Geo Technical Exploration Report

download Geo Technical Exploration Report

of 17

Transcript of Geo Technical Exploration Report

  • 8/23/2019 Geo Technical Exploration Report

    1/17

    THIELE GEOTECH, INC.13478 Chandler Road

    Omaha , Nebraska 68138-3716

    402.556.2171 Fax 402.556.7831

    www.thielegeotech.com

    G EO TEC H N I C A L M A TERI A L EN V I R O N M EN TA L EN G I N E ERI N G

    Geotechnical Exploration Report

    Pump Station

    Railroad Street and Herbert StreetBeatrice, Nebraska

    Prepared for:WLA Consulting, Inc.1640 L Street, Suite DLincoln, Nebraska 68508

    March 9, 2010

    TG Project No. 10026.00

  • 8/23/2019 Geo Technical Exploration Report

    2/17

    T h i e l e G e o t e c h I n c

    Geotechnical Exploration Report

    Pump Station

    Table of Contents

    INTRODUCTION ................................................................................................................................................. 1PROJ ECT DESCRIPTION .................................................................................................................................. 2SURFACE AND SUBSURFACE CONDITIONS ............................................................................................... 3

    SITE CONDITIONS ............................................................................................................................................................ 3LOCAL GEOLOGY ............................................................................................................................................................ 3SOIL CONDITIONS ........................................................................................................................................................... 3GROUND WATER OBSERVATIONS .............................................................................................................................. 4

    ANALYSIS AND RECOMMENDATIONS ........................................................................................................ 5GENERAL ........................................................................................................................................................................... 5EXCAVATION DEWATERING ........................................................................................................................................ 5SHORING ............................................................................................................................................................................ 5PUMP STATION ................................................................................................................................................................. 6EARTHWORK AND EXCAVATIONS ............................................................................................................................. 7OTHER RECOMMENDATIONS ....................................................................................................................................... 7

    APPENDIX

  • 8/23/2019 Geo Technical Exploration Report

    3/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 1

    T h i e l e G e o t e c h I n c

    INTRODUCTION

    Thiele Geotech, Inc. has completed a geotechnical exploration study for the proposed pump station to

    be located near Railroad Street and Herbert Street in Beatrice, Nebraska. The purpose of this study

    was to identify the general soil and ground water conditions underlying the site, to evaluate

    engineering properties of the existing soils, to provide earthwork and site preparation

    recommendations, and to recommend design criteria and parameters for foundations and other earth

    supported improvements.

    This study included soil borings, laboratory testing, and engineering analysis. One test boring was

    drilled at the location of the new pump station. The field and laboratory data are presented in the

    Appendix, along with a description of investigative methods.

    The drilling and testing performed for this study were conducted solely for geotechnical analysis. No

    analytical testing or environmental assessment has been conducted. Any statements or observations in

    this report regarding odors, discoloration, or suspicious conditions are strictly for the information of

    our client. If an evaluation of environmental conditions is desired, a separate environmental

    assessment should be conducted. This study did not include biological assessment (e.g. mold, fungi,

    bacteria) or evaluation of measures for their control.

    It should also be noted that this report was prepared for design purposes only, and may not be

    sufficient for a contractor in bid preparation. Prospective contractors should evaluate potential

    construction problems on the basis of their own knowledge and experience in the local area and on

    similar projects, taking into account their own intended construction methods and procedures.

    This report is an instrument of service prepared for use by our client on this specific project. The

    report may be duplicated as necessary and distributed to those directly associated with this project,

    including members of the design team and prospective contractors. However, the technical approach

    and report format shall be considered proprietary and confidential, and this report may not be

    distributed in whole or in part to any third party not directly associated with this project. By using and

    relying on this report, all other parties agree to the same terms, conditions, and limitations to which the

    client has agreed.

  • 8/23/2019 Geo Technical Exploration Report

    4/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 2

    T h i e l e G e o t e c h I n c

    PROJECT DESCRIPTION

    The project consists of a 28-foot deep wet well for a new pump station. We assume that the structure

    will consist of reinforced concrete floors, walls, and top. The new pump station will be located

    adjacent to an existing pump station near the intersection of Railroad Street and Herbert Street in

    Beatrice, Nebraska. The site is located on the north bank of Indian Creek on the east side of Railroad

    Street.

  • 8/23/2019 Geo Technical Exploration Report

    5/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 3

    T h i e l e G e o t e c h I n c

    SURFACE AND SUBSURFACE CONDITIONS

    SITE CONDITIONS

    The project site is located north of Railroad Street and east of Herbert Street, immediately north ofIndian Creek in Beatrice, Nebraska. The pump station site is built up by several feet. The site is in an

    open area which is grass and tree covered.

    LOCAL GEOLOGY

    The surface geology of eastern Nebraska is Pleistocene in age and consists of eolian (wind-blown)

    deposits of Peoria and Loveland loess. The loess formed in dune-shaped hills west of the Missouri

    River. The Peoria loess typically consists of silty lean clays that are stiff when dry but become softer

    with increasing moisture content. The Peoria often exhibits low unit weight and is collapse

    susceptible. The Loveland loess is an older deposit, and typically consists of lean clays. TheLoveland generally exhibits higher unit weights and shear strengths than the Peoria.

    The loess overlies Pleistocene glacial deposits of Kansan and Nebraskan till. The till consists of lean

    to fat clays mixed with sand, gravel, and occasional cobbles. The glacial deposits are generally fairly

    deep, but are sometimes near the surface at lower elevations on steep slopes. Cretaceous sandstone or

    Pennsylvanian limestone and shale form the bedrock unit below the glacial deposits. The depth to

    bedrock is normally great, and rock is rarely encountered in construction.

    Along drainageways, alluvial and colluvial deposits are typically present. These soils were formed by

    erosion of the adjoining loess-mantled hills. Alluvial deposits are generally present along creeks andin major drainageways. The upper several feet of alluvium are usually stiffer due to the effects of

    desiccation. Colluvial soils are usually located at the base of steep slopes and in upland draws, and are

    formed by local creep and sloughing.

    SOIL CONDITIONS

    The soils encountered in the test borings generally consisted of man-placed fill over alluvium.

    Man-placed fill was encountered in the upper 7 feet of the boring. It was described as dark gray,

    moist, hard lean clay. Based on an assumed Standard Proctor the fill had compaction levels of roughly

    100 percent.

    Alluvium was encountered below the fill, and extended to a 28 foot depth. It was described as light

    brown to reddish brown, slightly moist to wet, loose, poorly-graded sand.

    Shale and limestone rock was encountered at 28 feet below grade. It was described as light brown,

    wet, and very hard in consistency. Drilling refusal was encountered at 30 feet, where a Standard

    Penetration Test blow count of 50 for 2 inches of penetration was recorded.

  • 8/23/2019 Geo Technical Exploration Report

    6/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 4

    T h i e l e G e o t e c h I n c

    Ranges of engineering properties from laboratory tests on selected samples are presented in Table 1.

    Table 1 - Laboratory Results

    Soil Layer

    Moisture

    Content (%)

    Dry Unit

    Weight (pcf)

    Unconfin

    edCompressive

    Strength(tsf)

    Classification (LL/PI)

    Man-placed fill 17 to 18 103 to 111 2.3 CL (36/20)

    Alluvium 2 to 15 -- -- SP (P-200=4.3%)

    GROUND WATER OBSERVATIONS

    Ground water levels were observed in the borings as presented in Table 2. Note that ground water

    levels may fluctuate due to seasonal variations and other factors.

    Table 2 - Water Level Observations

    Boring

    Number

    Water Level (ft. below grade)

    During Drilling End of Drilling

    B-1 15.0 15.0

  • 8/23/2019 Geo Technical Exploration Report

    7/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 5

    T h i e l e G e o t e c h I n c

    ANALYSIS AND RECOMMENDATIONS

    GENERAL

    The soils encountered in the test boring were variable with depth. Soil in the upper 7 feet consistedof lean clay which was hard in consistency. Below the lean clay fill, alluvial poorly-graded sand was

    encountered to a 28 foot depth. Shale and limestone rock was found at 28 feet. The rock was very

    hard at 30 feet. Excavation into the rock will likely require pneumatic or hydraulic rock breakers.

    Ground water was fairly shallow in the boring, and dewatering will be a major consideration in

    making the excavation to construct the pump station.

    EXCAVATION DEWATERING

    Ground water was present at roughly 15 feet below existing grade. The proposed excavations extend

    below the water table and will require dewatering to facilitate construction.

    Soils encountered below the water table consist predominantly of poorly-graded sand. Since the soils

    beneath the water table are mainly sand, we expect seepage rates to be high. Sump pumps will not be

    sufficient to control the inflow of water into excavations. A well point or deep well system will be

    necessary to adequately dewater the excavations. We expect that multiple dewatering points will be

    necessary around the excavation to maintain a stable bottom condition.

    SHORING

    OSHAs Construction Standards for Excavations require that the contractors excavation activitiesfollow certain worker safety procedures. These include a requirement that excavations over 4 feet

    deep be sloped back, shored, or shielded. The soils encountered in the test borings generally classify

    as type B and C soils according to the OSHA standard. The maximum allowable slope for an

    unbraced excavation in these soils is 1H:1V and 1.5H:1V, respectively, although other provisions and

    restrictions apply. Excavations over 20 feet deep require specific design by a licensed Professional

    Engineer. The contractor is solely responsible for site/excavation safety and compliance with OSHA

    regulations. The geotechnical engineer assumes no responsibility for site safety, and the above

    information is provided only for consideration by the designers.

    For braced excavation design, we recommend using a cohesion of 1,000 psf where clay is

    encountered, and a friction angle of 30 degrees where sand is present. A soil unit weight of 120 pcf is

    recommended above the water table, and buoyant unit weight of 65 pcf is recommended below the

    water table. Dewatering will have a significant impact on shoring loads. The shoring design should

    carefully consider water levels, hydrostatic loads, and dewatering requirements.

  • 8/23/2019 Geo Technical Exploration Report

    8/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 6

    T h i e l e G e o t e c h I n c

    PUMP STATION

    The structure is planned for a 28-foot depth, which puts it very close to the rock layer at 28 to 30

    feet. We recommend extending the foundation to bear on the hard rock at roughly 30 feet below grade

    instead of bearing on a thin layer of sand at 28 feet. The following paragraphs include discussion

    about bearing on sand in case the structure becomes shallower than originally planned.

    The allowable bearing pressure for a buried structure would be the gross bearing pressure, which is the

    net allowable bearing pressure derived from the shear strength of the soil plus the surrounding

    overburden pressure. During construction, the net allowable bearing pressure controls before the

    structure is backfilled. Thus, we recommend that both the construction case and long-term case be

    considered in sizing the mat foundation for the structure.

    The net allowable bearing pressure for the saturated sand would be approximately 1,000 psf. The

    overburden pressure at a depth of 28 feet would be approximately 1,820 psf, based on a soil unit

    weight of 65 pcf and assuming the water table at the ground surface. Thus, the gross allowablebearing pressure for the lift station bearing on sand would be approximately 2,820 psf. A conservative

    net allowable bearing pressure for the hard rock would be approximately 5,000 psf. The overburden

    pressure at a depth of 30 feet would be approximately 1,950 psf, based on a soil unit weight of 65 pcf

    and assuming the water table at the ground surface. Thus, the gross allowable bearing pressure for the

    lift station bearing on rock would be approximately 6,950 psf. The actual contact pressure should be

    calculated by dividing the maximum operating weight of the lift station structure across the outside

    diameter of the lift station walls. Any footing projection outside of the walls should be neglected in

    the gross bearing calculation due to the balancing overburden pressure above this section of the

    foundation. For structural design of the base, this contact pressure should be uniformly distributedacross the interior slab as a conservative practice. The same contact pressure should be separately

    applied to the footing projection as a cantilever. In addition, the footing projection should be designed

    to support the full weight of the overlying soil acting downward to resist buoyant effects.

    Since the net contact pressure for the completed/backfilled structure is actually negative, resulting in a

    reduction in the effective stress below the structure, there should be minimal settlement due to

    compression of the underlying soil. Actual settlement will be a function of the installation process, but

    should be minor (less than 1 inch if supported on sand, and negligible if supported on rock) if the

    contractor can maintain a stable excavation. If the bottom of the excavation ends in sand, we

    recommend placing a layer of crushed rock below the base to provide a stable work platform. This

    layer should be 12 inches thick, consisting of a 6-inch thick layer of 3-inch stabilization rock and a 6-

    inch thick layer of pipe bedding material. A lean concrete mix may be placed as a mud slab in lieu of

    the bedding layer for construction convenience.

    For uplift design, we recommend that the design ground water level be taken at the ground surface.

    The uplift resistance should be calculated as the minimum operating weight of the lift station structure

    plus the effective weight of the soil mass above the footing projection outside of the barrel section.

  • 8/23/2019 Geo Technical Exploration Report

    9/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 7

    T h i e l e G e o t e c h I n c

    An effective unit weight of 65 pcf should be used for the backfill soil above the footing projection.

    The hydrostatic pressure and resisting loads should also be applied across the bottom of the structure

    to check the structural capacity of the base slab under this loading condition.

    For evaluating lateral pressures on the barrel section, we also recommend using the design ground

    water level at the ground surface. Lateral loads on the walls should be calculated at 30 pcf (equivalent

    fluid) for the effective soil pressure (at rest condition) plus full hydrostatic pressure.

    EARTHWORK AND EXCAVATIONS

    The excavated site soils will generally be suitable for reuse as structural fill, although significant

    moisture conditioning may be required. Any off-site borrow should be a clean, inorganic silt or lean

    clay with a liquid limit less than 45 and a plasticity index less than 20, or poorly-graded sand similar to

    the on-site soil. Borrow material should not contain an appreciable amount of roots, rock, or debris,

    and should not contain any foreign material with a dimension greater than 3 inches.

    All fills and backfill around the structure should be placed and compacted as structural fill. Fill should

    be placed in thin lifts not to exceed 8 inches loose thickness. Structural fill should be compacted with

    a sheepsfoot type roller to a minimum of 95 percent of the maximum dry density (ASTM D698,

    Standard Proctor). Moisture content should be controlled to between -3 and +4 percent of optimum.

    Quality control testing is an important part of any earthwork operation. It is recommended that a

    representative of the geotechnical engineer periodically monitor earthwork operations to verify proper

    compliance with these recommendations, including compaction levels.

    OTHER RECOMMENDATIONS

    During detailed design, additional issues may arise and possible conflicts may occur with our

    recommendations. Such issues and conflicts should be resolved through dialogue between the

    geotechnical engineer and designers. It is recommended that the geotechnical engineer review the

    final design, including the plans and specifications, to verify that our recommendations are properly

    interpreted and incorporated into the design.

    If any changes are made in the design of the project, including the nature or location of proposed

    facilities on the site or significant elevation changes, the analysis and recommendations of this report

    shall not be considered valid unless the changes are reviewed. The analysis and recommendations ofthis report should not be applied to different projects on the same site or to similar projects on different

    sites.

    The analysis and recommendations in this report are based upon borings at specific locations. The

    nature and extent of variation between boring locations is impossible to predict. Because of this,

    geotechnical recommendations are preliminary until they have been confirmed through observation of

    site excavation and earthwork preparation. If variations appear during subsequent exploration or

  • 8/23/2019 Geo Technical Exploration Report

    10/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Page 8

    T h i e l e G e o t e c h I n c

    during construction, we may reevaluate our recommendations and modify them, if appropriate. The

    geotechnical engineer should be retained during construction to observe compliance with the

    recommendations of this report and to provide quality control testing of earthwork construction. If

    these services are provided by others, including the contractor, the entity that provides construction

    phase observation and testing shares responsibility as the geotechnical engineer of record forimplementing or modifying these recommendations.

    Respectfully submitted,Thiele Geotech, Inc.

    Prepared by,

    John A. Christiansen, P.E.Nebraska License E-7821

    P:\10026.00\GEOTECHNICAL EXPLORATION REPORT.DOC

  • 8/23/2019 Geo Technical Exploration Report

    11/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Appendix

    T h i e l e G e o t e c h I n c

    APPENDIX

    Subsurface Exploration Methods

    Legend of Terms

    Boring Location Plan

    Boring Logs

    Soil Test Summary

  • 8/23/2019 Geo Technical Exploration Report

    12/17

    Geotechnical Exploration Report March 9, 2010TG #10026.00 Appendix

    T h i e l e G e o t e c h I n c

    SUBSURFACE EXPLORATION METHODS

    The fieldwork for this study was completed on February 15, 2010. The exploratory program consisted

    of 1 test boring drilled at the approximate location shown on the Boring Location Plan. Boring

    locations were selected to provide the desired site coverage and were adjusted to accommodate access

    conditions. The boring location was laid out by estimating angles and measuring with a cloth tape

    from existing site features. The boring location should only be considered accurate to the degree

    implied by the methods used to define them.

    The test boring was advanced using hollow stem augers powered by a truck-mounted drill rig. Soil

    samples were obtained at selected depths as indicated on the boring logs. A 3-inch nominal diameter

    thin-walled sampler was hydraulically pushed to obtain undisturbed samples. Disturbed samples were

    obtained by driving a 2-inch nominal diameter split barrel sampler while conducting standard

    penetration tests (SPT).

    The boring log was prepared based on visual classification of the samples and drill cuttings, and by

    observation of the drilling characteristics of the subsurface formations. The log was supplemented and

    modified based on the laboratory test results and further examination of the recovered samples. The

    stratification lines on the boring log represent the approximate boundary between soil types, but the

    insitu transition may be gradual.

    Water level observations were made at the times stated on the boring log. The boring was backfilled

    with drill cuttings at the completion of the fieldwork.

    The field boring logs were reviewed to outline the depths, thicknesses, and extent of the soil strata. A

    laboratory testing program was then developed to further classify the basic soils and to evaluate the

    engineering properties for use in our analysis.

    Laboratory tests to further classify the soils included visual classification, moisture content, dry unit

    weight, Atterberg limits, and fraction passing the #200 sieve. The shear strengths of cohesive samples

    were evaluated using the unconfined compression test.

    The boring log and related information in this report are indicators of subsurface conditions only at the

    specific locations and times noted. Subsurface conditions, including ground water levels, at other

    locations of the site may differ significantly from conditions that exist at the sampling locations. Also

    note that the passage of time may affect conditions at the sampling locations.

  • 8/23/2019 Geo Technical Exploration Report

    13/17

    LEGEND OF TERMSSoil Description Terms

    Consistency - Fine Grained Consistency - Coarse Grained Moisture Conditions

    Very Soft, Soft, Firm, Very Loose, Loose, Medium Dry, Slightly Moist, Moist

    Hard, Very Hard Dense, Dense, Very Dense Very Moist, Wet (Saturated)

    Sample Identification Sample Type Sample Data Laboratory Data

    U -- Undisturbed (Shelby Tube) No. -- Number MC -- Moisture contentS -- Split barrel (disturbed) SPT -- Standard penetration test d -- Dry unit weight

    C -- Continuous sample bpf -- blows per foot qu -- Unconfined compression

    A -- Auger cuttings (disturbed) Rec -- Recovery LL/PI -- Liquid limit & plasticity index

    Unified Soil Classification System Peat Pt Highly organic soils

    Fat Clay CH Clay - Liquid Limit >50 * 50% or more

    Elastic Silt MH Silt - Liquid Limit >50 * smaller than

    Lean Clay CL Clay - Liquid Limit % sand

    Poorly-Graded Gravel GP Gravels with less than 5 percentWell-Graded Gravel ** GW smaller than No. 200 sieve *

    * See Plasticity Chart for definition of silts and clays ** See Criteria for Sands and Gravels for definition of well-graded

    Plasticity Chart

    Pl

    as

    tic

    ity

    In

    d

    e

    x

    60

    50 CH or OH

    40

    30MH or OH

    20 CL or OL

    10CL-ML ML

    0 10 20 30 40 50 60 70 80 90 100

    L i q u i d L i m i t

    Criteria for Sands and Gravels Coarse Fine Coarse Medium Fine FINES

    Boulders Cobbles Gravel Gravel Sand Sand Sand (silt or clay)

    Sieve size 10" 3" " #4 #10 #40 #200

    Well-graded sands (SW) Cu=D60/D106 and Cc=(D30)2/(D10 x D60) 3 and 1

    Well-graded gravels (GW) Cu=D60/D104 and Cc=(D30)2/(D10 x D60) 3 and 1

  • 8/23/2019 Geo Technical Exploration Report

    14/17

  • 8/23/2019 Geo Technical Exploration Report

    15/17

    WAT

    D

    E

    DEP(ft.)

    bori

    5

    10

    15

    20

    25

    ER LEVEL OB

    uring Drilling

    nd of Drilling

    COLOR M

    ng backfilled

    darkgray

    light slibrown

    grayishbrown

    ERVATIONS

    VIS

    IST. CONSI

    15.0

    15.0

    ith cuttings

    oist hard

    htly loosoist

    et

    LO

    AL/MANUAL

    T.SOILTYPE

    Railroad St

    see B

    lean clay

    poorlygradedsand

    PROJECT

    LOCATION

    ATION OF BO

    ESCRIPTION

    GEOLOGICORIGIN

    Pump Statio

    & Herbert St,

    oring Locatio

    fill

    alluvium

    ING

    REMA

    eatrice, NE

    n Plan

    light bmottl

    fine tosa

    minor fin

    DRILLER

    DRILLI

    TYPE O

    S

    RKSNTY

    Epley

    3.2

    g

    U

    rown Uling

    oarse Ud

    S

    S

    gravel

    S

    LOGGER

    G METHOD

    F SURFACE

    AMPLE DATA

    . &PE

    SPT(bpf)

    RE(in.

    Kalbach

    5 HSA

    rass

    -1 11

    -2 11

    -3 12

    -4 3

    -5 5

    -6 5

    BOJOB NO.

    DRILL RI

    ELEVATIO

    LABORAT

    )

    MC(%)

    d(pcf)

    10026.0

    CME 45

    16.9 111.4

    18.3 103.0

    2.3

    11.0

    15.2

    ING LDATE

    BORING

    N DEPT

    ORY DATA

    qu(tsf)

    LL/PICLASS

    0 2/15/1

    B-1

    30

    LL=36

    2.25 PI=20

    CL

    P200

    4.3%

    SP

    D

  • 8/23/2019 Geo Technical Exploration Report

    16/17

    WAT

    D

    E

    DEP(ft.)

    bori

    30

    35

    40

    45

    50

    ER LEVEL OB

    uring Drilling

    nd of Drilling

    COLOR M

    ng backfilled

    reddishbrown

    lightbrown

    ERVATIONS

    VIS

    IST. CONSI

    15.0

    15.0

    ith cuttings

    et loos

    et veryhard

    LO

    AL/MANUAL

    T.SOILTYPE

    Railroad St

    see B

    poorlygradedsand

    rock

    PROJECT

    LOCATION

    ATION OF BO

    ESCRIPTION

    GEOLOGICORIGIN

    Pump Statio

    & Herbert St,

    oring Locatio

    alluvium

    ING

    REMA

    eatrice, NE

    n Plan

    weathewith lim

    bottom of h

    DRILLER

    DRILLI

    TYPE O

    S

    RKSNTY

    Epley

    3.2

    g

    shaleestone S

    ole @ 30

    LOGGER

    G METHOD

    F SURFACE

    AMPLE DATA

    . &PE

    SPT(bpf)

    RE(in.

    Kalbach

    5 HSA

    rass

    -7 50/2

    BOJOB NO.

    DRILL RI

    ELEVATIO

    LABORAT

    )

    MC(%)

    d(pcf)

    10026.0

    CME 45

    ING LDATE

    BORING

    N DEPT

    ORY DATA

    qu(tsf)

    LL/PICLASS

    0 2/15/1

    B-1(con

    30

    D

  • 8/23/2019 Geo Technical Exploration Report

    17/17

    SOIL TEST SUMMARProject J ob No.

    Pump Station 10026.00Location Date

    Railroad St & Herbert St, Beatrice, NEUNIT UNCONFINED SOIL CLASSIFICATION

    BORING SAMPLE SAMPLE SAMPLE MOISTURE WEIGHT VOID SAT. COMPRESSION ATTERBERG PASS REMARK

    NO. NO. DEPTH DIA. CONTENT WET DRY RATIO (%) qu STRAIN LIMITS #200

    (ft.) (in.) (%) (pcf) (pcf) (e) (tsf) (%) LL PL PI (%)

    B-1 U-1 1.5-3 16.9 130.2 111.4 0.512 89

    U-2 3.5-5 2.85 18.3 121.8 103.0 0.636 78 2.25 4.7 36 16 20 CL

    U-3 8.5-10 2.3

    S-4 13.5-15 11.0

    S-5 18.5-20 15.2 4.3 SP

    S-6 23.5-25

    S-7 28.5-30

    2/22/2010