General Technical Report 05

173
GENERAL TECHNICAL REPORT Equipment: DETAILED ENGINEERING Order: VEC001101 Customer:ROYAL GK PTE LTD

description

Technical Re

Transcript of General Technical Report 05

GENERAL TECHNICAL

REPORT

Equipment: DETAILED ENGINEERING

Order: VEC001101

Customer:ROYAL GK PTE LTD

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. i

- CONTENTS -

1 PURPOSE ............................................................................................................ 1

2 GENERAL DESCRIPTION ................................................................................ 3

3 CIVIL ENGINEERING ........................................................................................ 4

3.1 Prior Data ................................................................................................... 4

3.2 Foundations ................................................................................................ 5

3.3 Electrical Installations and Pits ................................................................. 7

3.4 Drainage System ...................................................................................... 10

3.5 Exterior Flooring ...................................................................................... 12

3.6 Interior Flooring ....................................................................................... 14

3.7 Fencing ...................................................................................................... 15

3.8 Metallic Structure .................................................................................... 15

3.9 Façades ...................................................................................................... 20

3.10 Roofs .......................................................................................................... 20

4 OPERATIONAL CONDITION AND TERMS ............................................... 22

4.1 Electrical power generation .................................................................... 22

4.2 Fire& gas leak detection .......................................................................... 25

5 ENGINE AND GENERATOR ASSEMBLY .................................................... 36

5.1 Engine features ......................................................................................... 38

5.2 Alternator features .................................................................................. 40

6 ENGINE FLUE SYSTEM .................................................................................. 43

6.1 Exhaust silencer ....................................................................................... 44

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. ii

6.2 Exhaust chimney ...................................................................................... 44

6.3 Piping and fittings ..................................................................................... 44

6.4 Design and definition chart ..................................................................... 46

7 ENGINE COOLING SYSTEM ......................................................................... 52

7.1 Engineering basis of design ..................................................................... 53

7.2 Electrical water pumps ............................................................................ 54

7.3 Expansion vessels ..................................................................................... 54

7.4 Double core air cooler ............................................................................. 55

7.5 Piping& fittings ......................................................................................... 56

7.6 Testing & inspection ................................................................................ 59

7.7 Design & definition chart ........................................................................ 60

8 ENGINE LUBE OIL SYSTEM .......................................................................... 73

8.1 Blowby gases exhausting system ............................................................ 74

9 ENGINE VENTILATION SYSTEM ................................................................ 77

9.1 Description of the engine room ventilation .......................................... 77

9.2 Ventilation system ................................................................................... 78

10 NATURAL GAS FUEL SUPPLY ..................................................................... 80

10.1 General description ................................................................................. 80

10.2 Engineering basis of design ..................................................................... 90

10.3 Testing & inspections ............................................................................... 91

11 FIRE & GAS LEAK DETECTION SYSTEM ................................................... 93

11.1 Basis of design ........................................................................................... 95

11.2 Design & definition ................................................................................... 97

11.3 Technical specifications ......................................................................... 105

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. iii

12 ELECTRICAL GENERATING SYSTEM ...................................................... 117

12.1 General description ............................................................................... 117

12.2 Grounding grid ....................................................................................... 129

12.3 Engineering basis of design ................................................................... 130

12.4 Supporting calculations ......................................................................... 131

12.5 Testing & inspection .............................................................................. 138

13 ANCILLARY SERVICES.LOW VOLTAGE SYSTEM. ................................ 139

13.1 General description ............................................................................... 139

13.2 Engineering basis of design ................................................................... 145

13.3 Electrical design & definition ................................................................ 145

13.4 Testing & inspection .............................................................................. 161

14 ENVIRONMENTAL POLLUTION SOURCES AND

MEASURES ..................................................................................................... 162

14.1 Standards basis of design....................................................................... 162

14.2 Location .................................................................................................. 163

14.3 Raw and auxiliary materials .................................................................. 163

14.4 Air Pollution-Emission sources ............................................................. 165

14.5 Noise Sources ......................................................................................... 166

14.6 industrial sewage water ......................................................................... 167

14.7 Industrial residues .................................................................................. 168

14.8 Environmental measures for the site soil ............................................ 169

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 1

1 PURPOSE

This project envisages the construction of a 26MW natural gas generation power plant in

the Republic of the Union of Myanmar. This power plant is conceived as a back-up to

increase the already existing power generation capacity that supplies the national grid in

the Yangon Region.

The power plant will be based on internal combustion engines technology. Although the

power plant will be managed as a single unit from a central control station, the design is

based on 26 gas gensets of 1MW, which can be also managed as independent generation

units.

The main advantage of this design is that using 1MW gensets the plant will have higher

degree of power availability in case of maintenance or reparations of the units than using

bigger sized gensets.

The plant has been designed foreseeing a future expansion with a second phase of

another 26 gensets. If this second phase is implemented the final capacity of the plant will

be of 52MW.

This new plant will be built adjacent to the existing Hlawga Gas Power Plant, which at

present day is composed by 3 gas turbines and a steam turbine, which have a total

available power capacity of 154,2MW. The gas supply for the new power plant will be

diverted from the MOGE gas regulation station that serves to the turbines.

The power plant is also adjacent to a power substation of YESB, where the turbines are

connected to Myanmar’s National Grid. The interconnection of the new power plant will

be made at the same busbar of 33kV as the turbines, using an available spare feeder.

Future expansion would require a second feeder in the same busbar.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 2

HlawgaPowerPlant

(Turbines)

YESB Substation (33kV)

Interconnectionfeeder

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 3

2 GENERAL DESCRIPTION

The power plant is composed by two warehouse buildings. Each of them will house

13x1MW electrical generators.

Between these buildings, there will be a space where the transformers and a MV

switchboard box are located. These elements are used to step-up the power to 33kV.

Surrounding these buildings there will be a 7-metre wide road and then, further beyond

and parallel to the warehouses, there will be installed the air coolers for the cooling

system of the gensets.

On one side of the plot, perpendicular to the warehouses, there will be a gas regulation

and measurement station (GRMS) and, on the other side, next to the plot entrance, there

will be a building with offices, warehouse, the main control station and other facilities.

Close to the entrance, there will be two large transformers and also some MV protection

switchboards.

The size of the power plant will be of 107m (length) x64,8m (width).

General lay-out can be viewed in the plan No.:31.01The future expansion requires the

duplication of these elements, except the building of the offices, warehouse, and main

control station, which will be common to all the installation. View plan No.: 39-01.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 4

3 CIVIL ENGINEERING

In the following chapter of this report is made the description of the Civil Engineering

works necessary to build the plant.

Related drawings 41-01 to 41-06 describe the necessary works for the urbanization of the

plant area, foundation, underground works, piping, slabs, etc..

Related drawings 42-01 to 42-17 describe the construction of the three main buildings;

the two engine rooms and the auxiliary services building.

In general terms this chapter describes the previous steps of the necessary works to

perform the plant construction; before strictly speaking, the generation plant equipment is

installed (generators, generator cooling system, electrical equipment and wiring, gas

installation, etc..)

Constructor should take in consideration that some works and installation not directly

described in this chapter should be performed in parallel to the underground civil works.

Notably underground installations like the buried grounding grid (view Plan 24-01) and

some buried water (view Plan 61-02 to 61-05) and gas (view Plan 62-03) pipes.

3.1 PRIOR DATA

The project will be on a horizontal area of levelled ground, which must be executed so

that it has volumetric stability without any settlement or shrinkage due to insufficient

compaction and without any increase in volume or expansivity. This levelled ground has

to be a regular surface in order to support the surface and the shallow and deep

foundations to avoid the undesired distribution of differential tensions and settlement

which may affect the layout of the facilities, the foundations of the buildings and the

foundations of the equipment. It must also be resistant to the erosion caused by water,

both the surface and underground water, and the levelled ground must prevent it from

sliding down the hillside.

The construction of the levelled ground is not part of this project and must be carried

out in accordance with the technical specifications of the project engineer and backed by

a local geotechnical study. The levelled ground’s design will also depend on the

construction techniques and available materials, as well as on the functional and structural

aspects and on the location’s height.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 5

The levelled ground must ensure that the terrain has a bearing capacity of 1.5 kg/cm2

(0.15 MPa) on the base of the building’s footing and on the base of the shallow

foundations, as well as the ballast module indicated in the plans.

Regarding the plot where the road will be located, the levelled ground must be a category

E2, i.e. its compressibility module in the second bearing cycle obtained by a "Plate bearing

trial" must be > than 120 MPa. CBR>10.

Note: The design of civil engineering described in the following document was done

according these premises and with shallow foundations. After the visit of November 2012

to the site it was stated that the critical buildings required deep foundations (piles) in

order to avoid any collapse possibility in case of earthquake. A study was done to argue

this statement. This document, the related calculations and a foundation design with piles

are included as appendixes of this project. (View Appendix Civil Enginnering- Pile

design) Customer has decided not to follow this recommendation and thus a complete

design of the metallic structures based in these foundations was not done. The following

document describes a shallow foundation design.

3.2 FOUNDATIONS

Once the levelled ground has been approved, the necessary excavation will be made in

order to build the foundations for the buildings, whose support height is deeper. The

shafts for the foundations and the ditches for the centring beams will be excavated. It will

be checked that the terrain’s bearing capacity in the foundation base is 1.5 kg/cm2 (0.15

MPa). The ballast module will be 1,000 - 3,500 T/m3.

All the reinforced concrete elements will be on a base of blinding concrete that is 10 cm

thick.

The excavations will be in accordance with the instructions of the geotechnical study, so

that the embankments are stable. It will be possible to consider placing reinforcements

and shoring in the deep excavations.

The design of the foundations has been made in accordance with the Instruction on

Structural Concrete (EHE-08) and the Basic Documents on Structural Safety (DB-SE),

Structural Safety of Foundations (DB-SE-C), Structural Safety of Steel (DB-SR-A) and

Structural Safety on Building Actions (DB-SE-AE) of the Spanish Technical Building Code

(CTE).

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 6

3.2.1.1 Footings

The two warehouses where the generators and the ancillary services building are located

will have insulated rigid footings made with HA-20 reinforced concrete (f'c=200 with fck

resistance = 200 kp/cm²), whose depth will be in accordance with the plans in order to

prevent interferences.

The dimensions, reinforcement and characteristics of the concrete will be in accordance

with the plans.

The footings will be joined by the centring beams.

The footings will have anchor plates for the metal pillars, whose dimensions and

characteristics are detailed in the plans, and will be secured to the concrete with bolts.

The metal posts have to be placed before filling and tamping the excavations.

The separating walls between the 35 MVA transformers will be made of reinforced

concrete, whose dimensions will be in accordance with the plans (View plan No.: 41-06)

and their foundations will have continuous footing of 150 x 50 cm. of section. The

supporting height of these walls will be the same as that for the transformer tanks.

The walls have R120 fire resistance.

The air coolers will have a reinforced concrete footing on which concrete pillars will be

built in accordance with the plans (View plan No.: 41-05).

3.2.1.2 Concrete Slab Foundations

The foundations for the transformers, the main cell box, the line input cell room and the

GRMS will be made of concrete slabs, whose dimensions and depths will be in accordance

with the plans. (View plan No.: 41-05, 41-06.) Apart from the GRMS which will be

directly supported by the slab, the other elements will be supported by the

corresponding slabs through walls, thus providing tanks to collect the oil in the case of

transformers as well as pits in the cell boxes through which the installations will pass.

The generators will have a reinforced concrete bedplate which will serve as the

foundations and settlement, carrying out the function of seismic mass, thus isolating the

vibrations of the surroundings.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 7

3.3 ELECTRICAL INSTALLATIONS AND PITS

In parallel to the generator rooms, along the lengthwise axis between them, a ditch will

be built for the electrical cables, with a minimum interior free height of 147 cm. Its

construction will base on reinforced concrete slabs and walls, with a thickness of 15 cm,

except in the cell box area and the prefabricated concrete caps. The cabling ditch will

have slopes towards the ends, where there will be a drainage system connected to the

rainwater sewage network to evacuate the water that may enter from outside.

Inside the generator warehouses, pits will be built for the electrical cabling under the

location of the control and power panels. Its construction will based on reinforced

concrete with anti-slip diamond plate caps with a thickness of 3 mm. They will have a

drainage system on the base through a PVC tube of Ø110 mm over a gravel bag.

The underground electrical installations go from these pits to the transformers and the

air coolers.

The plot’s other installations will be buried in ditches, whose design has been made in

accordance with the Spanish Technological Regulations (NTE) and Iberdrola’s specific

regulations in the case of the electrical pits.

The electrical pits, lighting and water pipes from the generator warehouses to the air

coolers will be made with HM-20 mass concrete to protect the pipes, and their support

height will be that stated in the development plans.

3.3.1 Electrical Pits

The electrical pits will be formed by corrugated polyethylene pipes whose diameters are

defined in the corresponding plans (View plans No.:41-02, 41-04 Detail Trenches 1

to 6), covered by an HM-20 mass concrete tray, whose dimensions and depth will

depend on the number of pipes that they have, and by a fill compacted to 100% of the S.P.

(standard Proctor) up to the level of the levelled ground. They will have boundary tapes

in the compacted fill.

The corrugated polyethylene pipes with a Ø200 mm connection between the electrical

conduits and the transformers will have a minimum turning radius of 40 cm, and those

which connect the transformers with the main cabling pit will have a minimum turning

radius of 72 cm.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 8

There will be inspection hatches for the electrical pits, whose dimensions are specified in

the plans (View plans No.:41-02, 41-04 Detail Trench (electrical)) and they will be

made of prefabricated concrete with a prefabricated concrete cover with a metal frame.

These inspection hatches will have a drainage system on the base through a PVC tube of

Ø110 mm over a geotextile gravel bag.

3.3.2 Pits for the Lighting

The pits for the lighting will connect the planned lamppost system and will be formed by 2

corrugated polyethylene pipes, with a diameter of 90 mm, covered by an HM-20 mass

concrete tray, whose dimensions and depth are defined in the plans (View plans No.:41-

02, 41-04 Detail Trench 7), and by a fill compacted to 100% of the S.P. up to the level

of the levelled ground. They will have boundary tapes in the compacted fill.

There will be inspection hatches for the pits for the lighting, which will coincide with the

lampposts’ positions, their dimensions are specified in the plans (view plan 41-04 detail

Foundation with street lamp), and they will be made of prefabricated concrete with a

prefabricated concrete cover with a metal frame. These inspection hatches will have a

drainage system on the base through a PVC tube of Ø110 mm over a gravel bag.

3.3.3 Pits for Electricity, Data and Other Conduits

These pits are those which will connect the generator warehouses with the air coolers.

They will be formed by a row of conduits, covered by an HM-20 mass concrete tray,

whose dimensions and depth are defined in the plans (View plans No.:41-02, 41-04

detail Trench 8 to 11), and by a fill compacted to 100% of the S.P. up to the level of

the levelled ground. They will have boundary tapes in the compacted fill.

The development plans define the polyethylene pipes that will protect the water pipes,

which will be made of stainless steel. The depth has been established at 120 cm from the

axis of the pipes to the floor of the generator warehouses (height: +0.00).

3.3.4 Pits for Water Supply

A water supply network has been planned with water hydrants that help to clean the

roads. This network will go from the plot’s connection through the ancillary services

building and will be through a DN 50 mm polyethylene pipe.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 9

The pits for the water supply network will be made with a sand base, which will have the

polyethylene pipe inserted, and a fill compacted to 100% of the S.P. up to the level of the

levelled ground. They will have boundary tapes in the compacted fill. The dimensions and

depth of the pits are defined in the plans. (View Plans 41-02, 41-04 details “Trench

for water pipe under the road”,”Trench for water pipe out of the road”)

3.3.5 Sewage Pits

To determine the width and depth of the pit, it is necessary to know the diameter of the

pipes, the geotechnical characteristics of the terrain and the possible mobile bearings that

can be transmitted to the subsoil, apart from the instructions from the site management.

To facilitate manipulation inside the pit, a minimum width has been defined for the lowest

point of the pit as the diameter of the tube plus 60 cm.

There will be a 10 cm-thick bed of granular materials to avoid contact with the sharp

elements that may deteriorate the pipe and, therefore, alter its sealing, resistance and

other characteristics. It will also be used to make a correct levelling of the terrain in

order to ensure the desired slope.

Once the pipe has been laid out, the pit will be filled with selected material compacted to

95% of the S.P. with a height of 30 cm over the line following the highest parts of the

pipe. The rest of the pit will be completed with a fill compacted to 100% of the S.P.

The compaction in any of the filling phases must be made with a lightweight tamper and

on both sides of the pipe, without compacting the central area that corresponds to the

pipe's projection.

The sewage network conduits with a diameter of 400 mm or less will be PVC SN4

compact pipes, while those with a diameter of more than 400 mm will be PVC SN8

compact pipes.

The inspection hatches and manholes of the sewage network will be prefabricated, except

the drains under the gutters and the grease separators.

There will be inspection hatches for the pits for the lighting, which will coincide with the

lampposts’ positions, their dimensions are specified in the plans (view Plan 41-02, 41-04

detail “Trench for sanitation water” & others), and they will be made of

prefabricated concrete with a prefabricated concrete cover with a metal frame. These

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 10

inspection hatches will have a drainage system on the base through a PVC tube of Ø110

mm over a gravel bag.

3.4 DRAINAGE SYSTEM

The drainage system has been designed to separate fecal waters, rain water and oily

water. The drains correspond to the items or surfaces where oil could have been

discharged.

3.4.1 Fecal Water Drainage System

Fecal waters to be drained come from the locker rooms and washrooms located in the

auxiliary services building. The water will flow to a septic tank equipped with a siphon

collection box at the beginning and a sampling collection tank at the end where a

discharge pipe is connected to an external channel with treated water. (view Plan 41-2,

41-04 detail “Siphonic Trench”)

3.4.2 Oily Water Drainage System

An oily water drainage system has been designed for the inside of each engine room. The

system is comprised of sumps that collect water originating from cleaning buildings, water

circuit spillage and engine base plate drains which is discharged via the sump drains. The

collection boxes are connected to each other via PVC pipes and drain to external oil

separator collection boxes where oil-free water goes to the rainwater drainage system.

Furthermore, rainwater that falls into the transformer basins will go to a collection box

controlled by a shutoff valve which will allow rainwater to be discharged or if there is an

oil spillage, it shall blocked until it can be removed by an authorized handler.

Collection boxes with shutoff valves are found in accessible locations in order to for

waste removal to be performed without having to be near restricted access areas located

near the transformers.

3.4.3 Rainwater Drainage System

Rainwater that falls upon the roofs of the buildings will be collected in pipes located

outside the building and transported by downpipes, attached to the facade, towards the

underground system.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 11

The road and the transformers are located between two buildings; this area will have a

2% slope angle which leads towards concrete ditches. These ditches will have a

longitudinal slope which is higher than 0.5% and which will lead towards sumps connected

to the underground network.

Sump grating will be placed at engine room access points in order to avoid rainwater

from entering.

The central electrical cable trench will drain into the underground rainwater drainage

system.

The electricity collection boxes and gutters are designed with a drainage channel located

at the bottom, which is connected to a bed of gravel on ground-level..

The rainwater drainage system will discharge into the ground, in the sloppy area which in

turn discharges into the lake located on the west side of the lot.

3.4.3.1 Rainwater system sizing

Rainwater flow (Q) to be drained will be indicated in L/s and will depend on the following

factors:

The average run-off coefficient: Depends on the run-off coefficients for different types of

surfaces and areas considered. A coefficient of 0.85 is used for asphalt and concrete

pavements.

Rainfall intensity that corresponds to the maximum precipitation for a specific return

period and the length corresponding to the period of concentration time, which is the

necessary time needed to ensure that the maximum flow for discharge arrives to the

section considered.

A 100 year return period has been established since flooding could cause serious damage.

This means that the intensity is set at a 1.91 coefficient.

The period of concentration is estimated at a maximum of 10 minutes.

Rainfall intensity calculations are estimated at 120 mm/hour and the maximum average

intensity is 360 mm/hour for 10 minute intervals.

Surface area for wastewater areas at the point considered.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 12

The rainwater drainage system is calculated based on severity patterns and a minimum

slope of 0.5%.

The drainage pipes need to be partially filled when in operation in order to ensure

adequate sewage network ventilation. The percentage of filling of the drainage pipes will

depend on the flow intake at each moment but the project has considered a filling level of

h=0.8Di, where Di corresponds to the inner diameter of the pipe.

Another determining factor for correct evacuation is the circulation speed. The minimum

speed has been set at 0.5 m/s which prevents sedimentation and a maximum speed of 2.5

m/s which prevents abrasion.

Full flow piping calculations were made based on the “Manning Formula” and the

“Thorman and Franke Table” was used to determine the relationship between, velocities,

flows and filling levels in partially filled circular conduits.

Manning´s roughness coefficient was considered at 0.008.

3.5 EXTERIOR FLOORING

Once the foundations had been executed and pipes buried, the next step is the

urbanisation of the plot’s exterior flooring. First the base of graded crushed aggregate will

be laid with the thickness and gradients as defined in the plans (view Plan 41-01, 41-05).

3.5.1 Roads

Given that at the time of the transport and installation of the engines and equipment,

heavy vehicles are going to circulate for a short period, a type of traffic D, medium light

T4.1, is established, corresponding to the movement of between 25 and 50 heavy

vehicles/day in low-traffic industrial areas.

25 cm. of graded crushed aggregate will be spread over the platform, with a density of not

less than 98% of the maximum reference obtained in the modified Proctor test, according

to UNE 103501.

The graded crushed aggregate to be used is a granular material, of continuous aggregate

grading consisting of totally crushed particles made from quarry stone or natural gravel.

Its cleaning coefficient according to annex C of UNE 146130 must be less than two. The

sand equivalent (Se) according to UNE-EN 933-8 must be greater than 30. According to

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 13

UNE-EN 1097-2 the Los Angeles coefficient of aggregates must be no greater than 35.

Limit of non-plastic Atterberg. CBR>20.

Above the graded crushed aggregate a surface treatment will be given with a prime coat

with a firm coat of hot bituminous mix on top.

The hot bituminous mix will be formed by a base coat AC 32 BASE 50/70 G LIMESTONE,

8 cm thick, adhesive primer, an intermediate layer AC 22 BIN 50/70 S SILICA, 6 cm thick,

adhesive primer, and a wearing course of AC 16 SURF 50/70 S OPHITE, 4 cm thick.

(Designation according to UNE-EN 13108).

The road will have at its perimeter a trowelled concrete ditch with smooth finish with

white cement and edged with a border of grey concrete.

3.5.2 Flooring in front of premises

Flooring in front of the premises at the entrance for the engines will consist of two layers

over the platform.

The base will be graded crushed aggregate compacted to 98% of Modified Proctor 20 cm

thick. Over the shingle will be placed HA-20 concrete (f’c=200 type with fck = 200

kp/cm² resistance), 20 cm thick, with 10 mm diameter reinforced wire mesh in a 20x20

cm grid with B 400 S steel (Grade 60 type with fyk = 4200 kp/cm² resistance). Between

the two layers will be a 150 micra layer of polyethylene and a anti-puncture geo-fabric.

The mesh will be placed on the upper part of the sill, with a coating of at least 3 cm.

The concrete will have a mechanical trowelled finish sprinkled with non-slip grey quartz

aggregate.

3.5.3 Flooring of the Transformer Area y Front of the GRMS and

the auxiliary services building

The flooring around the transformers between the premises, the transformers and line

entry cell room, the ERM and the auxiliary services building, will consist of two layers

over the platform.

The base will be graded crushed aggregate compacted to 98% of the Modified Proctor, 20

cm thick Over the shingle will be placed HA-20 concrete (f’c=200 type with fck = 200

kp/cm.² resistance), 15 cm thick, with 10 mm reinforced wire mesh, grid diameter 20x20

cm, with B 400 S steel (Grade 60 type with fyk = 4200 kp/cm² resistance). Between the

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 14

two layers will be a 150 micra layer of polyethylene and an anti-puncture geo-fabric. The

mesh will be placed on the upper part of the sill, with a coating of at least 3 cm.

The concrete will have a mechanical trowelled finish sprinkled with non-slip grey quartz

aggregate.

3.5.4 Air Coolers Area

There will be no flooring in these areas, a 10 cm thick layer of aggregate with 20-40 mm

diameter grading will be spread over the platform.

3.6 INTERIOR FLOORING

3.6.1 Engine Room

Once the platform has been accepted, a base of graded crushed aggregate will be spread

on top, compacted to 98% of the Modified Proctor, 20 cm thick. Over the shingle will be

placed HA-20 concrete (f’c=200 type with fck = 200 kp/cm² resistance), 20 cm thick, with

10 mm diameter reinforced wire mesh in 20x20 cm grid with B 400 S steel (Grade 60

type with fyk = 4200 kp/cm² resistance). Between the two layers will be a 150 micra layer

of polyethylene and an anti-puncture geo-fabric. The mesh will be placed on the upper

part of the sill, with a coating of at least 3 cm.

Retraction joints will be placed every 25 m2 and will be sealed with elastic material.

The ground will be finished with non-slip Epoxy paint.

3.6.2 Auxiliary Services Building

Once the platform has been accepted, a base of graded crushed aggregate will be spread

on top, compacted to 98% of the Modified Proctor, 20 cm thick. Over the shingle will be

placed HA-20 concrete (f’c=200 type with fck = 200 kp/cm² resistance), 15 cm thick, with

10 mm diameter reinforced wire mesh in 20x20 cm grid with B 400 S steel (Grade 60

type with fyk = 4200 kp/cm² resistance). Between the two layers will be a 150 micra layer

of polyethylene and an anti-puncture geo-fabric. The mesh will be placed on the upper

part of the sill, with a coating of at least 3 cm.

The concrete will have a mechanical trowelled finish sprinkled with non-slip grey quartz

aggregate.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 15

In the remaining premises considered permanent staff work stations the concrete sill will

be covered with 5 cm thick extruded polystyrene thermal insulation, and a 5 cm thick

levelling layer of mortar cement and will be finished with ceramic tiles.

3.7 FENCING

The 2.50 m high perimeter fencing will be made of a chain link wire mesh made of 3 mm

diameter, galvanised and plasticised wire. The pylons will be 3 m apart at most and will be

50x50 mm section galvanised, painted metal cemented into fingers in 50x50x50 cm HM-

20 mass concrete (f'c=200 type with fck = 200 kp/cm² resistance).

The upper of the fencing will be fitted with a security wire with anti-intruder spikes.

3.8 METALLIC STRUCTURE

The structure of all the buildings designed is screwed metal. Design has been done

according European Standard profiles. (HEB-120, HEB-200, UPN-300, IPE-100, IPE-160,

IPE-200,IPE-300, etc…)

Steel of the sections and plates is S 235 JR (JO in tubular sections) with tensile yield

strength of fy= 235 N/mm2.

The steel of the screws is 8.8 with tensile yield strength of fy= 640 N/mm2 and tensile

strength at break of fu= 800 N/mm2.

The metal structure will have two layers of antioxidant primer and two layers of enamel

finishing paint.

3.8.1 Engine Buildings

Will consist of porches in HEB-200 laminated steel pylons and IPE-300 lean-to beams with

a slope of 10%.

The porches will be braced by a continuous UPN-300 on each longitudinal façade.

The roofing bars will be IPE-160.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 16

3.8.2 Auxilliary Services Building

Will consist of porches in HEB-120 laminated steel pylons and IPE-200 lean-to beams with

a slope of 10%.

There are three circular 168.3 mm diameter, 8 mm thick pylons, on which HEB-120 will

be placed where they meet the beams.

The roofing bars will be IPE-100.

The whole structure of this building will be protected with intumescent fire-resistant

paint with a resistance of R15

3.8.3 Basis for calculation of the Structure

Design and calculation of the structure is according to the Code on Structural Concrete

(EHE-08) and the Basic Document on Structural Safety (DB-SE), Structural Safety -

Actions in Buildings (DB-SE-AE), and Structural Steel Safety (DB-MRS) of the Technical

Building Code (TBC).

Auxiliary services building

With enclosure on roof

- Enclosure weight: 25.00 kg/m²

- Enclosure load (maintenance): 40.00 kg/m²

With enclosure on sides

- Enclosure weight: 50.00 kg/m²

With roofing bars

- Weight of roofing bars: 10.00 kg/m²

Wind Data

Basic speed: 26 m/sec

Level of roughness: IV. Urban, industrial or forest area

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 17

Period of service (years): 50

Snow data

No snow action (less than and not concomitant with load in use)

Earthquake

Modal spectral analysis

Acceleration a=0.06g

Ductility=1

Engine rooms

With enclosure on roof

- Enclosure weight: 25.00 kg/m²

- Enclosure load (maintenance): 40.00 kg/m²

With enclosure on sides

- Enclosure weight: 50.00 kg/m²

With roofing bars

- Weight of roofing bars: 15.00 kg/m²

Wind data

Basic speed: 26 m/sec

Level of roughness: IV. Urban, industrial or forest area

Period of service (years): 50

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 18

Snow data

No snow action (less than and not concomitant with load in use)

Earthquake

Modal spectral analysis

Acceleration a=0.06g

Ductility =1

Walls separating between 35 MVA transformers

Wind data

Basic speed: 26 m/sg

Level of roughness: IV. Urban, industrial or forest area

Period of service (years): 50

Earthquake

Modal spectral analysis

Acceleration a=0.06g

Ductility =1

Cell cubicle foundation

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 19

Loads

According to technical specifications.

Thrust in walls

Angle of repose 0.00 Degrees

Apparent density 2.00 t/m³

Submerged density 1.10 t/m³

Internal angle of friction 30.00 Degrees

Drainage evacuation 100.00 %

Load in transformers

Type: Uniform

Value: 1.00 t/m

Earthquake

Modal spectral analysis

Acceleration a=0.06g

Ductility=1

Foundations of transformers

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 20

Loads

According to technical specifications.

Earthquake

Modal spectral analysis

Acceleration a=0.06g

Ductility =1

3.9 FAÇADES

Will be formed by sandwich type sheet panels with rock wool core.

The model will be Panel with concealed fixings, acoustic ACH, 100 mm.

Fire resistance RF-120 and fire stability EI-120.

Acoustic insulation Ra = 35.6 dBA and Rw = 36.0 dB.

Panel weight 23.6 kg/m2.

External sheet finish will be 35 micra thick High Durability Polyester (HDS35) coloured

Metallic Silver RAL 9006. The inside of the perforated sheet interior will be Pyrenean

white colour with 25 micra Polyester finish.

Finishes will be galvanised steel lacquered in Metallic Silver RAL 9006 colour.

Panels will be screwed to a structure formed by rectangular tubular profiles 100.50.3.

3.10 ROOFS

Will be formed by sandwich type sheet panels with rock wool core.

The model will be Panel 5 roof tiles with 100 mm thick acoustic ACH E100.

Fire resistance RF-120 and fire stability EI-120.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 21

Acoustic insulation Ra = 35.6 dBA and Rw = 36.0 dB.

Panel weight 23.6 kg/m2.

External sheet finish will be 35 micra thick High Durability Polyester (HDS35) coloured

Metallic Silver RAL 9006. The inside of the perforated sheet interior will be Pyrenean

white colour with 25 micra Polyester finish.

External finishes and gutters will be galvanised steel lacquered in Metallic Silver RAL 9006

colour.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 22

4 OPERATIONAL CONDITION AND TERMS

4.1 ELECTRICAL POWER GENERATION

4.1.1 Description of the power generation

The generators of the power plant are SFGM560 gas gensets of the Guascor-Dresser

Rand brand with a power capacity of 1MW.

These are 4-stroke Miller-cycle internal combustion engines with a 400Vac brushless

synchronous alternator coupled.

The power output of each genset is wired to his LV power switchboard. Each of these

switchboards will include his own synchronization and genset protection equipment. The

gensets will be connected and synchronized to Mains at this LV switchboard

independently. So they can be managed as independent generation units.

Each two gensets will be connected to a step-up transformer that will increase voltage

output to 33kV. These step-up transformers will be protected with MV switchboards

with overcurrent protections. The whole power output of the gensets will be conducted

to an outgoing switchgear. As total power output will be monitored at this point, the

central control system of the plant will be able to manage a “power plant” power setting,

deciding the power setting of each single gensets or eventually the disconnection of some

gensets if the power requirement is too low.

Isolation transformers have been foreseen at the outgoing of the power plant basically to

reduce the high short circuit current from Mains and isolate the power plant from the

grid. From the feeder a buried 33kV line will connect the substation with the plant. A

switchboard will protect this line at the power plant incoming. There’s foreseen a partial

redundancy of the common elements of the power plant (isolation transformers, outgoing

switchboards) to make sure that no failure of these elements would shut-down the whole

plant. Full redundancy is not possible due to lack of available interconnection feeders at

the substation.

Basically the working procedure will be that the gensets will synchronise to Mains and go

after frequency and voltage values of the Mains, controlling the active and reactive power

output with the set-up and adjustable values.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 23

If any Mains electrical value (voltage, frequency, vector shift) would go beyond the

protection settings, the gensets protections would trip the LV genset switchboard and the

genset would stay in idle-running for a while, until Mains values would come back to

proper values.

During the idle-running, gensets cooling power supply should be connected to the gensets

power generation to allow a durable idle-running. This will be made turning manually a

switch in the control panel. A maximum 1Hr idle-running is foreseen. After this time

gensets will shut-down.

In case of genset shut-down is possible to restart the gensets without having power from

the grid, due to the use of batteries powered prelube, gas train and engine cranking

system.

If Mains condition returns to proper values the gensets may be re-synchronized to Mains

and continue exporting power to the grid.

4.1.2 Island mode procedure

Island mode is considered the working procedure in which gensets will control the

frequency and voltage of the grid instead of controlling the active and reactive power

supplied by them to the grid. This working procedure is used in the cases in which the

gensets are the main or sole suppliers of a factory, plant or grid.

In the case of the Hlawga power plant no island mode procedure is foreseen, although

design allows the gensets to work in this mode, controlling frequency and voltage of the

factory and making the load sharing between the single gensets of the plant.

An hypothetical upgrade to this working procedure would require a detailed study of the

load requirements of such island to check if the gensets would withstand the load

changes; it should be studied also the way in which such island would be made (which

switches have to be disconnected to feed the required loads), which kind of protections

would be available to avoid unexpected/unsynchronised connections with other gensets

and also should be agreed some kind of feedback/information system to inform to the

control system of an island/parallel to Mains situation. All these considerations are

external to the power plant and not included in the scope of this project.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 24

4.1.3 Normal operation of the plant

Each genset will have its own power and control cabinet which is supplied with the

gensets scope of supply and, should be located in the engine room close to the gensets.

The documents IO-C-M-AP-00 and IO-G-M-AC-00 include a description of the

functionalities fulfilled by these cabinets.

These local control panels will be interconnected with a plant control panel which will

monitor all the local panels and also information coming from other elements of the plant

(MV substations, GMRS, fire detection system, etc..). This plant control panel will co-

ordinate the information of these different locals control systems.

Management of the gensets will be possible thus locally and remotely from the central

control system.

The engine-generator sets have two operation modes:

1) Automatic: A digital signal is generated for each engine-generator set from the main

control system in the plant. This digital signal has two position:

Remote start

Remote stop

Moreover, the main control system will send a signal with proper safety positions for

start-up. By means of this additional signal each generation engine will be enabled to

operate whenever required.

2) Manual: the operator will separately start or stop each engine-generator from the

control panel at man-machine terminal.

An automatic/manual selector switch will be provided for selection of operation

mode of each engine-generator set. When this selector switch is on manual position, it

will be possible stopping the engine-generator set on remote mode, but not starting it.

Likewise, if alternator protection devices detect any problem in waveform quality, the

related circuit breaker will be triggered. If alternator protection devices detect that the

electrical conditions in the system are normal, the alternator will be resynchronized and

the circuit breaker reset.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 25

4.1.4 Start-up

Commonly, each generation set will be started in automatic mode by means of a remote

command from control system.

Each generation set will be started according to the following sequence

1) The system will verify whether the related engine is ready for operation or not. If not

ready, a warning signal will be activated. After started, the system will try to start the

next engine in the preset sequence.

2) The control system will proceed to perform the following tasks:

a) Start-up of pumps for cooling circuits.

b) Start-up of cooling fans in generation set room.

c) Verification that the related circuit breaker is open.

3) If the auxiliary equipment is properly operating and there is no problem, the control

system will proceed to start the generation set. Otherwise a signal alarm will be

activated and the engine will not be started.

4) From this moment the control system will proceed to synchronize the generation set

and couple it to the electric network.

4.1.5 Stop

Commonly every generation set is stopped in remote mode. The stop sequence for the

generation set and auxiliary equipment will be determined by the control system of each

generation set.

4.2 FIRE& GAS LEAK DETECTION

4.2.1 Operation

The activation signal of a fire sensor will have priority over the pre-alarm or a monitoring

signal failure.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 26

The activation of one of these elements will cause the following (upon confirmation):

a) Local acoustic indication.

b) Message announced on the screen, indicating the date, time, location, nature of

the alarm and action message.

c) Printing of the nature of the alarm, type, date and time (requires external

printer).

d) Store the alarms until they are recognised and the system has been reset.

At any moment it will be possible to view the current status of the peripherals on the

screen, which ones are on alarm or have failed and print the information on a printer. It

will also be possible to pull up historical data of alarms, etc. and print them.

All of the detection circuits will be monitored for cable failures.

4.2.2 Fire protection system

4.2.2.1 Fire detection system

The fire detector signal is sent to the PLC. This activates the alarm sequence of each

genset and, at the same time, an alarm is send to the central control system. The central

control system starts the emergency stop protocol, as described below, and switch on

the general alarm light and horn located on the outside of the control room where is

located this central control system and SCADA.

4.2.2.2 Fire extinguisher system

Will be installed 5 and 10 Kg CO2 fire extinguishers in the transformers surroundings and

6 and 12 kg multipurpose dry powder fire extinguishers in the gensets building.

In the plan 35-01 are indicated the extinguishers needed according to standards; this

layout must be checked on field with the firefighter service.

The location of portable fire extinguishers will be readily visible and accessible; will be

located to points where more likely to start a fire and in evacuation routes. The path

from any point to the nearest fire extinguisher must be less than 15 m.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 27

4.2.3 Control and signaling equipment (fire detection centre)

This element is the heart of the system where all of the incidents from the site are

collected and which, using the resident programme, will decide on the activation of

devices. The Centre will be analogical and smart with its own microprocessor, memory

and power supply and batteries.

The Centre will supervise each sensor and module of the smart loop individually, such

that the alarms, pre-alarms and malfunctions are announced independently for each

element in the smart loop. It will have the capacity for programmable outlets. It will be

located in a metal cupboard and will be equipped with optic indicators to view the status

of the panel. It will supply power to all of the sensors and modules connected to it. The

memory data, events and programming will be kept in a non volatile memory.

The control centre will allow the programming of its output devices (sirens and control

modules) in such a way that the facility can be evacuated in a logical manner following the

evacuation plan. To do this it is necessary for the sirens to be individually operable.

The Fire Detection Centre will be installed in a building with the following characteristics:

It shall have easy access, a simple architecture and be located in the vicinity of the

main access or of the one usually used by firemen.

It will be protected by sensors.

It shall be well lit and shall be protected from vibrations and overcurrents.

4.2.4 Loops and equipment of analogical systems

4.2.4.1 General.

Each sensor, manual alarm button and module shall have a unique address assigned to it.

This will be done manually. The location of the equipment in the loop will not be

conditioned by the address in the loop (e.g. sensors can be added to the loop using an

address that is not being used, without the need to re-programme the existing

equipment). Plan 27.02 shows the layout of the detection loop with the equipment

included in the loop. For the future expansion of the plant a second loop should be made.

Each detection loop will be a couple of braided shielded wires usually with a section of 1.5

mm, wired in open or closed loop and on which the analogical fire sensors, alarm buttons,

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 28

warning sirens and digital modules that are required for the monitoring and control

operations of the rest of the devices that make up the system (loudspeakers,

electromagnets, extinguishers, smoke control, HVAC control, etc.) are installed directly.

The capacity of the detection loop will be 198 analogical/programmable points of which

99 addresses are reserved for the sensors and the other 99 for buttons and modules.

The cable lines shall be laid in an independent pipe with an isolated wire for a nominal

voltage of 500V. The type of cable required will be:

o Name: Loop Cable

o Type of cable: Hose cable

o Number of wires: Couple of braided and shielded wires.

o Section: 1 to 2.5 mm2(standard = 1.5 mm2).

o Length of loop: Up to 3000 m.

1800 m. with 1.5 mm2section cable

3000m with 2.5 mm2 section cable

o Braids: 20 to 40 turns per metre.

o Shielding: Aluminium Shield with drain wire.

o Resistance: Max. 40 Ohm. for the whole loop.

o Capacity: Min. 0,5 f.

The diameter of the tube (D) will be sized in accordance with the number of wires

arranged inside it, thus:

No. of wires 2 4 6 8 10

METRIC 16 16 20 25 25

Similar alternatives that require more than 2 communication wires with the sensors will

not be acceptable.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 29

Similar alternatives, in which the address of the equipment is automatic thus implying that

in possible extensions or modifications of the system or changes of the sensor re-

programming is required, will not be acceptable.

4.2.4.2 Smart analogical sensors.

All of the smart analogical sensors will be assembled on the same base so as to facilitate

the interchange of sensors of different types (if a different type of sensor were required).

Each sensor is assigned a unique address by means of a device which is simple to

understand and operate consisting of two rotating selectors numbered from 0 to 9 (not

binary type switches or using jumper breakers).

The procedure of automatic addressing according to its position on the loop was

discarded as when equipment is added in the near future, it would be necessary to re-

programme the existing addresses with the corresponding loss of flexibility and economic

cost.

Each sensor will have two LEDS that will make it possible to see the status of the sensor

from any position. The will flash each time of asking by the Detection Centre. From the

centre it will be possible to override the flashing of the sensors in idle status. If the sensor

is on alarm, these LED will be permanently lit up.

Each sensor will respond to the Centre with information and identification of its type

(multi criteria, optic or thermal). If there is a discrepancy about the information between

the sensor and the centre, a failure condition will appear. Each sensor will respond to the

Centre with analogical information related to its measurement of the fire phenomenon.

The values at which the sensor will go to pre-alarm and alarm will be programmable by

the user; these values can be changed manually by programming or automatically by the

centre based on the environment in which the sensor is located or by following the

hourly programme made by the system.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 30

All of the sensors have a micro switch that can be activated by a magnet in order to carry

out a local operation test. This test must also be carried out automatically and

periodically from the centre.

The sensors will be wired with1 2 x 1.5 mm2 hose cable with a common section, braided

and shielded and shall provide both the power and communications required.

4.2.4.2.1 SMOKE SENSORS.

The smoke sensors shall respond by measuring the density of the smoke. Each element

can respond with different ranges of sensitivity that are adjustable.

The type of smoke sensor will be ionic when there are visible or invisible aerosols,

coming from all combustion and without the need for a rise in the temperature.

The characteristics of an ionic sensor make it more appropriate for the detection of fires

that spread quickly and which have combustion particles to the order of 0.01 to 0.3

micras.

The type of smoke sensor selected will be optic when there are visible aerosols, coming

from all combustion and without the need for a rise in the temperature.

The characteristics of an ionic sensor make it more appropriate for the detection of fires

that spread slowly and which have combustion particles to the order of 0.3 to 10

microns.

For highly sensitive applications where it is necessary to detect fires at a very early stage

the laser technology optic sensor will be used. This detects invisible combustion particles

(aerosols).

The infrared smoke sensor will be installed in those areas in which, due to the elevated

height of the ceiling, point smoke sensors are not appropriate.

1See section 4.1

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 31

4.2.4.2.2 MANUAL ALARM BUTTONS.

The manual buttons may be included in the smart detection loop as they are

programmable.

They should make it possible to voluntarily provoke and transmit a signal to the control

and signaling centre, in such a way that the area in which the button has been activated is

easily identifiable.

The buttons will be of the glass breaking type. The glass will be protected by a plastic

membrane to prevent its activation from being interrupted. Resettable buttons will not be

used, unless resetting involves the checking of the button by qualified personnel.

4.2.4.3 Control module.

These modules will be installed in the smart loop to make it possible to control the

auxiliary elements of the fire detection system such as: alarm loudspeakers, magnetic

retainers, fire dampers, extinguishing systems, etc. and to give relay signals to auxiliary

equipment.

The control module will provide supervision to the peripheral circuit which is controlled

by the module. It will have an LED indicator of its status.

It will be capable of working in 3 statuses:

As NA, CN relay outputs

As supervised 24 V outputs. In this case they will need 24 Vdc power additional

to the loop cable.

As evacuation loudspeaker output, which will require supply from the audio

amplifier.

4.2.4.4 Monitor Module.

These modules will be installed in the smart loop, to direct the digital inputs of the type

of those provided by conventional buttons, pressure switches, flow sensors, technical

signals, etc.

The monitor module will provide supervision to the peripheral circuit which is controlled

by the module. It will have an LED indicator of its status.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 32

It will not need auxiliary power.

4.2.4.5 Programmable Sirens.

The sirens will be programmable which means they will have two rotating selectors

numbered from 0 to 9 ((not binary type switches or using jumper breakers) for the

assignation of their address.

They will have 4 programmable tones and a sound current no higher than 103 dB.

Depending on the model, the sirens will be able to work in the following manner:

Supplied directly from the analogical loop.

Supplied with 24 vdc additional to the 2 loop wires.

They will be distributed as indicated in the previous paragraph.

4.2.5 Operation mode in case of emergency

4.2.5.1 Operation mode in case of gas leak

The following describes the protocol in case of severe alarm from Gas Leak Detection.

4.2.5.1.1 ENGINEROOMS

o Genset running: an alarm of any gas detector above the gen-sets is send to the general

control system and triggers the following sequence:

Severe engine stop

Start of all ventilation fans at full capacity.

Shut off of the natural gas electrovalve located in the header that feeds all gen-sets

of the building. This electrovalve is located in the Regulation and Metering Gas

Station.

Activation of optical and acoustic alarms

o Genset off: an alarm of any gas detector above the gen-sets is send to the general

control system and triggers the following sequence:

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 33

Blocking of the gen-set start-up order

Start of all ventilation fans at full capacity

Shut off of the natural gas electrovalve located in the header that feeds all gen-sets

of the building. This electrovalve is located in the Regulation and Metering Gas

Station.

Activation of optical and acoustic alarms

4.2.5.1.2 OPERATION MODE IN R.M.S

The gas detector is monitoring continuously the CH4 content in the building. If presence

of CH4 is detected in the Regulation and Metering Station, the protocol will be the

following

o Regulation and Metering Station; the alarm is received by general control system and

triggers the following sequence

Blocking of all gen-sets start-up order

Shut off of the two natural gas electrovalves located in Regulation and

Measurement Gas Station that feeds each gensets buildings.

Activation of optical and acoustic alarms

4.2.5.2 Operation mode in case of fire detection

Following is described the protocol in case of fire alarm.

4.2.5.2.1 ENGINE PERFORMANCE

Infrared fire detectors are monitoring each building of gen-sets. If a fire is detected by any

of them, the group of affected gen-sets will follow the following protocol

o Genset running: the alarm of the fire detector installed in the gen-sets building is send

to the general control system and triggers the following sequence;

Severe stop for all gen-sets of the building,

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 34

Shut off of the natural gas electrovalve located in the header that feeds all gen-sets

of the building. This electrovalve is located in the Regulation and Measurement

Gas Station.

Activation of optical and acoustic alarms

o Genset off: the alarm of the fire detector installed in the gen-sets building is send to

the general control system and triggers the following sequence:

Blocking of the start-up order of gen-set in the building

Shut off of the natural gas electrovalve located in the header that feeds all gen-sets

of the building. This electrovalve is located in the Regulation and Measurement

Gas Station.

Activation of optical and acoustic alarms

4.2.5.2.2 OPERATION MODE IN R.M.S

Fire detectors are monitoring the Regulation and Metering Station. If a fire is detected the

protocol will be the following

o Regulation and Measurement Natural Gas Station; the alarm is received by general

control system and triggers the following sequence

Blocking of the start-up order of all gen-set of both buildings

Shut off of the two natural gas electrovalves located in Regulation and

Measurement Gas Station that feeds each gen-sets buildings.

Activation of optical and acoustic alarms

4.2.5.2.3 GENERAL SERVICES BUILDING

A fire detection system will be monitoring the building. In case of fire in the control room

the protocol will be the following:

o The fire alarm is received and sent to the general monitoring system

Blocking of the start-up order of all gen-set of both buildings

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 35

Shut off of the two natural gas electrovalves located in Regulation and

Measurement Gas Station that feeds each gensets buildings.

Activation of optical and acoustic alarms

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 36

5 ENGINE AND GENERATOR ASSEMBLY

The generators of the power plant are SFGM560 gas gensets of the Guascor-Dresser

Rand brand with a power capacity of 1MW.

These are 4-stroke Miller-cycle internal combustion engines with a 400Vac brushless

synchronous alternator coupled.

Main features are listed below. For further information see technical instructions

The plans 31-01, 31-02 and 31-11 to 31-14 layout drawings indicate the location and

installation position of the gensets in the plant with their closer auxiliary equipment.

Sizes of the genset and installation instructions can be consulted in the “Genset

Installation Manual”.

The gensets will be supplied with two configurations; cable output left side of the

alternator and cable output right side of the alternator. (13 gensets with one

configuration and 13 with the other) Depending of the configuration, alternator cable

connection bars will be at one or other side of the alternator. The alternator will be

identified with a label of the suited cable output position

At the moment of the installation of the gensets, the installer should be careful to put

each genset in the place of the layout where his cable output position would be facing the

electrical trench.

Beside the genset in itself and the electrical installation necessary to export the generated

power there are some auxiliary installations which are essential to keep the gensets in

working order. These installations are described in the chapters 6 to 10 of this

specification. These mechanical auxiliary installations of the gensets are:

Engine fuel (natural gas) supply system.

Engine cooling system.

Engine lube oil system.

Engine Flue system.

Engine room ventilation system.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 37

The circuits related to these systems are described in the Genset Flow Diagram (view

Plan 12-01).

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 38

5.1 ENGINE FEATURES

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 39

Tabla1.Engine power rating

The “Genset Installation Manual” includes more detailed information about the characteristics of the SFGM560, working and

installation procedure of these genset.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 40

5.2 ALTERNATOR FEATURES

Each GenSet has a synchronous generator to 400V, which is connected to the low voltage

terminal of a power transformer with a double port in this side: each transformer is

connected with two generators.

During normal operation,the installation will export all generated energy

Gensets are equipped with alternators LSAC 502 TR L8 C6S/4: main features are listed

below. For further data view “Alternator Information” attached to the Genset Installation

Manual.

Below we can see main electrical parameters of the alternator.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 41

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 42

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 43

6 ENGINE FLUE SYSTEM

The function of this circuit is basically to conduct safely the exhaust gases from the engine

to the outside of the building. Exhaust gas flow from each genset is of 5170 kg/h at full

power with an estimated temperature of 496ºC. At partial load the exhaust temperature

may be over 550ºC

The pipes and elements of the circuit have been designed to allow the evacuation of these

exhaust gases keeping a maximum admissible exhaust backpressure of 450mm of water

column.

The document IT-C-A-40-001e of the genset installation manual describes the

requirements that a correct installation should fulfill.

Design of the engine flue system is described in the following drawings:

12-01: General Flow Diagram.

13-04: Exhaust Gases P&I diagram.

61-02 to 61-05: Lay out of pipes (exhaust circuit in pink color)

62-02: Lay-out of pipes genset area typical detail (the exhaust circuit is shown in

pink color)

63-21: Exhaust Pipes design.

51-01 to 51-06: Metallic structures for silencer and conduits support

The main elements of these circuits are:

U-3: the exhaust adapter commonly called “the trousers”, because it resembles

some trousers. It’s supplied with exhaust flexibles as loose item of the genset and

has to be installed at the engine exhaust connection.

U-4: the exhaust silencer. Also supplied as loose item of the genset. Regarding

engine flue circuit should be taken in consideration that there will be four “typical

layouts” with different pipeline designs. Type A (for genset 1), type B (for gensets

2 to 13), type C (for genset 14) and type D (for gensets 15 to 26).

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 44

6.1 EXHAUST SILENCER

The pipeline for exhaust evacuation must be provided with a silencer (U-4 in the

drawings), which has the task of reduce the noise produced by the engine toward levels

allowed in current Standards.

Description of the exhaust silencer supplied by Guascor is included in the genset

installation manual. (view IC-C-D-40-002e and IT-O-A-2-001110-05e).

The exhaust silencers require supporting structures. These supporting structures are

shown in the drawings 51-01 to 51-06.

6.2 EXHAUST CHIMNEY

Exhaust line ends with vertical pipe protected from rain with a gate.

A sampling module has to be placed, according to current environmental standards, after

the silencer.

6.3 PIPING AND FITTINGS

Table 2.Exhaust chimney.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº B10 Rev. 00

SERVICE: ExhaustGases (EG)

NOMINAL PRESSURE: PIPING MATERIAL: Stainless steel CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 20º C TO: 1 bar; +502ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

PIPE

150 250 BE

EN 1127

Seamless Pipe EN ISO 1127 thickness

2mm; Material EN 1.4301 (AISI 304)

300 400 BE Seamless Pipe EN ISO 1127 thickness

3mm; Material EN 1.4301 (AISI 304)

FLANGES 150 400 Type A

(FF)

Flange LJ EN 1092-1, type 02, face A PN10; Material

Group 4E0 EN 10216-2

FITTINGS 150 400 Beveled

Elbows, tee, reducer and cap carbon steel Seamless

EN 10253-3 material EN 1.4301 (304)

Other accessories: malleable iron threaded ASA

B16.11, material EN 1.4301 (304), thread s/EN

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 45

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº B10 Rev. 00

SERVICE: ExhaustGases (EG)

NOMINAL PRESSURE: PIPING MATERIAL: Stainless steel CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 20º C TO: 1 bar; +502ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

10226

BOLTING

Screws EN 4014 (DIN931) Material Alloy Steel

quality 8.8

Nuts EN 4032 (DIN934) Material Alloy Steel quality

8.8

GASKET Gasket plate PN10 s/EN 1092; Asbestos free gasket

material like Klingersil 4430 or equivalent

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 46

6.4 DESIGN AND DEFINITION CHART

Table 3.Engine flue system.

GENSET

Tag Line DN NPS

(")

Mass Flow Rate

(kg/h)

Mass Flow Rate (Lb/h)

Temp.

(ºC)

Length (m)

Pressure

(mm.w.c g)

∆P(mm.w.c.)

01 6 "-B10-EG-0U3.01

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.01

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.01

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 01

283,678

02 6 "-B10-EG-0U3.02

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.02

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.02

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 02

283,678

03 6 "-B10-EG-0U3.03

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.03

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.03

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 03

283,678

04 6 "-B10-EG-0U3.04

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.04

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.04

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 04

283,678

05 6 "-B10-EG-0U3.05

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.05

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG- 35 14 5.170,0 11397,900 496,0 15 199 21,146

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 47

GENSET

Tag Line DN NPS

(")

Mass Flow Rate

(kg/h)

Mass Flow Rate (Lb/h)

Temp.

(ºC)

Length (m)

Pressure

(mm.w.c g)

∆P(mm.w.c.)

021.05 0 0 47

Total 05

283,678

06 6 "-B10-EG-0U3.06

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.06

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.06

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 06

283,678

07 6 "-B10-EG-0U3.07

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.07

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.07

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 07

283,678

08 6 "-B10-EG-0U3.08

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.08

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.08

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 08

283,678

09 6 "-B10-EG-0U3.09

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.09

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.09

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 09

283,678

10 6 "-B10-EG-0U3.10

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.10

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.10

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total

283,678

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 48

GENSET

Tag Line DN NPS

(")

Mass Flow Rate

(kg/h)

Mass Flow Rate (Lb/h)

Temp.

(ºC)

Length (m)

Pressure

(mm.w.c g)

∆P(mm.w.c.)

10

11 6 "-B10-EG-0U3.11

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.11

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.11

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 11

283,678

12 6 "-B10-EG-0U3.12

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.12

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.12

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 12

283,678

13 6 "-B10-EG-0U3.13

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.13

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.13

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 13

283,678

14 6 "-B10-EG-0U3.14

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.14

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.14

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 14

283,678

15 6 "-B10-EG-0U3.15

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.15

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.15

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 15

283,678

16 6 "-B10-EG- 15 6 2.585,0 5698,9502 496,0 15 450 251,659

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 49

GENSET

Tag Line DN NPS

(")

Mass Flow Rate

(kg/h)

Mass Flow Rate (Lb/h)

Temp.

(ºC)

Length (m)

Pressure

(mm.w.c g)

∆P(mm.w.c.)

0U3.16 0 0 34

16 "-B10-EG-021.16

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.16

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 16

283,678

17 6 "-B10-EG-0U3.17

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.17

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.17

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 17

283,678

18 6 "-B10-EG-0U3.18

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.18

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.18

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 18

283,678

19 6 "-B10-EG-0U3.19

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.19

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.19

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 19

283,678

20 6 "-B10-EG-0U3.20

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.20

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.20

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 20

283,678

21 6 "-B10-EG-0U3.21

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG- 40 16 5.170,0 11397,900 496,0 15 78 10,873

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 50

GENSET

Tag Line DN NPS

(")

Mass Flow Rate

(kg/h)

Mass Flow Rate (Lb/h)

Temp.

(ºC)

Length (m)

Pressure

(mm.w.c g)

∆P(mm.w.c.)

021.21 0 0 47

14 "-B10-EG-021.21

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 21

283,678

22 6 "-B10-EG-0U3.22

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.22

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.22

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 22

283,678

23 6 "-B10-EG-0U3.23

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.23

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.23

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 23

283,678

24 6 "-B10-EG-0U3.24

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.24

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.24

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 24

283,678

25 6 "-B10-EG-0U3.25

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.25

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG-021.25

350

14 5.170,0

0 11397,900

47 496,0 15 199 21,146

Total 25

283,678

26 6 "-B10-EG-0U3.26

150

6 2.585,0

0 5698,9502

34 496,0 15 450 251,659

16 "-B10-EG-021.26

400

16 5.170,0

0 11397,900

47 496,0 15 78 10,873

14 "-B10-EG- 35 14 5.170,0 11397,900 496,0 15 199 21,146

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 51

GENSET

Tag Line DN NPS

(")

Mass Flow Rate

(kg/h)

Mass Flow Rate (Lb/h)

Temp.

(ºC)

Length (m)

Pressure

(mm.w.c g)

∆P(mm.w.c.)

021.26 0 0 47

Total 26

283,678

The exhaust gas pipes are designed in the drawings 63-021.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 52

7 ENGINE COOLING SYSTEM

The function of this system is to dissipate the heat generated by engines internal

combustion while gensets are running. Treated water is used as coolant fluid. The

SFGM560 gensets have a double cooling circuit. A main high temperature (HT) circuit is

responsible for cooling most engine components. A second circuit with lower

temperature (LT) is used to cool the air/fuel mixture and the oil cooler.

In the case of a SFGM560 genset at full load the HT circuit needs to dissipate 524kW of

heat power while the LT circuit needs to dissipate 179kW. Design temperature for these

circuits is 90ºC for the HT and 55ºC for the LT circuits.

The document IT-C-A-20-003e of the genset installation manual describes general

information about the cooling system for Guascor engines.

In this project cooling is done by means of air coolers. The air coolers are from the

double core type, which allow with the same cooler to dissipate energy from two

independent circuits of different temperature. Electrical pumps will impulse the water

from the engine to the air coolers and back. The cooling system includes thus two

independent closed circuits filled with pressurized water.

The cooling water has to comply the requirements of the product information IO-C-M-

20-001e (Cooling Water Quality and Treatment).

Design of the engine cooling system is described in the following drawings:

12-01: General Flow Diagram.

13-01: Engine Cooling System P&I diagram. Note that in this drawing is shown the

scope of the “Pump set” or “Pump kit” already supplied and assembled from

Guascor factory.

60-02: Lay out of pipes section (cooling circuits in green colour)

61-02 to 61-05: Lay out of pipes (cooling circuits in green colour)

62-01: Lay-out of pipes air cooler typical detail (green colour)

62-02: Lay-out of pipes genset area typical detail (green colour)

63-01,-02: HT circuit pipes design.

63-04,-05: LT circuit pipes design.

The main elements of these circuit are:

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 53

P-1/P-2: centrifugal pumps for the HT and LT circuits. These pumps will be

installed in a “Pump kit” that will be installed attached to genset bedplate. This kit

will be already supplied mounted from Guascor’s facilities. (in the first 8 gensets

supplied. the components of this kit will be supplied as loose items and have to be

mounted at factory. The drawing of this kit is included in the genset installation

manual (Ref. 40.20.E80))

TK-2/TK-3: Expansion vessels.

E-1: Air cooler.

7.1 ENGINEERING BASIS OF DESIGN

This project was completed in compliance with the following standards:

UNE-EN ISO 15607 Specification and qualification of welding procedures for

metallic materials

UNE-EN 287 Qualification test of welders

UNE-EN 25817 Arc-welded joints in steel. Guidance on quality levels for

imperfections (ISO 5817:1992).

UNE-EN ISO 13920 Welding. General tolerances for welded constructions.

Dimensions for lengths and angles. Shape and position. (ISO 13920:1996).

ASME Code

UNE-EN 10255 Non-Alloy steel tubes suitable for welding and threading -

Technical delivery conditions

UNE-EN 10216 Seamless steel tubes for pressure purposes - Technical delivery

conditions

UNE-EN ISO 1127 Stainless steel tubes. Dimensions, tolerances and conventional

masses per unit length

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 54

7.2 ELECTRICAL WATER PUMPS

Water flowing through each cooling circuit is pumped with the following features:

1) Main water circuit or high temperature circuit (one per engine):

Type .................................................................................................. centrifugal

Motor drive ........................................................................................ electrical

Flow (m3/h) .................................................................................................... 70

Nominal temperature (ºC) ......................................................................... 90

2) Auxiliary water circuit or low temperature circuit (one per engine):

Type .................................................................................................. centrifugal

Motor drive ........................................................................................ electrical

Flow (m3/h).................................................................................................... 25

Nominal temperature (ºC) ......................................................................... 55

Information regarding the technical specifications and installation instructions of the

pumps are included in the genset installation manual, IT-C-A-20-011e (Installation

Manual), IC-G-D-20-067e (data sheet HT circuit water pump) and IC-G-D-20-066e. (data

sheet LT circuit water pump).

7.3 EXPANSION VESSELS

In each one of the two water circuits, is provided an expansion tank to support the

volume increase of water with the temperature variations.

1) Main water circuit or high temperature circuit (one per engine)::

Thermal load (kW) .................................................................................... 524

Static pressure (bar) ................................................................................... 2,2

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 55

2) Secondary water circuit or low temperature circuit (one per engine):

Thermal load (kW) .................................................................................... 179

Static pressure (bar) ................................................................................... 2,2

The genset installation manual includes a document (IT-O-A-2-001110-07e) with the

expansion tank adaptation installation instructions.

7.3.1 Relief

In both cooling circuits, safety-relief valves will be installed at engine outlet, set to 3.5 bar

in order to ensure that this pressure is the maximum working pressure in these cooling

circuits.

7.4 DOUBLE CORE AIR COOLER

A double core air cooler will be installed in each engine to dissipate the heat input in main

and auxiliary cooling circuits and resulting from flue gases generated during engine

operation.

1. Type .................................................................................... Double core air cooler

2. Main circuit

i. Thermal load (kW) .................................................................. 524

ii. Flow (m3/h)................................................................................... 70

iii. Range of temperature (ºC) ................................................. 90/83

3. Auxiliary circuit

i. Thermal load (kW) .................................................................. 179

ii. Flow (m3/h)................................................................................... 25

iii. Range of temperature (ºC) ................................................. 62/55

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 56

The genset installation manual includes following information regarding the air coolers:

IT-C-20-016e- Installation and user manual for Guascor standard dry-coolers.

76.73.625- Drawing of the supplied air coolers

IT-G-A-20-020e – User and installation manual for Standard air coolers. (TGR

model)

7.5 PIPING& FITTINGS

Table 4.Auxiliary circuit specification.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº S01 Rev. 00

SERVICE: Cooling water (CW),

NOMINAL PRESSURE: PIPING MATERIAL: stainless steel CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

PIPE 15 250 BE EN 1127

Seamless Pipe EN ISO 1127 thickness

2mm; Material EN 1.4301 (AISI 304)

FLANGES 32 250 Type A

(FF)

Flange LJ EN 1092-1, tipo 04, cara A PN10;

AluminumMaterial

FITTINGS 15 250 BE

Elbows, tee, reducer and cap carbon steel EN

10253-3; material EN 1.4301 (AISI 304).

Other accessories: malleable iron threaded ASA

B16.11, material AISI 304, thread s/EN 10226

BOLTING

Screws EN 4014 (DIN931) Alloy Steel Material

,quality 5.6

Nuts EN 4032 (DIN934) Alloy SteelMaterial quality

5.6

GASKET Gasket plat PN10 s/EN 1092; Asbestos-free gasket

material, Klingersil 4430 or equivalent

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 57

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº S01 Rev. 00

SERVICE: Cooling water (CW),

NOMINAL PRESSURE: PIPING MATERIAL: stainless steel CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

VA

LV

ES

BALL

15 25 female

thread Body and ball EN 10213-

4 1.4408 (316) Dimensions as EN 1983

2 pieces

Full bore

Drive lever 32 40 Flanged

Body cast iron EN-GJL-

250; stainless ball ;

length EN558-1 Series

27

BUTTERFLY

50 150

lug Dry Lever cast iron EN-GJL-

250; length EN558-1

Series 20 200 250

Manual wheel type

(Reduction gear operate )

CHECK

15 40 Wafer disk Cast iron EN-GJL-250 disk

andstainless spring

50 250 Wafer Dual plate Body and plates cast iron EN_GJL-

250; Length EN558-1 series 16

Table 5.Main circuit specification.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº A10 Rev. 00

SERVICE: Natural Gas (NG)& Cooling Watert (CW)

NOMINAL PRESSURE: PIPING MATERIAL: Carbon Steel

CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE DN (mm)

ENDS DESCRIPTION FROM TO

PIPE

15 40 PE EN 10255

(DIN 2440)

Seamless Pipe EN 10255 medium

series M; Material EN 1.0026 S195T

50 250 BE EN 10216

(DIN 2448)

Seamless Pipe EN 10216-2 series 1

normalized thickness; Material

P235GH EN 1.0254

FLANGES 32 250 Type A

(FF)

Flange SW EN 1092-1, type 01, face A PN10;

Material P235GH EN 10216-2

FITTINGS 15 250 Beveled

Elbows, tee, reducer and cap carbon seamless steel

EN 10253-1 material EN P235TR1 (st 37).

Other accessories: malleable iron threaded ASA

B16.11, material A-105, thread s/EN 10226

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 58

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº A10 Rev. 00

SERVICE: Natural Gas (NG)& Cooling Watert (CW)

NOMINAL PRESSURE: PIPING MATERIAL: Carbon Steel

CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE DN (mm)

ENDS DESCRIPTION FROM TO

BOLTING

Screws EN 4014 (DIN931) Alloy SteelMaterial,

quality 5.6

Nuts EN 4032 (DIN934) Alloy Steel Material,

quality 5.6

GASKET Gasket plate PN10 s/EN 1092; Asbestos free gasket

material like Klingersil 4430 or equivalent.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 59

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº A10 Rev. 00

SERVICE: Natural Gas (NG)& Cooling Watert (CW)

NOMINAL PRESSURE: PIPING MATERIAL: Carbon Steel

CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE DN (mm)

ENDS DESCRIPTION FROM TO

VA

LV

ES

BALL

15 25 female

thread Body and ball EN 10213-

4 1.4408 (316) Dimensions as EN 1983

2 pieces

Full bore

Drive lever 32 40 Flanged

Body cast iron EN-GJL-

250; ball inox. ; length

EN558-1 Series 27

BUTTERFLY

50 150

lug Dry Lever cast iron EN-GJL-

250; length EN558-1

Series 20 200 250

Manual wheel type

(Reduction gear operate )

CHECK

15 40 Wafer disk Cast iron EN-GJL-250 disk

andstainless spring.

50 250 Wafer Dual plate Body and plates cast iron EN_GJL-

250; Length EN558-1 series 16

FILTERS

15 25 female

thread

Tipe Y

Cast iron EN_GJL-250, sieve steel.

32 150 Flanged

Body cast iron EN_GJL-250,

Stainless Sieve; Length EN558-1

series 1

7.6 TESTING & INSPECTION

For the final acceptance of the in site assembly of pipelines installations, a hydraulic

pressure test is needed, considering each circuit as whole system. Test pressure will be

1.5 times the design pressure.

Before the hydrostatic test, equipment will be isolated in flanges using all the needed

elements for it(by-pass, closures, blind flanges, gaskets, etc..)

After pressure test, there will be a final cleaning of pipes, inside and outside of each one.

Once the hydrostatic test has finished, installation will be emptied in order to remove

metallic chips and dirt in line. Finally, before proceeding to final filling of each hydraulic

circuit, water is circulated by pumps, with basket filters placed at the entrance of each

equipment to protect them (one per pump, exchanger, genset, expansion tank, etc.).

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 60

7.7 DESIGN & DEFINITION CHART

Table 6.Water cooling circuit.

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

01 5 "-S01-CW-001.01 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.01 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.01 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.01 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.01 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.01 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.01 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.01 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.01 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.01 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

02 5 "-S01-CW-001.02 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.02 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.02 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.02 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.02 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.02 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.02 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 61

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

3 "-S01-CW-005.02 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.02 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.02 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

03 5 "-S01-CW-001.03 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.03 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.03 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.03 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.03 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.03 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.03 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.03 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.03 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.03 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

04 5 "-S01-CW-001.04 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.04 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.04 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.04 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.04 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.04 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.04 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.04 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 62

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

1 1/2"-A10-CW-005.04 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.04 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

05 5 "-S01-CW-001.05 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.05 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.05 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.05 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.05 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.05 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.05 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.05 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.05 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.05 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

06 5 "-S01-CW-001.06 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.06 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.06 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.06 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.06 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.06 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.06 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.06 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.06 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 63

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

2 "-A10-CW-008.06 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

07 5 "-S01-CW-001.07 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.07 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.07 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.07 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.07 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.07 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.07 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.07 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.07 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.07 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

08 5 "-S01-CW-001.08 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.08 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.08 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.08 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.08 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.08 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.08 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.08 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.08 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.08 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 64

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

09 5 "-S01-CW-001.09 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.09 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.09 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.09 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.09 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.09 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.09 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.09 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.09 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.09 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

10 5 "-S01-CW-001.10 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.10 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.10 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.10 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.10 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.10 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.10 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.10 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.10 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.10 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

11 5 "-S01-CW-001.11 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 65

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

5 "-S01-CW-002.11 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.11 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.11 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.11 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.11 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.11 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.11 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.11 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.11 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

12 5 "-S01-CW-001.12 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.12 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.12 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.12 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.12 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.12 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.12 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.12 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.12 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.12 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

13 5 "-S01-CW-001.13 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.13 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 66

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

3 "-A10-CW-003.13 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.13 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.13 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.13 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.13 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.13 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.13 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.13 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

14 5 "-S01-CW-001.14 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.14 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.14 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.14 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.14 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.14 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.14 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.14 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.14 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.14 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

15 5 "-S01-CW-001.15 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.15 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.15 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 67

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

3 "-A10-CW-002.15 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.15 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.15 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.15 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.15 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.15 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.15 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

16 5 "-S01-CW-001.16 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.16 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.16 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.16 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.16 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.16 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.16 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.16 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.16 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.16 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

17 5 "-S01-CW-001.17 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.17 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.17 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.17 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 68

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

3 "-A10-CW-001.17 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.17 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.17 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.17 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.17 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.17 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

18 5 "-S01-CW-001.18 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.18 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.18 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.18 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.18 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.18 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.18 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.18 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.18 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.18 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

19 5 "-S01-CW-001.19 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.19 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.19 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.19 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.19 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 69

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

2 "-A10-CW-004.19 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.19 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.19 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.19 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.19 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

20 5 "-S01-CW-001.20 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.20 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.20 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.20 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.20 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.20 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.20 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.20 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.20 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.20 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

21 5 "-S01-CW-001.21 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.21 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.21 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.21 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.21 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.21 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 70

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

3 "-S01-CW-004.21 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.21 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.21 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.21 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

22 5 "-S01-CW-001.22 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.22 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.22 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.22 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.22 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.22 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.22 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.22 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.22 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.22 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

23 5 "-S01-CW-001.23 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.23 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.23 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.23 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.23 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.23 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.23 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 71

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

3 "-S01-CW-005.23 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.23 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.23 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

24 5 "-S01-CW-001.24 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.24 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.24 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.24 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.24 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.24 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.24 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.24 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.24 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.24 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

25 5 "-S01-CW-001.25 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.25 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.25 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.25 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.25 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.25 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.25 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.25 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 72

GENSET Tag Line D

N

NP

S ("

)

Vo

lum

etri

c

flo

w r

ate

(m3

/h)

Vo

lum

etri

c

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

)

Pre

ssu

re

(psi

)

Tem

p. (

ºC)

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

∆P

(m.w

.c.)

∆P

(b

ar)

∆P

(%

)

1 1/2"-A10-CW-005.25 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.25 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

26 5 "-S01-CW-001.26 125 5 70 2507 3,50 87,02 90,00 34,29 1,35 1,06 0,10 1,73%

5 "-S01-CW-002.26 125 5 70 2472 3,50 87,02 90,00 29,79 1,34 0,65 0,06 1,06%

3 "-A10-CW-003.26 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-002.26 80 3 70 2472 3,50 87,02 90,00 3,34 3,63 0,51 0,05 0,84%

3 "-A10-CW-001.26 80 3 70 2507 3,50 87,02 90,00 3,34 3,65 0,51 0,05 0,84%

2 "-A10-CW-004.26 50 2 25 918 3,50 87,02 55,00 12,76 2,98 4,75 0,47 7,77%

3 "-S01-CW-004.26 80 3 25 918 3,50 87,02 55,00 27,72 1,23 0,55 0,05 0,91%

3 "-S01-CW-005.26 80 3 25 883 3,50 87,02 55,00 27,72 1,22 0,56 0,05 0,91%

1 1/2"-A10-CW-005.26 40 1 1/2 25 883 3,50 87,02 55,00 3,4 5,05 1,80 0,18 2,94%

2 "-A10-CW-008.26 50 2 25 918 3,50 87,02 55,00 3,38 2,98 0,52 0,05 0,85%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 73

8 ENGINE LUBE OIL SYSTEM

The function of this system is to ensure oil is available in all the lubricating circuits of the

engine, so that oil pressure quickly builds up a sufficient level for correct operations in

those applications where the engine is expected to develop its full power after the start

command.

For this application a single prelubrication process of 10 minutes is recommended prior

to any cold start operation. This operation is done with an electrical pump which is

supplied installed in an external oil tank of 300L. It’s a 24Vdc pump, thus it will be feed

from genset batteries allowing a start in a blackout condition of the plant. Once the

genset is started the mechanical oil pump of the genset will build up the oil pressure of

the engine.

Lube oil system includes four lines for connection of the engine and Lubricant oil tank.

The engine has three openings to connect the lubrication:

1. Filling

2. Pre-lubrication

3. Emptying

Connections are implemented under polyethylene ¾” pipes.

System includes a multifunctional pump with a set of valves defining the function to

perform. In normal operation the valves will allow the prelube operation, but the pump

may be used also to fill the engine with oil or empty it, being useful for the oil change

operations.

Technical instructions will be provided in further information for operation of this system.

The oil recommended for the lubrication is the Guascor Motoroil 3040 Plus Lube Oil for

Natural Gas-Fuelled and Ethanol engines.

Design of the oil prelube system is described in the following drawings:

12-01: General Flow Diagram.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 74

13-02: Lube Oil P&I diagram.

62-04: Lay out of pipes Lube Oil Typical Detail

Genset installation manual includes also information about the oil tank, automatic

engine oil level controller and oil level indicator.

Table 7.Lube oil specification.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº PE2 Rev. 00

SERVICE: Lube oil (LO)

NOMINAL PRESSURE: PIPING MATERIAL:

Multilayered Plastic

polymer/aluminium

(Al)/crosslinked

polyethylene pipes

(PE-X) CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 20 bar; 20º C TO: 10 bar; +95ºC

ITEM SIZE ENDS DESCRIPTION

FROM TO

PIPE 20x1,9mm PE Multilayered Plastic polymer/aluminium

(Al)/crosslinked polyethylene pipes (PE-X) UNE-EN

ISO 21003

FITTINGS 20x1,9mm

Copper; press fitting or Sliding sleeve Galadiator

system.

8.1 BLOWBY GASES EXHAUSTING SYSTEM

In parallel to oil prelube system it should be also be taking in consideration the blowby

gases exhausting system, also known as crankcase breathing.

The “blowby gases” are the portion of fire gases that enter the engine oil casing through

the combustion chamber sealing segments. These gases increase the pressure of the

crankcase casing over the atmospheric pressure and thus should be removed. They have

to be also conducted outside the engine room to avoid risks of explosion or fire, the

clogging of the filters or the creation of a polluted environment. The document of the

genset installation manual IT-C-A-25-001e makes a description of this installation.

These drawings show the design of this blowby exhausting circuit.

13-02: Lube Oil P&I diagram.

61-02 to 61-05: Lay out of pipes (blowby gases circuit in blue colour)

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 75

62-02: Lay-out of pipes genset area typical detail (blowby gases circuit is shown in

blue colour)

63-20: Blowby exhaust gases pipes design.

Table 8.Blowby exhaust gas pipe specification.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº S01 Rev. 00

SERVICE: Blowby Gases

NOMINAL PRESSURE: PIPING MATERIAL: stainless steel CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

PIPE 15 250 BE EN 1127

Seamless Pipe EN ISO 1127 thickness

2mm; Material EN 1.4301 (AISI 304)

FLANGES 32 250 Type A

(FF)

Flange LJ EN 1092-1, tipo 04, cara A PN10;

Aluminum Material

FITTINGS 15 250 BE

Elbows, tee, reducer and cap carbon steel EN

10253-3; material EN 1.4301 (AISI 304).

Other accessories: malleable iron threaded ASA

B16.11, material AISI 304, thread s/EN 10226

BOLTING

Screws EN 4014 (DIN931) Alloy Steel Material

,quality 5.6

Nuts EN 4032 (DIN934) Alloy SteelMaterial quality

5.6

GASKET Gasket plat PN10 s/EN 1092; Asbestos-free gasket

material, Klingersil 4430 or equivalent

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 76

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº S01 Rev. 00

SERVICE: Blowby Gases

NOMINAL PRESSURE: PIPING MATERIAL: stainless steel CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

VA

LV

ES

BALL

15 25 female

thread Body and ball EN 10213-

4 1.4408 (316) Dimensions as EN 1983

2 pieces

Full bore

Drive lever 32 40 Flanged

Body cast iron EN-GJL-

250; stainless ball ;

length EN558-1 Series

27

BUTTERFLY

50 150

lug Dry Lever cast iron EN-GJL-

250; length EN558-1

Series 20 200 250

Manual wheel type

(Reduction gear operate )

CHECK

15 40 Wafer disk Cast iron EN-GJL-250 disk

andstainless spring

50 250 Wafer Dual plate Body and plates cast iron EN_GJL-

250; Length EN558-1 series 16

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 77

9 ENGINE VENTILATION SYSTEM

9.1 DESCRIPTION OF THE ENGINE ROOM VENTILATION

The ventilation of the engine room should satisfy two fundamental functions:

Guarantee the environmental conditions, which permit the optimum performance

level of the engine and equipment.

Provide the most comfortable environmental conditions possible for the people

who have to work in the engine room.

In designing a ventilation system, the same importance should be given to the necessary

volume of air as to the flow direction.

The ventilation system must be able to provide sufficient combustion air and to remove

radiation heat from the rest of the facility.

Generally, the air flow direction in an engine room will match the following pattern

The entry of air in the engine room should be from the area furthest away from

any sources of heat.

The fresh air should be able to flow freely from the point of entry to the sources

of heat, in its circulation towards the point of exit.

The expulsion of hot air should be at a point directly above the most important

sources of heat, avoiding the intake of the exhaust gas.

Where the temperature of the engine room or, in particular, of the crankcase

gases return lines to the intake manifold is too low, the said lines must be heat-

insulated so as to prevent condensation in the said piping section.

In all cases, the hot air should be forced out of the engine room by means of an outlet

duct, without allowing it to mix with the fresh ventilation air.

The detailed information of the lay out and the ventilation system assembly is available in

the Annex (Ventilation System. Assembly Manual).

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 78

9.2 VENTILATION SYSTEM

9.2.1 Forced ventilation (pusher fan)

We recommend this ventilation system for all machine rooms in general. Both air inlet

and outlet depend on the location of the air intake filters and alternator, as the following

picture shows:

ALTERNATOR

SIDE

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 79

The air flow through each engine is guaranteed for a motor-fan located above

every single engine.

These fans will be flowing fresh air when the engine is running.

There is a circular duct mounted to the motor-fan in order to improve the fresh

air direction blowing through the Gensets.

9.2.2 Ventilation module feature

The Air input module will contain the following elements:

Plenum Dimensions ....................................................... 1,600x1,400x1,847 mm

Motor Driven Fan Model ................................................... S&P TGT 4/800 6/18

Flow Rate .............................................................................................. 25,000 m3/h

Airflow speed ............................................................................................... 13.7 m/s

Available Static Pressure .............................................................................. 150 Pa

Nominal Input ................................................................................................... 3 kW

Speed of Rotation .................................................................................... 1400 rpm

Voltage & Frequency ................................................................... 3P 400 V 50 HZ

Nominal Current .............................................................................................. 6.5 A

Degree of Protection ........................................................................................ IP55

Electrical insulation class ........................................................................................ F

Refer to the general drawing (35-02) for further information.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 80

10 NATURAL GAS FUEL SUPPLY

10.1 GENERAL DESCRIPTION

The Natural Gas is distributed inside the power plant through a pipelines network.

In the regulation and metering station (R.M.S.), the natural gas is filtered and adjusted to

appropriate pressure level, in order to provide at the engines the power needed for

electrical generation.

The R.M.S. is provided with a non continuous gas analyzer whose function is to monitor

CH4, O2 and CO2 content in natural gas, and the communications output will be through

digital modbus and 4-20 mA signal.

Also, 2 electrovalves will be installed at R.M.S. outlet, which will be actuated in case of

serious alarm caused by loss of gas quality, gas leakage or fire. This electrovalves will be

supplied by 24Vdc batteries set located at the R.M.S. control panel to allow their control

also in situations of black-out or power supply shortages.

After the R.M.S., natural gas is sent into the two power generation engine rooms through

pipe internal network. Every engine is fed from a manifold located outside the engine

room,it means that there is one pipe entering the building for each engine.

Head losses in pipes are allowed while the pressure level at the inlet of the feeding ramps

is adequate in order to ensure proper running of the engine.

These drawings show the design of the Natural Gas Fuel Supply circuits

12-01: General Flow Diagram.

13-03: Natural Gas P&I diagram.

61-01: Lay-out of pipes area GRMS

61-02 to 61-05: Lay out of pipes (natural gas circuit in red colour)

62-02: Lay-out of pipes genset area typical detail (natural gas circuit is shown in

red colour)

62-03: Section Pipes area GRMS

63-16 to 63-18: Natural gas pipes design.

65-01: General connection.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 81

10.1.1 Internal connection.

The Service Pipes includes the whole of pipelines and fittings between the Service Key

(main supply valve), excluding this, and the Buildings Key (shut off valves at the entrance

of engine rooms facility), including these, in case of gas receiver installations supplied from

distribution pipe network.

10.1.2 Service pipes

10.1.2.1 General features

The Service Pipes of Natural Gas involves the different gas pipes with its fittings and

auxiliary items between the Regulating and Metering Station (R.M.S.) and the gas train of

every engine.

The R.M.S. is located in the south side of the Power Plant. It has two pipe outlets to

provide natural gas, one for each engine room.

TheService Pipes is formed by the following stretches:

1) R.M.S. output:Stretch comprised between R.M.S. and the engine rooms

area. Both pipes run parallel each other and in a buried stretch for crossing

the road. Once the road is crossed, the pipes get out to the surface and runs

through an aerial stretch, above a lintel, up to the engine rooms.

2) Engine rooms: The pipes are separated, each one toward their own engine

room with a symmetric route. The pipes goes down to the ground at the

entrance of the engine rooms, where there are shut off valves (building keys)

to lock the gas supply.The pipe distribution in the engine rooms is through

an aerial stretch, 3 m above the ground and supported in metallic structures

fixed in the pillars of the building.

3) Gas supply to engines:Stretch between the pipe distribution and the gas

train of the engines. At the inlet of the gas train, there are a shut off valve to

isolate the engine from the gas supply.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 82

10.1.2.2 Calculations

10.1.2.2.1 INSIDE DIAMETER CALCULATION

The output pressure from the R.M.S. will be 3 bar g, and it will be the design pressure for

the gas distribution pipelines of the power plant.

The external gas service arrives at the power plant with a range between 10 and 40 bar g

so the design pressure will be 10 bar g because is the pressure that produces higher

velocities.

The procedure to calculate the inside diameter of the pipe is to establish an initial

diameter and apply the formula to determine the flow velocity and head loss to ensure

that the obtained values are according to the current Standards.

10.1.2.2.1.1 DESIGN ASSUMPTION

The design foundations are the following:

R.M.S. pressure output (bar g) ........................................................... 3

Max. Volumetric flow rate (Nm3/h):

Pipe distribution Engine Room 1 ........................................ 6.250,00

Pipe distribution Engine Room 2 ........................................ 6.250,00

Gas supply to engines (1-26) ........................................................ 481

Max. Design Velocity (m/s) ............................................................... 20

10.1.2.2.1.2 HEAD LOSS

The procedure to calculate the head loss in each stretch of the installation is through

applying the RENOUARD formula:

-4,821,822

B

2

A DQLS5,51PP

The parameters descriptions are as follow:

PA: Absolute pressure at the beginning of the stretch.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 83

PA- PB = Head loss (differential pressure between A and B)

S: Corrected density

Q: Volumetric flow rate (Nm3/h)

D: Pipe inside diameter (mm)

L: Length.

10.1.2.2.1.3 VELOCITY

The procedure to calculate the maximum velocity inside pipes is through applying the

following formula:

V = 378Q Z

P D 2

The parameters descriptions are as follow:

V: Velocity m/s

Q: Volumetric flow rate Nm3/h

Z: Compressibility factor

P: Absolute pressure (bar)

D: Inside diameter (mm)

10.1.2.2.1.4 PIPE THICKNESS CALCULATION

The procedure to calculate the minimum thickness of the pipe is through applying the

formula indicated in the Standard UNE 60309:

CFQ20

dP=e

e

The parameters descriptions are as follow:

P: Calculated absolute pressure (bar).

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 84

Qe: Yield strength of the pipe material (N/mm2).

e: Theoretical thickness of the pipe (mm).

d: Outside diameter of the pipe (mm).

F: Coefficient for calculations. Indicated in the Standard UNE 60305 = 0,4

C: Welding efficiency = 1

1) The minimum thickness of poliethylene pipes (HDPE) for gas are according to the

current standards so it is allowed to use in the specificated pressure range in the plant.

10.1.2.2.1.5 MEASUREMENT TABLE

The calculation results are shown in the following table.

As the table shows, the velocity values obtained in the calculations are under the

maximum velocity allowed by Standards for each stretch, 20 m/safter the R.M.S, and the

thickness of the selected pipes are above the minimum allowable thickness required by

the Standard.

The R.M.S. will adjust the pressure to 3 bar g, and thus this will be the nominal pressure

used for all gas pipelines installed in the plant.

The pipelines with tag “OTHER1, 2 or 3” correspond to the power plant main

connection of natural gas, before the R.M.S. For those pipelines the maximum velocity

allowed by the Standard is 30 m/s.

Gas supply at natural gas take-off will have a pressure between 10 and 40 bar g, and thus

design pressure for these pipelines will be 10 bar g as this is the pressure at which the

maximum flow rates are produced.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 85

Table9.Gas pipeline dimensions

Tag Line DN

NP

S ("

)

Flo

w R

ate

(Nm

³/h

)

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

g)

Pre

ssu

re

(psi

g)

Tem

p. º

C

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

Init

ialP

ress

ure

(b

ar a

) Fi

nal

P

ress

ure

(b

ar a

)

∆P

(m

bar

)

Pip

e Th

ickn

ess

(mm

)

Min

imu

mt

hic

knes

s

(mm

)

8 "-A300-NG-OTHER1 200 8 25.000 882.866,66 10 145,03 25 270,31 22,92 11,00 10,50 505,21 12,70 4,65

5 "-A300-NG-OTHER2 125 5 12.500 441.433,33 10 145,0333 25 10,62 28,28 11,00 10,95 53,91 9,52 2,97

5 "-A300-NG-OTHER3 125 5 12.500 441.433,33 10 145,0333 25 10,62 28,28 11,00 10,95 53,91 9,52 2,97

8 "-PE1-NG-017 200 8 6.250 220.716,66 3 43,51 25 20,32 18,75 4,00 3,99 12,93 11,90 -

8 "-PE1-NG-018 200 8 6.250 220.716,66 3 43,51 25 20,32 18,75 4,00 3,99 12,93 11,90 -

8 "-A10-NG-017 200 8 6.250 220.716,66 3 43,51 25 145,1 13,70 3,99 3,95 42,48 5,90 1,16

8 "-A10-NG-018 200 8 6.250 220.716,66 3 43,51 25 145,1 13,70 3,99 3,95 42,48 5,90 1,16

2 1/2"-A10-NG-16.1 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.2 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.3 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.4 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.5 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.7 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.8 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.9 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.10 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.11 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.13 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.14 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.15 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 86

Tag Line DN

NP

S ("

)

Flo

w R

ate

(Nm

³/h

)

Flo

w R

ate

(ft3

/h)

Pre

ssu

re

(bar

g)

Pre

ssu

re

(psi

g)

Tem

p. º

C

Equ

ival

ent

Len

gth

(m

)

Vel

oci

ty

(m/s

)

Init

ialP

ress

ure

(b

ar a

) Fi

nal

P

ress

ure

(b

ar a

)

∆P

(m

bar

)

Pip

e Th

ickn

ess

(mm

)

Min

imu

mt

hic

knes

s

(mm

)

2 1/2"-A10-NG-16.16 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.17 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.19 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.20 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.21 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.22 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.23 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.25 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

2 1/2"-A10-NG-16.26 65 2 1/2 481 16.978,20 3 43,51 25 16,14 9,18 3,95 3,94 8,19 2,90 0,40

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 87

10.1.2.3 Pipes & fittings specification.

The following table shows the material specifications for the pipes and fittings:

Table 10. Pipe specifications for internal gas supply.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº A10 Rev. 00

SERVICE: Natural Gas (NG)

NOMINAL PRESSURE: PIPING MATERIAL: Carbon Steel

CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

PIPE

15 40 PE EN 10255

(DIN 2440)

Seamless Pipe EN 10255 medium

series M; Material EN 1.0026 S195T

50 250 BE EN 10216

(DIN 2448)

Seamless Pipe EN 10216-2 series 1

normalized thickness; Material

P235GH EN 1.0254

FLANGES 32 250 Type A

(FF)

Flange SW EN 1092-1, type 01, face A PN10;

Material P235GH EN 10216-2

FITTINGS 15 250 Beveled

Elbows, tee, reducer and cap carbon steel Seamless

EN 10253-1 material EN P235TR1 (st 37).

Other accessories: malleable iron threaded ASA

B16.11, A-105material, thread s/EN 10226

BOLTING

Screws EN 4014 (DIN931) Alloy SteelMaterial,

quality 5.6

Nuts EN 4032 (DIN934) Alloy Steel Material

,quality 5.6

GASKET Gasket plat PN10 s/EN 1092; Asbestos free gasket

material like Klingersil 4430 or equivalent.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 88

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº A10 Rev. 00

SERVICE: Natural Gas (NG)

NOMINAL PRESSURE: PIPING MATERIAL: Carbon Steel

CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 9 bar; +120ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

VA

LV

ES

BALL

15 25 femaleth

read Body and ball EN 10213-

4 1.4408 (316) Dimensions as EN 1983

2 pieces

Full bore

Drive lever 32 40 Flanged

Body cast iron EN-GJL-

250; seamless ball ;

length EN558-1 Series

27

BUTTERFLY

50 150

lug DryLever castiron EN-GJL-

250; length EN558-1

Series 20 200 250

Manual wheel type

(Reduction gear operate )

CHECK

15 40 Wafer disk Cast iron body EN-GJL-250 disk

and stainless spring.

50 250 Wafer Dual plate Body and plates cast iron EN_GJL-

250; Length EN558-1 series 16

FILTERS

15 25 femaleth

read

Tipe Y

Body cast iron EN_GJL-250, sieve

steel.

32 150 Flanged

Cast iron body EN_GJL-250,

stainless sieve; Length EN558-1

series 1

Table 11.Gas supply at natural gas take-off.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº A300 Rev. 00

SERVICE: Natural gas (NG) NOMINAL PRESSURE: PIPING MATERIAL: Carbon Steel

CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 20º C TO: 50 bar; +50ºC

ITEM SIZE DN (mm)

ENDS DESCRIPTION FROM TO

PIPE 65 300 BE

Seamless Pipe XS ANSI B36.10; ASTM

A106Material

FLANGES 65 300 RF Flange WN 300# ANSI B16.5; Material ASTM A105

FITTINGS 15 250 BE ANSI B16.9, A234 WPBmaterial

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 89

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº A300 Rev. 00

SERVICE: Natural gas (NG) NOMINAL PRESSURE: PIPING MATERIAL: Carbon Steel

CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 20º C TO: 50 bar; +50ºC

ITEM SIZE DN (mm)

ENDS DESCRIPTION FROM TO

Other accessories: malleable iron threaded ASA

B16.11, material A-105

BOLTING Screws ANSI B18.2.1, A 193 B7material

Nuts ANSI 18.2.2, material A194 2H

GASKET Gasket flat 300# ANSI B16.21; Asbestos free gasket

material like Klingersil 4430 or equivalent.

Table 12.Buried gas pipelines.

PIPE MATERIAL

SPECIFICATIONS

SPECIFICATIONS

Nº PE1 Rev. 00

SERVICE: Natural gas (NG)

NOMINAL PRESSURE: PIPING MATERIAL: Polyethylene

(HDPE) CORROSION PERMISSIBLE:

SERVICE LIMITS FROM: 0 bar; 0º C TO: 7 bar; +60ºC

ITEM SIZE

ENDS DESCRIPTION FROM TO

PIPE 15 250 PE Polyethylene (HDPE) PE80 S5/SDR11 UNE EN

1555

FLANGES 32 250 Type A

(FF)

Flange LJ EN 1092-1, type 04, face A PN10;

Aluminum Material

FITTINGS 15 250 BE

Bend 90º PE80 S5/SDR11 But fusion

Flange adaptor; PE100 S5/SDR11

BOLTING

Screws EN 4014 (DIN931) Alloy Steel Material,

quality 5.6

Nuts EN 4032 (DIN934) Alloy Steel Material,

quality 5.6

GASKET Gasket plate PN10 s/EN 1092; PTFE Material

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 90

10.1.3 Engine gas trains

The description of the gas trains for the engines are shown in the plan 2.000553.040 of

the Genset Installation Manual

10.1.4 Identification of pipelines

The identification of gas pipelines will be according with the Standard UNE 1063and

which base color will be yellow.

10.2 ENGINEERING BASIS OF DESIGN

The installation for natural gas supply has been designed according to the following

standards and regulations:

UNE 60670, including all of its parts, Gas installations pipework supplied at

maximum operating pressure (MOP) up to and including 5 bar.

UNE 60620, including all of its parts, Natural gas receiving installations with

pressure supply over 5 bar.

UNE-EN 437, test gases – test pressures. Appliance categories.

UNE 1063, identification pipelines according to the fluid conveyed.

UNE 60305, steel gas pipelines, security areas and design factors.

UNE 60309, gas pipelines. Minimum wall thickness for steel pipes.

UNE 60311, gas supply systems. Pipelines for maximum operating pressure up to

and including 5 bar.

UNE-EN 1555, plastics piping systems for the supply of gaseous fuels. Polyethylene

(PE).

UNE-EN 12007, gas supply systems. Pipelines for maximum operating pressure up

to and including 16 bar.

2) Standards to take into account in the in site mechanical assembly of pipelines:

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 91

UNE-EN ISO 15607 Specification and qualification of welding procedures for

metallic materials.

UNE-EN 287 Qualification test of welders

UNE-EN 25817 Arc-welded joints in steel. Guidance on quality levels for

imperfections (ISO 5817:1992).

UNE-EN ISO 13920 Welding. General tolerances for welded constructions.

Dimensions for lengths and angles. Shape and position. (ISO 13920:1996).

ASME Code.

UNE-EN 10255 Non-Alloy steel tubes suitable for welding and threading -

Technical delivery conditions.

UNE-EN 10216 Seamless steel tubes for pressure purposes - Technical delivery

conditions.

UNE-EN ISO 1127 Stainless steel tubes. Dimensions, tolerances and conventional

masses per unit length.

10.3 TESTING & INSPECTIONS

Following test will be done in the natural gas installation:

1) Mechanical strength testing;

i) Fluid ................................................................... N2 or Air (according to EN 437)

ii) Test pressure .............................................................................................. 4,2 bar g

iii) Test time ............................................................................................................ 1hour

2) Tightness testing:

i) Fluid ..................................................................... N2or Air (according to EN 437)

ii) Test pressure .................................................................................... at least 1 bar g

iii) Test time ........................................................................................................... 6 hour

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 92

The test must be verified using an electronic or digital manometer of 0 to 10 bar range.

The time test could be of 10 minutes if the stretch is lower than 10 meters.

All components will be factory tested. However, a final test will be also carried out after

assembled on site.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 93

11 FIRE & GAS LEAK DETECTION SYSTEM

In this paragraph will be described the fire protection installed in the power plant.

The Fire gas & Gas leak detection system is described by the drawings 35-01 (layout of

detection equipment) and 27-02 (related electrical installations).The purpose of the

projected automatic fire detection system is to warn of the start of a fire in a timely and

efficient manner.

Basically, the fire detection system comprises the following elements as indicated in the

figure below:

A Sensors

B Control and signaling equipment

C Fire alarm devices

D Alarm buttons

E Fire alarm transmission device

F Fire alarm reception area

G Control of automatic fire protection systems

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 94

H Automatic fire protection system

J Malfunction warning transmission device

K Malfunction warning reception area

l Power supply

Some of the elements indicated represent the most important parts of a fire detection

system. These are:

a) Fire sensors (fire alarm devices) and manual alarm button that are distributed

around the site and are capable of indicating the presence of a fire in its initial

phase.

b) Fire detection centre (control and signaling equipment) where the alarms are

centralized and a series of programmed preventive actions are carried out:

Acoustic transmission of alarm or any operation that may be started by

means of electrical transmission.

Transmission of emergency signals to a remote position located on the

Control Desk in order to control the site using graphs.

The installation of all of this equipment is subject to the standards and regulations that

describe in which type of premises their implementation is necessary, as well as the type

of sensor and their location being the most appropriate according to the nature of the

risks to be protected.

Following recommendations of a general nature, the installation of fire detection and

alarm shall comply with the following conditions:

a) There will be manual fire alarm buttons in the areas of circulation and inside

the premises.

b) Sensors that are appropriate to the type of fire expected inside the premises

and in the circulation areas shall be provided.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 95

The sensors shall be smoke sensors except in those areas in which thus type

of sensor could provoke false alarms, in which case heat or flame sensors will

be installed.

c) The control and signaling equipment shall have a device that will allow manual

and automatic activation of the alarm systems and will be located in a

permanently guarded place.

The automatic activation of the alarm systems must be adjustable so that it

takes place a maximum of 5 minutes after the activation of a sensor or a

button.

d) The alarm warning system will be acoustic and shall be comprised of two tone

sirens that will allow the transmission of local alarms and of a general alarm.

11.1 BASIS OF DESIGN

This project was completed in compliance with the following standards:

Technical Edification Code -CTE-. «Basic Document: SI Safety in the case of a

fire». ROYAL DECREE 314/2006, of 17th March 2006.

Regulation on Fire Protection Installations. ROYAL DECREE 1942/ 5th November

1993.

Regulation on Fire Safety in Industrial Establishments. ROYAL DECREE 2267/2004

of 3rd December 2004.

UNE Standard 23.007/1. Fire detection and alarm systems. Part 1. Introduction.

UNE Standard 23.007/2. Fire detection and alarm systems. Part 2. Control and

signaling equipment.

UNE Standard-EN 54/3. Fire detection and alarm systems. Part 3. Fire alarm

devices. Sound alarm devices.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 96

UNE Standard 23.007/4. Fire detection and alarm systems. Part 4. Power supply.

UNE Standard-EN 54/5. Fire detection and alarm systems. Part 5. Heat sensors.

Point sensors.

UNE Standard 23.007/7. Fire detection and alarm systems. Part 7. Smoke sensors.

Point sensors that work according to the principle of diffuse light, transmitted light

or by ionization.

UNE Standard 23.007/9. Fire detection and alarm systems. Part 9. Sensitivity tests

in households.

UNE Standard-EN 54/10. Fire detection and alarm systems. Part 10. Flame

sensors. Point sensors.

UNE Standard-EN 54/11. Fire detection and alarm systems. Part 11. Manual alarm

buttons.

UNE Standard-EN 54/12. Fire detection and alarm systems. Part 12. Line sensors

that use an optic light beam.

UNE Standard 23.007/13. Fire detection and alarm systems. Part 13. Evaluation of

the compatibility of the components of a system.

UNE Standard 23.007/14. Fire detection and alarm systems. Part 14. Planning,

design, installation, implementation, use and maintenance.

UNE Standard-EN 54/16. Fire detection and alarm systems. Part 16. Control of

the alarm by voice and indicating equipment.

UNE Standard-EN 54/17. Fire detection and alarm systems. Part 17. Short circuit

isolators.

UNE Standard-EN 54/18. Fire detection and alarm systems. Part 18. Input /Output

devices.

UNE Standard EN 54/20. Components of the automatic fire detection systems.

Part 20. Smoke aspiration sensors.

UNE Standard-EN 54/21. Fire detection and alarm systems. Part 21. Alarm

transmission equipment and warnings of failures.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 97

UNE Standard-EN 54/24. Fire detection and alarm systems. Part 24. Components

of the voice alarm systems. Loudspeakers.

UNE Standard-EN 54/25. Fire detection and alarm systems. Part 25. Components

that use radioelectrical links.

UNE Standard-EN 12.094/1. Fixed fire protection systems. Components for fire

extinguishing using gas agents. Part 1. Test requisites and methods for automatic

and electrical control and delay devices.

UNE Standard-EN 12.094/3. Fixed fire protection systems. Components for fire

extinguishing using gas agents. Part 1. Test requisites and methods for manual trip

and shutdown devices.

Municipal ordinances and standards from the regional authorities on Fire

Protection Conditions.

Low Voltage Electrotechnical Regulation and Complementary Technical

Instructions.

The system will also be designed in accordance with the following recommendations:

Technical Rule CEPREVEN R.T.3.-DET. Technical Rule for Automatic

Fire Detection installations.

11.2 DESIGN & DEFINITION

11.2.1 Smoke and heat point sensors

The number of smoke and heat point sensors is determined in accordance with the

stipulations of UNE Standard 23007/14, Annex A.

The sensors must be located such that their sensitive elements are less than 5% from the

top of the room. Due to the possible existence of a cold limit layer, the sensors shall not

be embedded in the ceiling. The heat sensors must be located below under the ceiling.

For point sensors the indication is that they must be distributed in such a way that no

point of the ceiling or of the roof is at a horizontal distance from the sensor greater than

the values of Dmax indicated in table A.1.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 98

If there are unfavourable temperature gradients on the protected surface, the plume of

cloud rising from the fire can be suffocated and form a layer before reaching the ceiling. If

the height of this layer is foreseeable, sensors can be installed at the expected

stratification height as well as those sensors that are installed near the ceiling.

In narrow corridors and ceiling spaces that have a width of less than 3 metres, the

distances between sensors may be as follows:

- For heat sensors, up to 10m (5m for detection with coincidences or for

extinguishing systems);

- For smoke sensors, up to 15m (11m for detection with coincidences or

7.5m for extinguishing systems).

The horizontal distance between the sensor and the wall or the ceiling must not be

greater than half of the above mentioned distances.

The maximum area of authorized monitoring must not be greater than the added values

indicated in Table A.1.

Table 13.Distribution of smoke and heat point sensors.

Surface of the

premises in m2

Type of sensor

Height of the

premises in m

Slope ≤ 20º Slope >20º

Sv (m2) Dmax (m) Sv (m2) Dmax (m)

SL ≤ 80 UNE-EN54/7 h ≤ 12 80 6.6 80 8.2

SL > 80 UNE-EN54/7 h ≤ 6 60 5.7 90 8.7

6 < h ≤ 12 80 6.6 110 9.6

SL > 30

UNE-EN54/5, class A1 h ≤ 7,5 20 3.5 40 6.5

UNE-EN54/5, class A2,

B, C, D, E, F, G h ≤ 6 20 3.5 40 6.5

SL ≤ 30

UNE-EN54/5, class A1 h ≤ 7,5 30 4.4 30 5.7

UNE-EN54/5, class A2,

B, C, D, E, F, G h ≤ 6 30 4.4 30 5.7

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 99

Dmax

Incorrectdistribution Normal distribution Reduceddistribution

Key

Sv Monitored surface

Dmax Max.horizontal distance from any point to the sensor

Dmax

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 100

The SV monitoring area must be corrected according to the type of risk. Thus, the area

protected by sensors used in coinciding detection must be reduced by at least 30% and

for sensors aimed at activating a fixed extinguishing system it must be reduced by at least

50%.

A space of at least 0.5m must be left in all directions below each sensor.

11.2.2 Linear sensors

The lineal sensors comply with UNE 23007/12.

The distance between the emitter and the receiver shall vary between 10 metres as a

minimum and 100 m as a maximum.

The maximum distance of lateral cover of the ray is that indicated by the following table

extracted from UNE 23007.14:

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 101

Table 14.Maximum distance.

Type of

sensor Height of premises

in m

Distance in m,

D

Distance in m,

A

Maximum covered surface

in m2

Slope ≤

20º

Slope

>20º

Dv (m) Dv (m)

UNE-

EN54/12 h ≤ 6 100 12 1200 0.3 a 0.5 0.3 a 0.5

UNE-

EN54/12 6 < h ≤ 12 100 13 1300 0.4 a 0.6 0.5 a 0.8

UNE-

EN54/12 12 < h ≤ 25 100 15 1500 0.4 a 0.6 0.5 a 0.8

Key

D, maximum distance covered by the beam from the barrier

A, maximum distance between to lineal sensors

Dv, vertical distance from the beam of the barrier to the ceiling

In order to calculate the required number of elements we will have to take into account

their maximum area of coverage and the maximum lateral distance between sensors.

In the case of sloped ceilings, the lateral distance between lineal sensors will start to

count from the lintel where one device must be placed and measure between barriers

using it as a reference.

For buildings with ceiling with special forms such as saw tooth ceilings, a set of sensors

shall be installed for each tooth.

The sensor will be located at a distance from the ceiling between 0.3 and 0.8 m depending

on the height of the building, in order to avoid the thermal cushion of hot air.

11.2.3 Buttons

The distribution of buttons shall take into account the rules laid down in UNE-23007-14:

The buttons are located in such a way that it will not be necessary to move more

than 25 metres to reach one. In those premises in which the users may be

disabled, this distance should be reduced.

They are located at between 1.2 and 1.6 m from the floor.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 102

11.2.4 Sound alarms

These elements are distributed in such a way that guarantees the minimum sound levels

expressed in UNE Standard 23007-14.

The sound level of the alarm shall be at least 65 dB(A) or 5 dB(A) above any

sound that is expected to last more than 30 s.

If the idea of the alarm is to wake people who are asleep, the minimum sound

level shall be 75 dB(A).

This minimum level must be guaranteed in all parts of the enclosure.

The sound level must not exceed 120 dB(A) at any point which is more than 1m

from the device.

The number of devices to be installed will be determined in accordance with the

following:

The number of sirens/bells must be sufficient to reach the above mentioned sound level.

The minimum number of devices will be two per building and one per fire sector.

In order to avoid excessive levels in some areas it is preferable to place more sirens with

less power.

The tone used by the sirens to warn of a fire must be exclusive for that purpose.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 103

11.2.5 Cabling

The following specifications indicated in the Electrotechnical Low Voltage Regulation

were taken into account in the installation of the cabling required for the connection of

the elements with the control desk.

A braid shield wire with the following characteristics will be used as a communications

bus for the smart elements:

cable: braided and shielded for two wires.

braid: with 20 to 40 turns per meter.

shield: Mylar aluminum with drain wire.

total resistance of the loop cable: less than 40 ohms.

capacity: less than 0.5 microfarads.

The cable section was selected in accordance with the following table:

Length of loop Section

up to 1500 metres 2 x 1.5 mm2

up to 2200 metres 2 x 2.5 mm2

The power cable of the auxiliary equipment is a conventional single wire type. In order to

calculate the section required we will calculate the voltage drops in accordance with the

formula:

E=2PL/KSv

Where: e: voltage drop in volts

P: is power P= V x i

L: is the length of the cable in meters

k: for copper 56 and for aluminum 35

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 104

s: section of the cable in mm2.

V: voltage in volts.

11.2.6 Power and battery calculations

Power sources:

The UNE standards require the system to be equipped with a double power supply. This

is normally resolved by supplying the system directly from the general electrical grid of

the building and by using a group of batteries connected to a charger as standby. These

will be used if the main system fails.

Duration: according to UNE the emergency power supply in the case of failure shall

meet the requirements of the following table:

CONDITIONS STANDBY ALARM

Always 72 hours 30 min.

There is a local or remote monitoring

service with a commitment to repair in 24

h.

24 hours 30 min.

There are spare parts on site and

personnel and an emergency generator 4 hours 30 min.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 105

Calculation of the capacity:

The following formula was used to calculate:

Cmin = (A1 x t1 + A2 x t2) ampshour

where: t1 and t2 are the operating times on idle and on alarm respectively.

A1 and A2 are the consumptions of the system in amps on standby and

alarm..

25% extra should be considered for the ageing of the batteries which means that the total

capacity will be: 1.25 x Cmin.

For the calculation of A1, we add the consumptions of all the elements that make up the

detection system and in order to determine A2, we calculate the consumption in alarm of

all the elements that intervene simultaneously.

11.3 TECHNICAL SPECIFICATIONS

11.3.1 Smart analogical centres / accessories

11.3.1.1 Fire Detection Centre. ID3002

The analogical and algorithmic fire detection centre may be configured to be adapted to

the needs of each site. The size of the system will be defined by the number of loops (2

loops, 396 points of detection/control, individually identifiable and controllable).

Each loop will support 99 analogical sensors plus 99 programmable modules complying

with the requisites of EN 54 A and B cabling standards. It will be able to support sensors

of the following types: ionic, photo-electrical photo-thermal, high sensitivity lasers,

thermal and analogical sensors of an ionic or photo-electrical type. The modules can be:

programmable monitors for NA or NC contact reading, control modules for

programmable outputs, short circuit isolating modules and conventional area monitor

sensor modules.

Characteristics of the System

Automatic compensation of the dirt in the analogical smoke sensors.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 106

Function for automatic adaptation of each sensor to the environment.

10 levels of sensitivity.

AWACS algorithms for the control and stability of the sensors.

Automatic or manual testing of the system that activates and verifies each system

sensor.

Completely programmable and configurable in the field from the panel keyboard. It

will not require a special computer. It will allow automatic programming by default.

Customized messages for each point.

Programmable functions by events:

Predefined programming blocks.

Monitoring / interlocking selection.

Management of no alarm points (low priority).

Time function control for actions on a specific day and time.

Programming delays and output pulse times.

Historical archive in non volatile memory of 600 events which can be viewed on

screen or printed.

Non volatile clock for indicating the date and time of all events.

Uploading and downloading program using a PC.

Three levels of access with different and selectable passwords.

Self programming of the elements of the loops.

Operation test with an equipment meter and identification of 2 sensors assigned to

the same address. While the test is being carried out on the rest of the system it still

provides fire protection. Timer to stop the test.

Automatic maintenance alert function for sensors that are dirty before a false alarm

occurs.

Manual or automatic adjustment of the day/night sensitivity of the sensors.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 107

Enabling and disabling of all equipment.

Status report for all the system equipment including sensitivity and check totalizer.

Programmable silencer, alarm silence and alarm check.

High efficiency 24 V and 2.5 amp power supply

Liquid crystal screen with 240 x 64 pixels living complete on screen information about

the system.

30 key alphanumerical keyboard.

11.3.2 Smart analogical sensors

11.3.2.1 Super flat Analogical Optic Smoke Sensor. NFX/ISO-OPT

The white coloured analogical photo electrical smoke sensor with isolator will have an

optic sensor camera and will use the dispersion of light as its main principle for detection.

It detects the presence of smoke through the light dispersed by the smoke particles inside

the camera of the sensor.

Associated with the photoelectrical sensor, is the recognition circuit that provides a

threshold for a predetermined level of smoke in the system initialisation circuit.

The direction of each sensor will be assigned by rotating switches. Each sensor reports its

direction, its type and its analogical type in order to give an idea of the measured value

and its status.

The sensor will have two LEDS, which make it possible to see its status from any

position. The LEDS will flash in normal operation and remain on in the case of an alarm.

As an option, flashing can be eliminated when the system is used in rooms.

It includes a micro switch that is activated by a magnet to check that the equipment alarm

works.

The sensors will be assembled on a common bayonet type base with an interlocking

device to prevent their accidental extraction. They may be assembled on a base with a

built in horn to provide a local acoustic indication.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 108

Technical Characteristics:

Operating voltage 15 - 28Vdc

Consumption 0.2mA

Environmental conditions Temperature –10 to 60ºC

Humidity 10 to 93 %

Nominal Sensitivity 1.5 % o or 0.3 m. darkening.

Speed 8 m/s with constant flow.

Test By magnet.

Certifications Complies with Standards EN54, BSI, LPC,

VDS, UL, FM.

11.3.3 Smart digital modules and buttons

11.3.3.1 Single Entry Monitor Module. M710

The monitor module will provide a programmable input for devices that give potential

free contact signals and will supervise and manage voltage free contacts, either normally

open (NA) or normally closed (NC).

It assigns an address to the element that it manages inside the smart loop, so that the

Centre knows the exact location of the element that whose alarm is on. The control

circuit can be wired as Class B (closed) or Class A (Open). In the Class A circuits the

circuit will be supervised with an end of line resistance. The length of the activation circuit

must be less than 1000 metres [Rmax of the circuit 20W].

The direction of each module will be assigned by rotating selectors. They have a LED that

flashes each time they communicate with the Centre. The LED will remain on in the case

of an alarm and an indication will be sent to the Fire Centre.

It is supplied directly by the SLC communications loop. No additional supply is needed. It

must be protected against noise from interferences and must be easy to connect.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 109

It includes a micro switch which is activated by a magnet to check that the alarm is

working. It has an isolator at both loop inlets. Programmable action.Possibility of assembly

on a DIN rail using the M200DIN accessory.

Technical Characteristics:

Consumption: 2.8 mA on alarm, 660 μAin normal conditions

Environmental conditions: Temperature: -20 to 60ºC

Humidity: 5 to 95%, not condensed.

Dimensions: 93mm (height) x 94mm (width) x 23mm

Certifications: Complies with standards prEN 54-17, Vds 2489,

approved by CEA GEI 1-082 and GEI 1-084.

11.3.3.2 6 Relay output Control Module. CR6

The control module will provide up to six output orders to elements such as sirens,

electromagnets, etc. The connection of each circuit must be voltage free using a double

NA/NC contact.

Each output will have a direction assigned, using rotating selectors so that when it

receives an order from the Centre, its internal relay is activated and will switch to NA or

NC.

The control module will act on each of the relays in the cases indicated. The relay

contacts are of the SPDT type and set at 28 vdc and 2A.

There is a LED for each direction that flashes each time it communicates with the centre.

The LED remains on in the case of an alarm and indicates it to the Fire Centre.

The direction of each module will be assigned using rotating selectors.

Technical Characteristics:

Consumption: 7.6 mA on alarm, 1.45 mA in normal conditions.

Contacts: NA/NC, 2A to 28Vdc, 0,35 power factor.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 110

Environmental conditions: Temperature: -10 to 49ºC

Humidity: 10 to 93%, not condensed.

Dimensions: 185mm (height) x 147mm (width) x 25mm (depth)

Certifications: Complies with standards EN 54.

11.3.3.3 Programmable button. M700KAC-IFF/C

Manual alarm button assembled on a plastic red box made with impact resistant synthetic

material. It will be resettable and will have an in built short circuit isolator. It will have a

plastic cover or similar and shall have a key for testing. It will be surface mounted.

Certified in accordance with EN54 part 11.

It shall have extractable terminals to facilitate installation.

The direction of each button will be assigned using rotating selectors.

The button will have an LED that flashes each time it communicates with the centre. This

LED will go remain on when an alarm condition is detected.

Protection level IP44.

Technical Characteristics (Monitor) Module:

Consumption 7.6 mA on alarm, 160 A in normal conditions

Temperature conditions: Temperature: -10 to 49ºC

Humidity: 10 a 93%, non condensing

Certifications: Complies with standards EN54.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 111

11.3.4 Infrared barriers

11.3.4.1 Infrared Light reflection analogical smoke sensor

The linear optic beam reflector type analogical smoke sensorLPB700T is

compatible with all of the Notifier ID Seriescentres. Based on the principle of

darkening, it uses an infrared light beam. Optic beam smoke sensors are especially

appropriate for the protection of large areas, for example: industrial warehouses,

theatres, buildings with very high roofs where the installation of point sensors is not easy.

The LPB700Tsensor includes a transmitter and a receiver in the same unit and can

be connected directly to the analogical Notifier programmable loop without the need to

have an external power source, which is a considerable saving in the cost of installation as

it is only necessary to wire the emitter/receiver unit.

The infrared transmitter generates an invisible ray of light that towards the high

efficiency reflector and it returns the beam to the receiver of the LPB700Tsensor where

an analysis is made of the signal received. The change in the power of the signal received

determines the condition of the alarm.

The sensitivity of the sensors can be adjusted between 25% and 50% darkness. This

option makes it more adaptable to the different environments in which it is installed. As

well as the four fixed alarm thresholds, the sensor can be programmed to adjust

automatically to the environmental changes, within a known range of sensitivity, thus

reducing the number of possible unwanted alarms that could be generated because of

local activities in the protected area.

The LPB700T sensor is equipped with automatic dirt compensation, which means

that it will adapt its detection thresholds according to the signals received from the beam

caused by environmental contaminants. Once the sensor reaches its compensation limit,

the panel can identify and signal this condition.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 112

LPB700T lineal beam analogical reflection smoke sensor with an integrated

sensitivity test function.

Technical Characteristics:

Operating voltage 15-32 Vdc (15-28 Vdc with isolators)

Consumption Idle 2 mA.

Alarm 8.5 mA

Alignment 20 mA

Environmental Conditions Temperature -30 to 55ºC

Humidity 10% to 95% without condensation

Sensitivity 6 levels of sensitivity.

Certifications Complies with standard EN54/12

11.3.5 Warning elements

11.3.5.1 Alarm siren and loop flash. AWSB32/R/R-I

Siren with flash and isolator included, individually programmable, connected directly to

the communications loop of the analogical systems. Two rotating selectors are used for

direction. It will use the supply of the analogical loop. Certified in accordance with the

requirements of EN54 standard, Part 3.

3 different volume adjustments can be selected using the micro switch. Capability for 32

different tones.

The ABSB32/W/C-I model will allow for a base to be assembled on the siren forming a

sensor-siren set.

AWSB32/R/R-I.Supplied from analogical loop. Compatible with ID50, ID60, ID3002 and

ID3000 centers

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 113

Technical Characteristics:

Operating voltage 15 a 33 Vdc +/- 25%

Consumption AWSB32/R/R 5 mA

Sound power 83 - 103 dBA

Selectable sounds Continuous buzzing

Rapid frequency

Slow frequency

Temperature conditions: Temperature: -10 to 60 ºC

Humidity 10 to 93%, not condensed

Certifications Complies with standard EN 54, BASEFA

11.3.6 Accessories

11.3.6.1 Auxiliary power supplies . HLSPS50

The power supplies will be autonomous, providing auxiliary backup supply to the

fire control systems that cannot be supplied from the main power supply on the fire

control panel due to a lack of capacity or to avoid power losses along the cables.

They will have batteries through which in the case of a temporary loss of the main

supply the power supply is maintained. In this way the correct operation of the equipment

that requires 24 vdcsupply is guaranteed in an alarm. This includes optic and acoustic

announcers, electromagnetic retainers, extinguishing circuits, etc.

The power sources will be connected and controlled by a microprocessor which

supervises the supply, indicates any type of failure or irregularity and are protected

against short circuits. They will have outlets so that they can be monitored from the fire

control panel.

Characteristics:

Input voltage 230 V ~ ± 10% 50/60 Hz

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 114

Maximum absorbed current 0.5 A; 0.9 A; 1.8 A

Output voltage 27.6 V ± 1%

Nominal current 1.4 A2.5 A5.0 A

Maximum current supplied 1,2 A; 2.0 A; 4.0 A

Maximum current per output 1.8 A

Autonomy with a 2A charge 8 hours

Battery box 2 x (12 V 17 Ah)

Voltage thresholds: 22 V to 34 V

Charger cut off threshold 19 V

Operating temperature 5 to 40º C

Isolation level Class I

11.3.6.2 Fire resistant cable . 2x1,5 LHR

It must be capable of resisting the effects of the fire for at least 30 minutes as indicated in

standard UNE 23007-14 section A.6.11.3.

The cable will be red and will be made of flexible polished copper, class 1, fire resistant,

free from halogens, low smoke emission and low corrosiveness.

Characteristics:

Class 1 polished copper wire

Silicon isolator

Nominal isolation thickness 0.7

Drainage of rigid tinned copper 0.50 mm2.

Electrical resistance of the wire at 20 ºC ( /Km) 13.1

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 115

Electrical resistance of the isolation at 20 ºC ( /Km) 20

Capacity between wires (pf/m) 130

Characteristic impedance ( ) 50

11.3.7 Gas detection systems

11.3.7.1 Flammable gas sensor . SMART 3

The flammable gas sensor will be designed to act in atmospheres in which the main

component is air. The presence of combustible substances will be expressed in % of the

lower explosiveness limit (%LEL).

The sensor shall be catalytic and semi wire type will not be accepted. It will admit

watertight assembly (DUST IP55) and fireproof assembly (EXD) in compliance with ATEX

standards.

It shall include an 8 bit microprocessor for the Management of the following algorithms:

Self diagnosis to guarantee the correct operation of all parts of the sensor.

Zero level control to compensate the variations due to atmospheric conditions.

Digital filter of the values obtained and hysteresis cycle

TECHNICAL CHARACTERISTICS:

- Sensor Catalytic or Electrochemical

- Measuring range 0-100% LIE or 999 ppm according to the scale

- Power 12-24 Vdc +/- 15%

- Consumption 180 mA max. at 12 Vdc

- Work temperature -10 ºC to 55 ºC (Catalytic)

- Relative humidity 20% a 90% a 40 ºC

- Air speed < 6 m/s

- Resolution 1024 points

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 116

- Stability time < 1 hour

- Repetition +/- 1.5 % F.S.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 117

12 ELECTRICAL GENERATING SYSTEM

12.1 GENERAL DESCRIPTION

The power plant will consist of twenty-six generators of 1 MW and 400V that supply

electric power to a 33 kV network through a power line from a switching substation

The connection point with MV distribution network begins in the incoming switchgear

stall. It is a room which houses the input cabinet and two additional cabinets for

protection of insulation transformers.

Because of existing short circuit power of the public network nd potential increase in the

future, it was decided to install 2 insulation transformers of 35 MVA and 33.000/33.000 V.

One of them will be for stand-by.

From these transformers two lines are connected to a main cabinet room. These lines

enter in a protection cabinet in which busbars are connected to the protection cabinet of

13 step-up transformers for gensets and one protection cabinet for auxiliary services of

power plant.

The step-up transformers are provided in low voltage end with two connection busbars.

Step-up transformers are of 2500/1250/1250 KVA and 33000/400-400V. Each busbar is

connected to a genset.

Each genset is operated through a control and protection switchboard cabinet in which a

system for synchronization with network and management switch is located.

12.1.1 Connection line to company power substation of 33 kV

The connection line to the overhead power line of the company consists of a circuit

provided with 3(2(1x240) mm2 Cu 19/33 kV CU/XLPE/CU TAPE/PVC/AWA/PVC cables.

The line will be laid in pipes from the substation. The line will come protected against

overvoltage from the substation.

Main features of cables:

1) Insulation: .......................................................................................... 19/33 kV

2) Cross-section (mm2):................................................................................ 240

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 118

3) Number of cables per phase: ...................................................................... 2

4) Approximate permissible current (A): ................................................. 750

5) Conductor: .......................................................... Stranded Copper Wires

6) Conductor screen ....................................... Semi-conductive compound

7) Insulation: ............................................ Cross-linked polyethylene (XLPE)

8) Insulation screen ...................... Strippable Semi-conducting compound

9) Screen Layer ........................................................................... Copper Tape.

10) Separation sheath ............................................................ Polyvinyl chloride

11) Armor .................................................................................. Aluminum wires

12) Binder ............................................................................................ Binder tape

13) Outer sheath ...................................................... Polyvinyl chloride - Black

12.1.2 Incoming switchgear stall

The line from the substation enters in C17cabinet, and is connected to the busbars in

protection cabinet for the two insulation transformers of 35 MVA.

The cabinets will be of compact type with all equipment inside a metal enclosure. The

insulation voltage is 36 kV. The main characteristics of these cabinets are the following::

1) Insulation voltage (kV) ................................................................................ 36

2) Rated current of switchgear cabinets (A) ......................................... 1000

3) Rated current of main busbars (A)..................................................... 1000

4) Rated current of output switches (A) ............................................... 1250

5) Rated short-time withstand current1 sec. (kA) ................................ 31,5

6) Insulation level at industrial frequency 1 min. (kV) .............................. 70

7) Insulation level at lightning pulse (kV) .................................................. 170

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 119

The Cabinets are modules of medium voltage with air insulation, metal enclosure and

built according to IEC-62271-200.

Nominal performance values are guaranteed for the following environment conditions:

minimum environment temperature - 5 °C, maximum environment temperature + 40 °C,

maximum relative humidity 95%(without condensation).

The operation voltage of auxiliary equipment in cabinets is the following:

Operation voltage of auxiliary system + protection equipment: 48Vdc

Operation voltage of load engines-springs: 230 Vac

Operation voltage of indoor lighting: 230Vac

Operation voltage of condensation prevention system: 230Vac

12.1.3 Line from protection cabinets to insulation transformers

The connection line between protection cabinets in line input room and the transformer

consists of a circuit for each transformer, provided with3(2(1x240) mm2 Cu 19/33 kV

CU/XLPE/CU TAPE/PVC/AWA/PVC. cables The line will be laid in pipes from the input

switchgear stall.

Main features of cables:

1) Insulation: .......................................................................................... 19/33 kV

2) Cross-section (mm2):................................................................................ 240

3) Number of cables per phase: ...................................................................... 2

14) Approximate permissible current (A): ................................................. 750

4) Conductor: .......................................................... Stranded Copper Wires

5) Conductor screen ....................................... Semi-conductive compound

6) Insulation: ............................................ Cross-linked polyethylene (XLPE)

7) Insulation screen .................... Strippable semi-conductinve compound

8) Screen Layer ......................................................................... Copper tape.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 120

9) Separation sheath ............................................................ Polyvinyl chloride

10) Amour .................................................................................. Aluminum wires

11) Binder ............................................................................................ Binder tape

12) Outer sheath ...................................................... Polyvinyl chloride - Black

12.1.4 Insulation transformer 35 MVA 33/33 kV

Two insulation transformers will be installed to limit short circuit power inside the power

plant. They cannot be simultaneously operated One transformer is for stand-by.

The main features are the following:

1) Rated capacity (kVA) ONAN: ......................................................... 35.000

2) Rated voltage (KV) HV side ...................................................................... 33

3) Rated voltage (KV) LV side ....................................................................... 33

4) Tap voltage HV side (%) ................................................................. ±8x1,25

5) Connection ................................................................................ Delta – wye

6) Vector Diagram ................................................................................... Dyn11

7) Impedance voltage(%) at 75ºC ................................................................. 12

8) Winding material (HV/LV): ................................................................ Cu/Cu

9) Insulation level of winding (kV) Impulse (HV/LV) ......................170/170

10) Insulation level of winding (kV) AC (HV/LV) .................................. 70/70

11) Connection method ....................................................................Cable box

12) Efficiency (100% load) ........................................................................... 99,40

13) Efficiency (75% load) ............................................................................. 99,51

14) Efficiency (50% load) ............................................................................. 99,59

15) Efficiency (25% load) ............................................................................. 99,58

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 121

Protection functions of transformers. All the alarms will be monitored by the plant

control system:

1) Magnetic oil level gauge with alarm contacts

2) Dial type oil thermometer with alarm and trip contacts

3) Buchholz relay (flange type) with alarm and trip contacts.

4) Pressure relief device with trip contact.

5) On Load Tap Changer with Motor Drive. Remote control from the central

power system to increase/decrease Tap position.

6) Neutral of insulation transformers will be connected to a separate ground

system through a cabinet provided with resistance batteries and current

transformers for detection of earth derivation current.

12.1.5 Lines between insulation transformer and transformer

cabinet

The connection line between insulation transformers and transformer cabinet room

consists of a circuit for each transformer provided with2(1x240) mm2 Cu 19/33 kV

CU/XLPE/CU TAPE/PVC/AWA/PVC cables. The line will be laid in a pipe through the

central gallery to transformer cabinet room.

Main characteristics of cables:

1) Insulation: ..................................................................................... 19/33 kV

2) Cross-section (mm2): .......................................................................... 240

3) Number of cables per phase: ................................................................ 2

15) Approximate permissible current (A): ................................................. 750

4) Conductor ...................................................... Stranded Copper Wires

5) Conductor screen ............................... Semi-conductinve compound

6) Insulation: ....................................... Cross-linked polyethylene (XLPE)

7) Insulations screen ............. Strippable semi-conductinve compound

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 122

8) Screen Layer ........................................................................ Coppertape.

9) Separation sheath ...................................................... Polyvinyl chloride.

10) Armor ............................................................................. Aluminum wires

11) Binder ...................................................................................... Binder tape

12) Outer sheath ................................................. Polyvinyl chloride – Black

The rated current conducted by this circuit is 455 A. Cos π 1. With voltage 33kV.

The rated current conducted by this circuit is 568 A. Cos π0,8. With voltage 33kV.

12.1.6 Transformer cabinet room

A cabinet stall will be located in the center of power plant, housing the following

equipment:

Two cabinets of medium voltage, line and 35MVA transformers

protection.(C15 and C16). Cabinets C15 and C16 will be interlocked .

13 Protection cabinets for generation (step-up) transformers. (C1 to C13)

One protection cabinet for power plant auxiliary services transformer

(C14).

The cabinets will be of compact type with the equipment located inside a metal enclosure.

Insulation voltage 36kV. Equipped with powered automatic circuit breakers and line

disconnector switches with earthingswitch . Main features:

1) Insulation voltage (kV) ................................................................................ 36

2) Nominal current of the switchgearcabinets (A) ................................. 630

3) Nominal current of main busbars (A) .................................................. 630

4) Nominal current of output switches (A) ............................................. 630

5) Rated short-time withstand current 1 sec. (kA) .................................. 25

6) Insulation level at industrial frequency 1 min. (kV) .............................. 70

7) Insulation level at lightning pulse (kV) .................................................. 170

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 123

The cabinets are modules for medium voltage, with air insulation, metal enclosure and

built according to IEC-62271-200.

Nominal performance values are guaranteed for the following environmental conditions:

minimum environment temperature - 5°C, maximum environment temperature + 40°C,

maximum relative humidity 95%(without condensation).

The operation voltage of auxiliary equipment in the cabinets is the following:

Operation voltage of auxiliary system + protection equipment: 48Vdc

Operation voltage of load engines-springs: 230 Vac

Operation voltage of indoor lighting: 230Vac

Operation voltage of the condensation preventing equipment: 230Vac

12.1.6.1 Output switch cabinets and protection of transformer 35

MVA

There are two output cabinets housing measurement and protection equipment for

transformers of 35 MVA (C15 y C16) consisting of:

1) One three-pole breaker circuit breaker of the following characteristics:

a) Nominal voltage (kV) .......................................................................... 36

b) Nominal current (A) ......................................................................... 630

c) Breaking capacity (kA) ........................................................................ 25

d) Opening time of contacts (ms) ......................................................... 60

2) One three-pole breaker line disconnector switch of the following

characteristics:

a) Nominal voltage (kV) .......................................................................... 36

b) Nominal current (A) ......................................................................... 630

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 124

c) Location ......................................................................................... Indoor

3) Three current transformers of the following characteristics:

a) Transformation ratio (A) ............................................. 1000 / 1-1-1A

b) First secondary ................................................................. 20 VA Cl 0,5

c) Second secondary ........................................................... 20 VA 10P10

d) Third secondary .............................................................. 20 VA 10P10

e) Rated voltage (kV) ............................................................................... 36

f) Location ......................................................................................... Indoor

4) For both protection cabinets there are three voltage transformers of the

following characteristics:

a) Transformation ratio (V) ........................ 33.000:√3 / 100: √3 -100:3

b) Power (VA) ........................................................................................... 20

c) Accuracy class ...................................................................................... 0,5

d) Rated voltage (kV) ............................................................................... 36

e) Location ......................................................................................... Indoor

5) One earthing switch, interlocked with the line disconnector switch.

6) One set of voltage collectors to control voltage presence.

7) One ferroresonantresistance for closure of delta circuit in one secondary

voltage transformer.

These cabinets are equipped with the following equipment:

1) One protection relay whose functions are the following:

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 125

a) 50 Instant overcurrent

b) 51 AC Time overcurrent relay

c) 51N AC Neutral Time overcurrent relay

d) 67 AC Directional overcurrent relay

e) 67N AC neutral directional overcurrent relay

f) 87 Differential protective relay

12.1.6.2 Protection switchgear cabinets or generation transformers

and Aux. S.

There are 14 protection cabinets for generation transformers and auxiliary services

transformer in power plant, consisting of::

1) One three-pole automatic circuit breaker of the following characteristics:

a) Nominal voltage (kV) .......................................................................... 36

b) Nominal current (A) ......................................................................... 630

c) Breaking capacity (kA) ........................................................................ 25

d) Opening time of contacts (ms) ......................................................... 60

2) One three-pole line disconnect or switch of the following characteristics:

a) Nominal voltage (kV) .......................................................................... 36

b) Nominal current (A) ......................................................................... 630

c) Location ......................................................................................... Indoor

3) Three current transformers of the following characteristics (for the genset

transformers):

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 126

a) Transformation ratio (A) ...........................................................600 / 1

b) First secondary ................................................................. 20 VA 10P10

c) Assigned voltage (kV) .......................................................................... 36

d) To be installed in the wiring.

4) Three current transformers (for the auxiliary services transformer)

a) Transformation ratio (A) ...........................................................300 / 1

b) First secondary ................................................................. 20 VA 10P10

c) Assigned voltage (kV) .......................................................................... 36

5) One earthing switch, interlocked with the line disconnector switch..

6) One set of voltage collectors for control of voltage presence.

These cabinets are equipped with the following items:

2) One protection relay having the following functions:

a) 50 Instantaneous overcurrent

b) 51 AC Time overcurrent relay

12.1.7 Lines from protection cabinets to power generation

transformers and auxiliary services in the plant.

The line connecting protection cabinets at the input room and transformers consists of

one circuit per transformer provided with 3(1x95) mm2 Cu 19/33 kV CU/XLPE/CU

TAPE/PVC/AWA/PVC cables. The line is laid in a cable pipe from central gallery to

transformer.

Main characteristics of cables:

1) Insulation: .......................................................................................... 19/33 kV

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 127

2) Cross-section (mm2):.................................................................................. 95

3) Number of cables per phase: ...................................................................... 1

4) Approx. permissible current (A): .......................................................... 235

5) Conductor: ........................................................... Stranded Copper Wires

6) Conductor screen ..................................... Semi-conductinve compound

7) Insulation: ............................................ Cross-linked polyethylene (XLPE)

8) Insulation screen ................... Strippable Semi-conductinve compound

9) Screen Layer ............................................................................ Copper tape.

10) Separation sheath ........................................................... Polyvinyl chloride.

11) Armor .................................................................................. Aluminum wires

12) Binder ............................................................................................ Binder tape

13) Outer sheath ...................................................... Polyvinyl chloride – Black

The current conducted by these circuits is 43,73 A

(Voltage 33kV)

12.1.8 Generation transformers of 2500 kVA 33/0,4/0,4 kV

13 step-up transformers of 33000/400/400V and 2500 kVA, two windings of 1250 KVA

each one.

Main features:

1) Rated capacity (kVA) ONAN: ........................................ 2500/1250/1250

2) Cooling ................................................................................................ ONAN

3) Rated voltage (KV) HV side ...................................................................... 33

4) Rated voltage (KV) LV 1 side................................................................... 0,4

5) Rated voltage (KV) LV 2 side................................................................... 0,4

6) Tap voltage (KV) HV side (%) .......................................................... ±2x2,5

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 128

7) Connection (HV/LV/LV) ................................................Delta - wye - wye

8) Vector Diagram (HV/LV/LV) ................................................... Dyn11yn11

9) Impedance voltage(%) (HV/LV) .............................................................. 5,4

10) Impedance voltage(%) (LV1/LV2) ............................................................. 9

11) Winding material (HV/LV): ................................................................ Cu/Cu

12) Insulation level of winding (kV) Impulse (HV/LV/LV) .................. 170/-/-

13) Insulation level of winding (kV) AC (HV/LV/LV) ........................... 70/3/3

14) Connection method ....................................................................Cable box

The transformers have a DGPT2 relay having the following protection functions:

1) 26 thermal control devices

2) 63 Pressure relay

3) 71 level relay

12.1.9 160 kVA 33/0,4 kV transformer for auxiliary services

Transformer of 33000/400V, 160 kVA to supply power to auxiliary services in the plant.

Main features:

1) Rated power (kVA) ONAN: ................................................................. 160

2) Cooling ................................................................................................ ONAN

3) Rated voltage (KV) HV end ...................................................................... 33

4) Rated voltage (KV) LV end....................................................................... 0,4

5) Connection (HV/LV).................................................................. Delta - wye

6) Vector Diagram (HV/LV/LV) ............................................................ Dyn11

7) Impedance voltage (%) (HV/LV) ................................................................ 4

8) Winding material (HV/LV): ................................................................ Cu/Cu

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 129

9) Connection method ....................................................................Cable box

The transformer has a relay 26 thermal control device.

12.2 GROUNDING GRID

For protection against accidental contacts of persons with energized circuits, a grounding

grid is defined with the features specified in the plan “Diagram of Buried grounding grid

distribution 24-01”.

This grid has been designed to provide a safety system for persons and also to ensure

good conductivity with the ground so all protection devices will correctly operate.

In general, the grounding grid must comply with the following requirements:

1) The grounding grid must be buried at 800 mm of depth.

2) Will consist of naked copper wire of 70 mm2 section.

3) Steel and copper rods 16x1800 mm will be used.

4) Every connection of the buried grid will be made using thermo welding.

3) In the plan 24-02 “Grounding grid typical details” are showed the construction

details of the grounding grid.

The distribution of the grounding grid is according a TN-S ear thing scheme.

Every metal pieces unbound with the main circuits, and every devices and equipment

installed will be connected to the protection grounding grid

Cable bridges of 50 mm2 will be made between the buried grid and the reinforcement of

the concrete structure.

A surface grounding grid over the trays will be made, formed by naked copper wires of

50 and 35 mm2 that will be connected with the buried grounding grid through the

connection bars.

Cable bridges of 35 mm2 will be made from surface grid up to the bars of grounding

protection, casing of cabinets, doors, metal closures, etc.

Therefore, protection grounding grid will be connected with the following items:

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 130

Frames and casings of the operation devices.

Pipes, trays and metal structures.

The whole enclosures of metal cabinets.

Grid closures (if it exists) and protection of transformer and rails.

Structures and reinforcements of the different buildings.

Grounding grid for HV cables.

The service grounding will be connected with the general grounding grid. Also, the

secondary of the measurement instruments will be connected to that system

(voltage and current transformers).

Every item in the Regulation and Metering Station (R.M.S.) located between dielectric

joints of input and output, must be connected permanently with the same electric

potential and with the ground, with a resistance lower than 20 ohms an according with

the allowed in the current standards. That grounding outlet only must be used by the

R.M.S, so this grounding grid is separated from the general and lightning grounding grids

of the power plant.

This grounding grid will be formed by three rods installed with a minimum distance of 15

meters of the general and lightning grounding grids.

The neutral of the insulation transformers will be connected to ground outlet. This

grounding grid will be formed by three rods installed with a minimum distance of 15

meters of the general and lightning grounding grids.

12.3 ENGINEERING BASIS OF DESIGN

This project was completed in compliance with the following standards:

IEC 60129, Alternating current circuit breakers and ground-fault interrupters.

EN 60265-1, high-voltage switches. Part 1: switches for rated voltages above 1 kV

and less than 52 kV.

EN 50102, degrees of protection provided by enclosures for electrical equipment

against external mechanical impacts (IK code).

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 131

IEC 60076, including all of its parts, power transformers. Application guide.

EN 60044, including all of its parts, instruments transformers.

EN 60099, including all of its parts, surge arresters.

12.4 SUPPORTING CALCULATIONS

12.4.1 Short circuit

For the calculations of the current that causes a short circuit, it will be taken into account

the short circuit power of M.V. network, whose value have to be provided by the electric

company.

Due to lack of that value, we have assumed that it is about 2.000 MVA.

For this calculation was used the impedance method with the following starting data:

Table 15. Short circuit calculations

Network impedance in the connection point

Data: Scc = 2000 MVA

UAT = 33 kV

Connection from station to transformer of 35 MVA

Data: Section = 240 mm2

Length = 0,34 Km

Type= Cu )

Nº cond/phase 2

Inside impedance of the transformer of M.V. / L.V..

Data: %Ucc = 12 %

U20 = 33000 V

Sn = 35000 kVA

Cos φ = 0,8

n = 1

Connection from 35 MVA transformer to transformer cabinet room

Data: Section = 240 mm2

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 132

Length = 0,1 Km

Type= Cu ( Cu ó Al)

Nº cond/phase 2

Connection from transformer cabinet room to 2,5 MVA transformer

Data: Section = 95 mm2

Length = 0,02 Km

Type= Cu ( Cu ó Al)

Nº cond/phase 1

Inside impedance of the M.V. / L.V. transformer

Data: %Ucc = 5,4 %

U20 = 400 V

Sn = 2500 kVA

Cos φ = 0,8

Resistive drop 0,00 %

n = 1

Connection from transformer to genstet

Data: Section = 240 mm2

Length = 12 m

Type= Cu ( Cu ó Al)

No. of wires = 4

Genset

Data: Pn = 1250 kVA

Xsubt = 13,2 %

Un = 400 V

The breaking capacity needed for the protection cabinets of the genset transformers is

the value of a three-phase short circuit occurred in the circuit of the power plant

auxiliary services.

Short circuit current in cabinet bars

XE = 2629,29 mΩ

RE = 57,328 mΩ

ZE = 2,630 Ω

ICC = 7,978 kA

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 133

The short circuit current in busbars in transformer cabinet room is 8 kA.

These cabinets have a breaking capacity of 25 kA.

12.4.2 Grounding grid calculations

12.4.2.1 Maximum grounding voltage and extinguishing time

A ground mat will be provided for protection against incidental contacts. This ground mat

will be designed to ensure full operator protection and provide proper grounding,

ensuring correct operation of all protection devices.

To verify the ground mat, the following calculations have been performed for

substantiation purposes:

First, network fault current is determined. To limit the MV network fault current the

neutral of the MV isolation transformers will be grounded with a 381 resistor.

Where:

Id = network fault current - A

Rt = grounding resistance- 381

U = rated voltage - 33.000 V

Xn = grounding reactance -

2

n

2

t

d

X(R3

UI

The result obtained is:

Id = 50 A

12.4.2.2 Grounding resistance

The underground ground grid consists of a 70 mm2 naked copper wire and ground rods

drove into the ground to a depth of 0.8m.

Considering a ground resistivity of 100 . m

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 134

Network electrical data

Network frequency 50Hz

Environment temperature 35 ºC

Fault removal time 0.5 s

Existing voltage levels 33 kV

Ground data

Thickness of surface layer 0.1 m

Resistivity of surface layer 3000Ωm

Ground resistivity 100 Ωm

Geometrical data

Total area occupied by ground mat 6848m2

Ground mat depth 0,8m

Length of ground mat larger side 107m

Length of ground mat smaller side 64 m

Number of wires parallel to ground mat larger side 4

Number of wires parallel to ground mat smaller side 8

Average spacing between parallel wires 5 m

Wire length 2400 m

Number of ground rods 27

Ground rod length 1,8 m

12.4.2.3 Determination of grounding resistance

1.- Grounding resistance.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 135

lLrRt

4

.4

Where:

= ground resistivity in ohms per meter

L = total length of underground wires

l = total length of ground rods. 34x1.8=61,2 m

r = radius of a circle equivalent to the area covered by the ground mat

698,06,482400

1004

7,464

100 x

xRt

The ground grid provided in the plant will be connected to the ground grid of existing

lighting arresters, thus improving grounding resistance.

12.4.2.4 Allowed maximums voltages to ground rules according

To verify the ground mat, the following calculations have been performed for

substantiation purposes:

The maximum permissible step and touch voltages are the following:

1) Step and touch voltages at the area in which the transformers are located:

Where:

s = concrete resistivity - 3.000 . m

= ground resistivity - 100 . m

t = opening time - 1 s

n = 1

k = 72

Vp= step voltage - V

Vc= touchvoltage - V

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 136

Step voltage:

1.000

61

t

k10V s

np

Touchvoltage:

1.000

1,51

t

kV s

nc

From which the following is obtained:

1.000

300061

1

7210Vp =13.680 V

1.000

30001,51

1

72Vc = 396 V

12.4.2.5 Determination of step and touchvoltages

To determine fault and ground currents we should take into account the way in which

the neutral is connect to ground in MV section.

For networks with the neutral connected to ground, either rigid or through an

impedance, we should consider the applied contact or step voltage and the grounding

current (IE) which causes an increase of grounding system potential.

Step and touchvoltages are defined by the following equations:

L

I. . Ki . Kp Vp

L

I. . Ki . Kc Vc

Kp = 1/π ( 1/2h + 1/(D+N) + 1/2D + 1/3D +......+ 1/(N-1)D

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 137

Ki = ( 0,65 + 0,172N)

Kc= 1/2π Ln(D2 /16hd) + 1/π Ln [(3/4) (5/6) (7/8).........(2N-3/2N-2)]

Where:

D = Spacing between parallel wires

h = Depth at which ground grid is buried

d = Diameter of ground grid wires

N = Maximum number of parallel wires in a direction for step voltage

N = Geometric average value of wires in both directions for contact voltage

= Ground resistivity

L =Total length of buried wire

The coefficients have the following values

Kp = 0,324

Ki = 2,026 (for step voltage)

Ki = 1,68 (for touch voltage)

Kc = 1,74

Thus, the resulting step and touch voltages are the following:

V36,12400

50.100 . 2,026 . 0,324 Vp

V09,62400

50.100 . 1,74 . 1,68 Vc

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 138

12.4.2.6 Criteria for model validation

Step voltage:

Up = 1,36 V < Upmax = 13.680 V All requirements are met

Touch voltage:

Uc = 6,09 V < Uc max = 396 V All requirements are met

12.5 TESTING & INSPECTION

Measurements and verifications that are to be performed at the commissioning stage

1. Wire identification

2. Measurements on ground grid

3. Measurements on transformer insulation

a. MV –MV 5000 VDC

b. MV- LV5000 VDC

c. MV– G 5000 VDC

d. LV- G 500 VDC

The system is considered defective when a reading is below 1000 Ω xV

1. Verification for correct setting of protection relays by means of the required test

and related documentation.

2. Measurement of step and contact voltages at least on fencing, areas of frequent

passage, transformers and especially on components that could transfer voltages

to external areas.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 139

13 ANCILLARY SERVICES.LOW VOLTAGE SYSTEM.

13.1 GENERAL DESCRIPTION

The plant consist of 26 gen-sets spread over two buildings; 13 on each one

The transformer secondaries are connected with the power switch-board of each gen-set

by wires housed in tubes.

In the power switchboard of each gen-set include the main switch that connects the

genset to the grid and the feedings for the gen-set auxiliary equipment.

There is also a main auxiliary switchboard in the social building feeded by the transformer

of auxiliary services T14. From this switchboard, several local switchboards are feeded all

around the plant

-SWITCHBOARD ENGINE ROOM 1

-SWITCHBOARD ENGINE ROOM 2

-CABINET ROOM SWITCHBOARD. ENTRANCE -CABINET ROOM SWITCHBOARD. GEN. CABINETS

-R.M.S. SWITCHBOARD

-ACCESS CONTROL SWITCHBOARD

-WATER PUMPS SWITCHBOARDS (Future)

-OIL PUMPS SWITCHBOARDS (Future)

-WORKSHOP SWITCHBOARD

13.1.1 Connection from genset transformers up to genset

switchboards and gensets

The power distribution line from each of the transformer secondaries at 400 volts to

each power breaker will be installed under tube till the channel below the power

switchboard of the gen-set. From the power switchboard to the gen-set the line goes

through a tray within an inspectable channel

The power distribution line consists of 4 cables by phase 240 mm2 Cu RV-K (XLPE

insulated, PVC sheathed single core cable.

Cable main characteristics:

1) Insulation: ........................................................................................... 0,6/1 kV

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 140

2) Section (mm2): ............................................................................................ 240

3) Cables by phase: ............................................................................................ 4

4) Maximum intensity allowed (A): ......................................................... 1820

5) Material: ............................................................................................... Cooper

6) Nominal intensity. .............................................................................. 1804A

The power breaker will be regulated at a maximum of 1820 A

13.1.2 Protection and operation switchboards of gensets

Each genset has an operation and control switchboard composed by two cabinet

modules. The left module includes the power part of the switchboard composed basically

by a main automatic circuit breaker for the shut-off and synchronism command of the

genset and also a feeder to supply the auxiliary services of the genset. These auxiliary

services can be supplied either from the genset generating power or from the power

coming from Mains, being possible to choose one of these supplies by a manual switch

included inside the panel.

The right cabinet includes the protection and control devices of the auxiliary services and

the genst controlling system.

The genset will switch on through the following orders:

Time programming.

Ordered manually by de SCADA’s operator.

Control panel of each genset.

The synchronism system will verify the synchronism at both sides of the connection

switch and it will close automatically once the synchronism has been accomplished.

The auxiliary services that are supplied directly from the genset control panels are those

related with their cooling system.

Table 16.P&CC

Circuit No. Description Conductor Description of

protections

P&CC 3[4(1X240)]+G CB4P 2000 A

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 141

Circuit No. Description Conductor Description of

protections

P&CC-C1 AERO FAN 1 3(1X2,5)+G2,5 GV 3P 4-6,3A

P&CC-C2 AERO FAN 2 3(1X2,5)+G2,5 GV 3P 4-6,3A

P&CC-C3 AERO FAN 3 3(1X2,5)+G2,5 GV 3P 4-6,3A

P&CC-C4 AERO FAN 4 3(1X2,5)+G2,5 GV 3P 4-6,3A

P&CC-C5 AERO FAN 5 3(1X2,5)+G2,5 GV 3P 4-6,3A

P&CC-C6 AERO FAN 6 3(1X2,5)+G2,5 GV 3P 4-6,3A

P&CC-C7 MAIN CIRC. WATER PUMP 3(1X2,5)+G2,5 GV 3P 9-14A

P&CC-C8 AUX. CIRC. WATER PUMP 3(1X2,5)+G2,5 GV 3P 4-6,3A

P&CC-C9 AERO ROOM FAN 3(1X2,5)+G2,5 GV 3P 6-10A

CB – Masterpact circuit breaker

GV –Motor circuit-breakers.

13.1.3 General switchboard of power plant auxiliary services

The plant disposes of a general switchboard of distribution for electric power supply to

the auxiliary services of the plant.

The power supply up to this cabinet is through cable from the auxiliary services

transformer (T14) formed by one cable per phase of 120 mm2 of copper RV-K 0,6/1kV.

This cabinet has a molded case circuit breaker (MCB) of 250 A, and residual current

adjustable deviceRH99 with toroidal transformer.

Also, it has a network analyzer and overcurrent protection.

Where the outputs are the following:

Table 17. GSP switchboard

Circuit No.

Description Wire Description of

protections

GSP-P1 SWITCHBOARD ENGINE ROOM 1 4(1X35)+G16 MCCB4p 100A

GSP-P2 SWITCHBOARD ENGINE ROOM 2 4(1X35)+G16 MCCB4p 100A

GSP-P3 CABINET ROOM SWITCHBOARD. ENTRANCE 4(1X6)+G6 MCCB4p 20A

GSP-P4 CABINET ROOM SWITCHBOARD. GEN. CABINETS

4(1X6)+G6 MCCB4p 25A

GSP-P5 R.M.S. SWITCHBOARD 4(1X6)+G6 MCCB4p 20A

GSP-P6 ACCESS CONTROL SWITCHBOARD 4(1X6)+G6 MCCB4p 25A

GSP-P7 OUTSIDE LIGHTING LAMPOST 4(1X6)+G6 MCCB4p 20A + RCCB 4p 25A

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 142

Circuit No.

Description Wire Description of

protections

300mA

GSP-P8 OUTSIDE LIGHTING. ENGINE ROOM FRONTAGE

4(1X6)+G6 MCCB4p 20A + RCCB 4p 25A

300mA

GSP-P9 WATER PUMPS SWITCHBOARDS 4(1X10)+G10 MCCB 4p 40A + RCCB 4p 40A

300mA

GSP-P10 OIL PUMPS SWITCHBOARDS 4(1X10)+G10 MCCB 4p 40A + RCCB 4p 40A

300mA

GSP-P11 WORKSHOP SWITCHBOARD 4(1X10)+G10 MCCB 4p 40A

GSP-P12 RESERVE - MCCB 4p 32A

GSP-P13 POWER OUTLET. MEETING ROOM AND MANAGER OFFICE

2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P14 POWER OUTLET. CONTROL ROOM. 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P15 POWER OUTLET. VARIOUS AND CONTROL ROOM

2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P16 RESERVE - MCCB 2p 16A

GSP-P17 POWER OUTLET. VARIOUS DINING ROOM. 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P18 POWER OUTLET. DINING ROOM. 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P19 POWER OUTLET. DINING ROOM. 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P20 POWER OUTLET. BATHROOM. 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P21 POWER OUTLET. OUTSIDE. 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P22 RESERVE - MCCB 2p 16A

GSP-P23 UPS SCADA 2(1X2,5)+G2,5

MCCB 2p 16A + RCCB « SI » type 2p 25A

300mA

GSP-P24 FIRE-FIGHTING ALARM CONTROL 2(1X2,5)+G2,5

MCCB 2p 16A + RCCB « SI » type 2p 25A

300mA

GSP-P25 POWER OUTLET. COMPUTERS MEETING ROOM MANAGER OFFICE

2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P26 POWER OUTLET. CONTROL ROOM COMPUTERS.

2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P27 POWER OUTLET COMPUTERS CONTROL ROOM

2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P28 POWER OUTLET COMPUTERS DINIDG ROOM 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P29 RACK PHONE CONTROL UNIT 2(1X2,5)+G2,5 MCCB 2p 16A

GSP-P30 RESERVE - MCCB 2p 16A

GSP-P31 AIR CONDITIONING SWITCHBOARD 4(1X10)+G10 MCCB 4p 32A + RCCB 4p 40A

300mA

GSP-L1 LIGHTING MEETING ROOM MANAGER OFFICE

2(1X1,5)+G1,5 MCCB 2p 10A

GSP-L2 LIGHTING CONTROL ROOM DINING ROOM 2(1X1,5)+G1,5 MCCB 2p 10A

GSP-L3 BATHROOM LIGHTING 2(1X1,5)+G1,5 MCCB 2p 10A

GSP-E1 EMERGENCY LIGHTING 2(1X1,5) MCCB 2p 10A

GSP-L4 FLUORESCENT LIGHTING TIGHT PORCH 1 2(1X1,5)+G1,5 MCCB2p 10A

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 143

Circuit No.

Description Wire Description of

protections

GSP-L5 FLUORESCENT LIGHTING TIGHT PORCH 2 2(1X1,5)+G1,5 MCCB2p 10A

MCCB – Thermal-magnetic miniature circuit breaker.

RCCB= Residual current circuit breaker.

13.1.4 Engine room switchboard 1

Table 18. EN-1 switchboard

Circuit No. Description Wire Description of

protections

EN1-L1 HALL LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN1-L2 HALL LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN1-E1 EMERGENCY LIGHTING 2(1X1,5) MCCB2p 10A

EN1-L3 M1-M6 LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN1-L4 M7-M13 LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN1-L5 RESERVE - MCCB2p 10A

EN1-P1 POWER SOCKET ENGINE ROOM 4(1X16)+G16 MCCB4p 63A

EN1-P2 RESERVE - MCCB2p 16A

EN1-P3 RESERVE - MCCB2p 16A

MCCB – Thermal-magnetic miniature circuit breaker.

SR= Step-Relay.

13.1.5 Engine room switchboard 2

Table 19. EN-2 switchboard

Circuit No.

Description Wire Description of protections

EN2-L1 HALL LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN2-L2 HALL LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN2-E1 EMERGENCY LIGHTING 2(1X1,5) MCCB2p 10A

EN2-L3 M1-M6 LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN2-L4 M7-M13 LIGHTING 2(1X2,5)+G2,5 MCCB2p 10A + SR 2p 25A

EN2-L5 RESERVE - MCCB2p 10A

EN2-P1 POWER SOCKET ENGINE ROOM 4(1X16)+G16 MCCB4p 63A

EN2-P2 RESERVE - MCCB2p 16A

EN2-P3 RESERVE - MCCB2p 16A

MCCB – Thermal-magnetic miniature circuit breaker.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 144

SR= Step-Relay.

13.1.6 Workshop switchboard

Table 20. WP switchboard

Circuit No. Description Wire Description of

protections

WP-L1 WORKSHOP LIGHTING 2(1X1,5)+G1,5 MCCB 2p 10A

WP-L2 WAREHOUSE LIGHTING 2(1X1,5)+G1,5 MCCB 2p 10A

WP-L3 OIL STORAGE LIGHTING 2(1X1,5)+G1,5 MCCB 2p 10A

WP-E1 EMERGENCY LIGHTING 2(1X1,5) MCCB 2p 10A

WP-P1 POWER OUTLET WORKSHOP 2(1X2,5)+G2,5 MCCB 2p 16A

WP-P2 POWER OUTLET WAREHOUSE 2(1X2,5)+G2,5 MCCB 2p 16A

WP-P3 POWER OUTLET WAREHOUSE 2(1X2,5)+G2,5 MCCB 2p 16A

WP-P4 RESERVE - MCCB 2p 16A

WP-P5 POWER OUTLET 3P+N+T 16A 400V 4(1X2,5)+G2,5 MCCB 4p 16A

WP-P6 RESERVE - MCCB 4p 16A

WP-P7 POWER SOCKET 4(1X10)+G10 MCCB 4p 40A

MCCB – Thermal-magnetic miniature circuit breaker.

13.1.7 Access control switchboard

Table 21. ACS switchboard

Circuit No.

Description Wire Description of

protections

ACS-L1 ACCESS CONTROL LIGHTINT EMERGENCY 2(1X1,5)+G1,5 MCCB 2p 10A

ACS-L2 RESERVE - MCCB 2p 10A

ACS-P1 POWER OUTLET 2(1X2,5)+G2,5 MCCB 2p 16A

ACS-P2 RESERVE - MCCB 2p 16A

ACS-P3 POWER OUTLET COMPUTERS 2(1X2,5)+G2,5 MCCB 2p 16A

ACS-P4 RESERVE - MCCB 2p 16A

ACS-P5 AUTOMATIC GATE SWITCHBOARD 4(1X6)+G6 MCCB 4p 10A + RCCB 4p 25A 300mA

MCCB – Thermal-magnetic miniature circuit breaker.

RCCB= Residual current circuit breaker.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 145

13.2 ENGINEERING BASIS OF DESIGN

This project was completed in compliance with the following standards:

UNE 211435 Guidance on the selection of distribution cables for rated voltages up

to and including 0,6/1 kV.

UNE 21123 Industrial cables of rated voltage 0,6/1 kV. All parts

UNE 21144 Electric cables. Calculation of the current rating. All parts

UNE 36582 Rigid steel conduit, zinc coated for use in electrical raceway

UNE-EN 50085 Cable trunking systems and cable ducting systems for electrical

installations. All parts.

UNE-EN 50086 Conduit systems for cable management. All parts.

UNE EN 60309 Plugs, socket-outlets and couplers for industrial purposes. All

parts.

UNE-EN 60423 Conduit systems for cable management - Outside diameters of

conduits for electrical installations and threads for conduits and fittings.

UNE-EN 60439 Low-voltage switchgear and controlgear assemblies. All parts.

UNE-EN 60598 Luminaires. All parts.

UNE-EN 60947 Low-voltage switchgear and controlgear. All parts.

13.3 ELECTRICAL DESIGN & DEFINITION

The estimated power for all auxiliary services in the plant is 54 kW.

The table below shows the relationship between power values and simultaneity

coefficients considered for calculation purposes.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 146

Table 22. Electric power calculations

Circuit No. Description Load Pn

(W)

Simultaneity coefficient

Simult.

Pn Switchboard(W)

GSP 53792,498 100,00% 53792

GSP-P1 SWITCHBOARD ENGINE ROOM 1 9760,56 90,00% 8785

GSP-P2 SWITCHBOARD ENGINE ROOM 2 9767,76 90,00% 8791

GSP-P3 CABINET ROOM SWITCHBOARD. ENTRANCE 2500 90,00% 2250

GSP-P4 CABINET ROOM SWITCHBOARD. GEN. CABINETS 4000 90,00% 3600

GSP-P5 R.M.S. SWITCHBOARD 2500 90,00% 2250

GSP-P6 ACCESS CONTROL SWITCHBOARD 1059,4 90,00% 953

GSP-P7 OUTSIDE LIGHTING LAMPOST 4500 90,00% 4050

GSP-P8 OUTSIDE LIGHTING. ENGINE ROOM FRONTAGE 3600 90,00% 3240

GSP-P9 WATER PUMPS SWITCHBOARDS 0 90,00% 0

GSP-P10 OIL PUMPS SWITCHBOARDS 0 90,00% 0

GSP-P11 WORKSHOP SWITCHBOARD 7470,3 90,00% 6723

GSP-P12 RESERVE 0 90,00% 0

GSP-P13 POWER OUTLET. MEETING ROOM AND MANAGER OFFICE 3680 20,00% 736

GSP-P14 POWER OUTLET. CONTROL ROOM. 3680 20,00% 736

GSP-P15 POWER OUTLET. VARIOUS AND CONTROL ROOM 3680 20,00% 736

GSP-P16 RESERVE 0 70,00% 0

GSP-P17 POWER OUTLET. VARIOUS DINING ROOM. 3680 20,00% 736

GSP-P18 POWER OUTLET. DINING ROOM. 3680 20,00% 736

GSP-P19 POWER OUTLET. DINING ROOM. 3680 20,00% 736

GSP-P20 POWER OUTLET. BATHROOM. 3680 20,00% 736

GSP-P21 POWER OUTLET. OUTSIDE. 3680 20,00% 736

GSP-P22 RESERVE 0 20,00% 0

GSP-P23 UPS SCADA 1000 50,00% 500

GSP-P24 FIRE-FIGHTING ALARM CONTROL 300 100,00% 300

GSP-P25 POWER OUTLET. COMPUTERS MEETING ROOM MANAGER OFFICE 3680 20,00% 736

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 147

Circuit No. Description Load Pn

(W)

Simultaneity coefficient

Simult.

Pn Switchboard(W)

GSP-P26 POWER OUTLET. CONTROL ROOM COMPUTERS. 3680 20,00% 736

GSP-P27 POWER OUTLET COMPUTERS CONTROL ROOM 3680 20,00% 736

GSP-P28 POWER OUTLET COMPUTERS DINIDG ROOM 3680 20,00% 736

GSP-P29 RACK PHONE CONTROL UNIT 500 100,00% 500

GSP-P30 RESERVE 0 0,00% 0

GSP-P31 AIR CONDITIONING SWITCHBOARD 0 100,00% 0

GSP-L1 LIGHTING MEETING ROOM MANAGER OFFICE 518 90,00% 466

GSP-L2 LIGHTING CONTROL ROOM DINING ROOM 1144 90,00% 1030

GSP-L3 BATHROOM LIGHTING 712,8 90,00% 642

GSP-E1 EMERGENCY LIGHTING 115,2 90,00% 104

GSP-L4 FLUORESCENT LIGHTING TIGHT PORCH 1 417,6 90,00% 376

GSP-L5 FLUORESCENT LIGHTING TIGHT PORCH 2 417,6 90,00% 376

EN1-L1 HALL LIGHTING 1461,6 90,00% 1315

EN1-L2 HALL LIGHTING 1461,6 90,00% 1315

EN1-E1 EMERGENCY LIGHTING 72 90,00% 65

EN1-L3 M1-M6 LIGHTING 1461,6 90,00% 1315

EN1-L4 M7-M13 LIGHTING 1461,6 90,00% 1315

EN1-L5 RESERVE 0 90,00% 0

EN1-P1 POWER SOCKET ENGINE ROOM 22170 20,00% 4434

EN1-P2 RESERVE 0 100,00% 0

EN1-P3 RESERVE 0 90,00% 0

EN2-L1 HALL LIGHTING 1461,6 90,00% 1315

EN2-L2 HALL LIGHTING 1461,6 90,00% 1315

EN2-E1 EMERGENCY LIGHTING 72 100,00% 72

EN2-L3 M1-M6 LIGHTING 1461,6 90,00% 1315

EN2-L4 M7-M13 LIGHTING 1461,6 90,00% 1315

EN2-L5 RESERVE 0 100,00% 0

EN2-P1 POWER SOCKET ENGINE ROOM 22170 20,00% 4434

EN2-P2 RESERVE 0 100,00% 0

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 148

Circuit No. Description Load Pn

(W)

Simultaneity coefficient

Simult.

Pn Switchboard(W)

EN2-P3 RESERVE 0 90,00% 0

WP-L1 WORKSHOP LIGHTING 417,6 90,00% 376

WP-L2 WAREHOUSE LIGHTING 1252,8 90,00% 1128

WP-L3 OIL STORAGE LIGHTING 417,6 90,00% 376

WP-E1 EMERGENCY LIGHTING 57,6 100,00% 58

WP-P1 POWER OUTLET WORKSHOP 3680 20,00% 736

WP-P2 POWER OUTLET WAREHOUSE 3680 20,00% 736

WP-P3 POWER OUTLET WAREHOUSE 3680 20,00% 736

WP-P4 RESERVE 0 100,00% 0

WP-P5 POWER OUTLET 3P+N+T 16A 400V 11085 10,00% 1109

WP-P6 RESERVE 0 100,00% 0

WP-P7 POWER SOCKET 22170 10,00% 2217

ACS-L1 ACCESS CONTROL LIGHTINT EMERGENCY 306 90,00% 275

ACS-L2 RESERVE 0 100,00% 0

ACS-P1 POWER OUTLET 3680 20,00% 736

ACS-P2 RESERVE 0 90,00% 0

ACS-P3 POWER OUTLET COMPUTERS 3680 20,00% 48

ACS-P4 RESERVE 0 90,00% 0

ACS-P5 AUTOMATIC GATE SWITCHBOARD 0 100,00% 0

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 149

13.3.1 Calculation of short-circuit current

13.3.1.1 Calculation of short-circuit current in generator panels

The maximum short-circuit current on busbars of generator panel depends on the short-

circuit current input by the grid through the transformer and the generator of this

transformer through the contiguous LV windings.

Internal impedance of MV/LV transformer

Data:

MV-LV winding

Ucc= 5,4 %

U20 = 400 V

Sn = 1250 kVA

LV-LV winding

Ucc= 9 %

U20 = 400 V

Sn = 1250 kVA

Engine-generator

Data: Pn = 1250 kVA

Xsubt = 13,2 %

Un = 400 V

Short-circuit current in generator panels is 41,53 KA.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 150

13.3.1.2 Calculation of short-circuit current in Auxiliary Services

panel

The maximum short-circuit current on busbars of auxiliary services panel is determined

by T14 transformer.

Internal impedance of MV/LV

Data: %Ucc = 4 %

U20 = 400 V

Sn = 160 kVA

The maximum short-circuit current that could occur in auxiliary services line is 5,77 kA.

The switchgear provided in auxiliary services panel will have protection devices with a

breaking capacity above 5,77 kA.

13.3.2 Calculation of voltage drop

The rated voltage for the equipment to be installed in the plant is determined as a

function of supply voltage and considering a maximum voltage drop in internal circuits of

3% for lighting system and 5% for other equipment, according to the requirements of LV

regulations,

For plants directly supplied at high voltage by means of a separate distribution

transformer, the internal LV system will originate at the transformer outlet. In this case,

the maximum permissible voltage drop is 4,5% for lighting system and 6,5% for other

users.

13.3.2.1 Calculation of wire cross-section

(1) Current

The currents circulating through the wires in three-phase and single-phase systems are

determined from the following equations, respectively:

and ,

where:

cos3 U

PI

cosU

PI

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 151

I: current (A)

P: active power (W)

U: rated power (V)

cos : power factor

(2) Voltage drop

Voltage drop throughout the wires in three-phase and single-phase systems is determined

from the following equations, respectively:

and ,

where:

e: compound voltage drop (V)

L: wire length (m)

I: current in each phase or neutral (A)

cos : power factor

: wire electrical conductivity (m/ mm2)

S: wire cross-section (mm2)

The percentile value of voltage drop is:

.

We have considered an electrical conductivity of 56 and 35 m/ for Cu and Al

respectively.

S

ILe

cos3

S

ILe

cos2

)(

)(100(%)

VU

Vee

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 152

13.3.3 Voltage drop

Table 23.Voltage drop. Circuits of auxiliary services plant

Circuit No.

Description

Su

pp

ly

Sy

ste

m

Lo

ad

Pn

(W)

No

min

al

I(A

)

Le

ng

th

Wir

e

Ima

x

Description of protections D

U

D U

%

D U

To

t

D U

% T

ot

GSP-P1 SWITCHBOARD ENGINE ROOM 1 400

9760,56 17,61 60 4(1X35)+

G16 104 MCCB 4p 100A 0,64 0,16% 0,99 0,25%

GSP-P2 SWITCHBOARD ENGINE ROOM 2 400

9767,76 17,62 60 4(1X35)+

G16 104 MCCB 4p 100A 0,64 0,16% 0,99 0,25%

GSP-P3 CABINET ROOM SWITCHBOARD. ENTRANCE 400

2500 4,51 80 4(1X6)+G

6 36 MCCB 4p 20A 1,27 0,32% 1,62 0,40%

GSP-P4 CABINET ROOM SWITCHBOARD. GEN. CABINETS 400

4000 7,22 70 4(1X6)+G

6 36 MCCB 4p 25A 1,79 0,45% 2,14 0,53%

GSP-P5 R.M.S. SWITCHBOARD 400

2500 4,51 130 4(1X6)+G

6 36 MCCB 4p 20A 2,07 0,52% 2,41 0,60%

GSP-P6 ACCESS CONTROL SWITCHBOARD 400

1059,4 1,91 15 4(1X6)+G

6 36 MCCB 4p 25A 0,10 0,03% 0,45 0,11%

GSP-P7 OUTSIDE LIGHTING LAMPOST 400

4500 6,50 110 4(1X6)+G

6 36

MCCB 4p 20A + RCCB 4p 25A

300mA 3,94 0,99% 4,29 1,07%

GSP-P8 OUTSIDE LIGHTING. ENGINE ROOM FRONTAGE 400

3600 5,20 90 4(1X6)+G

6 36

MCCB 4p 20A + RCCB 4p 25A

300mA 2,58 0,64% 2,92 0,73%

GSP-P9 WATER PUMPS SWITCHBOARDS 400

0 0,00 0 4(1X10)+

G10 50

MCCB 4p 40A + RCCB 4p 40A

300mA 0,00 0,00% 0,35 0,09%

GSP-P10 OIL PUMPS SWITCHBOARDS 400

0 0,00 0 4(1X10)+

G10 50

MCCB 4p 40A + RCCB 4p 40A

300mA 0,00 0,00% 0,35 0,09%

GSP-P11 WORKSHOP SWITCHBOARD 400

7470,3 11,98 25 4(1X10)+

G10 50 MCCB 4p 32A 0,81 0,20% 1,16 0,29%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 153

Circuit No.

Description

Su

pp

ly

Sy

ste

m

Lo

ad

Pn

(W)

No

min

al

I(A

)

Le

ng

th

Wir

e

Ima

x

Description of protections D

U

D U

%

D U

To

t

D U

% T

ot

GSP-P12 RESERVE 400 0 Error 0 - 0 MCCB 4p 32A - - - -

GSP-P13 POWER OUTLET. MEETING ROOM AND MANAGER OFFICE 230

3680 16,00 28 2(1X2,5)+

G2,5 22 MCCB 2p 16A 7,48 3,25% 7,83 3,40%

GSP-P14 POWER OUTLET. CONTROL ROOM. 230

3680 16,00 20 2(1X2,5)+

G2,5 22 MCCB 2p 16A 5,34 2,32% 5,69 2,47%

GSP-P15 POWER OUTLET. VARIOUS AND CONTROL ROOM 230

3680 16,00 20 2(1X2,5)+

G2,5 22 MCCB 2p 16A 5,34 2,32% 5,69 2,47%

GSP-P16 RESERVE 230 0 Error 0 - 0 MCCB 2p 16A - - - -

GSP-P17 POWER OUTLET. VARIOUS DINING ROOM. 230

3680 16,00 28 2(1X2,5)+

G2,5 22 MCCB 2p 16A 7,48 3,25% 7,83 3,40%

GSP-P18 POWER OUTLET. DINING ROOM. 230

3680 16,00 26 2(1X2,5)+

G2,5 22 MCCB 2p 16A 6,95 3,02% 7,29 3,17%

GSP-P19 POWER OUTLET. DINING ROOM. 230

3680 16,00 28 2(1X2,5)+

G2,5 22 MCCB 2p 16A 7,48 3,25% 7,83 3,40%

GSP-P20 POWER OUTLET. BATHROOM. 230

3680 16,00 35 2(1X2,5)+

G2,5 22 MCCB 2p 16A 9,35 4,07% 9,70 4,22%

GSP-P21 POWER OUTLET. OUTSIDE. 230

3680 16,00 30 2(1X2,5)+

G2,5 22 MCCB 2p 16A 8,01 3,48% 8,36 3,64%

GSP-P22 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

GSP-P23 UPS SCADA 230

1000 4,35 8 2(1X2,5)+

G2,5 22

MCCB 2p 16A + RCCB 2p 25A

300mA 0,53 0,23% 0,88 0,38%

GSP-P24 FIRE-FIGHTING ALARM CONTROL 230

300 1,30 5 2(1X2,5)+

G2,5 22

MCCB 2p 16A + RCCB 2p 25A

300mA 0,10 0,04% 0,45 0,19%

GSP-P25 POWER OUTLET. COMPUTERS MEETING ROOM MANAGER OFFICE 230

3680 16,00 20 2(1X2,5)+

G2,5 22 MCCB 2p 16A 5,34 2,32% 5,69 2,47%

GSP-P26 POWER OUTLET. CONTROL ROOM COMPUTERS. 230

3680 16,00 15 2(1X2,5)+

G2,5 22 MCCB 2p 16A 4,01 1,74% 4,36 1,89%

GSP-P27 POWER OUTLET COMPUTERS CONTROL ROOM 230

3680 16,00 15 2(1X2,5)+

G2,5 22 MCCB 2p 16A 4,01 1,74% 4,36 1,89%

GSP-P28 POWER OUTLET COMPUTERS DINIDG ROOM 230

3680 16,00 20 2(1X2,5)+

G2,5 22 MCCB 2p 16A 5,34 2,32% 5,69 2,47%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 154

Circuit No.

Description

Su

pp

ly

Sy

ste

m

Lo

ad

Pn

(W)

No

min

al

I(A

)

Le

ng

th

Wir

e

Ima

x

Description of protections D

U

D U

%

D U

To

t

D U

% T

ot

GSP-P29 RACK PHONE CONTROL UNIT 230

500 2,17 10 2(1X2,5)+

G2,5 22 MCCB 2p 16A 0,33 0,14% 0,68 0,30%

GSP-P30 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

GSP-P31 AIR CONDITIONING SWITCHBOARD 400

0 0,00 0 4(1X10)+

G10 50

MCCB 4p 32A + 4p 40A 300mA

0,00 0,00% 0,35 0,09%

GSP-L1 LIGHTING MEETING ROOM MANAGER OFFICE 230

518 2,25 20 2(1X1,5)+

G1,5 16 MCCB 2p 10A 1,15 0,50% 1,49 0,65%

GSP-L2 LIGHTING CONTROL ROOM DINING ROOM 230

1144 4,97 20 2(1X1,5)+

G1,5 16 MCCB 2p 10A 2,57 1,12% 2,91 1,27%

GSP-L3 BATHROOM LIGHTING 230

712,8 3,10 30 2(1X1,5)+

G1,5 16 MCCB 2p 10A 2,37 1,03% 2,72 1,18%

GSP-E1 EMERGENCY LIGHTING 230 115,2 0,50 50 2(1X1,5) 16 MCCB 2p 10A 0,63 0,28% 0,98 0,43%

GSP-L4 FLUORESCENT LIGHTING TIGHT PORCH 1 230

417,6 1,82 20 2(1X1,5)+

G1,5 16 MCCB 2p 10A 0,92 0,40% 1,27 0,55%

GSP-L5 FLUORESCENT LIGHTING TIGHT PORCH 2 230

417,6 1,82 15 2(1X1,5)+

G1,5 16 MCCB 2p 10A 0,69 0,30% 1,04 0,45%

EN1-L1 HALL LIGHTING 230

1461,6 6,35 65 2(1X2,5)+

G2,5 22

MCCB 2p 10A + SR 2p 25A

6,38 2,77% 7,37 3,20%

EN1-L2 HALL LIGHTING 230

1461,6 6,35 68 2(1X2,5)+

G2,5 22

MCCB 2p 10A + SR 2p 25A

6,67 2,90% 7,66 3,33%

EN1-E1 EMERGENCY LIGHTING 230 72 0,31 68 2(1X1,5) 16 MCCB 2p 10A 0,54 0,23% 1,53 0,66%

EN1-L3 M1-M6 LIGHTING 230

1461,6 6,35 40 2(1X2,5)+

G2,5 44

MCCB 2p 10A + SR 2p 25A

3,88 1,69% 4,87 2,12%

EN1-L4 M7-M13 LIGHTING 230

1461,6 6,35 71 2(1X2,5)+

G2,5 22

MCCB 2p 10A + SR 2p 25A

6,97 3,03% 7,95 3,46%

EN1-L5 RESERVE 230 0

0 - 0 MCCB 2p 10A - - - -

EN1-P1 POWER SOCKET ENGINE ROOM 400

22170 32,00 70 4(1X16)+

G16 66 MCCB 4p 63A 4,81 1,20% 5,80 1,45%

EN1-P2 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

EN1-P3 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

EN2-L1 HALL LIGHTING 230

1461,6 6,35 65 2(1X2,5)+

G2,5 22

MCCB 2p 10A + SR 2p 25A

6,38 2,77% 7,37 3,20%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 155

Circuit No.

Description

Su

pp

ly

Sy

ste

m

Lo

ad

Pn

(W)

No

min

al

I(A

)

Le

ng

th

Wir

e

Ima

x

Description of protections D

U

D U

%

D U

To

t

D U

% T

ot

EN2-L2 HALL LIGHTING 230

1461,6 6,35 68 2(1X2,5)+

G2,5 22

MCCB 2p 10A + SR 2p 25A

6,67 2,90% 7,66 3,33%

EN2-E1 EMERGENCY LIGHTING 230 72 0,31 68 2(1X1,5) 16 MCCB 2p 10A 0,54 0,23% 1,53 0,66%

EN2-L3 M1-M6 LIGHTING 230

1461,6 6,35 40 2(1X2,5)+

G2,5 44

MCCB 2p 10A + SR 2p 25A

3,88 1,69% 4,87 2,12%

EN2-L4 M7-M13 LIGHTING 230

1461,6 6,35 71 2(1X2,5)+

G2,5 22

MCCB 2p 10A + SR 2p 25A

6,97 3,03% 7,96 3,46%

EN2-L5 RESERVE 230 0

0 - 0 MCCB 2p 10A - - - -

EN2-P1 POWER SOCKET ENGINE ROOM 400

22170 32,00 70 4(1X16)+

G16 66 MCCB 4p 63A 4,81 1,20% 5,80 1,45%

EN2-P2 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

EN2-P3 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

WP-L1 WORKSHOP LIGHTING 230

417,6 1,82 8 2(1X1,5)+

G1,5 16 MCCB 2p 10A 0,37 0,16% 1,52 0,66%

WP-L2 WAREHOUSE LIGHTING 230

1252,8 5,45 20 2(1X1,5)+

G1,5 16 MCCB 2p 10A 2,82 1,23% 3,98 1,73%

WP-L3 OIL STORAGE LIGHTING 230

417,6 1,82 22 2(1X1,5)+

G1,5 16 MCCB 2p 10A 1,01 0,44% 2,17 0,94%

WP-E1 EMERGENCY LIGHTING 230 57,6 0,25 28 2(1X1,5) 16 MCCB 2p 10A 0,18 0,08% 1,33 0,58%

WP-P1 POWER OUTLET WORKSHOP 230

3680 16,00 7 2(1X2,5)+

G2,5 22 MCCB 2p 16A 1,87 0,81% 3,03 1,32%

WP-P2 POWER OUTLET WAREHOUSE 230

3680 16,00 9 2(1X2,5)+

G2,5 22 MCCB 2p 16A 2,40 1,05% 3,56 1,55%

WP-P3 POWER OUTLET WAREHOUSE 230

3680 16,00 28 2(1X2,5)+

G2,5 22 MCCB 2p 16A 7,48 3,25% 8,64 3,75%

WP-P4 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

WP-P5 POWER OUTLET 3P+N+T 16A 400V 400

11085 16,00 7 4(1X2,5)+

G2,5 21 MCCB 4p 16A 1,63 0,41% 2,79 0,70%

WP-P6 RESERVE 230 0

0 - 0 MCCB 4p 16A - - - -

WP-P7 POWER SOCKET 400

22170 32,00 24 4(1X10)+

G10 50 MCCB 4p 40A 2,72 0,68% 3,88 0,97%

ACS-L1 ACCESS CONTROL LIGHTINT 230 306 1,33 6 2(1X1,5)+ 16 MCCB 2p 10A 0,20 0,09% 0,65 0,28%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 156

Circuit No.

Description

Su

pp

ly

Sy

ste

m

Lo

ad

Pn

(W)

No

min

al

I(A

)

Le

ng

th

Wir

e

Ima

x

Description of protections D

U

D U

%

D U

To

t

D U

% T

ot

EMERGENCY G1,5

ACS-L2 RESERVE 230 0

0 - 0 MCCB 2p 10A - - - -

ACS-P1 POWER OUTLET 230

3680 16,00 7 2(1X2,5)+

G2,5 22 MCCB 2p 16A 1,87 0,81% 2,32 1,01%

ACS-P2 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

ACS-P3 POWER OUTLET COMPUTERS 230

3680 16,00 8 2(1X2,5)+

G2,5 22 MCCB 2p 16A 2,14 0,93% 2,59 1,12%

ACS-P4 RESERVE 230 0

0 - 0 MCCB 2p 16A - - - -

ACS-P5 AUTOMATIC GATE SWITCHBOARD 400

0 0,00 0 4(1X6)+G

6 36

MCCB 4p 10A + RCCB4p 25A

300mA 0,00 0,00% 0,45 0,11%

Table 24.Voltage drop. Circuits of power and control cabinet

Circuit No.

Description

Su

pp

ly

Sy

ste

m

Lo

ad

Pn

(W)

No

min

al

I(A

)

Le

ng

th

Wir

e

Ima

x

Description of protectons D

U

D U

%

D U

To

t

D U

% T

ot

P&CC 400 1000000 1443,38 33

3[4(1X240)]+G

1820 CB4P 2000 A 0,91 0,23% 0,91 0,23%

P&CC-C1 AERO FAN 1 400

1800 3,25 40 3(1X2,5)+

G2,5 21 GV 3P 4-6,3A 1,10 0,27% 1,10 0,27%

P&CC-C2 AERO FAN 2 400

1800 3,25 40 3(1X2,5)+

G2,5 21 GV 3P 4-6,3A 1,10 0,27% 1,10 0,27%

P&CC-C3 AERO FAN 3 400

1800 3,25 40 3(1X2,5)+

G2,5 21 GV 3P 4-6,3A 1,10 0,27% 1,10 0,27%

P&CC-C4 AERO FAN 4 400

1800 3,25 40 3(1X2,5)+

G2,5 21 GV 3P 4-6,3A 1,10 0,27% 1,10 0,27%

P&CC-C5 AERO FAN 5 400

1800 3,25 40 3(1X2,5)+

G2,5 21 GV 3P 4-6,3A 1,10 0,27% 1,10 0,27%

P&CC-C6 AERO FAN 6 400

1800 3,25 40 3(1X2,5)+

G2,5 21 GV 3P 4-6,3A 1,10 0,27% 1,10 0,27%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 157

Circuit No.

Description

Su

pp

ly

Sy

ste

m

Lo

ad

Pn

(W)

No

min

al

I(A

)

Le

ng

th

Wir

e

Ima

x

Description of protectons D

U

D U

%

D U

To

t

D U

% T

ot

P&CC-C7 MAIN CIRC. WATER PUMP 400

5500 9,92 17 3(1X2,5)+

G2,5 21 GV 3P 9-14A 1,48 0,37% 1,48 0,37%

P&CC-C8 AUX. CIRC. WATER PUMP 400

2200 3,97 17 3(1X2,5)+

G2,5 21 GV 3P 4-6,3A 0,57 0,14% 0,57 0,14%

P&CC-C9 AERO ROOM FAN 400

3000 5,41 10 3(1X2,5)+

G2,5 21 GV 3P 6-10A 0,46 0,12% 0,46 0,12%

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 158

13.3.4 Lighting

The equipment in lighting circuits consuming power is listed below.

13.3.4.1 Engine bay

The lighting equipment consists of hermetically sealed fluorescent luminaries of 2x58W

The lighting system is controlled by means of push-buttons which actuate onstep relays.

The average luminance in these bays at working level is 407 lux.

The following picture shows the horizontal lighting matrix. Work plane. Values in lux.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 159

13.3.4.2 Social building

The lighting system in social building consists of hermetically sealed fluorescent luminaries.

Lighting of various compartments in this building will be controlled by means of switches.

Average luminance in office areas at working level will be above 500 lux.

Average luminance in warehouses and workshops at working level will be above 300 lux.

13.3.4.3 Outdoor lighting system

The outdoor lighting system will consist of two circuits.

GSP-P7 circuit- Outdoor Lighting Lampost

GSP-P8 circuit – Outdoor lighting. Engine bay frontage.

Outdoor lighting will be controlled by mean of an astronomical clock.

GSP-P7- Outdoor Lighting Lampost

This lighting system consists of luminaries provided with 250W sodium vapor lamps

supported by a lamppost 12 m high.

The luminance measured at working level is of about 22 lux.

The following picture shows the horizontal lighting matrix. Work plane. Values in lux.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 160

GSP- P8 Outdoor lighting. Engine bay frontage.

This lighting system consists of luminaries provided with sodium vapor lamps and fixed to

bay frontage.

Average luminance at working level is of about 48,2 lux.

The following picture shows the horizontal lighting matrix. Work plane. Values in lux.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 161

13.4 TESTING & INSPECTION

13.4.1 Verification by checking

Checking the installed material no showing visible damage affecting safety. Verify

that are installed under current regulations and instructions of the manufacturer

Existence and calibration of protective and signaling devices. All are correctly

identified.

Existence and availability of schemes, warning and information panels

Check the correct execution of the lead connections

13.4.2 Checksbymeasurement or test

Earthground resistance test

Protective conductor continuity test

insulation resistance test between live conductors

Dielectric testing

Checking the tripping time and current of differential relays

Phase sequence test

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 162

14 ENVIRONMENTAL POLLUTION SOURCES AND

MEASURES

14.1 STANDARDS BASIS OF DESIGN

The following directives and standards have been taken into account in environmental

matters:

Directive 2011/92/EU of the European Parliament and the Council of 13

December 2011 about assessment of aftermath of the effects of certain public and

private projects on the environment.

Directive 2010/75/EU of the European Parliament and of the Council of 24

November 2010 about industrial emissions (prevention and integrated control of

the pollution).

Directive 2008/98/EC of the European Parliament and of the Council of 19

November 2008 about waste and derogation of certain Directives.

Directive 2004/35/CE of the European Parliament and of the Council of 21 April

2004 about environmental liability related with the prevention and repairing of

environmental damages.

Directive 2002/49/EC of the European Parliament and of the Council of 25 June

2002 about assessment and management of environmental noise.

Directive 2001/80/EC of the European Parliament and of the Council of 23

October 2001 about limitations of air emissions of certain pollutants from large

combustion plants

Council Directive 96/61/EC of 24 September 1996 about prevention and control

of contamination.

EN-15259:2007 Air quality. Measurement of stationary source emissions.

Requirements for measurement sections and sites and for the measurement

objective, plan and report.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 163

14.2 LOCATION

The installation of 26 engines is located in industrial zone.

Near the location of the power plant does not exists towns or villages.

Near the power plant installation there is located a thermal power plant.

Picture 1. Location

14.3 RAW AND AUXILIARY MATERIALS

The raw material used is the engine fuel, natural gas.

For operation and maintenance of existing equipment, engines and transformers, are

needed lubricating oils, coolants and the own oil of the transformer.

The substances used are described below:

The safety data sheets are attached in Annex 1.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 164

Table 25. Substances used

Material Use Identification

of hazards

Means of

extinction

Storage

conditions

Sulfuric acid

37-38%

Loads of storage

batteries

Corrosive (C)

Reacts violently

with water

Water spray

Foam

Dry chemical

CO2

Sand

Storage

temperature

between 5 and 20 °

C.

Store in original

container protected

from

direct sunlight in a

dry, cool and well-

ventilated area

Lubricant oil

(Guascor

motoroil

3040 plus)

Lubricant oil for

engines

Not classified as

hazardous

Water spray

Foam

Dry chemical

CO2

Store in original

container protected

from

direct sunlight in a

dry, cool and well-

ventilated area

Antic. Cc

30%

Antifreeze for

cooling circuits

in internal

combustion

engines

Harmful (Xn)

All

extinguishing

agents are

allowed

Storage

temperature

between 5 and 40 °

C.

E-225

Hardener

Hardener for

paintings and/or

varnishes

Harmful (Xn)

Hazardous for

the environment

(N)

Flammable (R10)

Alcohol

resistant foam

CO2

Powder

Water

spray/mist

Storage

temperature

between 5 and 30 °

C.

Store in a dry, well

ventilated place

away from sources

of heat ignition and

direct sunlight

Urki-Nato Products for

mixing systems Flammable (R10)

Alcohol

resistant foam

CO2

Powder Water

spray/mist

Storage

temperature

between 5 and 30 °

C.

Store in a dry, well ventilated place

away from sources

of heat ignition and

direct sunlight

There are two warehouses for substances storage.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 165

One of them is an enclosed fenced area, under cover and properly identified. The

substances are stored in closed containers such as the distributor provides. In storage

substances are not handled. In this area are stored lubricant oils which are not dangerous.

The other warehouse is a storage building together at the oil storage, which keep the

other substances. This warehouse is protected with photoelectric smoke sensors.

The warehouses are located at the ending of the general services building next to the

parking.

The locations of the stores are identified in the plan No.: 31-01.1

14.4 AIR POLLUTION-EMISSION SOURCES

The power plant has 26 natural gas engines, each one with its own emission source of the

combustion gases.

The total thermal power associated with the 26 engines is higher than 50 MW

(approximately 67.26 MW, 2.6 MW each engine).

The total height of the smokestacks from the ground is 10.5 m. This height allows a good

dispersion of pollutants emitted.

The inside diameter of the smokestacks is 400 mm. All of the smokestacks have the same

dimensions.

The pollutants emitted into the atmosphere are NOx, CO and non-methane

hydrocarbons, (NMHC).

The emission control is done by measuring the gaseous pollutants in the sampling holes

above the silencers. View plan No.: 60-02.

The emissions balance emitted from smokestacks corrected to 5% O2 based NWMH C1,

are the following:

Table 26. Exhaust values

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 166

14.5 NOISE SOURCES

The noise associated with each generation engine at 1500 rpm with fuel full load

according to the manufacturer is:

Table 27. Total sound level with engine running continuously, at 1500 rpm and

100% power.

The exhaust chimneys have a silencer to reduce the noise of exhaust gases, and the

closure of the engine rooms has been built with sound deadening materials. With these

measures of insulation, the noise distribution map obtained is the following:

Picture 2. Noise distribution map

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 167

It’s possible to improve the noise level installing at the air ventilation inputs and outputs,

acoustic barriers that would improve the acoustic isolation. Ventilation has been designed

to allow this kind of improvement.

Picture 3. Noise distribution map with acoustic isolation at the air ventilation

system.

In this case the noise level reached in the surrounding industrial activities is lower than 45

dB (A). This level of noise is according with the current standards in noise matters for

industrial areas.

14.6 INDUSTRIAL SEWAGE WATER

The industrial sewage water associated with industrial activity carried out by power

generation of natural gas engines are the following:

o Network of sanitary sewage, from the existing toilets and showers. The sewage is

directed to a septic tank. It is a primary treatment unit of domestic sewage, inside is

performed the separation and physical-chemical transformation of solid matter

contained in those water. It is cleaned periodically by local operators.

o Network of rainwater from the downspouts from buildings. These waters do not

carry hazardous substances from the activity and go directly to the environment,

Hlawga Lake.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 168

o Network of rainwater from collection bunds of transformers. They are guided to the

intermediate manholes for each of the transformers. The manhole has valves that are

always closed so in case of accidental spill it can keep the residue in a safe place

pending of its removal. The spill is pumped into containers and taken to a local

operator for appropriate treatment. In case of rain, the manhole is checked to ensure

that it does not have any residue, and then the valve can be opened to drive the

rainwater to the network.

o Network of oil water from spills in the engine rooms, after passing through the grease

decanter. The waters spill from engines are carried to grease decanters where the oil

is separated from water by density and then the clean water passes to final discharge.

Greases are collected periodically for treatment by local operators.

o In the plan No.: 41-02, you can see the different wastewater networks.

14.7 INDUSTRIAL RESIDUES

The wastes generated in the activity are the following:

Table 28. Wastes generated

Waste Origin Storage Management

Motor oils and

lubricants used

Leaking engine and

motor circuits

In closed containers

in the warehouse

Treatment by local

manager

Waste coolant

(water glycols)

Accidental leakage

transformers

In closed containers

in the warehouse

Treatment by local

manager

Empty containers

with remnants of

hazardous

substances

Containers of

substances

In closed containers

in the warehouse

Treatment by local

manager

Absorbents and

cleaning cloths Clean spills

In closed containers

in the warehouse

Treatment by local

manager

There is an area identified for waste storage under deck and over concrete floor into the

warehouse.

The hazardous waste is regularly managed by local operators.

DOCUMENT ORDER DATE

Nov-2012

General technical report VEC001101 INDEX

CUSTOMER

ROYAL GK PTE LTD

CONSISTENTS WITH OUR CONTINUAL PRODUCT IMPROVEMENT POLICY, GUASCOR POWER RESERVES THE RIGHT TO CHANGE ANY SPECIFICATION WITHOUT PRIOR NOTICE. 169

14.8 ENVIRONMENTAL MEASURES FOR THE SITE SOIL

Industrial activity due to the power generation of the plant through gas fuel engines is

placed on native soil that never has hosted any other previous activity.

The plant has been designed according to an engineering basis “100% Environmentally

Friendly”, with the most advanced techniques in environmental matters.

The location where takes place the industrial activity has a concrete pavement that

protects the ground from spills of hazardous substances, and it is provided with a

drainage pipelines to avoid the uncontrolled spills.

There are two points of risk for ground contamination, spills from engines and

transformers. The spill risk is taken under control through the following measures:

The rooms where are placed the engines has a closures such as decks and

walls, and the floor is provided with a drainage network to drive the spills toward

a grease decanter manhole, which separate the oil from the water. The water

treated can be discharged in the lake near the plant and the grease will be

collected through pumps for its future management. The engines will be assembled

over a foundation to protect the ground of the building from vibrations and also

the accidentally spills.

The transformers are placed inside concrete cubes with the purpose of

keeping any oil spill and avoid its dispersion.

These spills are driven to separation manholes, one for each transformer,

which are connected to another larger manhole by valves that are always closed.

In case of rain, the content of the manholes is checked to ensure that there

are not any spills from transformers, and then the valve can be opened to

discharge the water in the large manhole, which is connected with the rain water

network.