Northwest River Forecast CenterGFE/ICS Grid Investigation and Utilization

by

Don Laurine

Martin Lee

Harold Opitz

DOH workshop – June 2004

Objectives of This Project:

Take Advantage of WFO Gridded Forecasts

Develop Understanding of Gridded Issues

Move Away from Climatologically based System

Position Office to be a customer and service provider for gridded information

Apply to Both Temperature and Precipitation

Support Finer Resolution Models

Utilize Nationally Supported Software

DOH workshop – June 2004

GFE System

2 – 1 Ghz CPUs

I GB memory

100 MB network band width

Linux Red Hat 7.3

GFE RPP 21.0

DOH workshop – June 2004

Basic System Issues

- Difficult to Use all WFO ISC Grids

- Lack of Tools for RFC to Deal with Grid Inconsistencies

- Limited Training and Support

- High Learning Curve for Python and Developing Procedures and CRON Applications

- Takes 10 Minutes to Generated NWSRFS Forecasts without Analysis

- All Input in NetCDF Format

DOH workshop – June 2004

Missing ISC Grids

DOH workshop – June 2004

Inconsistency

DOH workshop – June 2004

Lack of Tools

DOH workshop – June 2004

Grid Elevation and Value Issue

DOH workshop – June 2004

Current NWRFC Status

Focused Still - Grids to Points

Developing A Winter QPF Project for Winter 2004

Evaluating Temperature Forecasts This Spring

Working With FSL to Develop Methods to Deal With Multiple WFO ISC Grids

DOH workshop – June 2004

Temperature Verification Sites

DOH workshop – June 2004

Max Temperature Average Bias

WestSide ISC Area < 3k ft MAX_T AVG BIAS

-3.5

-3

-2.5

-2

-1.5

-1

-0.5

0

0.5

1

1 2 3 4 5 6

Forecast Day

AVG

BIA

S ws<3K CLMws<3k MOSws<3k GFEws<3k SFT

WestSide ISC Area > 3k ft MAX_T AVG BIAS

-6

-5

-4

-3

-2

-1

0

1

2

3

1 2 3 4 5 6

Forecast Day

AVG

BIA

S ws>3K CLMws>3k MOSws>3k GFEws>3k SFT

EastSide ISC Area < 3k ft MAX_T AVG BIAS

-3.5

-3

-2.5

-2

-1.5

-1

-0.5

0

0.5

1

1 2 3 4 5 6

Forecast Day

AVG

BIA

S es<3K CLMes<3k MOSes<3k GFEes<3k SFT

EeastSide ISC Area > 3k ft MAX_T AVG BIAS

-2.5

-2

-1.5

-1

-0.5

01 2 3 4 5 6

Forecast Day

AV

G B

IAS es>3K CLM

es>3k MOSes>3k GFEes>3k SFT

DOH workshop – June 2004

Max Temperature MAE

WestSide ISC Area < 3k ft MAX_T MAE

0

1

2

3

4

5

6

7

1 2 3 4 5 6

Forecast Day

MA

E

ws<3K CLMws<3k MOSws<3k GFEws<3k SFT

WestSide ISC Area > 3k ft MAX_T MAE

0

1

2

3

4

5

6

7

8

9

10

1 2 3 4 5 6

Forecast Day

MAE

ws>3K CLMws>3k MOSws>3k GFEws>3k SFT

WestSide ISC Area < 3k ft MAX_T MAE

0

1

2

3

4

5

6

7

1 2 3 4 5 6

Forecast Day

MA

E

ws<3K CLMws<3k MOSws<3k GFEws<3k SFT

EeastSide ISC Area > 3k ft MAX_T MAE

0

2

4

6

8

10

12

1 2 3 4 5 6

Forecast Day

MA

E

es>3K CLMes>3k MOSes>3k GFEes>3k SFT

DOH workshop – June 2004

Min Temperature Average Bias

WestSide ISC Area < 3k ft MIN_T AVG BIAS

-2.5

-2

-1.5

-1

-0.5

0

0.5

1

1.5

1 2 3 4 5 6

Forecast Day

AVG

BIA

S ws<3K CLMws<3k MOSws<3k GFEws<3k SFT

WestSide ISC Area > 3k ft MIN_T AVG BIAS

-4

-3

-2

-1

0

1

2

1 2 3 4 5 6

Forecast Day

AVG

BIA

S ws>3K CLMws>3k MOSws>3k GFEws>3k SFT

EeastSide ISC Area > 3k ft MIN_T AVG BIAS

-3

-2.5

-2

-1.5

-1

-0.5

0

0.5

1

1.5

1 2 3 4 5 6

Forecast Day

AVG

BIA

S es>3K CLMes>3k MOSes>3k GFEes>3k SFT

EastSide ISC Area < 3k ft MIN_T AVG BIAS

-2

-1.5

-1

-0.5

0

0.5

1

1.5

1 2 3 4 5 6

Forecast Day

AVG

BIA

S es<3K CLMes<3k MOSes<3k GFEes<3k SFT

DOH workshop – June 2004

Min Temperature MAE

WestSide ISC Area > 3k ft MIN_T MAE

0

1

2

3

4

5

6

1 2 3 4 5 6

Forecast Day

MAE

ws>3K CLMws>3k MOSws>3k GFEws>3k SFT

WestSide ISC Area < 3k ft MIN_T MAE

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

1 2 3 4 5 6

Forecast Day

MAE

ws<3K CLMws<3k MOSws<3k GFEws<3k SFT

EeastSide ISC Area > 3k ft MIN_T MAE

0

1

2

3

4

5

6

1 2 3 4 5 6

Forecast Day

MA

E

es>3K CLMes>3k MOSes>3k GFEes>3k SFT

EastSide ISC Area < 3k ft MIN_T MAE

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

5

1 2 3 4 5 6

Forecast Day

MAE

es<3K CLMes<3k MOSes<3k GFEes<3k SFT

DOH workshop – June 2004

Non ISC (Model Only) Average Bias

EastSide Non-ISC Area < 3k ft MAX_T AVG BIAS

-14

-12

-10

-8

-6

-4

-2

01 2 3 4 5 6

Forecast Day

AVG

BIA

S es<3K CLMes<3k MOSes<3k GFE

EASTSIDE Non-ISC AREA > 3k FT MAX_T AVG BIAS

-9

-8

-7

-6

-5

-4

-3

-2

-1

01 2 3 4 5 6

Forecast Day

AVG

BIA

S es>3K CLMes>3k MOSes>3k GFE

EastSide Non-ISC Area < 3k ft MIN_T AVG BIAS

-6

-4

-2

0

2

4

6

8

1 2 3 4 5 6

Forecast Day

AVG

BIA

S es<3K CLMes<3k MOSes<3k GFE

EASTSIDE Non-ISC AREA > 3k FT MIN_T AVG BIAS

-6

-4

-2

0

2

4

6

8

10

1 2 3 4 5 6

Forecast Day

AVG

BIA

S es>3K CLMes>3k MOSes>3k GFE

DOH workshop – June 2004

Non ISC (Model Only) MAE

EASTSIDE Non-ISC AREA > 3k FT MAX_T MAE

0

1

2

3

4

5

6

7

8

9

1 2 3 4 5 6

Forecast Day

MAE

es>3K CLMes>3k MOSes>3k GFE

EastSide Non-ISC Area < 3k ft MAX_T MAE

0

2

4

6

8

10

12

14

1 2 3 4 5 6

Forecast Day

MA

E

es<3K CLMes<3k MOSes<3k GFE

EASTSIDE Non-ISC AREA > 3k FT MIN_T MAE

0

1

2

3

4

5

6

7

8

9

1 2 3 4 5 6

Forecast Day

MAE

es>3K CLMes>3k MOSes>3k GFE

EastSide Non-ISC Area < 3k ft MIN_T MAE

0

1

2

3

4

5

6

7

8

1 2 3 4 5 6

Forecast Day

MA

E

es<3K CLMes<3k MOSes<3k GFE

DOH workshop – June 2004

Summary

Need for Standard Grid Initialization by WFOs

Need to Have Standard Grid Generation Methods

Need for the Grids to Represent Forecast

Need for Canadian Forecasts

Need for GFE Tools for RFC to Modify the ISC Mosaic Grid

Need for NWSRFS to Handle Finer Spatial and Temporal Forecast Data

DOH workshop – June 2004