopal Gurjar Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
20 Hira Lal /Seduram Saini Pancholi 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
21 Ram Singh /Ananda Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
22 Hukum Singh /Ramkishor Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
23 Rameshwar /Nehnu ram Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
24 Bane Singh / Sarwan Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
25 Mool Chand /Bheema Ram Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
26 Siyaram /Kanji ram Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
27 Sardar/Laxman Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
28 Ranglal /Ghamman Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
29 Vijay Singh /Ramphool Gurjar Murlipur 250 Anar, Niboo, Anwala, Amrood 1 Bigha
30 Raghuveer /Ramsahay Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
31 Babulal /Nahnuram Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
32 Rajaram /Kanhaiya Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
IWMP I, BLOCK SIKRAI, DAUSA
33 Buddaram Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
34 Bahadur /Ishwarmal Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
35 Ramotar /Chaju Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
36 Kishanlal /Shodaan Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
37 Bacchu /Kishor Gurjar Murlipur 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
38 Hari Singh /Moolchand Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
39 Laxman /Jagdev Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
40 Ram Singh /Ramdhan Gurjar Khedla 250 Anar, Niboo, Anwala, Amrood 1 Bigha
41 Karan Singh /Chaju Lal Gurjar Khedla 250 Anar, Niboo, Anwala, Amrood 1 Bigha
42 Ramotar /Rewadmal Gurjar Khedla 250 Anar, Niboo, Anwala, Amrood 1 Bigha
43 Nahar Singh /Meetha lal Gurjar Khedla 250 Anar, Niboo, Anwala, Amrood 1 Bigha
44 Hiralal /Seduram Saini Khedla 250 Anar, Niboo, Anwala, Amrood 1 Bigha
45 Bahgwan Sahay /Mangilal Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
46 Rajaram /Girraj Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
47 Nathuram/ Ganga Bishan Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
48 Radha Kishan /Kanhaiya Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
49 Hiralal /Mangilal Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
50 Rattiram /Raguveer Gurjar Khedla 100 Anar, Niboo, Anwala, Amrood 1/2 Bigha
8300Total
IWMP I, BLOCK SIKRAI, DAUSA
Gram Panchayat: Pipalki
S.No. Name/Father's Name Caste Village No. of Plants Varieties of Plants Area (Bigha)
1 Ganga Bishan/Ramsahay Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
2 Wish Bai/Ramdeen Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
3 Choti /Rakesh Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
4 Kanhaiya Lal/Shrinarayan Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
5 Molaram /Gangasahay Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
6 Ramesh /Chotu ram Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
7 Malkhan /Gokul Bairwa Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
8 Sukhlal /Bhorilal Koli Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
9 Mool Chand /Bhorilal Koli Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
10 Ghanshyan /Babulal Yogi Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
11 Vijay /Mangalram Yogi Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
12 Mohan lal /Kanhaiya Lal Yogi Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
13 Pintu /Kalyan Sahay Yogi Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
14 Bahmbhoo /Ghashi Yogi Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
15 Vinod /Kanniram Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
16 Gabdu /gopiram Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
17 Rajanti /Ratiram Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
18 Ramjilal / Phool Chand Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
19 Sukhram /Ranglal Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
20 Bhoti /Kishan Lal Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
21 Kali /Ramratan Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
22 Vishram /Ramhet Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
23 Ummedi /Ramsahay Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
24 Jagdish /Manohari Lal Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
25 Ramniwash /Kanna ram Bairwa Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
26 Harsahay /Panchuram Bairwa Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
27 Murari /Bhori Lal Bairwa Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
28 Devi Sahay /Bhajanlal Bairwa Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
29 Santosh /Mohanlal Bairwa Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
30 Bacchu lal/Gulab Bairwa Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
31 Ramkishor /Indar Meena Sikri 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
32 Manna /Badri Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
IWMP I, BLOCK SIKRAI, DAUSA
33 Lallu /Parsadi Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
34 Pooran /Kajod Meena Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
35 Somotya /Habu Bairwa Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
36 Babu /Hajari Gurjar Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
37 Chiranji /Nattha Khumar Sikri 250 Anar, Niboo, Anwala, Beel 1 Bigha
38 Girraj /Sariya Bairwa Dhulkot 250 Anar, Niboo, Anwala, Beel 1 Bigha
39 Ramjilal /Ghasi Bairwa Dhulkot 250 Anar, Niboo, Anwala, Beel 1 Bigha
40 Prabhati /Laxman Bairwa Dhulkot 250 Anar, Niboo, Anwala, Beel 1 Bigha
41 Kamal /Kajod Bairwa Dhulkot 250 Anar, Niboo, Anwala, Beel 1 Bigha
42 Ramkaran /Sariya Bairwa Dhulkot 250 Anar, Niboo, Anwala, Beel 1 Bigha
43 Buddaram /Gangadhar Bairwa Dhulkot 250 Anar, Niboo, Anwala, Beel 1 Bigha
44 Dhanya /Kajod Khumar Dhulkot 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
45 Babu lal /Nathya Saini Dhulkot 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
46 Ramdhan /Gangadhar Saini Dhulkot 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
47 Brijlal /Kanhaiya lal Saini Dhulkot 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
48 Ram Swaroop /Gangadhar Saini Dhulkot 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
49 Mukesh /Ramdhan Saini Dhulkot 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
50 Munna /Rewad Gurjar Dhulkot 100 Anar, Niboo, Anwala, Beel 1/2 Bigha
8750Total
IWMP I, BLOCK SIKRAI, DAUSA
Gram Panchayat: Kalwan
S.No. Name/Father's Name Caste Village No. of Plants Varieties of Plants Area (Bigha)
1 Umrao /Kishori Lal Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
2 Shivlal /Kishori Lal Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
3 Bacchu /Mishri Nath Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
4 Prakash /Hariram Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
5 Kamlesh /Chuttan Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
6 Ramkaram /Mishri Nath Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
7 Kaluram /Ramdhan Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
8 Chuttan /Johri Nath Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
9 Ramawtar/Jhutharam Yogi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
10 Krishan Awatar/ChaganLal Gupta Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
11 Mangalram /Harjiram Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
12 Lallu ram/Moolchand Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
13 Bharosi /Motilal Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
14 Kishan lal/Somotya Bairwa Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
15 Kamlesh /Prabhu Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
16 Sitaram /Rameshwar Bairwa Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
17 Kamal Singh /Ramkishan Gurjar Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
18 Ramphool /Sohanpal Gurjar Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
19 Bhagwan Sahay/Ramjilal Gangir Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
20 Chothmal /Shuklaram Khatik Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
21 Indramal /Suwalal Harijan Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
22 Kishan Lal/Moolchand Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
23 Ramkuwar /Jhulya ram Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
24 Siyaram /Gokal Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
25 Hansraj /Rameshwar Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
26 Sampati /Gulyaram Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
27 Kamlesh /Laxman Gurjar Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
28 Mukesh /Shankarlal Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
29 Mahendra /Harbhajan Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
30 Gordan /Devpal Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
31 Battu /Ratanlal Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
32 Hablu /Meetha lal Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
IWMP I, BLOCK SIKRAI, DAUSA
33 Banshi /Harya Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
34 Ramsawroop /Basanpal Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
35 Ramkishor /Gordhan Meena Kalwan 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
36 Nathya /Sedya Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
37 Kallu /Mulya Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
38 Ramsahay /Feli ram Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
39 Mewasi /Ramshya Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
40 Shree /Ramjilal Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
41 Babu /Ratanlal Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
42 Hargovind /Jyala Prasad Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
43 Shrikishan /Rampal Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
44 Murari /Ganesh Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
45 Shatrudhan das/ Ramcharam Vaishnav Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
46 Basna Devi/Shatrudahan Das Bairagi Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
47 Rajendra /Dhanak Lal Harijan Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
48 Nangram /Dharmpal Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
49 Ramdhan /Gopal Meena Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
50 Rambabu /Motilal Gupta Kalwan 250 Anar, Anwala, Beel,Amrood 1 Bigha
8900Total
IWMP I, BLOCK SIKRAI, DAUSA
Gram Panchayat: Achalpura
S.No. Name/Father's Name Caste Village No. of Plants Varieties of Plants Area (Bigha)
1 Murari Lal/Kishanlal Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
2 Dharmpal /Harjiram Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
3 Shivram /Arjun Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
4 Ramesh /Mahadeva Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
5 Laxman /Nathu Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
6 Battu /Ramdhan Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
7 Dholi /Girdhari Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
8 Gangasahay/Kanchan Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
9 Kailash /Laxman Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
10 Jaldhari /Jaiphool Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
11 Rampal /Badri Meena Chandpur 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
12 Sitaram /Ramkishor Gurjar Jhangiria 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
13 Jai Singh /Kilan Gurjar Jhangiria 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
14 Kumer Singh/Harsahay Gurjar Jhangiria 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
15 Radha Kishan /Shreeya Gurjar Jhangiria 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
16 Prabhati Lal /Rewad Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
17 Laxman /Meetha Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
18 Ramhet /Amarchand Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
19 Pukhraj /Rewad Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
20 Raghuveer /Ramsahay Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
21 Ramjilal /Kanhaiya Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
22 Ramdhan /Gulab Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
23 Mangilal /Panchuram Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
24 Dayaram /Hiralal Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
25 Moolchand/Ramsukha Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
26 Gangaram /Gordhan Gurjar Jhangiria 250 Anar, Anwala, Beel,Amrood 1 Bigha
27 Ramdhan Prajapat Prajapat Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
28 Mahesh /Kanhaiya Lal Prajapat Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
29 Arjun /Ramkishor Saini Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
30 Prakash /Gendaram Bairwa Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
31 Babulal /Nondaram Saini Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
32 Suresh /Durga Prasad Prajapat Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
33 Kaluram /Ramdhan Prajapat Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
34 RamCharan/Chajuram Sharma Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
IWMP I, BLOCK SIKRAI, DAUSA
35 Girraj /Ramkishan Sharma Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
36 Babu Singh/Mool Singh Rajpoot Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
37 Manohar /Dhannalal Saini Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
38 Gabduram/Puniram Saini Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
39 Harimohan/Prasadi Saini Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
40 Chandr Lal/Bansiram Saini Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
41 Girraj/Panna Lal Saini Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
42 Ramkaran/Gokul Saini Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
43 Chajuram/Netram Saini Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
44 Satish/Ramjilal Agarwal Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
45 Prabhu Singh/Sodan Singh Rajpoot Sarundla 250 Anar, Anwala, Beel,Amrood 1 Bigha
46 Banwari/Prabhu Dayal Sharma Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
47 Prahlad/Ramawtar Sharma Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
48 Mohan/Prabhati Lal Sharma Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
49 Manohar/Bhag Chand Sharma Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
50 Suresh /Rampratap Sharma Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
51 Raghunath/Moolchand Bairwa Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
52 Tehram /Moolchand Bairwa Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
53 Mahesh /Roshanlal Bairwa Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
54 Pachuram /Ishwar Bairwa Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
55 Babulal/Prabhatya Bairwa Achalpura 250 Anar, Anwala, Beel,Amrood 1 Bigha
56 Kaluram/Nathulal Bairwa Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
57 Ram Narayan/Budharam Bairwa Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
58 Mahesh /Devkaran Bairwa Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
59 Vishram /MoolChand Bairwa Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
60 RamDayal /Mangilal Bairwa Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
61 Omprakash/Jainaram Bairwa Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
62 Ganpat/Rewad Meena Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
63 Mohan Singh Rajpoot Chak Sarundla 100 Anar, Anwala, Beel,Amrood 1/2 Bigha
10800Total
IWMP I, BLOCK SIKRAI, DAUSA
Gram Panchayat: Geejgarh
S.No. Name/Father's Name Caste Village No. of Plants Varieties of Plants Area (Bigha)
1 Ramesh/Ramsahay Saini Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
2 Ram Kishan/Nanagram Saini Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
3 KrishanKant/Prabhu Dayal Tiwari Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
4 Chandra Prakash/Prakash Mohan Sharma Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
5 Lalluram /Surajmal Saini Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
6 Gangaram/Birdi Chand Saini Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
7 Jagdish/Ramdhan Saini Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
8 Moti Lal/Kanhaiya Lal Saini Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
9 Prabhu Dayal/Mool Chand Saini Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
10 Pursottam/Sitaram Sharma Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
11 Jagdish/ Ganeshram Sharma Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
12 Ram Charan/Ramji Lal Sharma Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
13 Hanuman/Haburam Sharma Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
14 Pintu/Mangilal Sharma Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
15 Ganga Ram/Ram Swaroop Sharma Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
16 Kanchan Lal/Chandar Ram Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
17 Ram Sahay/Pachu Ram Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
18 Kanhaiya/Dudaram Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
19 Jagdish/Gyarsi Lal Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
20 Ramdhan/Bhpri Lal Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
21 Girraj/Sharwan Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
22 Chote Lal/Badri Prasad Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
23 Chothmal/ Nahnuram Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
24 Johri/Moolchand Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
25 Kallu Ram/Ganesh Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
26 Babu Lal/Rooplya Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
27 Dundaram/Pachuram Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
28 Mangalram/ Ramdhan Saini Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
29 Ram Swroop/Mishri Lal Meena Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
30 Jaldhari/Sharwan Meena Geejgarh 250 Amrood, Anar, Anwala 1 Bigha
31 Prahlad/Prabhu Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
32 Ramawatar/Lalluram Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
33 Babulal/Mohanlal Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
34 Ramwatar/Chuttan Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
IWMP I, BLOCK SIKRAI, DAUSA
35 Khemraj/Bholaram Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
36 Rewad/Kalwan Sahay Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
37 Chiranji/Badriram Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
38 Kanwarpal/Daluram Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
39 Saohanlal/Shankarlal Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
40 Rakesh/Jagdish Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
41 Raju/Kishori Lal Meena Geejgarh 100 Amrood, Anar, Anwala 1/2 Bigha
6350Total
IWMP I, BLOCK SIKRAI, DAUSA
A. WATER TANKS.No. Item No L (Ft) B (Ft) H (Ft) Qty Rate Amount
3.14 10.00 1.00 3.00 94.29
3.14 15.50 1.00 2.00 97.43
191.71
Cum 5.43 75.00 407.32
3.14 10.00 1.00 0.50 15.71
3.14 15.50 1.00 0.50 24.36
0.785 9.50 9.50 0.333 23.615
Total 63.69
iRFkj dh fxêh ds lkFk Cum 1.80 1968.00 3550.59
3.14 15.50 1.00 2.50 121.68
lhesaV ctjh 1%6
Total 121.68
Cum 3.45 1499.00 5166.88
Inner 3.14 9.50 15.00 447.86
Outer 3.14 11.00 15.00 518.57
Total 966.43
sqm 89.82 83.00 7454.79
vk-lh-lh dke ds fy, yksgs dks dkVuk] eksM+uk rFkk LFkku ij yxkuk
rFkk cka/kus dk dk;Z e; vkiwfÙkZ dsA
10 mm dia 34.5 19.8 35 19.75 682.17
m 207.91
Kg 128.34
8mm 3 3.14 10 96.56
Binding 13 33 13 33 429.00
525.56
m 160.18
kg 63.28
Total 191.62 51.60 9887.76
0.786 11.00 11.00 95.07
sqm 8.84 722.00 6379.33
lhesaV IykLVj nhokj ij 1%4 vuqikr es lhesaV&ctjh feykdj dj
tksMksa dks dqjsnus rFkk rjkbZ lfgr 25 fe-eh-@20 fe-eh-@12 fe-eh-
esaA
3.14 9.50 12.00 358.29
20 eh- eh- 3.14 11.00 13.00 449.43
807.71
sqm 75.07 99.00 7431.57
lhesaV dkØhaV 1%1-5%3 feJ.k dh izofyr lhesaV dkØhaV esa Mkyuk
rFkk vkiwfÙkZ djuk] Nr dh Lysc] NTts] che] fyVay vkfn esa] nckuk]
rjkbZ djuk rFkk lrg dks 1%3 lhesaV elkys ls lery djuk vkfn
lesar ijUrq LVªhy rFkk 'kVfjax dh dher vyx lsA
3.14 10.25 0.75 15.00 362.41
flooring 0.79 9.50 9.50 0.50 35.46
Total 397.87
Cum 11.27 3522.00 39696.44
9 90 fe-eh- vkSlr eksVkbZ es lhesaV dkØhaV nM+ ftles 1 Hkkx lhesaV %
3 Hkkx ctjh rFkk 6 Hkkx 12 fe-eh- ukeh; ,xzhxsV feykdj vkj-lh-
lh- Nr ;k iêh ij bl izdkj Mkyuk fd pkgh xbZ fn'kk es <+yku
1%60 dk izkIr fd;k tk lds rFkk fo'ks"k fooj.k ds vuqlkj 6 fe-eh-
O;
0.786 10.5 10.5 86.63
sqm 8.05 421.00 3389.32
0.786 9.50 9.50 0.75 53.18
3.14 12.00 2.00 0.75 56.52
Total 109.703036
Cum 3.11 583.40 1813.05
3.14 13.00 3.00 122.57
sqm 11.39 208.00 2369.41
11 Providing & fixing Iron gate valve, tape 4Nos Pipe fittings etc 1000.00
TOTAL FOR WATER TANK 88546.47
1 (a) uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ djuk] ry
dks dwVuk] ikuh Mkyuk] cxy dks laokjuk] [kqnh feêh dks ckgj
fudkyuk] uhao Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk
rFkk cph gqbZ feêh dks 50 ehVj dh nwjh rd fuLrkj.k djuk
lk/kkj.k@eq
2
10 50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k ftlesa 1 lhesaV 2
ctjh 4 iRFkj dh ;k bZaV dh 12 - eh- ukHkh; fxV̀Vh ds lkFk
feykdj Mkyuk] dwVuk] nckuk rFkk rjkbZ vkfn lesr AiRFkj dh
fxV̀Vh
4 lsUVfjax&'kVfjax dk vkj-lh-lh- Nr] Lysc] che] NTts] fyUVy
vkfn Mkyus ds fy, yxkuk 4-5 ehVj ÅapkbZ rd ds fy, rFkk
gVkuk vkfn fo'ks"k fooj.k ds vuqlkjA
EPA ESTIMATE NO. 1
NAME OF WORK: CONSTRUCTION OF WATER TANK, KHEL AND SOAK PIT
lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki dh iRFkj
fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1 lhesUV % 4 jsr % 8
fxÍh vuqikr eas feykdj Mkyuk rFkk dqVkbZ djuk] rjkbZ lesrA
3 uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 % 3] 1 %
6 ;k 1 % 8 elkys es] e; cxy dh f>jh cUn djuk rFkk rjkbZ
vkfnA
5
6 vOoy ntsZ dh iRFkj dh ifê;ksa dh Nr Mkyuk] Åij rFkk uhps ls
tksMksa es iRFkj dh phi ds lkFk 1%4 vuqikr esa lhesaV elkys ls
HkjukA
7
8
9 Q'kZ ds uhps lw[ks iRFkjksa dk [kjatk yxkuk o vkiwfrZ djuk
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item No L (Ft) B (Ft) H (Ft) Qty Rate Amount
B. SOAK PIT
0.79 2.75 2.75 15.00 77.25
77.25
Cum 2.19 75.00 164.07
l[r] fpduh] dadj feêh esa
0.786 2.75 2.75 5.94
sqm 0.55 722.00 398.71
lhesaV dkØhaV 1%1-5%3 feJ.k dh izofyr lhesaV dkØhaV esa Mkyuk
rFkk vkiwfÙkZ djuk] Nr dh Lysc] NTts] che] fyVay vkfn esa] nckuk]
rjkbZ djuk rFkk lrg dks 1%3 lhesaV elkys ls lery djuk vkfn
lesar ijUrq LVªhy rFkk 'kVfjax dh dher vyx lsA
3.14 2.75 0.34 12.00 35.26
flooring
Total 35.26
Cum 1.00 3522.00 3518.29
TOTAL FOR SOAK PIT 4081.08
C. KHEL
2.00 17.00 2.00 2.50 170.00
2.00 2.50 2.00 2.50 25.00
195.00
Cum 5.52 75.00 414.19
lk/kkj.k@eqyk;e feêh esa
l[r] fpduh] dadj feêh esa
2.00 17.00 2.00 0.50 34.00
2.00 2.50 2.00 0.50 5.00
Total 39.00
iRFkj dh fxêh ds lkFk Cum 1.10 1774.00 1959.94
2 17.00 2.00 2.00 136.00
2 2.50 2.00 2.00 20.00
1 16.50 1.00 4.00 66.00
1 16.50 1.00 3.00 49.50
lhesaV ctjh 1%6 2 4.00 1.00 3.50 28.00
Total 299.50
Cum 8.48 1499.00 12714.54
1 16.50 4.00 66.00
2 16.50 3.00 99.00
4 4.00 3.50 56.00
221.00
sqm 20.54 99.00 2033.36
1.000 15.00 4.00 0.75 45.00
0 10.85 2.00 0.50 0.00
Total 45
Cum 1.27 583.40 743.71
1 15.00 4.00 60.00
60.00
sqm 5.58 208.00 1160.02
TOTAL FOR KHEL 19025.77
GRAND TOTAL 111653.32
1,00,000
3 uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 % 3] 1 % 6
;k 1 % 8 elkys es] e; cxy dh f>jh cUn djuk rFkk rjkbZ vkfnA
4
SAY
5 Q'kZ ds uhps lw[ks iRFkjksa dk [kjatk yxkuk o vkiwfrZ djuk
6 50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k ftlesa 1 lhesaV 2
ctjh 4 iRFkj dh ;k bZaV dh 12 - eh- ukHkh; fxV̀Vh ds lkFk
feykdj Mkyuk] dwVuk] nckuk rFkk rjkbZ vkfn lesr A
lhesaV IykLVj nhokj ij 1% 6 vuqikr es lhesaV&ctjh feykdj dj
tksMksa dks dqjsnus rFkk rjkbZ lfgr 20 fe-eh-esaA
1 uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ djuk] ry
dks dwVuk] ikuh Mkyuk] cxy dks laokjuk] [kqnh feêh dks ckgj
fudkyuk] uhao Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk
rFkk cph gqbZ feêh dks 50 ehVj dh nwjh rd fuLrkj.k djukA
2 vOoy ntsZ dh iRFkj dh ifê;ksa dh Nr Mkyuk] Åij rFkk uhps ls
tksMksa es iRFkj dh phi ds lkFk 1%4 vuqikr esa lhesaV elkys ls
HkjukA
3
1 uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ djuk] ry dks
dwVuk] ikuh Mkyuk] cxy dks laokjuk] [kqnh feêh dks ckgj
fudkyuk] uhao Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk
cph gqbZ feêh dks 50 ehVj dh nwjh rd fuLrkj.k djukA
2 lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki dh iRFkj
fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1 lhesUV % 5jsr % 10 fxÍh
vuqikr eas feykdj Mkyuk rFkk dqVkbZ djuk] rjkbZ lesrA
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item No L (Ft) B (Ft) H (Ft) Qty(CUft) Rate Amount
1 129.00 2.00 2.00 516.00
Total 516.00
Cum 14.62 75.00 1096.32
1 129.00 2.00 0.50 129.00
iRFkj dh fxêh ds lkFk 129.00
Cum 3.65 1968.00 7191.84
1 129.00 1.50 2.00 387.00
Total 387.00
lhesaV ctjh 1%6
Cum 10.96 1499.00 16433.804 1.50 1.50 4.50 40.50
Total 40.50
lhesaV ctjh 1%6 Cum 1.15 1619.00 1857.49
1 123 1.0 4.50 553.50
Total 553.50
Cum 15.68 1619.00 25385.74
lhesaV ctjh 1%6
1 129.00 4.50 580.50
Total 580.50sqm 53.95 99.00 5341.03
1 129.00 1.00 129.00
sqm 11.99 208.00 2493.68
Grand Total Rs 59799.90
Say Rs 60000.00
5 vf/kjpuk es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 % 3]
1 % 6 ;k 1 % 8 elkys es] e; cxy dh f>jh cUn djuk
rFkk rjkbZ vkfnA ¼30 ls-eh- ls de eksVkbZ ds fy;s½
3 uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 %
3] 1 % 6 ;k 1 % 8 elkys es] e; cxy dh f>jh cUn
djuk rFkk rjkbZ vkfnA
vf/kjpuk es iRFkj ds [kEcs oxkZdkj ;k vk;rkdkj 90 ls-
eh- yEckbZ rdA
4
EPA ESTIMATE NO. 2
NAME OF WORK: CONSTRUCTION OF BOUNDRY WALL
7
1 uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ
djuk] ry dks dwVuk] ikuh Mkyuk] cxy dks laokjuk]
[kqnh feêh dks ckgj fudkyuk] uhao Hkjus ds ckn [kkyh
LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph gqbZ feêh dks 50
ehVj dh nwjh rd fuLrkj.k djukA l[r] fpduh
50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k ftlesa 1
lhesaV 2 ctjh 4 iRFkj dh ;k bZaV dh 12 - eh- ukHkh;
fxV̀Vh ds lkFk feykdj Mkyuk] dwVuk] nckuk rFkk rjkbZ
vkfn lesr A
2
6 lhesaV IykLVj nhokj ij 1%4 vuqikr es lhesaV&ctjh
feykdj tksMksa dks dqjsnus rFkk rjkbZ lesr 20 eh- eh-A
lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki dh
iRFkj fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1 lhesUV %
4 jsr % 8 fxÍh vuqikr eas feykdj Mkyuk rFkk dqVkbZ
djuk] rjkbZ lesrA
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.NO. PARTICULARS QNTY UNIT
1A Construction of tube-well from ground level and upto 100mtr
depth and avove to accommodate cashing pipe of following sizes
in all type of soil in alluvium strata by bailing method and
without gravel packing as per is:2800(part-1&2)1979
specification (the
45 M. 240 per/mtr Rs. 10800
1B constrction of tube-well up to 100m depth&above in all type or
rocks by DTH system&overburden the work would be completed
after obtaining sand free water ,125mm dia nominal bore
20 M. 330 per/mtr Rs. 6600
2 Supply of ERW M.S. black cashing pipe ISI marked
(IS:4270/1992) of grade fe:410 of following size at site of work
125 mm dia nomonal bore outer dia 141.3 mm thikness of pipe 5
mm (Cashing pipe should be 5.12 kg
45 M. 743 per/mtr Rs. 33435
3 Supplying and installation of 32 mm dia GI pipe medium class
ISI marked in 3 mtr length including fitting all accessories and
fittings required for instalation of handpump
40 M. 229 per/mtr Rs. 9160
4 Supplying of india marked second handpump set complete ISI
marked with sylinder and ten connecting rods etc ISI
1 Each 6500 Each Rs. 6500
5 Construction of 185 cm dia plateform as per approved design and
drowing of UNICEF
1 Each 2200 Each Rs. 2200
6 Installation of INDIA marked second handpump complete on
existing plateform
1 Each 700 Each Rs. 700
7 Provided display board & photo each other LS Rs. 500
Rs. 69895
70000
EPA ESTIMATE NO. 3
SAY
NAME OF WORK: CONSTRUCTION OF HAND PUMP
TOTAL
AmountRate
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item No L (Ft) B (Ft) H (Ft) Qty Rate Amount
1.00 32.00 2.00 2.00 128.00
1.00 23.00 19.00 1.00 437.00
565.00
Cum 16.00 75.00 1200.08
lk/kkj.k@eqyk;e feêh esa
l[r] fpduh] dadj feêh esa
1.00 32.00 2.00 0.50 32.00
1.00 23.00 19.00 0.50 218.50
Total 250.50
iRFkj dh fxêh ds lkFk Cum 7.10 1968.00 13965.55
1 32.00 2.00 1.50 96.00
1 21.00 1.00 1.50 31.50
lhesaV ctjh 1%6
Total 127.50
Cum 3.61 1499.00 5412.70
1 23.50 19.00 446.50
2 21.00 1.50 63.00
509.50
sqm 47.35 99.00 4687.78
0.79 15.00 15.00 176.63
0.79 9.60 9.60 72.35
1 23.50 19.00 446.50
446.50
sqm 41.50 208.00 8632.51
33898.63
Say 33900.00
Grand Total Rs
2 lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki
dh iRFkj fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1
lhesUV % 4jsr % 8 fxÍh vuqikr eas feykdj Mkyuk
rFkk dqVkbZ djuk] rjkbZ lesrA
3 uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk lhesaV&ctjh
1 % 3] 1 % 6 ;k 1 % 8 elkys es] e; cxy dh f>jh
cUn djuk rFkk rjkbZ vkfnA
4 lhesaV IykLVj nhokj ij 1% 4 vuqikr es lhesaV&ctjh
feykdj dj tksMksa dks dqjsnus rFkk rjkbZ lfgr 20 fe-
eh-esaA
EPA ESTIMATE NO. 4
NAME OF WORK: CONSTRUCTION OF SAFTY WALL & CHABUTRA
50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k ftlesa
1 lhesaV 2 ctjh 4 iRFkj dh ;k bZaV dh 12 - eh-
ukHkh; fxV`Vh ds lkFk feykdj Mkyuk] dwVuk] nckuk
rFkk rjkbZ vkfn lesr A
1 uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ
djuk] ry dks dwVuk] ikuh Mkyuk] cxy dks laokjuk]
[kqnh feêh dks ckgj fudkyuk] uhao Hkjus ds ckn [kkyh
LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph gqbZ feêh dks
50 ehVj dh nwjh rd fuLrkj.k djukA
6
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item No L (Ft) B (Ft) H (Ft) Qty Rate Amount
2 20.00 2.00 2.50 200.00
2 5.50 2.00 2.50 55.00
255.00
Cum 7.22 75.00 541.63
2 20.00 2.00 0.50 40.00
2 5.50 2.00 0.50 11.00
1 6.50 18.00 0.50 58.50
Total 109.50
iRFkj dh fxêh ds lkFk Cum 3.10 1774.00 5502.92
2 20.00 2.00 2.00 160.00
2 5.50 2.00 2.00 44.00
1 19.50 1.00 4.00 78.00
1 19.50 1.00 2.50 48.75
lhesaV ctjh 1%6 2 6.50 1.00 3.25 42.25
Total 373.00
Cum 10.56 2185.00 23081.42
2 19.50 4.00 156.00
2 19.50 2.50 97.50
4 6.50 3.25 84.50
338.00
sqm 31.41 99.00 3109.85
0.79 15.00 15.00 176.63
0.79 9.60 9.60 72.35
1 6.50 18.00 117.00
117.00
sqm 10.88 208.00 2262.05
34497.87
34500.00
Grand Total Rs
Say
2 lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki
dh iRFkj fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1
lhesUV % 5jsr % 10 fxÍh vuqikr eas feykdj Mkyuk
rFkk dqVkbZ djuk] rjkbZ lesrA
3 uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk
lhesaV&ctjh 1 % 3] 1 % 6 ;k 1 % 8 elkys es] e;
cxy dh f>jh cUn djuk rFkk rjkbZ vkfnA
4
5
lhesaV IykLVj nhokj ij 1% 4 vuqikr es
lhesaV&ctjh feykdj dj tksMksa dks dqjsnus rFkk
rjkbZ lfgr 20 fe-eh-esaA
50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k
ftlesa 1 lhesaV 2 ctjh 4 iRFkj dh ;k bZaV dh 12 -
eh- ukHkh; fxVV̀h ds lkFk feykdj Mkyuk] dwVuk]
nckuk rFkk rjkbZ vkfn lesr A
1 uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh
[kqnkbZ djuk] ry dks dwVuk] ikuh Mkyuk] cxy dks
laokjuk] [kqnh feêh dks ckgj fudkyuk] uhao Hkjus ds
ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph
gqbZ feêh dks 50 ehVj dh nwjh rd fuLrkj.k djuk]
l[r] fpduh
EPA ESTIMATE NO. 5
NAME OF WORK: CONSTRUCTION OF KHEL
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item No L (Ft) B (Ft) H (Ft) Qty Rate Amount
1 3.00 3.00 5.00 45.00
0.785 3.00 3.00 5.00 35.33
1 7.50 5.50 7.00 288.75
0.785 3.00 3.00 15.00 105.98
475.05
Cum 13.46 75.00 1009.31
1 3.00 3.00 0.50 4.50
1 3.00 3.00 0.50 3.531 7.50 5.50 0.50 20.63
Total 28.66
iRFkj dh fxêh ds lkFk Cum 0.81 1968.00 1597.68
2 3.00 0.75 4.50 20.25
2 3.00 0.75 4.50 18.00
2 7.50 0.75 6.00 67.50
2 4.00 0.75 6.00 36.00
Total 141.75
Cum 4.02 2185.00 8774.044
11 11.00 449.00 4939.00
5 Providing and Fixing Unplasticized
PolyVinylChloride(UPVC) SWR Pipes
TypeB for scil and waste discharges
ystem(IS:13592:1992Marked) of approved
quality.
75 mm dia 26.00 100.00 2600.00110 mm dia 11.00 200.00 2200.00160 mm dia 15.00 235.00 3525.00
1 3.00 3.00 9.00
0.785 4.50 4.50 15.90
1 7.50 5.50 41.25
0.785 4.50 4.50 15.90
82.04
sqm 7.62 722.00 5505.08
2 3.00 3.00 18.00
2 6.00 4.00 48.00
1 3.00 3.00 9.00
2 4.50 4.50 40.50
115.50
sqm 10.73 208.00 2232.71
1 1.00 2200.00 2200.00
2 3.00 4.50 27.00
2 3.00 4.00 24.00
EPA ESTIMATE NO. 6
NAME OF WORK: CONSTRUCTION OF ROOFTOP RAINWATER HARVESTING STRUCTURE
Supplying & Installation of india marked
second handpump set complete ISI marked
8
1 uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh
[kqnkbZ djuk] ry dks dwVuk] ikuh Mkyuk] cxy
dks laokjuk] [kqnh feêh dks ckgj fudkyuk] uhao
Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk
rFkk cph gqbZ feêh dks 50 ehVj dh nwjh rd
fuLrkj.k djukAl[r feêh e
2 lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh;
eki dh iRFkj fxÍh@bZV fxÍh] lhesUV & jsr
elkyk esa 1 lhesUV % 4 jsr % 8 fxÍh vuqikr eas
feykdj Mkyuk rFkk dqVkbZ djuk] rjkbZ lesrA
9
Providing & Fixing Precasted Cemented
rings of 3' dia & 18" ht.
lhesaV IykLVj nhokj ij 1%4 vuqikr es lhesaV&ctjh
feykdj dj tksMksa dks dqjsnus rFkk rjkbZ lfgr 20
fe-eh-- esaA
3 uhao rFkk dqlhZ esa izFke Js.kh bZaVksa dh fpukbZ
lhesaV&ctjh 1%6 elkys esa] e; cxy dh f>jh
cUn djus rFkk rjkbZ lesrA
6 vOoy ntsZ dh iRFkj dh ifê;ksa dh Nr Mkyuk]
Åij rFkk uhps ls tksMksa es iRFkj dh phi ds lkFk
1%4 vuqikr esa lhesaV elkys ls HkjukA
7 50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k
ftlesa 1 lhesaV 2 ctjh 4 iRFkj dh ;k bZaV dh 12 -
eh- ukHkh; fxVV̀h ds lkFk feykdj Mkyuk] dwVuk]
nckuk rFkk rjkbZ vkfn lesr AiRFkj dh fxVV̀h
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item No L (Ft) B (Ft) H (Ft) Qty Rate Amount
2 6.00 6.00 72.00
2 4.00 6.00 48.00
171.00
sqm 15.89 99.00 1573.33
36156.16
36000.00
Grand Total Rs
Say
9 lhesaV IykLVj nhokj ij 1%4 vuqikr es lhesaV&ctjh
feykdj dj tksMksa dks dqjsnus rFkk rjkbZ lfgr 20
fe-eh-- esaA
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
A. WATER TANK
S.No. Item No L (Ft) B (Ft) H (Ft) Qty Rate Amount
0.786 3.00 3.00
7.07
sqm 0.66 722.00 474.50
PRECASTED CEMENT FERMA OF DIA 3' & HT.
2' SUPPLY & FIXING
Total
Cum 4.00 1250.00 5000.00
5474.50
B. CHABUTRA
1.00 6.00 7.00 0.50 21.00
1.00 5.50 4.00 0.50 11.00
Total 32.00
iRFkj dh fxêh ds lkFk Cum 0.911968.00
1784.02
1.00 5.50 4.00 22.00
1 6.00 7.00 42.00
64.00
sqm 5.95 208.00 1237.36
3021.38
C. KHEL
1.00 20.00 2.00 2.00 80.00
2.00 2.50 2.00 2.00 20.00
100.00
Cum 2.83 75.00 212.40
lk/kkj.k@eqyk;e feêh esa
l[r] fpduh] dadj feêh esa
1 20.00 2.00 0.50 20.00
2 2.50 2.00 0.50 5.00
1.000 18.00 3.00 0.50 27.00
Total 52.00
iRFkj dh fxêh ds lkFk Cum 1.47 1968.00 2899.04
1 20.00 2.00 1.50 60.00
2 2.50 2.00 1.50 15.00
1 19.50 1.00 2.50 48.75
lhesaV ctjh 1%6 2 2.50 1.00 3.00 15.00
Total 138.75
Cum 3.93 1499.00 5890.29
3 19.50 2.50 146.25
4 3.00 3.00 36.00
182.25
sqm 16.94 85.00 1439.71
1 18.00 3.00 54.00
54.00
sqm 5.02 208.00 1044.02
11485.46
19981.3420000.00SAY
EPA ESTIMATE NO. 7
NAME OF WORK: CONSTRUCTION OF WATER TANK, KHEL AND SOAK PIT
TOTAL FOR KHEL
GRAND TOTAL
6 50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k
ftlesa 1 lhesaV 2 ctjh 4 iRFkj dh ;k bZaV dh 12 -
eh- ukHkh; fxVV̀h ds lkFk feykdj Mkyuk] dwVuk]
nckuk rFkk rjkbZ vkfn lesr A
TOTAL FOR WATER TANK
TOTAL FOR CHABUTRA
2 lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki
dh iRFkj fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1
lhesUV % 4jsr % 8 fxÍh vuqikr eas feykdj Mkyuk
rFkk dqVkbZ djuk] rjkbZ lesrA
3 uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk
lhesaV&ctjh 1 % 3] 1 % 6 ;k 1 % 8 elkys es] e;
cxy dh f>jh cUn djuk rFkk rjkbZ vkfnA
4 lhesaV IykLVj nhokj ij 1% 4 vuqikr es
lhesaV&ctjh feykdj dj tksMksa dks dqjsnus rFkk
rjkbZ lfgr 20 fe-eh-esaA
1 uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh
[kqnkbZ djuk] ry dks dwVuk] ikuh Mkyuk] cxy dks
laokjuk] [kqnh feêh dks ckgj fudkyuk] uhao Hkjus ds
ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph
gqbZ feêh dks 50 ehVj dh nwjh rd fuLrkj.k djukA
2 vOoy ntsZ dh iRFkj dh ifê;ksa dh Nr Mkyuk]
Åij rFkk uhps ls tksMksa es iRFkj dh phi ds lkFk
1%4 vuqikr esa lhesaV elkys ls HkjukA
3
1 lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki
dh iRFkj fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1
lhesUV % 4jsr % 8 fxÍh vuqikr eas feykdj Mkyuk
rFkk dqVkbZ djuk] rjkbZ lesrA
2 50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k
ftlesa 1 lhesaV 2 ctjh 4 iRFkj dh ;k bZaV dh 12 -
eh- ukHkh; fxVV̀h ds lkFk feykdj Mkyuk] dwVuk]
nckuk rFkk rjkbZ vkfn lesr A
IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item Quantity Unit Rate Amount
1 Dag belling work up to 5-7 cm depth 400 Rm 0.25 100.00
2 Earth work in hard soil for
construction of bund including
ramming compaction and dressing up
to the lead of 50m and lift 1.5 m
90 Cum 85.00 7650.00
3 Sowing of seed on bunds 300 Rm 0.59 177.00
4 Grass seed
Dhaman/Stylohemata 1 LS 40.00 40.00
7967.00
5 Contingency @ 3 % 239.01
8206.01
Say 8206
82.00
0.60
ESTIMATE NO. 8
NAME OF WORK: CONSTRUCTION OF CONTOUR BUND TYPE "A"
Cross section of bund - 0.9 sqm
For lenth 100 M.
Grand Total
Sub Total
Per. M. Cost
1.5:
10.60
1.5:1
G.L G.L
. 0.4 2.4
. 0.9
X-Section
1.0
E B TYPE A IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.no. Item Quantity Unit Rate Amount
1 Dag belling work up to 5-7 cm depth 400 Rm 0.25 100.00
2 Earth work in hard soil for
construction of bund including
ramming compaction and dressing up
to the lead of 50m and lift 1.5 m
129 Cum 85.00 10965.00
3 Sowing of seed on bunds 400 Rm 0.59 236.00
4 Grass seed
Dhaman/Stylohemata 1 LS 40.00 40.00
11241.00
5 Contingency @ 3 % 337.23
11578.23
Say 11578
116.00
0.60
ESTIMATE NO. 9
NAME OF WORK: CONSTRUCTION OF CONTOUR BUND TYPE "B"
Cross section of bund - 1.29 sqm
For lenth 100 M.
Grand Total
Sub Total
Per. M. Cost
1.5:
10.75
1.5:1
G.L G.L
. 0.4 2.85
. 1.1
X-Section
1.17
E B TYPE B) IWMPI, BLOCK-SIKRAI,DAUSA 4-
S.no. Item Quantity Unit Rate Amount
1 Dag belling work up to 5-7 cm depth 400 Rm 0.25 100.00
2 Earth work in hard soil for
construction of bund including
ramming compaction and dressing up
to the lead of 50m and lift 1.5 m
210 Cum 85.00 17850.00
3 Sowing of seed on bunds 500 Rm 0.59 295.00
4 Grass seed
Dhaman/Stylohemata 1 LS 40.00 40.00
18185.00
5 Contingency @ 3 % 545.55
18730.55
Say 18731
187.00
0.60
Per. M. Cost
ESTIMATE NO. 10
NAME OF WORK: CONSTRUCTION OF CONTOUR BUND TYPE "C"
Cross section of bund - 2.1 sqm
For lenth 100 M.
Grand Total
Sub Total
1.5:
11.00
1.5:1
G.L G.L
. 0.4 3.6
. 1.1
X-Section
1.91
E B TYPE C IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.no. Item Quantity Unit Rate Amount
1 Dag belling work up to 5-7 cm depth 400 Rm 0.25 100.00
2 Earth work in hard soil for
construction of bund including
ramming compaction and dressing up
to the lead of 50m and lift 1.5 m
288 Cum 85.00 24480.00
3 Sowing of seed on bunds 600 Rm 0.59 354.00
4 Grass seed
Dhaman/Stylohemata 1 LS 40.00 40.00
24874.00
5 Contingency @ 3 % 746.22
25620.22
Say 25620
256.00
0.60
Per. M. Cost
ESTIMATE NO. 11
NAME OF WORK: CONSTRUCTION OF CONTOUR BUND TYPE "D"
Cross section of bund - 2.88 sqm
For lenth 100 M.
Grand Total
Sub Total
1.5:
11.20
1.5:1
G.L G.L
. 0.4 4.2
. 1.1
X-Section
2.61
E B TYPE D IWMP-I, BLOCK-SIKRAI,DAUSA 4-
S.No. Item Part No. L W H/D Qty Unit Rate Amount
HW 1 4.20 2.50 0.30 3.15
3.15 Cum 92.00 289.80
SW 2 2.40 0.30 1.50 3.15
Apron/
foundation
1 4.20 1.90 0.30 2.39
apron 1 4.20 1.90 0.15 1.20
6.74 Cum 820.00 5527.62
3 Rehandling and carriage of stone
by head load or animal transport
including loading and unloading
for lead up to 200m
Cum 44.50 299.97
4 Contingency @ 3 % 183.52
6300.92
Say
Total
1 Excavation in hard soil disposal
of excavated material within
initial lead of 30 m and lift of
1.5 m dressing etc. complete. Total E/W
NAME OF WORK: CONSTRUCTION OF BUND WASTE WEIR
ESTIMATE NO. 12
Rates are taken from Dar Anusuchie 2011, ZP Dausa Rs. 6300 /- only
2 Dry stone masonary for~
Sub total
6.74
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
dz- la- bdkbZ nj lkexzh lfgr jkf'k
1
l[r] fpduh] dadj feêh esa
H.W. 1 6.00 2.50 3.00 45.000
H.W.Ext. 2 5.00 2.50 3.00 75.000
S.W. 2 5.00 2.00 3.00 60.000
T.W. 1 6.00 1.50 2.00 18.000
Apron 1 6.00 3.50 1.00 21.000
219.000 ?ku QhV 85.00 527.18
6.202 ?ku eh- izfr ?kueh
2
iRFkj dh fxêh ds lkFk
H.W. 1 6.00 2.50 0.50 7.500
H.W.Ext. 2 5.00 2.50 0.50 12.500
S.W. 2 5.00 2.00 0.50 10.000
T.W. 1 6.00 1.50 0.50 4.500
34.500 ?ku QhV 2014.00 1967.76
0.977 ?ku eh- izfr ?kueh
3
lhesaV ctjh 1%6
H.W. 1 6.00 2.50 2.50 37.500
H.W.Ext. 2 5.00 2.50 2.50 62.500
S.W. 2 5.00 2.00 2.50 50.000
T.W. 1 6.00 1.50 1.50 13.500
163.500 ?ku QhV 1442.00 6676.924.630 ?ku eh- izfr ?kueh
4
lhesaV ctjh 1%6
H.W. 1 6.00 2.00 0.750 9.000
H.W.Ext. 2 5.00 2.00 1.350 27.000
S.W. 2 5.00 1.85 0.825 15.263
T.W. 1 6.00 1.35 0.300 2.430
53.693 ?ku QhV 1562.00 2375.13
1.521 ?ku eh- izfr ?kueh
NAME OF WORK: CONSTRUCTION OF WASTE WEIR TYPE "A"
uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ djuk] ry dks
dwVuk] ikuh Mkyuk] cxy dks laokjuk] [kqnh feêh dks ckgj fudkyuk]
uhao Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph gqbZ feêh
dks 50 ehVj dh nwjh rd fuLrkj.k djukA
lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki dh iRFkj
fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1 lhesUV % 4 jsr % 8 fxÍh
vuqikr eas feykdj Mkyuk rFkk dqVkbZ djuk] rjkbZ lesrA
uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 % 3]
1 % 6 ;k 1 % 8 elkys es] e; cxy dh f>jh cUn djuk rFkk
rjkbZ vkfnA
ESTIMATE NO. 13
dk;Z fooj.k
vf/kjpuk es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 % 3] 1 % 6 ;k 1 %
8 elkys es] e; cxy dh f>jh cUn djuk rFkk rjkbZ vkfnA
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
dz- la- bdkbZ nj lkexzh lfgr jkf'k
uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ djuk] ry dks
dwVuk] ikuh Mkyuk] cxy dks laokjuk] [kqnh feêh dks ckgj fudkyuk]
uhao Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph gqbZ feêh
dks 50 ehVj dh nwjh rd fuLrkj.k djukA
dk;Z fooj.k
5
Apron 1 6.00 3.60 0.50 10.800 ?ku QhV 618.00 189.02
0.306 ?ku eh- izfr ?kueh
6
H.W. 1 6.00 2.00 12.000
H.W.Ext. 2 5.00 2.00 20.000
S.W. 2 2.00 1.85 7.400
T.W. 1 6.00 1.35 8.100
47.500 oxZ QhV 208.00 917.85
4.413 oxZ eh- izfr oxZ eh-
7
Apron 1 6.00 3.60 0.100 2.16 ?ku QhV 2156.00 131.89
0.061 ?ku eh- izfr ?kueh
8
20 eh- eh-
H.W. 1 2 rjQ 6.00 0.75 9.000
H.W.Ext. 2 2 rjQ 5.00 1.35 27.000
S.W. 2 2 rjQ 2.00 0.83 6.600
T.W. 1 2 rjQ 6.00 0.30 3.600
46.200 oxZ QhV 99.00 424.914.292 oxZ eh- izfr oxZ eh-
dqy 13210.65
9 vkdfLed O;; 3 izfr'kr :i;s 396.32dqy :i;s 13606.97
ekuk 13600.00
15 ls 30 ls-eh- eksVs] gFkksMs ls rjkls gq, ,dy iRFkj dh fifpax leLr
mBku ds lkFk] vkiwfÙkZ ds lkFkA
50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k ftlesa 1 lhesaV 2
ctjh 4 iRFkj dh ;k bZaV dh 12 - eh- ukHkh; fxV`Vh ds lkFk feykdj
Mkyuk] dwVuk] nckuk rFkk rjkbZ vkfn lesr A
lhesaV dkØhaV 1 lhesaV] 3 ctjh rFkk 6 fxêh iRFkj dh 20 fe-eh- ukeh;
eki dh uhao es Mkyuk ,uhdV ds fy,A
lhesaV IykLVj nhokj ij 1%6 vuqikr es lhesaV&ctjh feykdj tksMksa dks
dqjsnus rFkk rjkbZ lesrA
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
dz- la- bdkbZ nj lkexzh
lfgr
jkf'k
1
l[r] fpduh] dadj feêh esa
H.W. 1 10.00 3.00 3.50 105.00
H.W.Ext. 2 5.00 3.00 3.50 105.00
S.W. 2 8.00 2.50 3.50 140.00
T.W. 1 10.00 2.00 2.00 40.00
Apron 1 10.00 6.00 1.50 90.00
480.00 ?ku QhV 92.00 1250.61
13.59 ?ku eh- izfr ?kueh
2
iRFkj dh fxêh ds lkFk
H.W. 1 10.00 3.00 0.50 15.00
H.W.Ext. 2 5.00 3.00 0.50 15.00
S.W. 2 8.00 2.50 0.50 20.00
T.W. 1 10.00 2.00 0.50 10.00
60.00 ?ku QhV 2014.00 3422.19
1.70 ?ku eh- izfr ?kueh
3
lhesaV ctjh 1%6
H.W. 1 10.00 3.00 3.00 90.00
H.W.Ext. 2 5.00 3.00 3.00 90.00
S.W. 2 8.00 2.50 3.00 120.00
T.W. 1 10.00 2.00 1.50 30.00
330.00 ?ku QhV 1442.00 13476.36
9.35 ?ku eh- izfr ?kueh
4
lhesaV ctjh 1%6
H.W. 1 10.00 2.50 0.75 18.75
H.W.Ext. 2 5.00 2.50 1.35 33.75
S.W. 2 8.00 2.35 0.83 31.02
T.W. 1 10.00 1.85 0.30 5.55
89.07 ?ku QhV 1442.00 3637.39
2.52 ?ku eh- izfr ?kueh
ESTIMATE NO. 14
NAME OF WORK: CONSTRUCTION OF WASTE WEIR TYPE "B"
dk;Z fooj.k
vf/kjpuk es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 % 3] 1 % 6 ;k 1 %
8 elkys es] e; cxy dh f>jh cUn djuk rFkk rjkbZ vkfnA
uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ djuk] ry dks
dwVuk] ikuh Mkyuk] cxy dks laokjuk] [kqnh feêh dks ckgj fudkyuk]
uhao Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph gqbZ
feêh dks 50 ehVj dh nwjh rd fuLrkj.k djukA
lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki dh iRFkj
fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1 lhesUV % 4 jsr % 8 fxÍh
vuqikr eas feykdj Mkyuk rFkk dqVkbZ djuk] rjkbZ lesrA
uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1
% 3] 1 % 6 ;k 1 % 8 elkys es] e; cxy dh f>jh cUn djuk
rFkk rjkbZ vkfnA
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
dz- la- bdkbZ nj lkexzh
lfgr
jkf'kdk;Z fooj.k
uhao] [kkbZ] ijukyk esa 1-5 xgjkbZ rd feêh dh [kqnkbZ djuk] ry dks
dwVuk] ikuh Mkyuk] cxy dks laokjuk] [kqnh feêh dks ckgj fudkyuk]
uhao Hkjus ds ckn [kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk cph gqbZ
feêh dks 50 ehVj dh nwjh rd fuLrkj.k djukA
5
Apron 1 10.00 6.10 0.50 30.50 ?ku QhV 618.00 533.80
0.86 ?ku eh- izfr ?kueh
6
H.W. 1 10.00 2.50 25.00
H.W.Ext. 2 5.00 2.50 25.00
S.W. 2 2.00 2.35 9.40
T.W. 1 10.00 1.85 18.50
77.90 oxZ QhV 208.00 1505.28
7.24 oxZ eh- izfr oxZ eh-
7
Apron 1 10.00 6.10 0.10 6.10 ?ku QhV 2156.00 372.45
0.17 ?ku eh- izfr ?kueh
8
20 eh- eh-
H.W. 1 2 rjQ 10.00 0.75 15.00
H.W.Ext. 2 2 rjQ 5.00 1.35 27.00
S.W. 2 2 rjQ 2.00 0.83 6.60
T.W. 1 2 rjQ 10.00 0.30 6.00
54.60 oxZ QhV 84.00 426.08
5.07 oxZ eh- izfr oxZ eh-
dqy 24624.16
9 vkdfLed O;; 3 izfr'kr :i;s 738.72
dqy :i;s 25362.88
ekuk 25000.00
15 ls 30 ls-eh- eksVs] gFkksMs ls rjkls gq, ,dy iRFkj dh fifpax leLr
mBku ds lkFk] vkiwfÙkZ ds lkFkA
50 eh- eh- eksVkbZ esa lhesaV dadzhV 1%2%4 feJ.k ftlesa 1 lhesaV 2
ctjh 4 iRFkj dh ;k bZaV dh 12 - eh- ukHkh; fxV`Vh ds lkFk feykdj
Mkyuk] dwVuk] nckuk rFkk rjkbZ vkfn lesr A
lhesaV dkØhaV 1 lhesaV] 3 ctjh rFkk 6 fxêh iRFkj dh 20 fe-eh- ukeh;
eki dh uhao es Mkyuk ,uhdV ds fy,A
lhesaV IykLVj nhokj ij 1%6 vuqikr es lhesaV&ctjh feykdj tksMksa dks
dqjsnus rFkk rjkbZ lesrA
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
Considerations -
A Seepage Line 5:1
B Side Slope
U/s 3:1
D/S 2:1
C Length of Structure 10.00 Mtr.
D Height of Structure 1.60 Mtr.
Øe la[;k ek=k nj jkf'k
1 Mkx csfyax 2-5 ls 5 lseh- xgjkbZ rd 30.00 0.25 7.50Áfr ehVj
2 feêh dk dk;Z cU/k es ¼lw[kh ;k xhyh½] 15 ls-
eh- ijr es Mkyuk] <syksa dks rksM+uk]
?kkl&ikr rFkk dadj chudj vyx djuk
rFkk feêh dh njslh djuk rFkk 'khi QwV
jksyj@gSaM jSej ls feêh nckuk] 1-5 eh mBku
rFkk 50 eh- nwjh ds fy,A
dBksj feVV̀h 112.00 85.00 9520.00Áfr Äu ehVj
3 cht cqokbZ cuk;s x;s fjt ijA 50.00 0.59 29.50Áfr ehVj
10 ls-eh- nwjh ij (4 ls 5 LyhIl ,d txg) 4 okuLifrd vojks/k LFkkfir djuk
ewatk@[kl fLyi Áwfuax ,oa lsisjsfVax dk;Z 40.00 525.00 21.00Áfr fdeh
5 IykUVhax ,oa Mªsflax dk;Z 40.00 1425.00 57.00Áfr fdeh
6 bUlsDVhlkbM@ isLVhlkbM ls mipkj djuk 40.00 308.00 12.32Áfr fdeh
7 ÁkÑfrd L«k¨«k l¢ ewatk@[kl fLyi m[kkMus dk dk;Z 2000 1638.50 32.771 yk[k fLyi
;ksx 9680.098 vkdfLed O;; 3 izfr'kr 290.40
dqy ;ksx 9970.49ekuk 10000.00
(5*yEckbZ)
(4*yEckbZ)
ESTIMATE NO. 15
NAME OF WORK: CONSTRUCTION OF GULLY CONTROL STRUCTURE IN ARABLE LAND "A"
fooj.k
(3*yEckbZ)
10*(2.0+12.0)/2*1.60
12.00m
2.00m
1.60m
0.50m Free board
9.90 m
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
Considerations -
A Seepage Line 5;1
B Side Slope
U/s 3;1
D/S 2;1
C Length of Structure 10.00 Mtr.
D Height of Structure 2.00 Mtr.
Øe
la[;k
ek=k nj jkf'k
1 Mkx csfyax 2-5 ls 5 lseh- xgjkbZ rd 30.00 0.25 7.50
Áfr ehVj
2 feêh dk dk;Z cU/k es ¼lw[kh ;k xhyh½] 15
ls-eh- ijr es Mkyuk] <syksa dks rksM+uk]
?kkl&ikr rFkk dadj chudj vyx djuk
rFkk feêh dh njslh djuk rFkk 'khi QwV
jksyj@gSaM jSej ls feêh nckuk] 1-5 eh
mBku rFkk 50 eh- nwjh ds fy,A
dBksj feVV̀h 10*(2.5+12.50)/2*2.00 150.00 85 12750.00
Áfr Äu ehVj
3 cht cqokbZ cuk;s x;s fjt ijA 50.00 0.59 29.50
Áfr ehVj
10 ls-eh- nwjh ij (4 ls 5 LyhIl ,d txg) 4 okuLifrd vojks/k LFkkfir djuk
ewatk@[kl fLyi Áwfuax ,oa lsisjsfVax dk;Z 40.00 525 21.00
Áfr fdeh
5 40.00 1425 57.00
Áfr fdeh
6 bUlsDVhlkbM@ isLVhlkbM ls mipkj djuk 40.00 308 12.32
Áfr fdeh
7 ÁkÑfrd L«k¨«k l¢ ewatk@[kl fLyi m[kkMus dk dk;Z 2000 1638.50 32.771 yk[k fLyi
;ksx 12910.098 vkdfLed O;; 3 izfr'kr 387.30
dqy ;ksx 13297.39ekuk 13300.00
(4*yEckbZ)
Dimensions are not to the scale
ESTIMATE NO. 16
NAME OF WORK: CONSTRUCTION OF GULLY CONTROL STRUCTURE IN ARABLE LAND "B"
fooj.k
(3*yEckbZ)
(5*yEckbZ)
IykUVhax ,oa Mªsflax dk;Z
12.50m
2.50m
2.00m
0.70m Free board
11.70mm
GCS ARBLE B IWMP-I, BLOCK-SIKRAI, DAUSA
Considerations -
A Seepage Line 6:1
B Side Slope
U/s 3:1
D/S 2:1
C Length of Structure 15.00 Mtr.
D Height of Structure 2.50 Mtr.
Ø-l- ek=k nj jkf'k
1 Mkx csfyax 2-5 ls 5 lseh- xgjkbZ rd 45.00 0.25 11.25
ehVj Áfr ehVj
2 feêh dk dk;Z cU/k es ¼lw[kh ;k xhyh½] 15 ls-
eh- ijr es Mkyuk] <syksa dks rksM+uk] ?kkl&ikr
rFkk dadj chudj vyx djuk rFkk feêh dh
njslh djuk rFkk 'khi QwV jksyj@gSaM jSej ls
feêh nckuk] 1-5 eh mBku rFkk 50 eh- nwjh ds
fy,A
dBksj feVV̀h 328.13 85 27890.63
Äu ehVj Áfr Äu ehVj
3 cht cqokbZ cuk;s x;s fjt ijA 75.00 0.59 44.25
ehVj Áfr ehVj
10 ls-eh- nwjh ij (4 ls 5 LyhIl ,d txg) 4 okuLifrd vojks/k LFkkfir djuk
ewatk@[kl fLyi Áwfuax ,oa lsisjsfVax dk;Z 60.00 525 31.50 fdeh Áfr fdeh
5 IykUVhax ,oa Mªsflax dk;Z 60.00 1425 85.50 fdeh Áfr fdeh
6 bUlsDVhlkbM@ isLVhlkbM ls mipkj djuk 60.00 308 18.48 fdeh Áfr fdeh
7 ÁkÑfrd L«k¨«k l¢ ewatk@[kl fLyi m[kkMus dk dk;Z 2000 1638.50 32.771 yk[k fLyi
;ksx 28114.388 vkdfLed O;; 3 izfr'kr 843.43
dqy ;ksx 28957.81
ekuk 29000.00
(4*yEckbZ)
Dimensions are not to the scale
ESTIMATE NO. 17
NAME OF WORK: CONSTRUCTION OF GULLY CONTROL STRUCTURE IN ARABLE LAND "C"
fooj.k
(3*yEckbZ)
15*(2.50+15.0)/2*2.50
(5*yEckbZ)
15.00m
2.50m
2.50m
1.00m Free board
13.50m M
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
No. L W D T.Q. Labour Material Total Labour Material Total
1 pkjkxkg {ks= esa fM+p de cUM+ [kqnkbZ dk;Z dBksj feV~Vh esa CUM. 0 1800 1.2 1.2 2592.00 85 85.00 220320 0 220320
2 lrr dUVj V~zspst dk fuek.kZ ¼dBksj feV~Vh esa½ CUM. 0 6000 0.6 0.3 1080.00 82 85.00 91800 0 91800
3 [kM~Ms+ [kqnkbZ dk dk;Z & lrr dUVj V~zspst esa NO. 4000 4000.00 6.8 6.80 27200 0 27200
?kkl cht cqokbZ dk dk;Z
¼v-½ Vz~sDVj }kjk gdkbZ dk;Z HA. 10.00 30 259 289.00 2890 2890
¼c-½ ?kkl cht dks rkykc feV~Vh ds lkFk feykdj xksfy;k cukuk KG. 90.00 10.43 10.43 938.7 0 938.7
¼l-½ ?kkl cht dks Qsykus dk dk;Z MD 15.00 135 135.00 2025 0 2025
cht cqokbZ cuk;s xk;s fjt ij rhuksa ykbZuksa esa 0.00 0 0
¼v-½ lrr dUVj V~zspst ds cUM+ ij ¼/kke.k@geSVk½ M. 0 6000 0 0 6000.00 0.59 0.59 3540 0 3540
¼c-½ M+hlhch cUM+ ij ¼dsLVj]M+hch]jrutksr½ M. 2000 2000.00 0.59 0.59 1180 0 1180
ikS/ks dk ifjogu ¼30 fdeh yhM+ ls½ e; yksfM+x o vuyksfM+x lfgr
& izFke o"kZ
NO. 4000 4000.00 1.35 1.35 5400 5400
ikS/ks dk ifjogu ¼30 fdeh yhM+ ls½ e; yksfM+x o vuyksfM+x lfgr
& f}rh; o"kZ
NO. 800 800.00 1.35 1.35 1080 1080
ikS/kkjksi.k djuk& lkekU; tehu ij ¼izFke o"kZ½ NO. 4000 4000.00 3.00 3.00 12000 0 12000
ikS/kkjksi.k djuk& lkekU; tehu ij ¼f}rh; o"kZ½ 20 izfr'kr xsi
fQfyxa
NO. 800 800.00 3.00 3.00 2400 0 2400
[kM~MkS+ dks fdVuk'kd@isLVhlkbZM+ ,oa QfVZykbZtj ls mipkj djuk NO. 0.00 0.00 0 0
¼v-½ fdVuk'kd@isLVhlkbZM+ NO. 4000 4000.00 0.3 0.30 1200 0 1200
¼c-½ QfVZykbZtj NO. 4000 4000.00 0.15 0.15 600 0 600
ikS/ks dks ikuh fiykuk ¼15 yh- izfr ikS/kk½ & izFke o"kZ NO. 3 4000 12000.00 1.8 1.80 21600 0 21600
ikS/ks dks ikuh fiykuk ¼15 yh- izfr ikS/kk½ & f}rh; o"kZ NO. 2 4000 8000.00 1.8 1.80 14400 0 14400
ikS/ks dks ikuh fiykuk ¼15 yh- izfr ikS/kk½ & r`rh; o"kZ NO. 1 4000 4000.00 1.8 1.80 7200 0 7200
8
9
UNIT
0.45 X .45 X .45
NAME OF WORK: CONSTRUCTION OF PASTURE DEVELOPMENT WORK IN W/S IWMP Ist
ESTIMATE NO. 18
6
7
FOR 10 HACT.
4
5
AMOUNTRATEDETAILS OF QUANTITYS.NO. ITME OF WORK
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
No. L W D T.Q. Labour Material Total Labour Material Total
UNIT AMOUNTRATEDETAILS OF QUANTITYS.NO. ITME OF WORK
ikS/kks dks fujkbZ xqM+kbZ 15 lseh xgjkbZ ,oa 45 lseh v)ZO;kl rd &
izFke o"kZ
NO. 1 4000 4000.00 1.2 1.20 4800 0 4800
ikS/kks dks fujkbZ xqM+kbZ 15 lseh xgjkbZ ,oa 45 lseh v)ZO;kl rd &
f}rh; o"kZ
NO. 2 4000 8000.00 1.2 1.20 9600 0 9600
ikS/kks dks fujkbZ xqM+kbZ 15 lseh xgjkbZ ,oa 45 lseh v)ZO;kl rd &
r`rh; o"kZ
NO. 3 4000 12000.00 1.2 1.20 14400 0 14400
ikS/kks gsrq ikuh dh lIykbZ ¼VSdj }kjk½ & Vz~SDVj e; Vsadj 4000 yh-
{kerk e; Mkz~bZoj ds & izFke o"kZ
TRIP. 3 15 45.00 200 200.00 0 9000 9000.00
ikS/kks gsrq ikuh dh lIykbZ ¼VSdj }kjk½ & Vz~SDVj e; Vsadj 4000 yh-
{kerk e; Mkz~bZoj ds & f}rh; o"kZ
TRIP. 2 15 30.00 200 200.00 0 6000 6000.00
ikS/kks gsrq ikuh dh lIykbZ ¼VSdj }kjk½ & Vz~SDVj e; Vsadj 4000 yh-
{kerk e; Mkz~bZoj ds & r`rh; o"kZ
TRIP. 1 15 15.00 200 200.00 0 3000 3000.00
lkekxzh dh ykxr & 0.00 0 0 0.00
¼v-½ ikS/ks & izFke o"kZ NO. 4000 4000.00 2.5 2.50 0 10000 10000.00
¼c-½ ikS/ks & f}rh; o"kZ NO. 800 800.00 2.5 2.50 0 2000 2000.00
¼l-½ /kke.k?kkl cht KG. 60 60.00 150 150.00 0 9000 9000.00
¼n-½ LVz~kbZyksesaVk cht KG. 40 40.00 50 50.00 0 2000 2000.00
¼;-½ dsLVj lhM+ KG. 7 7.00 100 100.00 0 700 700.00
¼y-½ jrutksr cht KG. 7 7.00 100 100.00 0 700 700.00
¼o-½ ns'kh ccwy cht KG. 7 7.00 50 50.00 0 350 350.00
¼j½ ;wfj;k@oehZ dEiksLV [kkn BAG 10 10.00 300 300.00 0 3000 3000.00
¼g-½ ,yfM+Zu nok LTR. 10 10.00 250 250.00 0 2500 2500.00
13 pjkxkg dh pkSdhnkjh MONTH 40 40.00 2600 0 2600.00 104000 0 104000
539204 57620 596823.7
Rs /-
12
TOTAL
10
11
60000SAY COST PER HACT.
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
S.no. Item Quantity Unit Rate Amount
1 Dag belling work up to 5-7 cm depth 400 Rm 0.25 100.00
2 Earth work in hard soil for
construction of bund including
ramming compaction and dressing up
to the lead of 50m and lift 1.5 m
0.945 Cum 85.00 80.33
3 Sowing of seed on bunds 500 Rm 0.59 295.00
4 Grass seed
Dhaman/Stylohemata 1 LS 40.00 40.00
515.33
5 Contingency @ 3 % 15.46
530.78
Say 531
53.00
2 X(BOTH SIDE BUND)
G.L
. 0.4
. 0.9
X-Section
Per. M. Cost
For lenth 100 M.
ESTIMATE NO. 19
NAME OF WORK: CONSTRUCTION OF DIVERSION CHANNEL CUM BUND
Cross section of Channel - 0.945 sqm
0.6
Grand Total
1.5
Sub Total
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
Mkx csfyax 2-5 ls 5 lseh xgjkbZ
150.00 0.25 37.50
ehVj izfr ehVj
feV~Vh dk dk;Z cU/k esa ¼lq[kh ;k xhyh½ 15 lseh - dh
ijr esa fcNkuk] <syksa dks rksM+uk] ?kkl ikr chudj
vyx djuk rFkk fe~Vh dh Mªsflax djuk] 1-5 eh-
mBku rFkk 50 eh- nwjh ds fy;s] dBksj feV~Vh esa
764.50 85.00 64982.50
?ku ehVj izfr ?kuehVj
cht cqokbZ cuk;s x;s fjt ij ¼3 ykbZu esa½
150.00 0.59 88.50
ehVj izfr ehVj
10 lseh nwjh ij ¼4 ls 5 LyhIl ,d txg½
okufLird vojks/k LFkkfir djuk] ewatk@[kl LyhIl]
izqfuax ,oa lsijsfVax dk;Z
200.00 0.525 105.00
ehVj izfr ehVj
ehVj izfr ehVj
ehVj izfr ehVj
yk[k LyhIl izfr yk[k LyhIl
0.30 45.00 13.50
fdxzk izfr fdxzk
65737.45
vkdfLed O;; 3 izfr'kr 1972.12
67709.57
67700.00
jkf'k
1
3 x yackbZ
Øa-la- fooj.k ek=k nj
163.85
2
3
3xyackbZ
4
4xyackbZ
5 IykfVax ,oa Msªflax dk;Z 200.00 1.425
5
dqy ;ksx
ekuk
7 izkd`frd L=ksr ls ewatk@[kl LyhIl m[kkM+us dk
dk;Z
0.10
4 cht dh ykxr
1638.500
ESTIMATE NO. 20
NAME OF WORK: CONSTRUCTION OF WATER HARVESTING STRUCTURE IN NON ARABLE TYPE "A"
;ksx
285.00
6 bUlsDVhlkbM@isLVhlkbM ls mipkj djuk 200.00 0.308 61.60
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
Mkx csfyax 2-5 ls 5 lseh xgjkbZ
210.00 0.25 52.50
ehVj izfr ehVj
feV~Vh dk dk;Z cU/k esa ¼lq[kh ;k xhyh½ 15 lseh -
dh ijr esa fcNkuk] <syksa dks rksM+uk] ?kkl ikr
chudj vyx djuk rFkk fe~Vh dh Mªsflax djuk] 1-
5 eh- mBku rFkk 50 eh- nwjh ds fy;s] dBksj feV~Vh
esa
1256.49 85.00 106801.65
?ku ehVj izfr ?kuehVj
cht cqokbZ cuk;s x;s fjt ij ¼3 ykbZu esa½
210.00 0.59 123.90
ehVj izfr ehVj
10 lseh nwjh ij ¼4 ls 5 LyhIl ,d txg½
okufLird vojks/k LFkkfir djuk] ewatk@[kl
LyhIl] izqfuax ,oa lsijsfVax dk;Z
280.00 0.525 147.00
ehVj izfr ehVj
ehVj izfr ehVj
ehVj izfr ehVj
yk[k LyhIl izfr yk[k LyhIl
0.50 45.00 22.50
fdxzk izfr fdxzk
107862.18
vkdfLed O;; 3 izfr'kr 3235.87
111098.05
111100.00
0.308
ek=k nj jkf'k
1
3 x yackbZ
4
4xyackbZ
Øa-la- fooj.k
ESTIMATE NO. 21
NAME OF WORK: CONSTRUCTION OF WATER HARVESTING STRUCTURE IN NON ARABLE TYPE "B"
3
3xyackbZ
2
280.00 1.425
1638.500
86.24
5 IykfVax ,oa Msªflax dk;Z 399.00
6 bUlsDVhlkbM@isLVhlkbM ls mipkj djuk 280.00
229.39
;ksx
5
dqy ;ksx
ekuk
7 izkd`frd L=ksr ls ewatk@[kl LyhIl m[kkM+us dk
dk;Z
0.14
4 cht dh ykxr
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
Assumptions:
C. I. =5 MTS No. of trenches per ha = 500 Nos
Size of trenches = 2x0.60x0.37m = 0.44 Cum
S.No. Item Quantity Unit Rate Amount
1 Lay out of trenches
2*500*2*2 4000.00 Mtr 0.17 680.00
2 Dag belling 2.5 to 5 cm deep
2*500*2 2000.00 Mtr 0.25 500.00
3 Excavation in dry or moist including disposal
of excavated material within initial lead of
50mtr and lift 1.5 mtrincluding dressing etc
complete in hard Soil 220.00 Cum 85.00 18700.00
4 Labour charges of sowing of Dhaman / Stylo-
Hameta / Karad grass seed on contour furrow
in three rows 3000.00 Rmt 0.59 1770.00
5 Cost of Dhaman / Stylo-Hameta / Karad grass
seed @4kg/ha 4.00 Per Kg/Ha 50.00 200.00
21850.00
6 Contingency @ 3 % 655.50
TOTAL 22505.50
Say Rs. 22500 per Ha
ESTIMATE NO. 22
NAME OF WORK: CONSTRUCTION OF STAGGERED TRENCHES IN NON ARABLE LAND FOR HILLY AREAS
Sub Total
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
S.No. Item Part No. L W H/D Qty Unit Rate Amount
HW 1 5.00 0.84 0.24 1.01
HWE 2 0.30 0.84 0.24 0.12
1.13 Cum 85.00 95.96
Foundation Same as Item no. 1 1.13
Super structure
HW 1 5.00 0.54 0.60 1.62
HWE 2 0.30 0.84 0.90 0.45
3.20 Cum 820.00 2626.10
3 Rehandling and carriage of stone by head
load or animal transport including
loading and unloading for lead up to
200m
Cum 44.50 192.75
4 Vegetation L.S. 115.00
3029.81
Say Rates are taken from Dar Anusuchie 2011, ZP Dausa Rs.3000 /- only
2 Dry stone masonary for~
Sub total
4.33
Total
NAME OF WORK: CONSTRUCTION OF LOOSE STONE CHECK DAM
ESTIMATE NO. 23
1 Excavation in hard soil disposal of
excavated material within initial lead of
30m and lift of 1.5mtr dressing etc.
complete. Total E/W
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of w/s :- IWMP I
2 Name of work :- CONTRUCTION OF SAFTY WALL
1 Available crest length 8 M
2 Hight of structure 0.60 M
3 Top Width 0.6 M
4 Bottom Width 1.10 M
5 Depth of foundation taking as 0.90 M
6 Length of Basin 1.00 M
7 Head wall ext. 2+2 M
S.No. PARTICULAR No. L B H/D Qty Rate Amount
1 Excavation in hard soil dry or
most&disposal of excavated
material within intial lead of
30 m and liftof 1.5m
including dressing etc
complete 100%of
TotalExcavation
H.W. 1.00 8.00 1.10 0.90 7.92
H.W.EX. 2.00 2.00 0.90 0.90 3.24
Apron 1.00 8.00 1.00 0.60 4.80
Total (cu.m) 15.96
Total 15.96 82.00 1308.72
2 cement concrete well mixed in
cement mortar(1:4:8) laid in
position complete including
curing Aggregate size upto
50mm. H.W. 1.00 8.00 1.10 0.30 2.64
H.W.EX. 2.00 2.00 0.90 0.30 1.08
Apron 1.00 8.00 1.00 0.30 2.40
Total 6.12 2014 12325.68
3 Random rubble stone
masonary in cement sand
mortar(1:6) for foundation
H.W. 1.00 8.00 1.10 0.60 5.28
H.W.EX. 2.00 2.00 0.60 0.60 1.44
Apron 1.00 8.00 1.00 0.30 2.40
Total 9.12 1499 13670.88
4 Random rubble stone
masonary in cement sand
mortar(1:6) for super structure
H.W. 1.00 8.00 0.85 0.60 4.08
H.W.EX. 2.00 2.00 0.60 1.10 2.64
Total 4.08 1619 6605.52
DETAILED ESTIMATE
P.S . SIKRAI DISTT. DAUSA ( RAJ.)
ESTIMATE NO. 24
NAME OF WORK: CONSTRUCTION OF SAFTY WALL "A"
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
5 Cement plaster including
smooth finishing in cement
mortar (1:4)25mm thick
H.W. 1.00 8.00 0.60 4.80
1.00 8.00 0.90 7.20
H.W.EX. 2.00 0.60 0.50 0.60
Apron 1.00 8.00 1.00 8.00
Total 20.60 141 2904.60
6 Cement concrete coping in
cement mortar1:1:5 :3 100
mm thick
H.W. 1.00 8.00 0.60 0.075 0.36
H.W.EX. 2.00 2.00 0.60 0.075 0.18
Apron 1.00 8.00 1.10 0.075 0.66
Total 1.20 3316 3979.20
TOTAL 40794.60
METARIAL 32944.44
LABOUR 7850.16
TOTAL 40794.60
Add 3% Contingency Charges 1223.84
TOTAL Rs. 42018.44
Say 42000.00
.0.6 2.00 8
1.00 0.3 8
G.L G.L
0.90 0.3
0.3
1.1
X-Section
0.6
0.50
1.00
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of w/s :- IWMP I
2 Name of work :- CONTRUCTION OF SAFTY WALL
1 Available crest length 9 M
2 Hight of structure 0.80 M
3 Top Width 0.6 M
4 Bottom Width 1.25 M
5 Depth of foundation taking as 1.10 M
6 Length of Basin 1.00 M
7 Head wall ext. 2+2 M
S.No. PARTICULAR No. L B H/D Qty Rate Amount
1 Excavation in hard soil dry or
most&disposal of excavated
material within intial lead of
30 m and liftof 1.5m
including dressing etc
complete
H.W. 1.00 9.00 1.25 1.10 12.38
H.W.EX. 2.00 2.00 0.90 1.10 3.96
Apron 1.00 9.00 1.00 0.60 5.40
Total (cu.m) 21.74
Total 21.74 82.00 1782.27
2 cement concrete well mixed in
cement mortar(1:4:8) laid in
position complete including
curing Aggregate size upto
50mm. HB
H.W. 1.00 9.00 1.25 0.30 3.38
H.W.EX. 2.00 2.00 0.90 0.30 1.08
Apron 1.00 9.00 1.00 0.30 2.70
Total 7.16 2014 14410.17
3 Random rubble stone
masonary in cement sand
mortar(1:6) for foundation
H.W. 1.00 9.00 1.25 0.80 9.00
H.W.EX. 2.00 2.00 0.60 0.80 1.92
Apron 1.00 9.00 1.00 0.30 2.70
Total 13.62 1499 20416.38
4 Random rubble stone
masonary in cement sand
mortar(1:6) for super structure
H.W. 1.00 9.00 0.93 0.80 6.66
H.W.EX. 2.00 2.00 0.60 1.30 3.12
Total 6.66 1619 10782.54
ESTIMATE NO. 25
NAME OF WORK: CONSTRUCTION OF SAFTY WALL "B"
P.S . SIKRAI DISTT. DAUSA ( RAJ.)
DETAILED ESTIMATE
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
5 Cement plaster including
smooth finishing in cement
mortar (1:4)25mm thick
H.W. 1.00 9.00 0.80 7.20
1.00 9.00 1.10 9.90
H.W.EX. 2.00 0.60 0.50 0.60
Apron 1.00 9.00 1.00 9.00
Total 26.70 141 3764.70
6 Cement concrete coping in
cement mortar1:1:5 :3 100
mm thick
H.W. 1.00 9.00 0.60 0.075 0.41
H.W.EX. 2.00 2.00 0.60 0.075 0.18
Apron 1.00 9.00 1.25 0.075 0.84
Total 1.43 3316 4737.74
TOTAL 55893.80
MATERIAL 44805.50
LABOUR 11088.30
TOTAL 55893.80
Add 3% Contingency Charges 1676.81
TOTAL Rs. 57570.61
Say 57500.00
.0.6 2.00 9
1.00 0.3 9
G.L G.L
1.10 0.3
0.3
1.3
0.6
1.00
X-Section
0.50
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of w/s :- IWMP I
2 Name of work :- CONTRUCTION OF SAFTY WALL
1 Available crest length 14 M
2 Hight of structure 0.90 M
3 Top Width 0.6 M
4 Bottom Width 1.35 M
5 Depth of foundation taking as 1.20 M
6 Length of Basin 1.00 M
7 Head wall ext. 2+2 M
S.No. PARTICULAR No. L B H/D Qty Rate Amount
1 Excavation in hard soil dry or
most&disposal of excavated
material within intial lead of
30 m and liftof 1.5m
including dressing etc
complete 100%of
TotalExcavation
H.W. 1.00 14.00 1.35 1.20 22.68
H.W.EX. 2.00 2.00 0.90 1.20 4.32
Apron 1.00 14.00 1.00 0.60 8.40
Total (cu.m) 35.40
Total 35.40 82.00 2902.80
2 cement concrete well mixed in
cement mortar(1:4:8) laid in
position complete including
curing Aggregate size upto
50mm. HB H.W.
1.00 14.00 1.35 0.30 5.67
H.W.EX. 2.00 2.00 0.90 0.30 1.08
Apron 1.00 14.00 1.00 0.30 4.20
Total 10.95 2014 22053.30
3 Random rubble stone
masonary in cement sand
mortar(1:6) for foundation
H.W. 1.00 14.00 1.35 0.90 17.01
H.W.EX. 2.00 2.00 0.60 0.90 2.16
Apron 1.00 14.00 1.00 0.30 4.20
Total 23.37 1499 35031.63
4 Random rubble stone
masonary in cement sand
mortar(1:6) for super structure
H.W. 1.00 14.00 0.98 0.90 12.29
H.W.EX. 2.00 2.00 0.60 1.40 3.36
Total 12.29 1619 19889.42
ESTIMATE NO. 26
NAME OF WORK: CONSTRUCTION OF SAFTY WALL "C"
P.S . SIKRAI DISTT. DAUSA ( RAJ.)
DETAILED ESTIMATE
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
5 Cement plaster including
smooth finishing in cement
mortar (1:4)25mm thick
H.W. 1.00 14.00 0.90 12.60
1.00 14.00 1.20 16.80
H.W.EX. 2.00 0.60 0.50 0.60
Apron 1.00 14.00 1.00 14.00
Total 44.00 141 6204.00
6 Cement concrete coping in
cement mortar1:1:5 :3 100
mm thick
H.W. 1.00 14.00 0.60 0.075 0.63
H.W.EX. 2.00 2.00 0.60 0.075 0.18
Apron 1.00 14.00 1.35 0.075 1.42
Total 2.23 3316 7386.39
TOTAL 93467.54
METARIAL 74664.74
LABOUR 18802.79
TOTAL 93467.54
Add 3% Contingency Charges 2804.03
TOTAL Rs. 96271.56
Say 96000.00
.0.6 2.00 14
1.00 0.3 14
G.L G.L
1.20 0.3
0.3
1.4
0.50
0.6
1.00
X-Section
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of w/s :- IWMP I
2 Name of work :- CONTRUCTION OF SAFTY WALL
1 Available crest length 17 M
2 Hight of structure 1.00 M
3 Top Width 0.6 M
4 Bottom Width 1.40 M
5 Depth of foundation taking as 1.30 M
6 Length of Basin 1.00 M
7 Head wall ext. 2+2 M
S.No. PARTICULAR No. L B H/D Qty Rate Amount
1 Excavation in hard soil dry or
most&disposal of excavated
material within intial lead of
30 m and liftof 1.5m
including dressing etc
complete 100%of
TotalExcavation
H.W. 1.00 17.00 1.40 1.30 30.94
H.W.EX. 2.00 2.00 0.90 1.30 4.68
Apron 1.00 17.00 1.00 0.60 10.20
Total (cu.m) 45.82
Total 45.82 82.00 3757.24
2 cement concrete well mixed in
cement mortar(1:4:8) laid in
position complete including
curing Aggregate size upto
50mm. HB H.W.
1.00 17.00 1.40 0.30 7.14
H.W.EX. 2.00 2.00 0.90 0.30 1.08
Apron 1.00 17.00 1.00 0.30 5.10
Total 13.32 2014 26826.48
3 Random rubble stone
masonary in cement sand
mortar(1:6) for foundation
H.W. 1.00 17.00 1.40 1.00 23.80
H.W.EX. 2.00 2.00 0.60 1.00 2.40
Apron 1.00 17.00 1.00 0.30 5.10
Total 31.30 1499 46918.70
4 Random rubble stone
masonary in cement sand
mortar(1:6) for super structure
H.W. 1.00 17.00 1.00 1.00 17.00
H.W.EX. 2.00 2.00 0.60 1.50 3.60
Total 17.00 1619 27523.00
NAME OF WORK: CONSTRUCTION OF SAFTY WALL "D"
P.S . SIKRAI DISTT. DAUSA ( RAJ.)
DETAILED ESTIMATE
ESTIMATE NO. 27
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
5 Cement plaster including
smooth finishing in cement
mortar (1:4)25mm thick
H.W. 1.00 17.00 1.00 17.00
1.00 17.00 1.30 22.10
H.W.EX. 2.00 0.60 0.50 0.60
Apron 1.00 17.00 1.00 17.00
Total 56.70 141 7994.70
6 Cement concrete coping in
cement mortar1:1:5 :3 100
mm thick
H.W. 1.00 17.00 0.60 0.075 0.77
H.W.EX. 2.00 2.00 0.60 0.075 0.18
Apron 1.00 17.00 1.40 0.075 1.79
Total 2.73 3316 9052.68
TOTAL 122072.80
METARIAL 97247.63
LABOUR 24825.17
TOTAL 122072.80
Add 3% Contingency Charges 3662.18
TOTAL Rs. 125734.98
Say 125000.00
.0.6 2.00 17
1.00 0.3 17
G.L G.L
1.30 0.3
0.3
1.4
0.6
1.00
X-Section
0.50
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of w/s :- IWMP I
2 Name of work :- CONTRUCTION OF SAFTY WALL
1 Available crest length 22 M
2 Hight of structure 1.30 M
3 Top Width 0.6 M
4 Bottom Width 1.70 M
5 Depth of foundation taking as 1.60 M
6 Length of Basin 1.00 M
7 Head wall ext. 2+2 M
S.No. PARTICULAR No. L B H/D Qty Rate Amount
1 Excavation in hard soil dry or
most&disposal of excavated
material within intial lead of
30 m and liftof 1.5m
including dressing etc
complete 100%of
TotalExcavation
H.W. 1.00 22.00 1.70 1.60 59.84
H.W.EX. 2.00 2.00 0.90 1.60 5.76
Apron 1.00 22.00 1.00 0.60 13.20
Total (cu.m) 78.80
Total 78.80 82.00 6461.60
2 cement concrete well mixed in
cement mortar(1:4:8) laid in
position complete including
curing Aggregate size upto
50mm. HB H.W.
1.00 22.00 1.70 0.30 11.22
H.W.EX. 2.00 2.00 0.90 0.30 1.08
Apron 1.00 22.00 1.00 0.30 6.60
Total 18.90 2014 38064.60
3 Random rubble stone
masonary in cement sand
mortar(1:6) for foundation
H.W. 1.00 22.00 1.70 1.30 48.62
H.W.EX. 2.00 2.00 0.60 1.30 3.12
Apron 1.00 22.00 1.00 0.30 6.60
Total 58.34 1499 87451.66
4 Random rubble stone
masonary in cement sand
mortar(1:6) for super structure
H.W. 1.00 22.00 1.15 1.30 32.89
H.W.EX. 2.00 2.00 0.60 1.80 4.32
Total 32.89 1619 53248.91
ESTIMATE NO. 28
NAME OF WORK: CONSTRUCTION OF SAFTY WALL "E"
P.S . SIKRAI DISTT. DAUSA ( RAJ.)
DETAILED ESTIMATE
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
5 Cement plaster including
smooth finishing in cement
mortar (1:4)25mm thick
H.W. 1.00 22.00 1.30 28.60
1.00 22.00 1.60 35.20
H.W.EX. 2.00 0.60 0.50 0.60
Apron 1.00 22.00 1.00 22.00
Total 86.40 141 12182.40
6 Cement concrete coping in
cement mortar1:1:5 :3 100
mm thick
H.W. 1.00 22.00 0.60 0.075 0.99
H.W.EX. 2.00 2.00 0.60 0.075 0.18
Apron 1.00 22.00 1.70 0.075 2.81
Total 3.98 3316 13181.10
TOTAL 210590.27
METARIAL 166775.37
LABOUR 43814.91
TOTAL 210590.27
Add 3% Contingency Charges 6317.71
TOTAL Rs. 216907.98
Say 217000.00
.0.6 2.00 22
1.00 0.3 22
G.L G.L
1.60 0.3
0.3
1.7
0.50
0.6
1.00
X-Section
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of W/S IWMP I
2 Name of work :- CONTRUCTION OF WATER HARVESTING STR.
Design
1 Available crest length 6.00 M
2 Total catchment area 100.00 Ha
3 Hight of structure 1.30 M
A Design discharge (By flood discharge method)
A HYDROLIC DESIGN
Peak rate of run off in cum/sec.=
Q = C I A C= 0.40
36 Catchment Area 100.00
Q = 4.89 cumsec K = L3
H
L= 3800.00
Say 4.9 cumsec H= 40.00
K 37037.82
Tc=0.0195K0.77
64.25
I = 4.40
B HYDROLIC DESIGN
Q = 1.71L(h)3/2
L = 6.00 mt length available at site
h =[Q/1.71L]2/3
h = 0.61 Say = 0.60
Taking free board as 0.3 M
Total d = 0.90
C. STRUCTURAL DESIGN
(I) Top width of Head wall
h /(p-1)0.5
0.53 0.53 say = 0.60 M
(as per site condition where h = 0.60 m p = 2.30 0.60 M
p Specific gravty of stone masnory in cm = 2.3
(ii) Bottom width of head wall
b = h+H /(p-1)0.5
1.67 Say = 1.70 M
H =heigth of head wall in meters = 1.3 m 1.30 M
(iii) Length of head wall extension
H +d + 1 3.20 3.20 M
d = h+free board = 0.90 0.90 M
but as per side condition L/S M 1.5 R/S M 1.5 3.00 M
(iv) Heigth of Head wall extension
H + d = 2.20 M
(v) Botton width of HW ext. side wall & wing wall
0.5(H+h)= 0.95 1.10 M
(vi) Top width of HW ext
0.4H= 0.52 0.60 M
(vii) Length of Basin
L.B =0.75(H+d)+H 2.95 2.95 M
(viii) Thickness of Basin =0.60m(incloding concreting)
(ix) Height of side wall
H+d = 2.20 2.20 M
P.S.SIKRAI, DISTT. DAUSA
ESTIMATE NO. 29
NAME OF WORK: CONSTRUCTION OF MASONARY WATER HARVESTING STRUCTURE "A"
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
(x) Height of side wall =1.5h at W W joints
1.5h = 0.90 1.10 M
(xi) Length of side wall = B. W. of H. W -B.W of H W E+L.B+ width of toe wall
4.00
(xii) Length of wing wall = 2.25 h= 1.35 1.50 M
(xiii) Height of the wing wall = 0.90 1.10 M
(xiv) Top width of Head wall ext site wall wing wall = 0.60mt
(xv) Width of toe wall= 0.45 M
(xvi)Height of toe wall = 0.30 M
(xvii)Height of wing wall at wing end = 1.10 M
(xviii)Bottem width of the side wall &wing wall taking as per Bottom width
of the head wall ext as in item no.5= m 1.10 M
(xix)Depth of foundation taking as 2.00 M
STABILITY CHECK'S
a Top width of anicut = 0.60 m
b Bottm width of anicut = 1.70 m
w1 + w2self weight of anicut
p1 Pressure due to water besswall
p2 Horizontal water pressure
p3 Up lift pressure
h Food heigth = 0.60 m
H heigth of anicut = 1.30 m
L considening one metre = 1
S 2.3
C 0.6
Forces acting on a over flow gravity dam
Forces and momrnt calculation's
considening one metre length of ancut and taking
Restoring moment as positive (+ ve) and overturning moment
as negative (-ve)
moment taken at B
s. no. Forces
v- vertical
forces
H- horizontal
forces
Force
acting at a
distance
from B
moment at B
2x5
+ ve -ve
1 w1 = a x H xLxS
1.79 1.79 2.20 3.95
2 w2 = 1/2x(b-a)xHxLxS
1.64 1.64 1.13 1.86
3 p1 =wh x H
0.78 0.78 0.90 0.70
4 p2 =wH2/2 x H
0.85 0.85 0.60 0.51
5 p3 =cxwbx(H+h)/2
0.80 0.80 1.80 1.43
TOTAL 2.64 1.63 5.81 2.64
Em=mr-mo 3.16
CHECKS IN OVERTURNING
Factor of satety agaist overturning
Emr/Emo =+m/-m = Restoning moment/overturning moment
2.20
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
it is more than 1.50 hance structure is safe against overturning
SLINDING
Factor of safety against slinding
Ev/Eh = 1.63
it is more than 1.0 hance structure is safe against slinding
RUPTURE (safety against tension at the bese)
X Relne Position of resultant measured from toe
x = Em/Ev = 1.20
e = b/2 - X -0.35
Ev/b (1+6e/b) 0.33
Ev/b (1-6e/b) 2.78
P max = 0.33
P min = 2.78
S.No Particular Qty. Rate Labour
Rate
Unit Amount
1 Excavation in soil dry or
most&disposal of excavated
material within intial lead of 30 m
and liftof 1.5m including dressing
etc complete 7.62 77.00 77 cum 586.43
2 Excavation in ordinary murram or
earth mixed with bajri and kankar or
boulder dry or most&disposal of
excavated material within intial lead
of 30 m and liftof 1.5m including
dressing etc complete 22.85 85.00 85 cum 1942.08
3 Excavation in disintegrated rock and
or soft rock or hard bankar or
compacted murrum dry or moist
including dressing&disposal of
exeavated matarual with intial lead
of 30m and lift of 1.5m 45.70 130.00 130 cum 5940.48
4 cement concrete well mixed in
cement mortar(1:4:8) laid in position
complete including curing
Aggregate size upto 50mm. HB 12.62 2014.00 133.99 cum 25406.61
5 Random rubble stone masonary in
cement sand mortar(1:6) for
foundation 56.47 1442.00 318 cum 81422.53
6 Random rubble stone masonary in
cement sand mortar(1:6) forsuper
structure 42.34 1562.00 438 cum 66136.64
7 Cement plaster including smooth
finishing in cement mortar
(1:4)25mm thick 42.82 141.00 59.45 sqm 6037.62
8 Cement concrete coping in cement
mortar1:2:4.100mm thick 3.11 3316.00 304.75 cum 10301.15
ABSTRACT OF COST
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
9 E/W for bind / embankment in dry
or mosit soil including laying on
layers 1.5cm Breaking of clods sort
ing of grass pabbles ete and dressing
in requred profile when compacted
manually or by plain roller with
initial lead of 30mt and lift 1.5 mt
(exeluding
Hard soil 50% 112.50 85.00 85 cum 9562.50
Ordinary murram 50% 112.50 96.00 96 cum 10800.00
10 Rehandling of cement beyond 100 m
initial lead lead up to 200 11.67 44.00 44 mt. 513.46
TOTAL 218649.51
METARIAL 147620.69
LABOUR 71028.82
TOTAL 218649.51
Add 3% Contingency Charges 6559.49
TOTAL Rs. 225208.99
Say 2.25
S.No. PARTICULAR No. LENGTH WIDTH HT/DEPTH QUANTITY
1 Total Excavation
H.W. 1.00 6.00 1.70 2.00 20.40
H.W.E. 2.00 3.00 1.10 2.00 13.20
S.W. 2.00 4.00 1.10 2.00 17.60
wing wall 2.00 1.50 1.10 2.00 6.60
Toe wall 1.00 6.00 0.45 0.90 2.43
Apron 1.00 6.00 2.95 0.90 15.93
Total (cu.m) 76.16
2 Excavation in hard soil dry or
most&disposal of excavated
material within intial lead of 30 m
and liftof 1.5m including dressing
etc complete 10%of
TotalExcavation
Total 7.62
3 Excavation in ordinary murram or
earth mixed with bajri and kankar or
boulder dry or most&disposal of
excavated material within intial lead
of 30 m and liftof 1.5m including
dressing etc complete 30% of Total
Excavation
Total 22.85
DETAILED ESTIMATE
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
4 Excavation in disintegrated rock and
or soft rock or hard bankar or
compacted murrum dry or moist
including dressing&disposal of
exeavated matarual with intial lead
of 30m and lift of 1.5m 60% of
Total Excavation
Total 45.70
5 cement concrete well mixed in
cement mortar(1:4:8) laid in position
complete including curing
Aggregate size upto 50mm. HB
Total Excavation H.W. 1.00 6.00 1.70 0.30 3.06
H.W.E. 2.00 3.00 1.10 0.30 1.98
S.W. 2.00 4.00 1.10 0.30 2.64
Wing Wall 2.00 1.50 1.10 0.30 0.99
Toe Wall 1.00 6.00 0.45 0.15 0.41
Apron 1.00 6.00 2.95 0.20 3.54
Total 12.62
6 Random rubble stone masonary in
cement sand mortar(1:6) for
foundation
H.W. 1.00 6.00 1.70 1.70 17.34
H.W.E. 2.00 3.00 1.10 1.70 11.22
S.W. 2.00 4.00 1.10 1.70 14.96
Wing Wall 2.00 1.50 1.10 1.70 5.61
Toe Wall 1.00 6.00 0.45 0.75 2.03
Apron 1.00 6.00 2.95 0.30 5.31
Total 56.47
7 Random rubble stone masonary in
cement sand mortar(1:6) for super
structure
H.W. 1.00 6.00 1.15 1.30 8.97
H.W.E 1.00 3.00 0.85 2.20 5.61
S.W. 2.00 3.40 0.85 1.65 9.54
2.00 0.60 0.85 2.20 2.24
2.00 0.50 0.85 1.10 0.94
Wing Wall 4.00 1.50 0.85 2.95 15.05
Total 42.34
8 Cement plaster including smooth
finishing in cement mortar
(1:3)25mm thick
H.W. 1.00 6.00 1.30 7.80
1.00 6.00 1.60 9.60
1.00 6.00 0.30 1.80
S.W. 2.00 0.60 0.90 1.08
2.00 1.10 1.55 1.08
2.00 3.40 1.65 11.22
2.00 2.95 0.30 1.77
Wing Wall 2.00 1.50 1.10 3.30
2.00 0.85 1.10 1.87
H.W.E. 1.00 3.00 0.50 1.50
Toe Wall 1.00 6.00 0.30 1.80
Total 42.82
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
9 Cement concrete coping in cement
mortar 1:2:4.75 mm thick
H.W. 1.00 6.00 0.60 0.08 0.27
S.W. 2.00 5.10 0.60 0.08 0.46
Wing Wall 4.00 1.50 0.60 0.08 0.27
H.W.E. 1.00 3.00 0.60 0.08 0.14
Toe.Wall 1.00 6.00 0.45 0.08 0.20
Apron 1.00 6.00 2.95 0.10 1.77
Total 3.11
10 E/W for bind / embankment in dry
or mosit soil including laying on
layers 1.5cm Breaking of clods sort
ing of grass pabbles ete and dressing
in requred profile when compacted
manually or by plain roller with
initial lead of 30mt and lift 1.5 mt
(exeluding 225
Total 225
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
0.60 P3
0.60
P1
1.30 w1 1.4
P2 0.65
0.43 w2
1.90
1.30
1.14
PLAN
1.5 6.00 1.5
4.00
0.45
0.60
1.70
0.60
0.57 1.13
1.50
0.60
1.30 1.10
G.L G.L
0.10
0.30 0.90
2.00
0.20
0.3 2.95
1.70
X-Section
2.
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
0.60
0.60
2.20
1.10
G.L G.L
2.00 2.00
0.3 0.3
1.10
S.W.& H.Ex- X- Sec.
1.10
W.W. X- Sec.
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of W/S IWMP I
2 Name of work :- CONTRUCTION OF WATER HARVESTING STR.
Design
1 Available crest length 10.00 M
2 Total catchment area 150.00 Ha
3 Hight of structure 1.50 M
A Design discharge (By flood discharge method)
A HYDROLIC DESIGN
Peak rate of run off in cum/sec.=
Q = C I A C= 0.40
36 Catchment Area 150.00
Q = 7.33 cumsec K = L3
H
L= 3800.00
Say 8 cumsec H= 40.00
K 37037.82
Tc=0.0195K0.77
64.25
I = 4.40
B HYDROLIC DESIGN
Q = 1.71L(h)3/2
L = 10.00 mt length available at site
h =[Q/1.71L]2/3
h = 0.58 Say = 0.60
Taking free board as 0.3 M
Total d = 0.90
C. STRUCTURAL DESIGN
(I) Top width of Head wall
h /(p-1)0.5
0.53 0.53 say = 0.80 M
(as per site condition where h = 0.60 m p = 2.30 0.60 M
p Specific gravty of stone masnory in cm = 2.3
(ii) Bottom width of head wall
b = h+H /(p-1)0.5
1.84 Say = 1.70 M
H =heigth of head wall in meters = 1.5 m 1.50 M
(iii) Length of head wall extension
H +d + 1 3.40 3.40 M
d = h+free board = 0.90 0.90 M
but as per side condition L/S M 1.5 R/S M 1.5 3.00 M
(iv) Heigth of Head wall extension
H + d = 2.40 M
(v) Botton width of HW ext. side wall & wing wall
0.5(H+h)= 1.05 1.10 M
(vi) Top width of HW ext
0.4H= 0.6 0.60 M
(vii) Length of Basin
L.B =0.75(H+d)+H 3.30 2.95 M
(viii) Thickness of Basin =0.60m(incloding concreting)
(ix) Height of side wall
P.S.SIKRAI, DISTT. DAUSA
ESTIMATE NO. 30
NAME OF WORK: CONSTRUCTION OF MASONARY WATER HARVESTING STRUCTURE
"B"
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
H+d = 2.40 2.40 M
(x) Height of side wall =1.5h at W W joints
1.5h = 0.90 1.10 M
(xi) Length of side wall = B. W. of H. W -B.W of H W E+L.B+ width of toe wall
4.00
(xii) Length of wing wall = 2.25 h= 1.35 1.50 M
(xiii) Height of the wing wall = 0.90 1.10 M
(xiv) Top width of Head wall ext site wall wing wall = 0.60mt
(xv) Width of toe wall= 0.45 M
(xvi)Height of toe wall = 0.30 M
(xvii)Height of wing wall at wing end = 1.10 M
(xviii)Bottem width of the side wall &wing wall taking as per Bottom width
of the head wall ext as in item no.5= m 1.10 M
(xix)Depth of foundation taking as 2.00 M
STABILITY CHECK'S
a Top width of anicut = 0.80 m
b Bottm width of anicut = 1.70 m
w1 + w2self weight of anicut
p1 Pressure due to water besswall
p2 Horizontal water pressure
p3 Up lift pressure
h Food heigth = 0.60 m
H heigth of anicut = 1.50 m
L considening one metre = 1
S 2.3
C 0.6
Forces acting on a over flow gravity dam
Forces and momrnt calculation's
considening one metre length of ancut and taking
Restoring moment as positive (+ ve) and overturning moment
as negative (-ve)
moment taken at B
s. no. Forces
v- vertical
forces
H-
horizontal
forces
Force
acting at a
distance
from B
moment at
B 2x5
+ ve -ve
1 w1 = a x H xLxS
2.76 2.76 2.20 6.07
2 w2 = 1/2x(b-a)xHxLxS
1.55 1.55 1.13 1.75
3 p1 =wh x H
0.90 0.90 0.90 0.81
4 p2 =wH2/2 x H
1.13 1.13 0.60 0.68
5 p3 =cxwbx(H+h)/2
0.92 0.92 1.80 1.65
TOTAL 3.39 2.03 7.83 3.14
Em=mr-mo 4.69
CHECKS IN OVERTURNING
Factor of satety agaist overturning
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
Emr/Emo =+m/-m = Restoning moment/overturning moment
2.49
it is more than 1.50 hance structure is safe against overturning
SLIDING
Factor of safety against slinding
Ev/Eh = 1.68
it is more than 1.0 hance structure is safe against slinding
RUPTURE (safety against tension at the bese)
X Relne Position of resultant measured from toe
x = Em/Ev = 1.38
e = b/2 - X -0.53
Ev/b (1+6e/b) 0.12
Ev/b (1-6e/b) 3.87
P max = 0.12
P min = 3.87
S.No Particular Qty. Rate Labour Rate Unit Amount
1 Excavation in soil dry or
most&disposal of excavated material
within intial lead of 30 m and liftof
1.5m including dressing etc
complete 10.20 77.00 77 cum 785.40
2 Excavation in ordinary murram or
earth mixed with bajri and kankar or
boulder dry or most&disposal of
excavated material within intial lead
of 30 m and liftof 1.5m including
dressing etc complete 30.60 85.00 85 cum 2601.00
3 Excavation in disintegrated rock and
or soft rock or hard bankar or
compacted murrum dry or moist
including dressing&disposal of
exeavated matarual with intial lead
of 30m and lift of 1.5m 61.20 130.00 130 cum 7956.00
4 cement concrete well mixed in
cement mortar(1:4:8) laid in position
complete including curing Aggregate
size upto 50mm. HB 17.29 2014.00 133.9 cum 34811.99
5 Random rubble stone masonary in
cement sand mortar(1:6) for
foundation 72.92 1442.00 318 cum 105143.43
6 Random rubble stone masonary in
cement sand mortar(1:6) for super
structure 53.50 1562.00 438 cum 83563.88
7 Cement plaster including smooth
finishing in cement mortar
(1:4)25mm thick 62.22 141.00 59.45 sqm 8773.02
8 Cement concrete coping in cement
mortar1:1.5:3.100mm thick 4.75 3316.00 304.75 cum 15755.97
ABSTRACT OF COST
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
9 E/W for bind / embankment in dry
or mosit soil including laying on
layers 1.5cm Breaking of clods sort
ing of grass pabbles ete and dressing
in requred profile when compacted
manually or by plain roller with
initial lead of 30mt and lift 1.5 mt
(exeluding
Hard soil 50% 112.50 85.00 85 cum 9562.50
Ordinary murram 50% 112.50 96.00 96 cum 10800.00
10 Rehandling of cement beyond 100 m
initial lead lead up to 200 15.41 44.00 44 mt. 678.20
TOTAL 280431.39
METARIAL 193967.74
LABOUR 86463.65
TOTAL 280431.39
Add 3% Contingency Charges 8412.94
TOTAL Rs. 288844.33
Say 2.89
Prepared by checked by Approved by
S.No.PARTICULAR No. LENGTH WIDTH HT/DEPTH QUANTITY
1 Total Excavation
H.W. 1.00 10.00 1.70 2.00 34.00
H.W.E. 2.00 3.00 1.10 2.00 13.20
S.W. 2.00 4.00 1.10 2.00 17.60
wing wall 2.00 1.50 1.10 2.00 6.60
Toe wall 1.00 10.00 0.45 0.90 4.05
Apron 1.00 10.00 2.95 0.90 26.55
Total (cu.m) 102.00
2 Excavation in hard soil dry or
most&disposal of excavated material
within intial lead of 30 m and liftof
1.5m including dressing etc
complete 10%of TotalExcavation
Total 10.20
3 Excavation in ordinary murram or
earth mixed with bajri and kankar or
boulder dry or most&disposal of
excavated material within intial lead
of 30 m and liftof 1.5m including
dressing etc complete 30% of Total
Excavation
Total 30.60
DETAILED ESTIMATE
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
4 Excavation in disintegrated rock and
or soft rock or hard bankar or
compacted murrum dry or moist
including dressing&disposal of
exeavated matarual with intial lead
of 30m and lift of 1.5m 60% of
Total Excavation
Total 61.20
5 cement concrete well mixed in
cement mortar(1:4:8) laid in position
complete including curing Aggregate
size upto 50mm. HB Total
Excavation H.W. 1.00 10.00 1.70 0.30 5.10
H.W.E. 2.00 3.00 1.10 0.30 1.98
S.W. 2.00 4.00 1.10 0.30 2.64
Wing Wall 2.00 1.50 1.10 0.30 0.99
Toe Wall 1.00 10.00 0.45 0.15 0.68
Apron 1.00 10.00 2.95 0.20 5.90
Total 17.29
6 Random rubble stone masonary in
cement sand mortar(1:6) for
foundation
H.W. 1.00 10.00 1.70 1.70 28.90
H.W.E. 2.00 3.00 1.10 1.70 11.22
S.W. 2.00 4.00 1.10 1.70 14.96
Wing Wall 2.00 1.50 1.10 1.70 5.61
Toe Wall 1.00 10.00 0.45 0.75 3.38
Apron 1.00 10.00 2.95 0.30 8.85
Total 72.92
7 Random rubble stone masonary in
cement sand mortar(1:6) forsuper
structure
H.W. 1.00 10.00 1.25 1.50 18.75
H.W.E 1.00 3.00 0.85 2.40 6.12
S.W. 2.00 3.40 0.85 1.75 10.12
2.00 0.60 0.85 2.40 2.45
2.00 0.50 0.85 1.20 1.02
Wing Wall 4.00 1.50 0.85 2.95 15.05
Total 53.50
8 Cement plaster including smooth
finishing in cement mortar
(1:3)25mm thick
H.W. 1.00 10.00 1.50 15.00
1.00 10.00 1.80 18.00
1.00 10.00 0.30 3.00
S.W. 2.00 0.80 0.90 1.44
2.00 0.90 1.65 1.44
2.00 3.40 1.75 11.90
2.00 2.95 0.30 1.77
Wing Wall 2.00 1.50 1.10 3.30
2.00 0.85 1.10 1.87
H.W.E. 1.00 3.00 0.50 1.50
Toe Wall 1.00 10.00 0.30 3.00
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
Total 62.22
9 Cement concrete coping in cement
mortar 1:2:4.75 mm thick
H.W. 1.00 10.00 0.80 0.08 0.60
S.W. 2.00 5.10 0.60 0.08 0.46
Wing Wall 4.00 1.50 0.60 0.08 0.27
H.W.E. 1.00 3.00 0.60 0.08 0.14
Toe.Wall 1.00 10.00 0.45 0.08 0.34
Apron 1.00 10.00 2.95 0.10 2.95
Total 4.75
10 E/W for bind / embankment in dry
or mosit soil including laying on
layers 1.5cm Breaking of clods sort
ing of grass pabbles ete and dressing
in requred profile when compacted
manually or by plain roller with
initial lead of 30mt and lift 1.5 mt
(exeluding 225
Total 225
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
0.60 P3
0.80
P1
1.50 w1 1.3
P2 0.75
0.50 w2
2.10
1.50
1.26
PLAN
1.5 10.00 1.5
4.00
0.45
0.60
1.70
0.80
0.57 1.13
1.50
0.80
1.50 1.10
G.L G.L
0.10
0.30 0.90
2.00
0.20
0.3 2.95
1.70
X-Section
2.
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
0.60
0.60
2.40
1.10
G.L G.L
2.00 2.00
0.3 0.3
1.10
S.W.& H.Ex- X- Sec.
1.10
W.W. X- Sec.
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
1 Name of W/S IWMP I
2 Name of work :- CONTRUCTION OF WATER HARVESTING STR.
Design
1 Available crest length 20.00 M
2 Total catchment area 200.00 Ha
3 Hight of structure 1.80 M
A Design discharge (By flood discharge method)
A HYDRAULIC DESIGN
Peak rate of run off in cum/sec.=
Q = C I A C= 0.40
36 Catchment Area 200.00
Q = 9.78 cumsec K = L3
H
L= 3800.00
Say 9.8 cumsec H= 40.00
K 37037.82
Tc=0.0195K0.77
64.25
I = 4.40
B HYDRAULIC DESIGN
Q = 1.71L(h)3/2
L = 20.00 mt length available at site
h =[Q/1.71L]2/3
h = 0.56 Say = 0.60
Taking free board as 0.3 M
Total d = 0.90
C. STRUCTURAL DESIGN
(I) Top width of Head wall
h /(p-1)0.5
0.53 0.53 say = 0.80 M
(as per site condition where h = 0.60 m p = 2.30 0.60 M
p Specific gravty of stone masnory in cm = 2.3
(ii) Bottom width of head wall
b = h+H /(p-1)0.5
2.10 Say = 1.70 M
H =heigth of head wall in meters = 1.8 m 1.80 M
(iii) Length of head wall extension
H +d + 1 3.70 3.70 M
d = h+free board = 0.90 0.90 M
but as per side condition L/S M 1.5 R/S M 1.5 3.00 M
(iv) Heigth of Head wall extension
H + d = 2.70 M
(v) Botton width of HW ext. side wall & wing wall
0.5(H+h)= 1.20 1.10 M
(vi) Top width of HW ext
0.4H= 0.72 0.60 M
(vii) Length of Basin
L.B =0.75(H+d)+H 3.83 2.95 M
(viii) Thickness of Basin =0.60m(incloding concreting)
(ix) Height of side wall
H+d = 2.70 2.70 M
(x) Height of side wall =1.5h at W W joints
1.5h = 0.90 1.10 M
(xi) Length of side wall = B. W. of H. W -B.W of H W E+L.B+ width of toe wall
P.S.SIKRAI, DISTT. DAUSA
ESTIMATE NO. 31
NAME OF WORK: CONSTRUCTION OF MASONARY WATER HARVESTING STRUCTURE "B"
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
4.00
(xii) Length of wing wall = 2.25 h= 1.35 1.50 M
(xiii) Height of the wing wall = 0.90 1.10 M
(xiv) Top width of Head wall ext site wall wing wall = 0.60mt
(xv) Width of toe wall= 0.45 M
(xvi) Height of toe wall = 0.30 M
(xvii) Height of wing wall at wing end = 1.10 M
(xviii) Bottem width of the side wall &wing wall taking as per Bottom width
of the head wall ext as in item no.5= m 1.10 M
(xix) Depth of foundation taking as 2.00 M
STABILITY CHECK'S
a Top width of anicut = 0.80 m
b Bottm width of anicut = 1.70 m
w1 + w2 self weight of anicut
p1 Pressure due to water besswall
p2 Horizontal water pressure
p3 Up lift pressure
h Food heigth = 0.60 m
H heigth of anicut = 1.80 m
L considening one metre = 1
S 2.3
C 0.6
Forces acting on a over flow gravity dam
Forces and momrnt calculation's
considening one metre length of ancut and taking
Restoring moment as positive (+ ve) and overturning moment
as negative (-ve)
moment taken at B
s. no. Forces v- vertical
forces
H-
horizontal
forces
Force
acting at a
distance
from B
moment at
B 2x5
+ ve -ve
1 w1 = a x H xLxS
3.31 3.31 2.20 7.29
2 w2 = 1/2x(b-a)xHxLxS
1.86 1.86 1.13 2.11
3 p1 =wh x H
1.08 1.08 0.90 0.97
4 p2 =wH2/2 x H
1.62 1.62 0.60 0.97
5 p3 =cxwbx(H+h)/2
1.10 1.10 1.80 1.98
TOTAL 4.07 2.70 9.39 3.93
Em=mr-mo 5.46
CHECKS IN OVERTURNING
Factor of satety agaist overturning
Emr/Emo =+m/-m = Restoning moment/overturning moment
2.39
it is more than 1.50 hance structure is safe against overturning
SLINDING
Factor of safety against slinding
Ev/Eh = 1.51
it is more than 1.0 hance structure is safe against slinding
RUPTURE (safety against tension at the bese)
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
X Relne Position of resultant measured from toe
x = Em/Ev = 1.34
e = b/2 - X -0.49
Ev/b (1+6e/b) 0.66
Ev/b (1-6e/b) 4.13
P max = 0.66
P min = 4.13
S.No Particular Qty. Rate Labour Rate Unit Amount
1
Excavation in soil dry or
most&disposal of excavated
material within intial lead of 30 m
and liftof 1.5m including dressing
etc complete 16.66 77.00 77 cum 1282.82
2
Excavation in ordinary murram or
earth mixed with bajri and kankar or
boulder dry or most&disposal of
excavated material within intial lead
of 30 m and liftof 1.5m including
dressing etc complete 49.98 85.00 85 cum 4248.30
3
Excavation in disintegrated rock and
or soft rock or hard bankar or
compacted murrum dry or moist
including dressing&disposal of
exeavated matarual with intial lead
of 30m and lift of 1.5m 99.96 130.00 130 cum 12994.80
4
cement concrete well mixed in
cement mortar(1:4:8) laid in
position complete including curing
Aggregate size upto 50mm. HB 28.96 2014.00 133.9 cum 58325.44
5
Random rubble stone masonary in
cement sand mortar(1:6) for
foundation 114.04 1442.00 318 cum 164445.68
6
Random rubble stone masonary in
cement sand mortar(1:6) forsuper
structure 81.81 1562.00 438 cum 127792.69
7
Cement plaster including smooth
finishing in cement mortar
(1:4)25mm thick 114.24 141.00 59.45 sqm 16107.84
8Cement concrete coping in cement
mortar1:2:4.100mm thick 8.64 3316.00 304.75 cum 28646.92
9
E/W for bind / embankment in dry
or mosit soil including laying on
layers 1.5cm Breaking of clods sort
ing of grass pabbles ete and dressing
in requred profile when compacted
manually or by plain roller with
initial lead of 30mt and lift 1.5 mt
(exeluding
Hard soil 50% 112.50 85.00 85 cum 9562.50
Ordinary murram 50% 112.50 96.00 96 cum 10800.00
10Rehandling of cement beyond 100
m initial lead lead up to 200 24.76 44.00 44 mt. 1089.28
TOTAL 435296.27
ABSTRACT OF COST
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
METARIAL 309917.49
LABOUR 125378.78
TOTAL 435296.27
Add 3% Contingency Charges 13058.89
TOTAL Rs. 448355.15
Say 4.48
S.No. PARTICULAR No. LENGTH WIDTH HT/DEPTH QUANTITY
1 Total Excavation
H.W. 1.00 20.00 1.70 2.00 68.00
H.W.E. 2.00 3.00 1.10 2.00 13.20
S.W. 2.00 4.00 1.10 2.00 17.60
wing wall 2.00 1.50 1.10 2.00 6.60
Toe wall 1.00 20.00 0.45 0.90 8.10
Apron 1.00 20.00 2.95 0.90 53.10
Total (cu.m) 166.60
2
Excavation in hard soil dry or
most&disposal of excavated
material within intial lead of 30 m
and liftof 1.5m including dressing
etc complete 10%of
TotalExcavation
Total 16.66
3
Excavation in ordinary murram or
earth mixed with bajri and kankar or
boulder dry or most&disposal of
excavated material within intial lead
of 30 m and liftof 1.5m including
dressing etc complete 30% of Total
Excavation
Total 49.98
DETAILED ESTIMATE
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
4
Excavation in disintegrated rock and
or soft rock or hard bankar or
compacted murrum dry or moist
including dressing&disposal of
exeavated matarual with intial lead
of 30m and lift of 1.5m 60% of
Total Excavation
Total 99.96
5
cement concrete well mixed in
cement mortar(1:4:8) laid in
position complete including curing
Aggregate size upto 50mm. HB
Total Excavation H.W. 1.00 20.00 1.70 0.30 10.20
H.W.E. 2.00 3.00 1.10 0.30 1.98
S.W. 2.00 4.00 1.10 0.30 2.64
Wing Wall 2.00 1.50 1.10 0.30 0.99
Toe Wall 1.00 20.00 0.45 0.15 1.35
Apron 1.00 20.00 2.95 0.20 11.80
Total 28.96
6
Random rubble stone masonary in
cement sand mortar(1:6) for
foundation
H.W. 1.00 20.00 1.70 1.70 57.80
H.W.E. 2.00 3.00 1.10 1.70 11.22
S.W. 2.00 4.00 1.10 1.70 14.96
Wing Wall 2.00 1.50 1.10 1.70 5.61
Toe Wall 1.00 20.00 0.45 0.75 6.75
Apron 1.00 20.00 2.95 0.30 17.70
Total 114.04
7
Random rubble stone masonary in
cement sand mortar(1:6) forsuper
structure
H.W. 1.00 20.00 1.25 1.80 45.00
H.W.E 1.00 3.00 0.85 2.70 6.89
S.W. 2.00 3.40 0.85 1.90 10.98
2.00 0.60 0.85 2.70 2.75
2.00 0.50 0.85 1.35 1.15
Wing Wall 4.00 1.50 0.85 2.95 15.05
Total 81.81
8
Cement plaster including smooth
finishing in cement mortar
(1:3)25mm thick
H.W. 1.00 20.00 1.80 36.00
1.00 20.00 2.10 42.00
1.00 20.00 0.30 6.00
S.W. 2.00 0.80 0.90 1.44
2.00 0.90 1.80 1.44
2.00 3.40 1.90 12.92
2.00 2.95 0.30 1.77
Wing Wall 2.00 1.50 1.10 3.30
2.00 0.85 1.10 1.87
H.W.E. 1.00 3.00 0.50 1.50
Toe Wall 1.00 20.00 0.30 6.00
Total 114.24
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
9Cement concrete coping in cement
mortar1:2:4.75 mm thick
H.W. 1.00 20.00 0.80 0.08 1.20
S.W. 2.00 5.10 0.60 0.08 0.46
Wing Wall 4.00 1.50 0.60 0.08 0.27
H.W.E. 1.00 3.00 0.60 0.08 0.14
Toe.Wall 1.00 20.00 0.45 0.08 0.68
Apron 1.00 20.00 2.95 0.10 5.90
Total 8.64
10
E/W for bind / embankment in dry
or mosit soil including laying on
layers 1.5cm Breaking of clods sort
ing of grass pabbles ete and dressing
in requred profile when compacted
manually or by plain roller with
initial lead of 30mt and lift 1.5 mt
(exeluding 225
Total 225
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
0.60 P3
0.80
P1
1.80 w1 1.3
P2 0.90
0.60 w2
2.40
1.80
1.44
PLAN
1.5 20.00 1.5
4.00
0.45
0.60
1.70
0.80
0.57 1.13
1.50
0.80
1.80 1.10
G.L G.L
0.10
0.30 0.90
2.00
0.20
0.3 2.95
1.70
X-Section
2.
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
0.60
0.60
2.70
1.10
G.L G.L
2.00 2.00
0.3 0.3
1.10
S.W.& H.Ex- X- Sec.
1.10
W.W. X- Sec.
IWMP-I, BLOCK-SIKRAI, DAUSA 4-
S.N Details of work Qty Rate Unit Amount
1
Excavation of earth work in hard
soil for digging of pits, 0.75 x0.75
x0.90 = 0.5062cum
0.51 68.00 cum 34.43
2 Treatment of pits
a Through chemicals 1.00 0.41 Per plant 0.41
b Through mannure 1.00 0.20 Per plant 0.20
3
Planting of plant with rehandling
upto 100m,refilling of soil &
compaction etc
1.00 5.50 Per plant 5.50
4Cost of Plant including
transportation1.00 23.00 Per plant 23.00
4Making of thanwala,of 50 cm
radious1.00 1.30 Per plant 1.30
5Watering of plant,15 lit per plant
five times in the year5.00 1.35 Per plant 6.75
6Weeding & hoeing three times in
the year3.00 0.90 Per plant 2.70
7Cost of Mannure including
transportation1.00 5.00 Per Kg 5.00
Total 79.29
Contengency 3% 2.38
Grand total 81.66
Per plant 82.00
S.No Details of work Qty Rate Unit Amount
1 Plant spacing c/c 8mx8m 156 82 No 12792
2 20% Plant Gap filling in second year 31.2 82 No 2558.4
3 Protection Work of plant 156 5 Ha 780
4 Protection Work 20% in second year 31.2 5 Ha 156
Total Amount 16286.4
Say Rs 16300
MODEL ESTIMATE OF HORTICULTURE PLANTATION
Cost per Ha of Aawla Plant
Aawla IWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant
S.N Details of work Qty Rate Unit Amount
1
Excavation of earth work in hard
soil for digging of pits, 0.75 x0.75
x0.90 = 0.5062cum
0.51 68.00 cum 34.43
2 Treatment of pits
a Through chemicals 1.00 0.41 Per plant 0.41
b Through mannure 1.00 0.20 Per plant 0.20
3
Planting of plant with rehandling
upto 100m,refilling of soil &
compaction etc
1.00 5.50 Per plant 5.50
4Cost of Plant including
transportation1.00 20.00 Per plant 20.00
4Making of thanwala,of 50 cm
radious1.00 1.30 Per plant 1.30
5Watering of plant,15 lit per plant
five times in the year5.00 1.35 Per plant 6.75
6Weeding & hoeing three times in
the year3.00 0.90 Per plant 2.70
7Cost of Mannure including
transportation1.00 5.00 Per Kg 5.00
Total 76.29
Contengency 3% 2.29
Grand total 78.57
Per plant 79.00
S.No Details of work Qty Rate Unit Amount
1 Plant spacing c/c 8mx8m 156 79 No 12324
2 20% Plant Gap filling in second year 31.2 79 No 2464.8
3 Protection Work of plant 156 5 Ha 780
4 Protection Work 20% in second year 31.2 5 Ha 156
Total Amount 15724.8
Say Rs 15800
MODEL ESTIMATE OF HORTICULTURE PLANTATION
Cost per Ha of Orange Plant
Orange IIWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant
S.N Details of work Qty Rate Unit Amount
1
Excavation of earth work in hard soil
for digging of pits, 0.45 x0.45 x0.45 =
0.091cum
0.09 68.00 cum 6.20
2 Treatment of pits
a Through chemicals 1.00 0.41 Per plant 0.41
b Through mannure 1.00 0.20 Per plant 0.20
3Planting of plant with rehandling upto
100m,refilling of soil & compaction etc1.00 5.50 Per plant 5.50
4 Cost of Plant including transportation 1.00 9.00 Per plant 9.00
4 Making of thanwala,of 50 cm radious 1.00 1.30 Per plant 1.30
5Watering of plant,15 lit per plant five
times in the year5.00 1.35 Per plant 6.75
6Weeding & hoeing three times in the
year3.00 0.90 Per plant 2.70
7Cost of Mannure including
transportation1.00 5.00 Per Kg 5.00
Total 37.06
Contengency 3% 1.11
Grand total 38.17
Per plant 39.00
2500 Plant per Ha
S.No Details of work Qty Rate Unit Amount
1 Plant spacing c/c 2mx2m 2500 39 No 97500
2 20% Plant Gap filling in second year 500 39 No 19500
3 Protection Work of plant 2500 5 Ha 12500
4 Protection Work 20% in second year 500 5 Ha 2500
Total Amount 132000
Say Rs 132000
MODEL ESTIMATE OF HORTICULTURE PLANTATION
Cost per Ha of Papaya Plant
Papaya IWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant
S.N Details of work Qty Rate Unit Amount
1
Excavation of earth work in hard
soil for digging of pits, 0.75 x0.75
x0.90 = 0.5062cum
0.51 68.00 cum 34.43
2 Treatment of pits
a Through chemicals 1.00 0.41 Per plant 0.41
b Through mannure 1.00 0.20 Per plant 0.20
3
Planting of plant with rehandling
upto 100m,refilling of soil &
compaction etc
1.00 5.50 Per plant 5.50
4Cost of Plant including
transportation1.00 20.00 Per plant 20.00
4Making of thanwala,of 50 cm
radious1.00 1.30 Per plant 1.30
5Watering of plant,15 lit per plant
five times in the year5.00 1.35 Per plant 6.75
6Weeding & hoeing three times in
the year3.00 0.90 Per plant 2.70
7Cost of Mannure including
transportation1.00 5.00 Per Kg 5.00
Total 76.29
Contengency 3% 2.29
Grand total 78.57
Per plant 79.00
277 Plant per Ha
S.No Details of work Qty Rate Unit Amount
1 Plant spacing c/c 6mx6m 277 79.00 No 21883
2 20% Plant Gap filling in second year 55.4 79.00 No 4376.6
3 Protection Work of plant 277 5 Ha 1385
4 Protection Work 20% in second year 55.4 5 Ha 277
Total Amount 27921.6
Say Rs 28000
MODEL ESTIMATE OF HORTICULTURE PLANTATION
Cost per Ha of Guava Plant
Guava IWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant
S.N Details of work Qty Rate Unit Amount
1
Excavation of earth work in hard
soil for digging of pits, 0.75 x0.75
x0.90 = 0.5062cum
0.51 68.00 cum 34.43
2 Treatment of pits
a Through chemicals 1.00 0.41 Per plant 0.41
b Through mannure 1.00 0.20 Per plant 0.20
3
Planting of plant with rehandling
upto 100m,refilling of soil &
compaction etc
1.00 5.50 Per plant 5.50
4Cost of Plant including
transportation1.00 20.00 Per plant 20.00
4Making of thanwala,of 50 cm
radious1.00 1.30 Per plant 1.30
5Watering of plant,15 lit per plant
five times in the year5.00 1.35 Per plant 6.75
6Weeding & hoeing three times in
the year3.00 0.90 Per plant 2.70
7Cost of Mannure including
transportation1.00 5.00 Per Kg 5.00
Total 76.29
Contengency 3% 2.29
Grand total 78.57
Per plant 79.00
277 Plant per Ha
S.No Details of work Qty Rate Unit Amount
1 Plant spacing c/c 6mx6m 277 79.00 No 21883
2 20% Plant Gap filling in second year 55.4 79.00 No 4376.6
3 Protection Work of plant 277 5 Ha 1385
4 Protection Work 20% in second year 55.4 5 Ha 277
Total Amount 27921.6
Say Rs 28000
MODEL ESTIMATE OF HORTICULTURE PLANTATION
Cost per Ha of Ber Plant
Ber IWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant
S.N Details of work Qty Rate Unit Amount
1
Excavation of earth work in hard
soil for digging of pits, 0.75 x0.75
x0.90 = 0.5062cum
0.51 68.00 cum 34.43
2 Treatment of pits
a Through chemicals 1.00 0.41 Per plant 0.41
b Through mannure 1.00 0.20 Per plant 0.20
3
Planting of plant with rehandling
upto 100m,refilling of soil &
compaction etc
1.00 5.50 Per plant 5.50
4Cost of Plant including
transportation1.00 8.00 Per plant 8.00
4Making of thanwala,of 50 cm
radious1.00 1.30 Per plant 1.30
5Watering of plant,15 lit per plant
five times in the year5.00 1.35 Per plant 6.75
6Weeding & hoeing three times in
the year3.00 0.90 Per plant 2.70
7Cost of Mannure including
transportation1.00 5.00 Per Kg 5.00
Total 64.29
Contengency 3% 1.93
Grand total 66.21
Per plant 67.00
277 Plant per Ha
S.No Details of work Qty Rate Unit Amount
1 Plant spacing c/c 6mx6m 277 67.00 No 18559
2 20% Plant Gap filling in second year 55.4 67.00 No 3711.8
3 Protection Work of plant 277 5 Ha 1385
4 Protection Work 20% in second year 55.4 5 Ha 277
Total Amount 23932.8
Say Rs 24000
MODEL ESTIMATE OF HORTICULTURE PLANTATION
Cost per Ha of Karonda Plant
Karonda IWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant
S.N Details of work Qty Rate Unit Amount
1
Excavation of earth work in hard
soil for digging of pits, 0.75 x0.75
x0.90 = 0.5062cum
0.51 68.00 cum 34.43
2 Treatment of pits
a Through chemicals 1.00 0.41 Per plant 0.41
b Through mannure 1.00 0.20 Per plant 0.20
3
Planting of plant with rehandling
upto 100m,refilling of soil &
compaction etc
1.00 5.50 Per plant 5.50
4Cost of Plant including
transportation1.00 20.00 Per plant 20.00
4Making of thanwala,of 50 cm
radious1.00 1.30 Per plant 1.30
5Watering of plant,15 lit per plant
five times in the year5.00 1.35 Per plant 6.75
6Weeding & hoeing three times in
the year3.00 0.90 Per plant 2.70
7Cost of Mannure including
transportation1.00 5.00 Per Kg 5.00
Total 76.29
Contengency 3% 2.29
Grand total 78.57
Per plant 79.00
277 Plant per Ha
S.No Details of work Qty Rate Unit Amount
1 Plant spacing c/c 6mx6m 277 79.00 No 21883
2 20% Plant Gap filling in second year 55.4 79.00 No 4376.6
3 Protection Work of plant 277 5 Ha 1385
4 Protection Work 20% in second year 55.4 5 Ha 277
Total Amount 27921.6
Say Rs 28000
MODEL ESTIMATE OF HORTICULTURE PLANTATION
Cost per Ha of Neebu Plant
Neebu IWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant
S.N Details of work Qty Rate Unit Amount
1 CVH 112 47.59 PER MET. 5330.08
2
Excavation of earth work in hard
soil for digging of pits, 0.45 x0.45
x0.45 = 0.0911X22 = 2 cum
2.00 68.00 cum 136.00
3 Treatment of pits
A Through chemicals 22.00 0.41 Per plant 9.02
B Through mannure 22.00 0.20 Per plant 4.40
4
Planting of plant with rehandling
upto 100m,refilling of soil &
compaction etc
22.00 5.50 Per plant 121.00
5Cost of Plant including
transportation22.00 2.50 Per plant 55.00
6Cost of Mannure including
transportation22.00 1.00 Per Kg 22.00
Total 5677.50
Contengency 3% 170.33
Grand total 5847.83
Per Hac 5848.00
Add 20% for GAPFILLING 1169.6
Rs. 7017.60
MODEL ESTIMATE OF AGRO FORESTY
AGRO FORESTRY IWMP-I, BLOCK-SIKRAI, DAUSA Estimate of horticulture plant