General Aspects of Restoration

download General Aspects of Restoration

of 43

Transcript of General Aspects of Restoration

  • 8/3/2019 General Aspects of Restoration

    1/43

  • 8/3/2019 General Aspects of Restoration

    2/43

    Definition of Grid Incident as per CEA

    Grid Incident is tripping of one or more power system elements of theGrid like a Generator, Transmission Line, Transformer, Shunt Reactor,

    Series Capacitor and Static VAR Compensator (SVC), which requires re-

    scheduling of Generation or Load, without total loss of supply at a Sub-

    Station or loss of integrity of the Grid at 220 kV and above (132 kV and

    above in case of North Eastern Region)

    Grid Disturbance is tripping of one or more power system elements of

    the Grid like a Generator, Transmission Line, Transformer, Shunt

    Reactor, Series Capacitor and Static VAR Compensator (SVC),resulting in total power failure or supply at a Sub-Station or loss of

    integrity of the Grid, at the level of transmission system at 220 kV and

    above ( 132 kV and above in the case of North Eastern Region ).

    Definition of Grid Disturbance as per CEA

  • 8/3/2019 General Aspects of Restoration

    3/43

    TYPE OF GRID INCIDENT

    GI 1: Tripping of one or more power system elements of the Grid like a

    Generator, Transmission Line, Transformer, Shunt Reactor, Series

    Capacitor and Static VAR Compensator (SVC), which requires re-

    scheduling of Generation or Load, without total loss of supply at aSub-Station or loss of integrity of the Grid at 220 kV (132 kV in case

    of North Eastern Region)

    GI 2: Tripping of one or more power system elements of the Grid like a

    Generator, Transmission Line, Transformer, Shunt Reactor, Series

    Capacitor and Static VAR Compensator (SVC), which requires re-scheduling of Generation or Load, without total loss of supply at a

    Sub-Station or loss of integrity of the Grid at 400 kV and above (220

    kV and above in case of North Eastern Region)

    In increasing order of severity, Grid Incident (GI) is

    categorized as

  • 8/3/2019 General Aspects of Restoration

    4/43

    TYPE OF GRID DISTURBANCE

    GD 1: When loss of antecedent generation / load is less than 10% in a

    regional Grid

    GD 2: When loss of antecedent generation / load is between 10% to less

    than 20% in a regional Grid

    GD 3: When loss of antecedent generation / load is between 20% to less

    than 30% in a regional Grid

    GD 4: When loss of antecedent generation / load is between 30% to lessthan 40% in a regional Grid

    GD 5: When loss of antecedent generation / load is 40% or more

    In increasing order of severity, Grid Disturbances(GD) is categorized as

  • 8/3/2019 General Aspects of Restoration

    5/43

    Recovery ProceduresRecovery ProceduresA. Detailed plans and procedures for restoration of the regional grid under

    partial/total blackout shall be developed by RLDC in consultation with NLDC,

    all Users, STU,SLDC, CTU and RPC Secretariat and shall be reviewed /

    updated annually.

    B. Detailed plans and procedures for restoration after partial/total blackout of each

    Users/STU/CTU system within a Region, will be finalized by the concerned

    Users/STU/CTU in coordination with the RLDC. The procedure will be

    reviewed, confirmed and/or revised once every subsequent year. Mock trial

    runs of the procedure for different subsystems shall be carried out by theUsers/CTU/STU at least once every six months under intimation to the RLDC.

    Diesel Generator sets for black start would be tested on weekly basis and test

    report shall be sent to RLDC on quarterly basis.

  • 8/3/2019 General Aspects of Restoration

    6/43

    C. List of generating stations with black start facility, inter-State/interregional ties, synchronizing points and essential loads to

    be restored on priority, shall be prepared and be available with

    NLDC, RLDC and SLDC.

    D. The RLDC is authorised during the restoration process following

    a black out, to operate with reduced security standards for

    voltage and frequency as necessary in order to achieve the fastest

    possible recovery of the grid.

    E. All communication channels required for restoration process shall

    be used for operational communication only, till grid normalcy is

    restored.

  • 8/3/2019 General Aspects of Restoration

    7/43

  • 8/3/2019 General Aspects of Restoration

    8/43

    Objective

    RESTORING NORMAL SYSTEM OPERATION ASQUICKLY AS POSSIBLE

    ESTABLISHING ALL INTERCONNECTIONS

    RESTORING ESSENTIAL LOADS

    SYNCHRONISING OF ATLEAST ONE UNIT AT ALLPOWER STATION

    STARTING ALLOCATION OF C. S SHARE

    STARTING ECONOMIC DISPATCH

    MINIMIZING AMOUNT OF UNSERVED ENERGY

  • 8/3/2019 General Aspects of Restoration

    9/43

    Possible System Problems

    UNITUNIT

    FAILUREFAILURE

    UNITUNIT

    FAILUREFAILURE

    INSUFFICIENTINSUFFICIENT

    GENERATIONGENERATION

    INSUFFICIENTINSUFFICIENT

    GENERATIONGENERATION

    TRANSFORMER/TRANSFORMER/LINE FAILURELINE FAILURE

    LOSS OFLOSS OF

    LOADLOAD

    LOSS OFLOSS OF

    LOADLOAD

    REDUCEDREDUCED

    NETWORKNETWORK

    REDUNDANCYREDUNDANCY

    REDUCEDREDUCED

    NETWORKNETWORK

    REDUNDANCYREDUNDANCY

    LINELINEOVERLOADOVERLOAD

    OROR

    UNSATISFACTUNSATISFACT

    ORYORY

    BUS VOLTAGEBUS VOLTAGE

    LINELINEOVERLOADOVERLOAD

    OROR

    UNSATISFACTUNSATISFACT

    ORYORY

    BUS VOLTAGEBUS VOLTAGE

    BUSBUS

    ISOLATEDISOLATED

    LOSS OFLOSS OF

    GENERATIONGENERATION

    LOSS OFLOSS OF

    GENERATIONGENERATION

    ISLANDINGISLANDINGISLANDINGISLANDING

    SYSTEMSYSTEM

    COLLAPSCOLLAPS

    EE

  • 8/3/2019 General Aspects of Restoration

    10/43

    Types of Blackouts

    Localized

    Partial System Full System With Outside support

    Full System Without Outside support

    Restoration strategy may be differentRestoration strategy may be different

    for each type of outage !for each type of outage !

  • 8/3/2019 General Aspects of Restoration

    11/43

    Causes of Blackouts

    Conditions that could contribute to a system blackout:

    Maintenance (Planned & forced) outages

    Heavy/Uncontrolled loop flow through system

    Changing generation patterns

    Weather

    Unexpected events/FAULTS

    Relay mal-operation

    Circuit breaker failure

  • 8/3/2019 General Aspects of Restoration

    12/43

    Causes of Blackouts

    Cascading Thermal over loads Voltage Instability

    Dynamic Instability

    Load Generation Imbalance

    Thermal Limit

    Voltage Limit

    Stability Limit

    Total Transfer capability

    Time Horizon

    Power Flow

  • 8/3/2019 General Aspects of Restoration

    13/43

    Causes of Blackouts

    Common Sequence of events in blackouts

    InitiatingInitiating

    EventsEvents

    FormatioFormatio

    n ofn of

    IslandsIslands

    SystemSystem

    SeparationSeparation

    Load /GenerationLoad /GenerationImbalance inImbalance in

    islandsislands

    Blackout ofBlackout of

    IslandsIslands

    BeginBeginRestorationRestoration

    ProcessProcess

  • 8/3/2019 General Aspects of Restoration

    14/43

    TIME CONSUMING NATURE OF SWITCHING

    OPERATION

    START-UP TIMINGS OF THERMAL UNITS

    COLD LOAD INRUSH, POWER FACTORS AND

    COINCIDENT DEMAND FACTORS

    AVAILABILITY OF GOVERNOR FACILITIES OF

    UNITS

    Common Concerns

  • 8/3/2019 General Aspects of Restoration

    15/43

    Problems /Constraints

    RE-ASSEMBLING TIE ELEMENTS OF POWER

    SYSTEM.

    IMPAIRED COMMUNICATIONS,LIMITED

    INFORMATION.

    NON-AVAILABILITY OF SCADA/EMS

    APPLICATION SYSTEM.

    UNFAMILIARITY WITH THE SITUATION(DOES NOT OCCUR REGULARLY)

    TIME CONSTRAINTS

  • 8/3/2019 General Aspects of Restoration

    16/43

    Restoration Tasks

    INITIAL ASSESSMENT

    SYSTEM STATUS DETERMINATION

    PLANT PREPARATIONSERVICES/START-UP

    NETWORK PREPARATION

    NETWORK ENERGISATION LOAD RESTORATION

    SYSTEM REBUILDING

  • 8/3/2019 General Aspects of Restoration

    17/43

    INITIAL COURSE OF ACTION

    Assess extent of black out

    Check whether any sub-system/island is alive or not

    Check the interconnection with other region(s)

    Appraise the severity of disturbance to all concerned

    Chalk out the optimum path for restoration

    Defer all planned outage as per IEGC 5.74 (g)

    Power Station /

    Sub-station

    Open all circuit breakers

    Note relay indications and reset them

    Check for damage or technical snag

    developed at any element

    RLDC

  • 8/3/2019 General Aspects of Restoration

    18/43

    Important Considerations during RestorationRLDC / SLDC

    Generating Stations having black-startfacilities start up immediately.

    Generation availability in each island / subsystem to be ensured

    Transmission lines available in theinterconnection between islands / sub

    systems to be ensured.

    Coordinate the load pick-ups with theramp rate of generation to maintain

    sustainable frequency (around 50 Hz) .

    Proper coordinationbefore

    synchronization of two islands

    Risky synchronization should beavoided

    Load to be added in small steps withsmaller and radial loads preceding

    larger load.

    Restoration work should be shared &coordinated among the shift

    personnel

    Shift personnel should preferably beretained till restoration is over

    Shift personnel of sub/power-stationshall be promptly formulated the

    restoration strategy to be adopted

  • 8/3/2019 General Aspects of Restoration

    19/43

    Power / Sub-Station

    Important Considerations during Restoration

    Governor and AVR are to be kept in

    manual mode, if required

    A reasonable active to reactive power

    ratio is to be maintained to operate the

    machine normally

    Auxiliary power to be readily

    available

    Total auxiliary power drawn is to be

    kept within 3% of the sources

    capacity

    Ascertain whether machines can

    supply the power, while releasing

    loads

    Tap Position of Transformer,

    Bus Voltage and frequency shall

    be closely monitored to avertover fluxing

    UFRs, SPS, UVR to be kept

    deactivated

  • 8/3/2019 General Aspects of Restoration

    20/43

    Special Consideration in extending/availing start up power

    Power Plant Operators should be able to differentiate between

    Full auxiliary power needed to start all machines

    Minimum auxiliary power needed to start a minimumnumber of machines

    Considerations to be kept in mind for availing start up power

    Nearness to the source 132 kV lines vis --vis 220 kV/ 400 kV lines

    Shorter route having a number of intermediate sub-stations

    Longer route having very few/ no intermediate sub-stations

  • 8/3/2019 General Aspects of Restoration

    21/43

    Clear-cut authority should be given to SLDC for extending start

    up power from one sub-system to another sub-system or from one

    constituent to another constituent as

    oLine through which start up power is to be extended

    oQuantum of such start up power

    oNormal time period admissible Concerned SLDC should also be empowered to resort to load

    shedding or bring up additional generation wherever possible, to

    extend start up power to neighboring sub- systems/constituentsduring the period of crisis.

    Special Consideration in extending/availing start up power

  • 8/3/2019 General Aspects of Restoration

    22/43

    SOME DONTS

    Do not panic

    Do not load any generator beyond

    80% of its capacity

    Do not load any line/ICT beyond80% of its capacity

    Do not hastily connect loads andensure that the island / sub-system

    frequency be within sustainable

    range

    Extended power should not bewithdrawn except in case of extreme

    emergency and without intimation to

    RLDC

    No communication disputes should beraised during the restoration period.

    Load dispatch centers should not bedisturbed while discharging their duties

    and expected to function as Management

    information system.

  • 8/3/2019 General Aspects of Restoration

    23/43

    Restoration Process

    Bottom-up/Build-up StrategyBottom-up/Build-up StrategySteps involved in the Bottom-up Strategy

    Select units to black-start.

    Start and stabilize black-start units.

    Determine restoration transmission path.

    Begin expanding island(s) by restoringtransmission and load.

    Synchronize island(s) when appropriate.

  • 8/3/2019 General Aspects of Restoration

    24/43

    Build-up StrategyMultiple island Method of Restoration

  • 8/3/2019 General Aspects of Restoration

    25/43

    Build-up StrategyCore island Method of Restoration

  • 8/3/2019 General Aspects of Restoration

    26/43

    Build-up Strategy

    Backbone island Method ofRestoration

  • 8/3/2019 General Aspects of Restoration

    27/43

    Restoration Process

    Restore backbone transmission system, usually from

    outside assistance. Restore critical generating station and substation load

    from transmission system.

    Bring more generation. Restore underlying transmission system.

    Continue restoring load.

    p-down / Build down strategy

  • 8/3/2019 General Aspects of Restoration

    28/43

    Build-Down Strategy

    Core island Method of Restoration

  • 8/3/2019 General Aspects of Restoration

    29/43

    Combination Approach

    Combines the Build-up and Build-down

    approach.

    Steps in this approach include:Restoring transmission from an outside source at the

    same time as building islands of generation.

    Interconnecting islands with each other or outside

    source when able.

  • 8/3/2019 General Aspects of Restoration

    30/43

  • 8/3/2019 General Aspects of Restoration

    31/43

    Selection of Restoration

    Strategy

    Restoration method chosen depends on:

    Extent of blackout

    Availability of outside assistance

    Availability of internal black-start generation

    Utility philosophy/procedure

  • 8/3/2019 General Aspects of Restoration

    32/43

    Load Restoration

    Priority load for restoration

    Generating Unit auxiliary power

    Nuclear Station auxiliary power

    Substation light and power

    Traction Supplies

    Supply to Collieries Natural gas or oil supply facilities

  • 8/3/2019 General Aspects of Restoration

    33/43

  • 8/3/2019 General Aspects of Restoration

    34/43

    POWER STATION INSTALLEDCAPACITY

    (MW)

    UNITTYPE

    START UPFACILITY

    BLACK STARTFACILITY

    SOURCE CAPACITYin

    kVA

    KHANDONG 2*25 HYDRO DG SET 1X250 YES

    KHANDONG (KOPILI STII)

    25 HYDRO DG SET 1X125 YES

    KOPILI

    4*50 HYDRO DG SET 1X600 YES

    DOYANG 3*25 HYDRO DG SET 2X625 YES

    RANGANADI 3*135 HYDRO DG SET 1x500 YES

    R. C. NAGAR 4*21 GAS DG SET 1X250 YES

    KATHALGURI 4*33.66+2*35+3*30

    GAS+STEAM DG SET 1X950;1X250

    NO

    ISGS : NEEPCO

    contd

    ISGS : NHPC

  • 8/3/2019 General Aspects of Restoration

    35/43

    POWER STATION INSTALLEDCAPACITY(MW)

    UNITTYPE

    START UPFACILITY

    BLACK STARTFACILITY

    SOURCE CAPACITYin

    kVA

    LOKTAK 3*35 HYDRO DG SET 2X315 YES

    ISGS : NHPC

    POWER STATION INSTALLEDCAPACITY(MW)

    UNITTYPE

    START UPFACILITY

    BLACK STARTFACILITY

    SOURCE CAPACITY inkVA

    NAMRUP 3*23+12.5+30+22 GAS DG SET 844 YES

    LAKWA 4*15+3*20 GAS NO NO NO

    ADAMTILA(IPP-DLF)

    3*3+5 GAS GRIDPOWER

    NA NO

    BASKANDI 3*3.5 GAS GRIDPOWER

    NA NO

    KARBI LANGPI 2*50 HYDRO DG SET 1X500 YES

    STATE : ASSAM

    contd

  • 8/3/2019 General Aspects of Restoration

    36/43

    POWER STATION INSTALLEDCAPACITY(MW)

    UNITTYPE

    START UPFACILITY

    BLACK STARTFACILITY

    SOURCE CAPACITY in

    Volt

    UMIUM ST I 4*9 HYDRO BatteryBank

    110 YES

    UMIUM ST II 2*9 HYDRO BatteryBank

    110 YES

    UMIUM ST III 2*30 HYDRO BatteryBank

    110 YES

    UMIUM ST IV 2*30 HYDRO Battery

    Bank

    220 YES

    UMTRU 4*2.8 HYDRO BatteryBank

    110 YES

    STATE : MEGHALAYA

    contd

  • 8/3/2019 General Aspects of Restoration

    37/43

    POWER STATION INSTALLEDCAPACITY(MW)

    UNITTYPE

    START UPFACILITY

    BLACK STARTFACILITY

    SOURCE CAPACITY inkVA

    GUMTI 3*5 HYDRO NO NO NO

    BARAMURA 2*5+6.5+21 GAS DG SET 1X380 YES

    ROKHIA 6*8+21 GAS DG SET 2X380 YES

    STATE : TRIPURA

  • 8/3/2019 General Aspects of Restoration

    38/43

    Synchronizing facilities at power

    stations / major Sub-Stations

    in NER

  • 8/3/2019 General Aspects of Restoration

    39/43

  • 8/3/2019 General Aspects of Restoration

    40/43

    SUB-STATIONS VOLTAGELEVEL

    (kV)

    SYNCHRONISINGFACILITY

    DG SETDETAILS

    in kVA

    HALFLONG 132 YES 1X63

    AIZWAL 132 YES 1X63

    KUMARGHAT 132 YES(NOT OPERATIONAL) 1X63

    BADARPUR 132 YES 1X100

    KHLIEHRIAT 132 YES 1X100

    NIRJULI 132 YES 1X100

    ZIRO 132 YES 1X100

    contd

    CTU : POWERGRID

  • 8/3/2019 General Aspects of Restoration

    41/43

    SUB-STATIONS VOLTAGELEVEL

    (kV)

    SYNCHRONISINGFACILITY

    DG SETDETAILS

    inkVA

    BTPS 220 YES NO

    SARUSAJAI 220 YES NO

    SAMAGURI 220 YES(NOT OPERATIONAL) NO

    MARIANI 220 YES NO

    TINSUKIA 220 YES NO

    KAHELIPARA 132 YES 1X30

    DEPOTA 132 YES(NOT OPERATIONAL) NO

    STATE : ASSAM

    contd

  • 8/3/2019 General Aspects of Restoration

    42/43

    SUB-STATIONS VOLTAGELEVEL

    (kV)

    SYNCHRONISINGFACILITY

    79 TILLA(AGARTALA)

    132 YES

    STATE : TRIPURA

    SUB-STATIONS VOLTAGELEVEL

    (kV)

    SYNCHRONISINGFACILITY

    UMIUM STG-I 132 YES

    UMIUM STG-III 132 YES

    STATE : MEGHALAYA

  • 8/3/2019 General Aspects of Restoration

    43/43