General Aspects of Restoration
Transcript of General Aspects of Restoration
-
8/3/2019 General Aspects of Restoration
1/43
-
8/3/2019 General Aspects of Restoration
2/43
Definition of Grid Incident as per CEA
Grid Incident is tripping of one or more power system elements of theGrid like a Generator, Transmission Line, Transformer, Shunt Reactor,
Series Capacitor and Static VAR Compensator (SVC), which requires re-
scheduling of Generation or Load, without total loss of supply at a Sub-
Station or loss of integrity of the Grid at 220 kV and above (132 kV and
above in case of North Eastern Region)
Grid Disturbance is tripping of one or more power system elements of
the Grid like a Generator, Transmission Line, Transformer, Shunt
Reactor, Series Capacitor and Static VAR Compensator (SVC),resulting in total power failure or supply at a Sub-Station or loss of
integrity of the Grid, at the level of transmission system at 220 kV and
above ( 132 kV and above in the case of North Eastern Region ).
Definition of Grid Disturbance as per CEA
-
8/3/2019 General Aspects of Restoration
3/43
TYPE OF GRID INCIDENT
GI 1: Tripping of one or more power system elements of the Grid like a
Generator, Transmission Line, Transformer, Shunt Reactor, Series
Capacitor and Static VAR Compensator (SVC), which requires re-
scheduling of Generation or Load, without total loss of supply at aSub-Station or loss of integrity of the Grid at 220 kV (132 kV in case
of North Eastern Region)
GI 2: Tripping of one or more power system elements of the Grid like a
Generator, Transmission Line, Transformer, Shunt Reactor, Series
Capacitor and Static VAR Compensator (SVC), which requires re-scheduling of Generation or Load, without total loss of supply at a
Sub-Station or loss of integrity of the Grid at 400 kV and above (220
kV and above in case of North Eastern Region)
In increasing order of severity, Grid Incident (GI) is
categorized as
-
8/3/2019 General Aspects of Restoration
4/43
TYPE OF GRID DISTURBANCE
GD 1: When loss of antecedent generation / load is less than 10% in a
regional Grid
GD 2: When loss of antecedent generation / load is between 10% to less
than 20% in a regional Grid
GD 3: When loss of antecedent generation / load is between 20% to less
than 30% in a regional Grid
GD 4: When loss of antecedent generation / load is between 30% to lessthan 40% in a regional Grid
GD 5: When loss of antecedent generation / load is 40% or more
In increasing order of severity, Grid Disturbances(GD) is categorized as
-
8/3/2019 General Aspects of Restoration
5/43
Recovery ProceduresRecovery ProceduresA. Detailed plans and procedures for restoration of the regional grid under
partial/total blackout shall be developed by RLDC in consultation with NLDC,
all Users, STU,SLDC, CTU and RPC Secretariat and shall be reviewed /
updated annually.
B. Detailed plans and procedures for restoration after partial/total blackout of each
Users/STU/CTU system within a Region, will be finalized by the concerned
Users/STU/CTU in coordination with the RLDC. The procedure will be
reviewed, confirmed and/or revised once every subsequent year. Mock trial
runs of the procedure for different subsystems shall be carried out by theUsers/CTU/STU at least once every six months under intimation to the RLDC.
Diesel Generator sets for black start would be tested on weekly basis and test
report shall be sent to RLDC on quarterly basis.
-
8/3/2019 General Aspects of Restoration
6/43
C. List of generating stations with black start facility, inter-State/interregional ties, synchronizing points and essential loads to
be restored on priority, shall be prepared and be available with
NLDC, RLDC and SLDC.
D. The RLDC is authorised during the restoration process following
a black out, to operate with reduced security standards for
voltage and frequency as necessary in order to achieve the fastest
possible recovery of the grid.
E. All communication channels required for restoration process shall
be used for operational communication only, till grid normalcy is
restored.
-
8/3/2019 General Aspects of Restoration
7/43
-
8/3/2019 General Aspects of Restoration
8/43
Objective
RESTORING NORMAL SYSTEM OPERATION ASQUICKLY AS POSSIBLE
ESTABLISHING ALL INTERCONNECTIONS
RESTORING ESSENTIAL LOADS
SYNCHRONISING OF ATLEAST ONE UNIT AT ALLPOWER STATION
STARTING ALLOCATION OF C. S SHARE
STARTING ECONOMIC DISPATCH
MINIMIZING AMOUNT OF UNSERVED ENERGY
-
8/3/2019 General Aspects of Restoration
9/43
Possible System Problems
UNITUNIT
FAILUREFAILURE
UNITUNIT
FAILUREFAILURE
INSUFFICIENTINSUFFICIENT
GENERATIONGENERATION
INSUFFICIENTINSUFFICIENT
GENERATIONGENERATION
TRANSFORMER/TRANSFORMER/LINE FAILURELINE FAILURE
LOSS OFLOSS OF
LOADLOAD
LOSS OFLOSS OF
LOADLOAD
REDUCEDREDUCED
NETWORKNETWORK
REDUNDANCYREDUNDANCY
REDUCEDREDUCED
NETWORKNETWORK
REDUNDANCYREDUNDANCY
LINELINEOVERLOADOVERLOAD
OROR
UNSATISFACTUNSATISFACT
ORYORY
BUS VOLTAGEBUS VOLTAGE
LINELINEOVERLOADOVERLOAD
OROR
UNSATISFACTUNSATISFACT
ORYORY
BUS VOLTAGEBUS VOLTAGE
BUSBUS
ISOLATEDISOLATED
LOSS OFLOSS OF
GENERATIONGENERATION
LOSS OFLOSS OF
GENERATIONGENERATION
ISLANDINGISLANDINGISLANDINGISLANDING
SYSTEMSYSTEM
COLLAPSCOLLAPS
EE
-
8/3/2019 General Aspects of Restoration
10/43
Types of Blackouts
Localized
Partial System Full System With Outside support
Full System Without Outside support
Restoration strategy may be differentRestoration strategy may be different
for each type of outage !for each type of outage !
-
8/3/2019 General Aspects of Restoration
11/43
Causes of Blackouts
Conditions that could contribute to a system blackout:
Maintenance (Planned & forced) outages
Heavy/Uncontrolled loop flow through system
Changing generation patterns
Weather
Unexpected events/FAULTS
Relay mal-operation
Circuit breaker failure
-
8/3/2019 General Aspects of Restoration
12/43
Causes of Blackouts
Cascading Thermal over loads Voltage Instability
Dynamic Instability
Load Generation Imbalance
Thermal Limit
Voltage Limit
Stability Limit
Total Transfer capability
Time Horizon
Power Flow
-
8/3/2019 General Aspects of Restoration
13/43
Causes of Blackouts
Common Sequence of events in blackouts
InitiatingInitiating
EventsEvents
FormatioFormatio
n ofn of
IslandsIslands
SystemSystem
SeparationSeparation
Load /GenerationLoad /GenerationImbalance inImbalance in
islandsislands
Blackout ofBlackout of
IslandsIslands
BeginBeginRestorationRestoration
ProcessProcess
-
8/3/2019 General Aspects of Restoration
14/43
TIME CONSUMING NATURE OF SWITCHING
OPERATION
START-UP TIMINGS OF THERMAL UNITS
COLD LOAD INRUSH, POWER FACTORS AND
COINCIDENT DEMAND FACTORS
AVAILABILITY OF GOVERNOR FACILITIES OF
UNITS
Common Concerns
-
8/3/2019 General Aspects of Restoration
15/43
Problems /Constraints
RE-ASSEMBLING TIE ELEMENTS OF POWER
SYSTEM.
IMPAIRED COMMUNICATIONS,LIMITED
INFORMATION.
NON-AVAILABILITY OF SCADA/EMS
APPLICATION SYSTEM.
UNFAMILIARITY WITH THE SITUATION(DOES NOT OCCUR REGULARLY)
TIME CONSTRAINTS
-
8/3/2019 General Aspects of Restoration
16/43
Restoration Tasks
INITIAL ASSESSMENT
SYSTEM STATUS DETERMINATION
PLANT PREPARATIONSERVICES/START-UP
NETWORK PREPARATION
NETWORK ENERGISATION LOAD RESTORATION
SYSTEM REBUILDING
-
8/3/2019 General Aspects of Restoration
17/43
INITIAL COURSE OF ACTION
Assess extent of black out
Check whether any sub-system/island is alive or not
Check the interconnection with other region(s)
Appraise the severity of disturbance to all concerned
Chalk out the optimum path for restoration
Defer all planned outage as per IEGC 5.74 (g)
Power Station /
Sub-station
Open all circuit breakers
Note relay indications and reset them
Check for damage or technical snag
developed at any element
RLDC
-
8/3/2019 General Aspects of Restoration
18/43
Important Considerations during RestorationRLDC / SLDC
Generating Stations having black-startfacilities start up immediately.
Generation availability in each island / subsystem to be ensured
Transmission lines available in theinterconnection between islands / sub
systems to be ensured.
Coordinate the load pick-ups with theramp rate of generation to maintain
sustainable frequency (around 50 Hz) .
Proper coordinationbefore
synchronization of two islands
Risky synchronization should beavoided
Load to be added in small steps withsmaller and radial loads preceding
larger load.
Restoration work should be shared &coordinated among the shift
personnel
Shift personnel should preferably beretained till restoration is over
Shift personnel of sub/power-stationshall be promptly formulated the
restoration strategy to be adopted
-
8/3/2019 General Aspects of Restoration
19/43
Power / Sub-Station
Important Considerations during Restoration
Governor and AVR are to be kept in
manual mode, if required
A reasonable active to reactive power
ratio is to be maintained to operate the
machine normally
Auxiliary power to be readily
available
Total auxiliary power drawn is to be
kept within 3% of the sources
capacity
Ascertain whether machines can
supply the power, while releasing
loads
Tap Position of Transformer,
Bus Voltage and frequency shall
be closely monitored to avertover fluxing
UFRs, SPS, UVR to be kept
deactivated
-
8/3/2019 General Aspects of Restoration
20/43
Special Consideration in extending/availing start up power
Power Plant Operators should be able to differentiate between
Full auxiliary power needed to start all machines
Minimum auxiliary power needed to start a minimumnumber of machines
Considerations to be kept in mind for availing start up power
Nearness to the source 132 kV lines vis --vis 220 kV/ 400 kV lines
Shorter route having a number of intermediate sub-stations
Longer route having very few/ no intermediate sub-stations
-
8/3/2019 General Aspects of Restoration
21/43
Clear-cut authority should be given to SLDC for extending start
up power from one sub-system to another sub-system or from one
constituent to another constituent as
oLine through which start up power is to be extended
oQuantum of such start up power
oNormal time period admissible Concerned SLDC should also be empowered to resort to load
shedding or bring up additional generation wherever possible, to
extend start up power to neighboring sub- systems/constituentsduring the period of crisis.
Special Consideration in extending/availing start up power
-
8/3/2019 General Aspects of Restoration
22/43
SOME DONTS
Do not panic
Do not load any generator beyond
80% of its capacity
Do not load any line/ICT beyond80% of its capacity
Do not hastily connect loads andensure that the island / sub-system
frequency be within sustainable
range
Extended power should not bewithdrawn except in case of extreme
emergency and without intimation to
RLDC
No communication disputes should beraised during the restoration period.
Load dispatch centers should not bedisturbed while discharging their duties
and expected to function as Management
information system.
-
8/3/2019 General Aspects of Restoration
23/43
Restoration Process
Bottom-up/Build-up StrategyBottom-up/Build-up StrategySteps involved in the Bottom-up Strategy
Select units to black-start.
Start and stabilize black-start units.
Determine restoration transmission path.
Begin expanding island(s) by restoringtransmission and load.
Synchronize island(s) when appropriate.
-
8/3/2019 General Aspects of Restoration
24/43
Build-up StrategyMultiple island Method of Restoration
-
8/3/2019 General Aspects of Restoration
25/43
Build-up StrategyCore island Method of Restoration
-
8/3/2019 General Aspects of Restoration
26/43
Build-up Strategy
Backbone island Method ofRestoration
-
8/3/2019 General Aspects of Restoration
27/43
Restoration Process
Restore backbone transmission system, usually from
outside assistance. Restore critical generating station and substation load
from transmission system.
Bring more generation. Restore underlying transmission system.
Continue restoring load.
p-down / Build down strategy
-
8/3/2019 General Aspects of Restoration
28/43
Build-Down Strategy
Core island Method of Restoration
-
8/3/2019 General Aspects of Restoration
29/43
Combination Approach
Combines the Build-up and Build-down
approach.
Steps in this approach include:Restoring transmission from an outside source at the
same time as building islands of generation.
Interconnecting islands with each other or outside
source when able.
-
8/3/2019 General Aspects of Restoration
30/43
-
8/3/2019 General Aspects of Restoration
31/43
Selection of Restoration
Strategy
Restoration method chosen depends on:
Extent of blackout
Availability of outside assistance
Availability of internal black-start generation
Utility philosophy/procedure
-
8/3/2019 General Aspects of Restoration
32/43
Load Restoration
Priority load for restoration
Generating Unit auxiliary power
Nuclear Station auxiliary power
Substation light and power
Traction Supplies
Supply to Collieries Natural gas or oil supply facilities
-
8/3/2019 General Aspects of Restoration
33/43
-
8/3/2019 General Aspects of Restoration
34/43
POWER STATION INSTALLEDCAPACITY
(MW)
UNITTYPE
START UPFACILITY
BLACK STARTFACILITY
SOURCE CAPACITYin
kVA
KHANDONG 2*25 HYDRO DG SET 1X250 YES
KHANDONG (KOPILI STII)
25 HYDRO DG SET 1X125 YES
KOPILI
4*50 HYDRO DG SET 1X600 YES
DOYANG 3*25 HYDRO DG SET 2X625 YES
RANGANADI 3*135 HYDRO DG SET 1x500 YES
R. C. NAGAR 4*21 GAS DG SET 1X250 YES
KATHALGURI 4*33.66+2*35+3*30
GAS+STEAM DG SET 1X950;1X250
NO
ISGS : NEEPCO
contd
ISGS : NHPC
-
8/3/2019 General Aspects of Restoration
35/43
POWER STATION INSTALLEDCAPACITY(MW)
UNITTYPE
START UPFACILITY
BLACK STARTFACILITY
SOURCE CAPACITYin
kVA
LOKTAK 3*35 HYDRO DG SET 2X315 YES
ISGS : NHPC
POWER STATION INSTALLEDCAPACITY(MW)
UNITTYPE
START UPFACILITY
BLACK STARTFACILITY
SOURCE CAPACITY inkVA
NAMRUP 3*23+12.5+30+22 GAS DG SET 844 YES
LAKWA 4*15+3*20 GAS NO NO NO
ADAMTILA(IPP-DLF)
3*3+5 GAS GRIDPOWER
NA NO
BASKANDI 3*3.5 GAS GRIDPOWER
NA NO
KARBI LANGPI 2*50 HYDRO DG SET 1X500 YES
STATE : ASSAM
contd
-
8/3/2019 General Aspects of Restoration
36/43
POWER STATION INSTALLEDCAPACITY(MW)
UNITTYPE
START UPFACILITY
BLACK STARTFACILITY
SOURCE CAPACITY in
Volt
UMIUM ST I 4*9 HYDRO BatteryBank
110 YES
UMIUM ST II 2*9 HYDRO BatteryBank
110 YES
UMIUM ST III 2*30 HYDRO BatteryBank
110 YES
UMIUM ST IV 2*30 HYDRO Battery
Bank
220 YES
UMTRU 4*2.8 HYDRO BatteryBank
110 YES
STATE : MEGHALAYA
contd
-
8/3/2019 General Aspects of Restoration
37/43
POWER STATION INSTALLEDCAPACITY(MW)
UNITTYPE
START UPFACILITY
BLACK STARTFACILITY
SOURCE CAPACITY inkVA
GUMTI 3*5 HYDRO NO NO NO
BARAMURA 2*5+6.5+21 GAS DG SET 1X380 YES
ROKHIA 6*8+21 GAS DG SET 2X380 YES
STATE : TRIPURA
-
8/3/2019 General Aspects of Restoration
38/43
Synchronizing facilities at power
stations / major Sub-Stations
in NER
-
8/3/2019 General Aspects of Restoration
39/43
-
8/3/2019 General Aspects of Restoration
40/43
SUB-STATIONS VOLTAGELEVEL
(kV)
SYNCHRONISINGFACILITY
DG SETDETAILS
in kVA
HALFLONG 132 YES 1X63
AIZWAL 132 YES 1X63
KUMARGHAT 132 YES(NOT OPERATIONAL) 1X63
BADARPUR 132 YES 1X100
KHLIEHRIAT 132 YES 1X100
NIRJULI 132 YES 1X100
ZIRO 132 YES 1X100
contd
CTU : POWERGRID
-
8/3/2019 General Aspects of Restoration
41/43
SUB-STATIONS VOLTAGELEVEL
(kV)
SYNCHRONISINGFACILITY
DG SETDETAILS
inkVA
BTPS 220 YES NO
SARUSAJAI 220 YES NO
SAMAGURI 220 YES(NOT OPERATIONAL) NO
MARIANI 220 YES NO
TINSUKIA 220 YES NO
KAHELIPARA 132 YES 1X30
DEPOTA 132 YES(NOT OPERATIONAL) NO
STATE : ASSAM
contd
-
8/3/2019 General Aspects of Restoration
42/43
SUB-STATIONS VOLTAGELEVEL
(kV)
SYNCHRONISINGFACILITY
79 TILLA(AGARTALA)
132 YES
STATE : TRIPURA
SUB-STATIONS VOLTAGELEVEL
(kV)
SYNCHRONISINGFACILITY
UMIUM STG-I 132 YES
UMIUM STG-III 132 YES
STATE : MEGHALAYA
-
8/3/2019 General Aspects of Restoration
43/43