Getting Good Compaction

51
307-213-0223 [email protected] © Mike Robinson, PE 307-213-0223 [email protected] © Mike Robinson, PE Getting Good Compaction California Asphalt Pavement Association – Sacramento, October 27, 2016

Transcript of Getting Good Compaction

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Getting Good Compaction

California Asphalt Pavement Association – Sacramento, October 27, 2016

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

First, some terminology…

Compaction is how hard you try

Density is what you may or may not get

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

And some history…

Method Spec

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Compaction relative to lab-compacted

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Compaction relative to theoretical max (Rice)

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Compaction Specifications

0

1

2

3

4

5

6

7

8

9

10

Mix Design Air Voids

% of Rice

100

99

98

97

96

95

94

93

92

91

90

% of Laboratory

100

99

98

97

96

95

94

% of Test Strip

100

99

98

97

0

1

2

3

4

5

6

7

8

9

10

In-Place Air Voids

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Why Worry?

NCAT Report 16-02

• Decreasing in-place air voids improves performance

• 1% decrease in air voids:– 8 - 44% improvement in

fatigue

– 7 - 66% improvement in rutting

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Why Worry?

NCAT Report 16-02

• 1% decrease in air voids can extend service life by 10% (conservatively)

• Increasing the required minimum density can save nearly 10% in net present value

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

All it takes is…

• The Right Mix

• On the Right Substrate

• Using the Right Equipment and the Right Methods

• Under the Right Conditions

(thanks (or apologies) to the pavement preservation folks)

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

The Right Mix

• Lift thickness AT LEAST three times the nominal maximum aggregate size

• Appropriate for the loading

– Balance rut resistance against durability and fatigue resistance

– Keep workability in mind

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

NOTE• You can change

– The aggregate requirements

– The grading

– The natural sand content

– The fracture content

– Voids in Mineral Aggregate

– The laboratory compaction effort

– The target air voids

– The binder type / grade

– The target field density

– Etcetera – one mix does not fit all

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Suitable support is required

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Uniform support is important

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Equipment

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Pneumatic Rollers

• Compact with shear

– Bottom up instead of top down

• Don’t bridge high spots like steel drums

• Have a tendency to introduce more variability into nuclear gauge results

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Don’t kid yourself

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

The right conditionsUse Multicool

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

The right methods

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

A few basics

The right tack at the right application rate

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

A few basics

Control the mix

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

A few basics

Keep the rollers close to the paver

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

A few basics

10-12 impacts per foot

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

A few basics

Monitor lab properties, temps, mix behavior

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Subgrade / Base / Bottom Lift

Compacted HMA

Paving the First Pass

Longitudinal Joints

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Paving the First Pass

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Subgrade / Base / Bottom Lift

Paving the Second Pass

Compacted HMA

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Subgrade / Base / Bottom Lift

Raking the Second Pass

Compacted HMA

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Subgrade / Base / Bottom Lift

Raking the Second Pass

Compacted HMA

Steel Drum Roller

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Photo courtesy of James Signore

Don’t rake the joint

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Roll from the hot side

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

The right specs

• Need to suit the project

• Need to define acceptance criteria

• Need to assess conformance

Be very careful when cutting and pasting or using blanket referrals to other agency specifications

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Need to test

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Quality Control

Keep deleterious materials out of the mix

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Employ qualified individuals

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Thin Overlays

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

• 1” overlay, 70 degrees, 15 mph wind, 300o

mix temp – less than 9 minutes to compact

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Higher paver speed

300 tph * 2,000 lb/ton / 60 min/hr / 145 pcf / 12’ wide / 1” deep = 70 feet per minute

Optimum paver speed for ride quality – 45 fpm?

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

10 – 12 impacts per foot

70 fpm * 5 passes * 12 impacts/ft / 90% efficiency = 4,700 vibrations per minute

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

ALL of the rolling has to be completed in less than 9 minutes

And remember…

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Greater influence of underlying layers for nuke gauges

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Thin cores can be difficult

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

And yet density is still critical

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Intelligent Compaction

Image courtesy of Sakai

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

But the mapping is very helpful

Image courtesy of Topcon

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

So how do we succeed?

• Forget the “one size fits all” mentality –

– Agencies / consultants / designers / producers / contractors

• Obtain knowledge and guidance if necessary

• Adjust to fit

– The project

– The conditions

• Evaluate and correct as necessary

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Put your sole into it

307-213-0223 [email protected] © Mike Robinson, PE307-213-0223 [email protected] © Mike Robinson, PE

Mike Robinson LLC

101 Upper Canyon Loop

Ten Sleep, WY 82442

307-213-0223

[email protected]