Geotechnical Engineering 07 Batch

115
Soil Mechanics Compaction

Transcript of Geotechnical Engineering 07 Batch

Page 1: Geotechnical Engineering 07 Batch

Soil Mechanics

Compaction

Page 2: Geotechnical Engineering 07 Batch

2

What is compaction?

A simple ground improvement technique, where the soil is densified through external compactive effort.

+ water =

Copactive effort

+ water =

Page 3: Geotechnical Engineering 07 Batch

3

2.1 Compaction and Objectives

•Compaction•Many types of earth construction, such as dams, retaining walls, highways,

and airport, require man-placed soil, or fill. To compact a soil, that is, to place it in a dense state.

•The dense state is achieved through the reduction of the air voids in the soil, with little or no reduction in the water content. This process must not be confused with consolidation, in which water is squeezed out under the action of a continuous static load.

•Objectives:(1) Decrease future settlements(2) Increase shear strength(3) Decrease permeability

(From Lambe, 1991; Head, 1992)

Page 4: Geotechnical Engineering 07 Batch

Compaction

Five factors affecting compaction1. Physical & chemical properties2. Moisture content3. Method of compaction4. Amount of compactive effort5. Thickness of layer or “lift” being

compacted

Page 5: Geotechnical Engineering 07 Batch

Soils are compacted for the following reasons:

1. To increase strength and stability2. To decrease permeability3. To enhance resistance to erosion4. Decrease compressibility under load and

minimize settlement

Page 6: Geotechnical Engineering 07 Batch

Results of Poor Compaction

Page 7: Geotechnical Engineering 07 Batch

Compaction

Methods of Compaction1. Static weight2. Impact3. Vibration4. Manipulation or kneading5. Percolation

Page 8: Geotechnical Engineering 07 Batch

8

General Compaction MethodsCoarse-grained soils Fine-grained soils

•Hand-operated vibration plates

•Motorized vibratory rollers

•Rubber-tired equipment

•Free-falling weight; dynamic compaction (low frequency vibration, 4~10 Hz)

•Falling weight and hammers

•Kneading compactors

•Static loading and press

•Hand-operated tampers

•Sheepsfoot rollers

•Rubber-tired rollers

Labo

rato

ryFi

eld

Vibration

•Vibrating hammer (BS)

(Holtz and Kovacs, 1981; Head, 1992)

Kneading

dough

Page 9: Geotechnical Engineering 07 Batch

9

3. Theory of Compaction(Laboratory Test)

Page 10: Geotechnical Engineering 07 Batch

10

Laboratory Compaction•Origin•The fundamentals of compaction of fine-grained soils are relatively new. R.R. Proctor in the early 1930’s was building dams for the old Bureau of Waterworks and Supply in Los Angeles, and he developed the principles of compaction in a series of articles in Engineering News-Record. In his honor, the standard laboratory compaction test which he developed is commonly called the proctor test.•Purpose•The purpose of a laboratory compaction test is to determine the proper amount of mixing water to use when compacting the soil in the field and the resulting degree of denseness which can be expected from compaction at this optimum water•Impact compaction•The proctor test is an impact compaction. A hammer is dropped several times on a soil sample in a mold. The mass of the hammer, height of drop, number of drops, number of layers of soil, and the volume of the mold are specified.

Page 11: Geotechnical Engineering 07 Batch

11

Various TypesVarious types of compaction test

1

2

3

1: your test 2: Standard Proctor test 3: Modified Proctor test

Page 12: Geotechnical Engineering 07 Batch
Page 13: Geotechnical Engineering 07 Batch

The Proctor Compaction Test

• Test developed to help specify levels of compaction (1933).

• Ralph R. Proctor first defined this standard compaction test in Engineering News Record

Page 14: Geotechnical Engineering 07 Batch

Equipment:

1. Proctor mould with a detachable collar assembly and base plate.2. Manual rammer weighing 2.5 kg and equipped to provide a height of drop to a free fall of 30 cm.3. Sample Extruder.4. A sensitive balance.5. Straight edge.6. Squeeze bottle7. Mixing tools such as mixing pan, spoon, trowel, spatula etc.8. Moisture cans.9. Drying Oven

Page 15: Geotechnical Engineering 07 Batch

15

Test EquipmentStandard Proctor test equipment

Das, 1998

Page 16: Geotechnical Engineering 07 Batch
Page 17: Geotechnical Engineering 07 Batch

Standard Proctor Compaction Test Summary

• Uses 5.5 pound hammer

• dropped 12 inches• mold filled in 3 lifts• 25 blows of hammer

per lift• Total energy is

12,400 ft-lbs/ft3

12”drop

3 lifts

5.5 # hammer

Page 18: Geotechnical Engineering 07 Batch

Modified Proctor Compaction Test Summary

• Uses 10 pound hammer

• dropped 12 inches• mold filled in 5 lifts• 25 blows of hammer

per lift• Total energy is

12,400 ft-lbs/ft3

18”drop

10 # hammer

5 lifts

Page 19: Geotechnical Engineering 07 Batch

Proctor Compaction Test Summary

• Several Standard molds are used depending on maximum particle size in sample– 4”diameter mold (1/30 ft3) used for soils

with low gravel contents– Method A for soils with < 20 % gravel– Method B for soils with > 20 % gravel and <

20 % larger than 3/8”

Page 20: Geotechnical Engineering 07 Batch

Proctor Compaction Test Summary

• Several Standard molds are used depending on maximum particle size in sample– 6”diameter mold (1/13.33 ft3) used for soils

with significant gravel contents – More than 20 % gravel larger than 3/8”– Must have less than 30 % larger than 3/4”

Page 21: Geotechnical Engineering 07 Batch

Proctor Compaction Test Summary

• Standardized tests are not available for soils with more than 30 percent by weight of the total sample being larger than 3/4”in diameter gravels

• ASTM Compaction Test Methods are – D698A D1557A– D698B D1557B – D698C D1557C

Page 22: Geotechnical Engineering 07 Batch

Proctor Compaction Test Summary

• Prepare 4 to 5 specimens at increasing water contents about 2 % apart. Example - prepared samples at 14, 16, 18, and 20 percent. Use range of moistures based on feel and experience.

Page 23: Geotechnical Engineering 07 Batch

Proctor Compaction Test Summary

• Then, compact each sample into a steel mold with standard procedures

Compaction mold

Cured soil

Hammer

Page 24: Geotechnical Engineering 07 Batch

Proctor Compaction Test Summary

• Then, strike off excess soil so the mold has a known volume of soil.

Page 25: Geotechnical Engineering 07 Batch

Proctor Compaction Test Summary

• For each sample, measure the weight and the water content of the soil in the mold

• The mold volume and weight are pre-measured. Don’t assume nominal volume of 1/30 ft3 or 1/13.33 ft3

• Calculate moist density• Calculate dry density• Plot dry density and water content for each point

Page 26: Geotechnical Engineering 07 Batch

Proctor Compaction Procedure

• Soil is air dried, pulverized & passed thru #4 sieve.

• Separated into 4 to 6 samples.

• Adjust the water content of each sample by adding water.

Page 27: Geotechnical Engineering 07 Batch

• Using the proctor mould (1/30th cubic foot) place & compact soil in 3 layers.

• Each layer should receive 25 drops of the compaction hammer.

Proctor Compaction Procedure

Page 28: Geotechnical Engineering 07 Batch

Proctor Compaction Procedure

• After the last layer, use a straight edge to trim the excess soil leveling to the top of the mould.

Page 29: Geotechnical Engineering 07 Batch

Proctor Compaction Procedure

• Determine the weight of the mould with the moist soil.

• Extrude from mould and collect a sample for water content determination.

• Repeat for each sample.

Page 30: Geotechnical Engineering 07 Batch

Proctor Compaction Procedure

• After collecting all pertinent weights, calculate dry density and plot vs. water content:

Page 31: Geotechnical Engineering 07 Batch

31

Comparison- Standard and Modified Proctor Compaction Test

Summary of Standard Proctor Compaction Test Specifications (ASTM D-698, AASHTO)

Das, 1998

Page 32: Geotechnical Engineering 07 Batch

32

Comparison- Standard and Modified Proctor Compaction Test (Cont.)

Summary of Modified Proctor Compaction Test Specifications (ASTM D-698, AASHTO)

Das, 1998

Page 33: Geotechnical Engineering 07 Batch

33

Comparison-SummaryStandard Proctor Test

12 in height of drop

5.5 lb hammer

25 blows/layer

3 layers

Mold size: 1/30 ft3

Energy 12,375 ft·lb/ft3

Modified Proctor Test

18 in height of drop

10 lb hammer

25 blows/layer

5 layers

Mold size: 1/30 ft3

Energy 56,250 ft·lb/ft3

Higher compacting energy

Page 34: Geotechnical Engineering 07 Batch

34

Comparison-Why?• In the early days of compaction, because construction equipment was

small and gave relatively low compaction densities, a laboratory method that used a small amount of compacting energy was required. As construction equipment and procedures were developed which gave higher densities, it became necessary to increase the amount of compacting energy in the laboratory test.

• The modified test was developed during World War II by the U.S. Army Corps of Engineering to better represent the compaction required for airfield to support heavy aircraft. The point is that increasing the compactive effort tends to increase the maximum dry density, as expected, but also decrease the optimum water content.

(Holtz and Kovacs, 1981; Lambe, 1991)

Page 35: Geotechnical Engineering 07 Batch

35

Variables of CompactionProctor established that compaction is a function of four variables:

(1)Dry density (d) or dry unit weight d.

(2)Water content w

(3)Compactive effort (energy E)

(4)Soil type (gradation, presence of clay minerals, etc.)

)ft/lbft375,12(m/kJ7.592

m10944.0

)layer/blows25)(layers3)(m3048.0)(s/m81.9(kg495.2E

33

33

2

Volume of mold

Number of blows per layer

Number of layers

Weight of hammer

Height of drop of hammer

E =

For standard Proctor test

Page 36: Geotechnical Engineering 07 Batch

36

Procedures and Results• Procedures(1) Several samples of the same soil, but at different water contents, are

compacted according to the compaction test specifications.

(2) The total or wet density and the actual water content of each compacted sample are measured.

(3) Plot the dry densities d versus water contents w for each compacted sample. The curve is called as a compaction curve.

w1,

V

Md

t

t

Derive d from the known

and w

The first four blows The successive blows

Page 37: Geotechnical Engineering 07 Batch

37

Procedures and Results (Cont.)Results

Zero air void

Water content w (%)

Dry

den

sity

d (M

g/m

3 )

Dry

den

sity

d (l

b/ft

3 )

Line of optimums

Modified Proctor

Standard Proctor

Peak point

Line of optimum

Zero air void

Holtz and Kovacs, 1981

d max

wopt

Page 38: Geotechnical Engineering 07 Batch

38

Procedures and Results (Cont.)•The peak point of the compaction curve•The peak point of the compaction curve is the point with the maximum dry density d max. Corresponding to the maximum dry density d max is a water content known as the optimum water content wopt (also known as the optimum moisture content, OMC). Note that the maximum dry density is only a maximum for a specific compactive effort and method of compaction. This does not necessarily reflect the maximum dry density that can be obtained in the field.

•Zero air voids curve•The curve represents the fully saturated condition (S = 100 %). (It cannot be reached by compaction)

•Line of optimums•A line drawn through the peak points of several compaction curves at different compactive efforts for the same soil will be almost parallel to a 100 % S curve, it is called the line of optimums

Page 39: Geotechnical Engineering 07 Batch

39

Procedures and Results (Cont.)

s

w

s

w

wd

GS

w

S

Sw

S

The Equation for the curves with different degree of saturation is :

s

sd

wGSee1

You can derive the equation by yourself

Hint:

Holtz and Kovacs, 1981

Page 40: Geotechnical Engineering 07 Batch

40

w

d

(wopt, d max)

Procedures and Results-Explanation

Below wopt (dry side of optimum):

As the water content increases, the particles develop larger and larger water films around them, which tend to “lubricate” the particles and make them easier to be moved about and reoriented into a denser configuration.

At wopt:

The density is at the maximum, and it does not increase any further.

Above wopt (wet side of optimum):

Water starts to replace soil particles in the mold, and since w << s the dry density starts to decrease.

Holtz and Kovacs, 1981

Lubrication or loss of suction??

Page 41: Geotechnical Engineering 07 Batch

41

Procedures and Results-Notes• Each data point on the curve represents a single compaction

test, and usually four or five individual compaction tests are required to completely determine the compaction curve.

• At least two specimens wet and two specimens dry of optimum, and water contents varying by about 2%.

• Optimum water content is typically slightly less than the plastic limit (ASTM suggestion).

• Typical values of maximum dry density are around 1.6 to 2.0 Mg/m3 with the maximum range from about 1.3 to 2.4 Mg/m3. Typical optimum water contents are between 10% and 20%, with an outside maximum range of about 5% to 40%.

Holtz and Kovacs, 1981

Page 42: Geotechnical Engineering 07 Batch

Compaction Maximum Dry Density

Page 43: Geotechnical Engineering 07 Batch

ENCI 579 43

Compaction Maximum Dry Density

Table 3-1MAXIMU DRY DENSITY AND OPTIMUM MOISTURE

CONTENT (TYPICAL)AASHTO

ClassificationMaximum DryDensity (kg/m3)

Optimum MoistureContent (%)

A – 1 Granular 1850-220 7-15A – 2 Sands 1750-2150 9-18A – 3 1750-1850 10-18A – 4 Silts 1500-2100 10-20A – 5 1400-1650 15-30A – 6 Clays 1500-1900 10-25A – 7 1400-1850 15-30

1400-

Page 44: Geotechnical Engineering 07 Batch

44

Effects of Soil Types on Compaction•The soil type-that is, grain-size distribution, shape of the soil grains, specific gravity of soil solids, and amount and type of clay minerals present.

Holtz and Kovacs, 1981; Das, 1998

Page 45: Geotechnical Engineering 07 Batch

45

Field and Laboratory Compaction

• It is difficult to choose a laboratory test that reproduces a given field compaction procedure.

•The laboratory curves generally yield a somewhat lower optimum water content than the actual field optimum.

•The majority of field compaction is controlled by the dynamic laboratory tests. Curve 1, 2,3,4: laboratory compaction

Curve 5, 6: Field compaction

(From Lambe and Whitman, 1979)

Page 46: Geotechnical Engineering 07 Batch

46

Properties and Structure of Compacted Fine-grained Soils

Page 47: Geotechnical Engineering 07 Batch

47

Structure of Compacted Clays

•For a given compactive effort and dry density, the soil tends to be more flocculated (random) for compaction on the dry side as compared on the wet side.

•For a given molding water content, increasing the compactive effort tends to disperse (parallel, oriented) the soil, especially on the dry side.

Lambe and Whitman, 1979

Page 48: Geotechnical Engineering 07 Batch

48

Engineering Properties-Permeability

• Increasing the water content results in a decrease in permeability on the dry side of the optimum moisture content and a slight increase in permeability on the wet side of optimum.

• Increasing the compactive effort reduces the permeability since it both increases the dry density, thereby reducing the voids available for flow, and increases the orientation of particles.

From Lambe and Whitman, 1979; Holtz and Kovacs, 1981

Page 49: Geotechnical Engineering 07 Batch

49

Engineering Properties-Compressibility

At low stresses the sample compacted on the wet side is more compressible than the one compacted on the dry side.

From Lambe and Whitman, 1979; Holtz and Kovacs, 1981

Page 50: Geotechnical Engineering 07 Batch

50

Engineering Properties-Swelling • Swelling of compacted clays is greater for those compacted dry

of optimum. They have a relatively greater deficiency of water and therefore have a greater tendency to adsorb water and thus swell more.

w

d

(wopt, d max)Higher swelling potential

From Holtz and Kovacs, 1981

Higher shrinkage potential

Page 51: Geotechnical Engineering 07 Batch

51

Engineering Properties-StrengthSamples (Kaolinite) compacted dry of optimum tend to be more rigid and stronger than samples compacted wet of optimum

From Lambe and Whitman, 1979

Page 52: Geotechnical Engineering 07 Batch

52

Engineering Properties-Strength (Cont.)

The CBR (California bearing ratio)

CBR= the ratio between resistance required to penetrate a 3-in2 piston into the compacted specimen and resistance required to penetrate the same depth into a standard sample of crushed stone.

Holtz and Kovacs, 1981

A greater compactive effort produces a greater CBR for the dry of optimum. However, the CBR is actually less for the wet of optimum for the higher compaction energies (overcompaction).

Page 53: Geotechnical Engineering 07 Batch

53

Engineering Properties-SummaryDry side Wet side

Permeability

Compressibility

Swelling

Strength

Structure More random More oriented (parallel)

More permeable

More compressible in high pressure range

More compressible in low pressure range

Swell more, higher water deficiency

Higher

Please see Table 5-1

*Shrink more

Page 54: Geotechnical Engineering 07 Batch

54

Engineering Properties-Summary (Cont.)

Please find this table in the handout

Holtz and Kovacs, 1981

Page 55: Geotechnical Engineering 07 Batch

55

Engineering Properties-Notes• Engineers must consider not only the behavior of the soil as compacted

but the behavior of the soil in the completed structure, especially at the time when the stability or deformation of the structure is most critical.

• For example, consider an element of compacted soil in a dam core. As the height of the dam increases, the total stresses on the soil element increase. When the dam is performing its intended function of retaining water, the percent saturation of the compacted soil element is increased by the permeating water. Thus the engineer designing the earth dam must consider not only the strength and compressibility of the soil element as compacted, but also its properties after is has been subjected to increased total stresses and saturated by permeating water.

Lambe and Whitman, 1979

Page 56: Geotechnical Engineering 07 Batch

Achieving Maximum Compaction In The Field

• By using the Proctor Compaction Test, we an determine the optimum water content for a soil.

• It is difficult for a contractor in the field to get the soil water content right on the optimum.

• Therefore, a range is usually specified by the engineer.

• A typical range is 3% below and 2% above optimum.

• For example, if optimum water content is 16%, the acceptable range would be from 13% to 18%.

• % Compaction = ρdry field /ρdry max

Page 57: Geotechnical Engineering 07 Batch

Lab Proctor Data Looks Like This

Page 58: Geotechnical Engineering 07 Batch

How Does A Contractor Modify Compaction in the Field?

• Adjust Water Content • More Passes • Thinner Lifts • Bigger Rollers • Right Compactor For The Soil Type

Page 59: Geotechnical Engineering 07 Batch

59

5.2.1 Frequency

Holtz and Kovacs, 1981

The frequency at which a maximum density is achieved is called the optimum frequency.

Page 60: Geotechnical Engineering 07 Batch

60

5.2.2 Roller Travel SpeedFor a given number of passes, a higher density is obtained if the vibrator is towed more slowly.

Holtz and Kovacs, 1981

Page 61: Geotechnical Engineering 07 Batch

61

5.2.3 Roller Passes

Holtz and Kovacs, 1981

When compacting past five or so coverages, there is not a great increase in density

•240 cm think layer of northern Indiana dune sand

•5670 kg roller operating at a frequency of 27.5 Hz.

Page 62: Geotechnical Engineering 07 Batch

62

5.2.4 Determine the Lift Height

Holtz and Kovacs, 1981

Page 63: Geotechnical Engineering 07 Batch

FIELD COMPACTION

Page 64: Geotechnical Engineering 07 Batch

Compaction

Page 65: Geotechnical Engineering 07 Batch

Compaction

Compaction in the field depends on several factors, such as:-

a) Type of compactorb) Soil typec) Moisture contentd) Lift Thickness e) Towing speed of the compactorf) The number of the roller passes

Page 66: Geotechnical Engineering 07 Batch

Field Compaction

• Ordinary compaction in the fields is done by rollers.

• Of the several types of roller used, the most common are:-

a) Smooth wheel rollb) Pneumatic rubber-tired rollersc) Sheepsfoot rollersd) Vibratory rollers

Page 67: Geotechnical Engineering 07 Batch

Field Compaction

Page 68: Geotechnical Engineering 07 Batch

Field Compaction

Page 69: Geotechnical Engineering 07 Batch

Field Compaction

Page 70: Geotechnical Engineering 07 Batch

Smooth Wheel Roller

• Can create vertical vibration during compaction.• Suitable for proof-rolling subgrades and for finishing

the construction of fills with sandy or clayey soils.• Provide 100% coverage under the wheels, and the

contact pressure can be as high as 300-400kN/m2.• However, they do not produce uniform unit weight

of compaction when used on thick layers.

Page 71: Geotechnical Engineering 07 Batch

Smooth Wheel Roller

Page 72: Geotechnical Engineering 07 Batch

Smooth Wheel Roller

Page 73: Geotechnical Engineering 07 Batch

Smooth Wheel Roller

Page 74: Geotechnical Engineering 07 Batch

Smooth Wheel Roller

Page 75: Geotechnical Engineering 07 Batch

Smooth Wheel Roller

Page 76: Geotechnical Engineering 07 Batch

Pneumatic Rubber-Tired Rollers

• Better in many respects than smooth wheel rollers.• May weight as much as 2000 kN, consist of a heavily loaded

wagon with several rows of tires.• These tires are closely spaced – four to six in a row.• The contact pressure under the tires may range up to 600-

700kN/m2, and they produce about 70-80% coverage.• Can be used for sandy and clayey soil compaction, produce

a combination of pressure and kneading action.

Page 77: Geotechnical Engineering 07 Batch

Hamm® Model GRW 18 Rubber Tired (Pneumatic) Roller

Page 78: Geotechnical Engineering 07 Batch

Pneumatic Rubber-Tired Rollers

Page 79: Geotechnical Engineering 07 Batch

Sheepsfoot Rollers

• Consist basically of drums with large numbers of projections.

• The area of each of the projections may be 25-90 cm2.• Most effective in compacting cohesive soils.• The contact pressure under the projections may range

from 1500-7500 kN/m2.• During compaction in the field, the initial passes compact

the lower portion of a lift.• Later, the middle and top of the lift are compacted.

Page 80: Geotechnical Engineering 07 Batch

Sheepsfoot Rollers

Page 81: Geotechnical Engineering 07 Batch

Vibratory Rollers

• Efficient in compacting granular soils.• Vibrators can be attached to smooth wheel,

pneumatic rubber-tired, or sheepsfoot rollers to send vibrations into the soil being compacted.

Page 82: Geotechnical Engineering 07 Batch

82

6. Field Compaction Control and Specifications

Page 83: Geotechnical Engineering 07 Batch

83

6.1 Control Parameters• Dry density and water content correlate well with the

engineering properties, and thus they are convenient construction control parameters.

• Since the objective of compaction is to stabilize soils and improve their engineering behavior, it is important to keep in mind the desired engineering properties of the fill, not just its dry density and water content. This point is often lost in the earthwork construction control.

From Holtz and Kovacs, 1981

Page 84: Geotechnical Engineering 07 Batch

84

6.2 Design-Construct Procedures• Laboratory tests are conducted on samples of the proposed

borrow materials to define the properties required for design.• After the earth structure is designed, the compaction

specifications are written. Field compaction control tests are specified, and the results of these become the standard for controlling the project.

From Holtz and Kovacs, 1981

Page 85: Geotechnical Engineering 07 Batch

85

6.3 Specifications

(1) End-product specifications•This specification is used for most highways and building foundation, as long as the contractor is able to obtain the specified relative compaction , how he obtains it doesn’t matter, nor does the equipment he uses.•Care the results only !•(2) Method specifications•The type and weight of roller, the number of passes of that roller, as well as the lift thickness are specified. A maximum allowable size of material may also be specified.•It is typically used for large compaction project.

From Holtz and Kovacs, 1981

Page 86: Geotechnical Engineering 07 Batch

86

6.4 Relative Compaction (R.C.)

%100.C.Rlaboratorymaxd

filedd

rD2.080.C.R

Relative compaction or percent compaction

Correlation between relative compaction (R.C.) and the relative density Dr

It is a statistical result based on 47 soil samples.

As Dr = 0, R.C. is 80

Typical required R.C. = 90% ~ 95%

Page 87: Geotechnical Engineering 07 Batch

87

6.5 Determine the Water Content (in Field)

Control

(1) Relative compaction

(2) Water content (dry side or wet side)

Holtz and Kovacs, 1981

Note: the engineering properties may be different between the compacted sample at the dry side and at the wet side.

100% saturation

Water content w %

wopt

Dry

den

sity

, d

d max

Line of optimums

90% R.C.

a c

Increase compaction energy

b

Page 88: Geotechnical Engineering 07 Batch

88

6.6 Determine the Relative Compaction in the Field

• Where and When• First, the test site is selected. It should be representative or typical of

the compacted lift and borrow material. Typical specifications call for a new field test for every 1000 to 3000 m2 or so, or when the borrow material changes significantly. It is also advisable to make the field test at least one or maybe two compacted lifts below the already compacted ground surface, especially when sheepsfoot rollers are used or in granular soils.

• Method• Field control tests, measuring the dry density and water content in the

field can either be destructive or nondestructive.

Holtz and Kovacs, 1981

Page 89: Geotechnical Engineering 07 Batch
Page 90: Geotechnical Engineering 07 Batch

90

6.6.1 Destructive Methods

Holtz and Kovacs, 1981

Methods

(a) Sand cone(b) Balloon(c) Oil (or water) method

Calculations•Know Ms and Vt

•Get d field and w (water content)•Compare d field with d max-lab and calculate relative compaction R.C.

(a)

(b)

(c)

Page 91: Geotechnical Engineering 07 Batch

91

6.6.1 Destructive Methods (Cont.)

•Sometimes, the laboratory maximum density may not be known exactly. It is not uncommon, especially in highway construction, for a series of laboratory compaction tests to be conducted on “representative” samples of the borrow materials for the highway. If the soils at the site are highly varied, there will be no laboratory results to be compared with. It is time consuming and expensive to conduct a new compaction curve. The alternative is to implement a field check point, or 1 point Proctor test.

Holtz and Kovacs, 1981

Page 92: Geotechnical Engineering 07 Batch

92

6.6.1 Destructive Methods (Cont.)

Check Point Method

Water content w %

wopt

Dry

den

sity

, d

d max

100% saturationLine of optimums

A

B

M

C

X

Y(no)

•1 point Proctor test

•Known compaction curves A, B, C

•Field check point X (it should be on the dry side of optimum)

Holtz and Kovacs, 1981

Page 93: Geotechnical Engineering 07 Batch

93

6.6.1 Destructive Methods (Cont.)• The measuring error is mainly from the determination of

the volume of the excavated material.

• For example,• For the sand cone method, the vibration from nearby working

equipment will increase the density of the sand in the hole, which will gives a larger hole volume and a lower field density.

• If the compacted fill is gravel or contains large gravel particles. Any kind of unevenness in the walls of the hole causes a significant error in the balloon method.

• If the soil is coarse sand or gravel, none of the liquid methods works well, unless the hole is very large and a polyethylene sheet is used to contain the water or oil.

tsfieldd V/M

Holtz and Kovacs, 1981

Page 94: Geotechnical Engineering 07 Batch

94

6.6.2 Nondestructive Methods (Cont.)

•Calibration•Calibration against compacted materials of known density is necessary, and for instruments operating on the surface the presence of an uncontrolled air gap can significantly affect the measurements.

Page 95: Geotechnical Engineering 07 Batch

ENCI 579 95

Compaction Field Density Tests

• Balloon densometer– Dry mass of the soil is determined– Volume of the sample hole is found by forcing a

liquid filled balloon into the test hole– A rubber membrane allows the fluid to fill all

the cavities of the hole– The volume of fluid required is measured– density calculated– water content determined

Page 96: Geotechnical Engineering 07 Batch

Equipment• Sand cone apparatus which consists of a one- gallon plastic bottle with a metal cone attached to it.• One-Gallon plastic can with cap.• Balance sensitive to 1 g.• Base plate• Tools for excavating a hole in the ground• Clean, uniformly graded sand ranging from #20 to #30 sieve such as Ottawa Sand• Proctor compaction mold without attached extension (used for calibration)• Plastic air-tight bag for carrying wet excavated soil from field to the lab.• Metal tray with a hole in the centre.• Oven with temperature kept at about 105-110o

Page 97: Geotechnical Engineering 07 Batch

Test procedure

• 1- Measure the weight of Proctor mold + Base, W1 (Go to row 1 of table)

2- Fig. (a). Pour the sand into the compaction moldFig. (b). Level the surface (Do not disturb the mold as the sand may rearrange and get compacted)Fig. (c). Compaction mold filled with sandFig. (d). Measure the weight of proctor mold+ base + Sand, W2 (Go to row 2 of table)

Page 98: Geotechnical Engineering 07 Batch

3- Measure the weight of plastic Gallon+Cone+Sand, W3 (before use) (Go to row 5 of table)

Page 99: Geotechnical Engineering 07 Batch

• 4- (a). Close the valve attached to the cone (b). Turn the cone and gallon upside down on the tray (c). Open the valve, sand flows from the gallon

to the cone, after the flow stops close the valve and take the gallon+cone from the

tray (d). Measure the weight of plastic Gallon+Cone+Sand, W4 (after use) (Go to row 6 of table)

Page 100: Geotechnical Engineering 07 Batch

5- Weight of plastic Gallon+Cone+Sand, W5 (before use) (Go to row 8 of table)

Page 101: Geotechnical Engineering 07 Batch

• 6- Go to the field where the soil's unit weight is to be measured, place the metal tray and

fasten the 4• 7- Dig up a 10 to 15 cm deep hole.• 8- As you are digging the hole put the retrieved

soil into the plastic bag in order that the soil does not lose moisture. All of the soil

including the soft soil at the bottom of the hole is poured into the bag as well. screws.

Page 102: Geotechnical Engineering 07 Batch

• 9- Having the valve closed turn the gallon+cone upside down and place the cone in the center hole of tray and open the valve so that sand flows down to the hole.

• 10- After flow of sand stops close the valve and pick the assembly up, the sand in the cone will be poured into the tray. This sand will be left there in the field. (Notice, Unlike this picture, the plastic bag should be kept closed while transferring to the lab to avoid moisture loss and consequently weight of the soil)

Page 103: Geotechnical Engineering 07 Batch

11- Measure the weight of plastic Gallon+Cone+Sand, W6 (after use) (Go to row 9 of table)

Page 104: Geotechnical Engineering 07 Batch

• 12- Measure the weigh the evaporating dish, W7 (Go to row 11 of table)

Page 105: Geotechnical Engineering 07 Batch

• 13- Measure the weigh the evaporating dish + wet soil from the field, W8 (Go to row 12 of table

Page 106: Geotechnical Engineering 07 Batch

• 14- Put the evaporating dish + wet soil in the oven and after 24hrs weigh it again, W9 (Go to row 13 of table).

• In the sample test wedid for you W9turned out to be2.251 Kg.

Page 107: Geotechnical Engineering 07 Batch

• 15- Having the information you got so far in the table, Calculations can be carried out easily. Do the calculations, fill out the table and include the answers to the following questions in your reports.

Page 108: Geotechnical Engineering 07 Batch
Page 109: Geotechnical Engineering 07 Batch
Page 110: Geotechnical Engineering 07 Batch
Page 111: Geotechnical Engineering 07 Batch

111

Nondestructive Methods

Holtz and Kovacs, 1981

Nuclear density meter(a) Direct transmission(b) Backscatter(c) Air gap

(a)

(b)

(c)

PrinciplesDensityThe Gamma radiation is scattered by the soil particles and the amount of scatter is proportional to the total density of the material. The Gamma radiation is typically provided by the radium or a radioactive isotope of cesium.

Water contentThe water content can be determined based on the neutron scatter by hydrogen atoms. Typical neutron sources are americium-beryllium isotopes.

Page 112: Geotechnical Engineering 07 Batch

ENCI 579 112

Compaction Field Density Tests

Page 113: Geotechnical Engineering 07 Batch

• Sand Cone Test

• Nuclear Densometer

How Do We Determine Actual Field Density?

Page 114: Geotechnical Engineering 07 Batch

ENCI 579 114

Compaction Field Density Tests

• Nuclear Moisture-Density Gauge– Results are available within minutes

• Increases equipment efficiency• Know that your construction methods are correct

– Gamma rays are emitted into the soil• absorbed by the soil according to it’s density• rays that pass through the soil are measured by a

detector• density is then calculated

Page 115: Geotechnical Engineering 07 Batch

ENCI 579 115

Compaction Field Density Tests

• Nuclear Moisture-Density Gauge– Neutron radiation emitted into the soil

• neutrons loose energy when they collide with hydrogen atoms in the soil water

• detector measures the amount of moderated neutrons

• water content can be calculated

– Direct transmission mode– Backscatter mode