Gate Installation Work Procedures

12
3x15MW WAMPU HEPP PROJECT DOCU. NO. : 1000-0175-EM-463-000 Rev. No. : A Page. No : Cover TITLE GATE INSTALLATION WORK PROCEDURES GATE INSTALLATION WORK PROCEDURES DISCIPLINE : MECHENICAL PROJECT NAME : 3×15MW WAMPU HEPP PROJECT

description

How to install gate

Transcript of Gate Installation Work Procedures

  • 3x15MW WAMPU HEPP PROJECTDOCU. NO. :1000-0175-EM-463-000

    Rev. No. : A

    Page. No : CoverTITLE GATE INSTALLATION WORKPROCEDURES

    GATE INSTALLATION WORK PROCEDURES

    DISCIPLINE : MECHENICAL

    PROJECT NAME : 315MW WAMPU HEPP PROJECT

  • 3x15MW WAMPU HEPP PROJECTDOCU. NO. :1000-0175-EM-463-000

    Rev. No. : A

    Page. No : 1 / 6TITLE GATE INSTALLATION WORKPROCEDURES

    GATE INSTALLATION WORK PROCEDURES

    DISCIPLINE : MECHANICAL

    PROJECT NAME : 315MW WAMPU HEPP PROJECT

    A 29/10/14 For Approval S.G.LEEM J.H.CHO N/A C.W. JUNG

    REV.NO.

    DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL

    REV.NO.

    PREPARATIONGROUP.

    PREPARATION CHECK REVIEW APPROVAL

    A CIVIL E&MS.G.LEEM J.H.CHO N/A C.W. JUNG

    29/10/14 29/10/14 - 29/10/14

    For Approval

  • TABLE OF CONTENTS

    1.0 PURPOSE

    2.0 SCOPE OF APPLICATION

    3.0 GENERAL SPECIFICATION

    4.0 RESPONSIBILITY

    5.0 PREPARATION

    6.0 WORKING PROCEDURE

    7.0 ATTACHMENTS

    PAGE 2 OF 6

    DATE 2014.10.29TITLE

    3x15MW WAMPU HEPP PROJECT

    GATE INSTALLATION WORKPROCEDURES

    DOCU. NO

    Rev. No.

    1000-0175-EM-463-000

    A

  • 1.0 PURPOSE

    1.1 This procedure has purpose about that it enhance costruction ability and economics

    through quality improvement and safety of workers and construction.

    For construction ability and economics This procedure has working procedure about

    gate facilities of WAMPU HEPP project

    2.0 SCOPE OF APPLICATION

    2.1 This procedure apply to gate facilities of WAMPU HEPP

    3.0 GENERAL SPECIFICATION

    3.1 Quality provisions from preparing for installaion to installation of guide frame, overall gate

    facilities perform this procedure.

    4.0 RESPONSIBILITY

    4.1 SITE MANAGER

    It has overall responsibility about installaion of gate facilities.

    4.2 HEAD OF THE CONSTRUCTION DEPARTMENT

    It has overall responsibility about management of regulated provisions according to

    procedure and technical specification.

    4.3 HEAD OF THE QUALITY CONTROL MANAGEMENT DEPARTMENT

    It has overall responsibility about fulfillment of inspection.

    4.4 THE PERSON IN CHARGE OF CONSTRUCTION AT SITE

    It has overall responsibility about fulfillment of regulated provisions according to

    procedure and technical specification.

    TITLEGATE INSTALLATION WORK

    PROCEDURES

    DATE 2014.10.29

    PAGE 3 OF 6

    3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000

    Rev. No. A

  • 4.5 PERSON RESPONSIBLE FOR SAFETY

    It has overall responsibility about fulfillment for protection safety accident through

    safety education to workers.

    5.0 PREPARATION

    5.1 All equipment installation shoud follow according to supply installation guide and drawing,

    construction specification.

    5.2 The person in charge of construction at site should confirm whether packing list of drawing

    and construction specification match to taking equipments over.

    5.3 When it takes all equipment over it should check whether or not all equipments is true.

    If it have damage it should transfer to site after restoration to the original state.

    5.4 The equipments protected should be handle carafully for not removing protector.

    But if this removed for inspection it should reinstall after inspection.

    5.5 When equipments transfer to installation site from storage it should confirm obstacle

    on passage after protection for avoiding damage through crash.

    6.0 WORKING PROCEDURE

    6.1 Structure and order procedure review

    Guide frame installation should be planed for the first time according to structure procedure

    because of multi work with structure concrete work.

    So it should not disrupt precedence process.

    TITLEGATE INSTALLATION WORK

    PROCEDURES

    DATE 2014.10.29

    PAGE 4 OF 6

    3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000

    Rev. No. A

  • 6.2 Preparation before installation

    6.2.1 Confirms about material condition and drawings, procedure

    6.2.2 Check datum line ,Center line , Elevation

    6.2.3 Check for route of heavy equipment and working position

    6.2.4 Check civil interference

    6.2.5 Preparation tempory fixture material and jig

    6.2.6 Check power source

    6.3 Guide frame Installation

    6.3.1 Guide frame assemble on ground 3~6M through site conditions

    6.3.2 Frame should be assemble before rebar and form installation for avoiding civil

    interference.

    6.3.3 Rail control gap through using adjuster bolt.

    6.3.4 Frame should be fixed for avoiding move after alignment through Frame right and left

    span is under +5mm, perpendicularity is under 2mm by based bench mark.

    6.3.5 It should inspect after installation according to inspection plan

    - Center of gate

    - Elevation of gate

    - Datum line

    - Allow scope

    6.3.6 It should not leakage of mortar in gap through sealing with taping to contact face after

    installation form.

    TITLEGATE INSTALLATION WORK

    PROCEDURES

    DATE 2014.10.29

    PAGE 5 OF 6

    3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000

    Rev. No. A

  • 6.3.7 It is grinding on rail surface and concrete surface after removing form. So it measures

    variation between pouring before and pouring after.

    6.4 Gate installation

    6.4.1 It should check items to obstacle installation and impurities on sill beam before

    installation gate and cleaning on guide frame surface.

    6.4.2 Gate transfers to installation site using crane after fetch inspection under owner

    supervision.

    6.4.3 When it lifts for installation through crane it use lifting beam assembly jig.

    6.4.4 It check rubber sealing conditions and side roller right position when gate comes down

    in guide rail home.

    6.4.5 Final check whether it has interference or not and guide rail contact conditions against

    gate when gate moving top and bottom.

    7.0 ATTACHMENTS

    7.1 CHECK LIST FOR INSTALLATION

    7.2 CHECK LIST FOR INSPECTION

    7.3 DIMENSION INSPECTION RECORD

    7.4 DIMENSION INSPECTION RECORD

    3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000

    TITLEGATE INSTALLATION WORK

    PROCEDURES

    DATE 2014.10.29

    Rev. No. A

    PAGE 6 OF 6

  • `WAMPU HEPP

    NAME SIGNATURE DATE

    MBW Inspect. by

    PEN Witness. by

    WEP Approv. by

    CONTENT :

    DIVISION

    CHECK LIST FOR INSTALLATION

    PROJECT

    EQUIPMENT

    Q I P NEMBER

    REFERENCE DRAWING

    SUBJECT

  • `* Accept : A, Reject : R

    CHECK LIST FOR INSPECTIONPAGE 1 OF 1

    EQUIPMENT :

    NO. ITEMS CHECK POINT RESULT REMARK

    1Material

    Inspection

    1. Check whether material inspection is true or not

    2. Check whether painting damage and violent modify

    is true or not

    3. Check Frame Assembly

    2Guide

    Installation

    1. Check criteria center line

    2. Check assembly conditions on ground before

    installation

    3. Check civil construction interference

    4. Check alignment & centering

    5. Check guide vertical and horizontal condition

    6. Check frame strengthen condition

    7. Check interference between form and rebar

    3

    Form

    Installation

    and Removal

    1. Check the gap between frame and form

    2. Check concrete surface condition

    DIVISION NAME SIGNATURE DATE

    MBW Inspect. By

    PEN Witness. By

    WEP Approv. By

  • Equipment : Subject :

    Project : WAMPU HEPP DWG N0 :

    CHECK POINT : GATE SILL BEAM ELEVATION CHECK

    1 2 3 4 5 6 7

    * Allowance :3mm

    61 3 4 5

    2 7

    "A"-"A"section

    DIMENSION INSPECTION RECORD

    DIVISION NAME SIGNATURE

    SILL BEAM ELEVATION CHECK

    Division DWGMeasurement Point

    DATE

    Approv. ByWEP

    MBW Inspect. By

    Witness. ByPEN

    length

    FLOW

    BOTTOM FRAME DETAIL DWG

    ACTUAL

  • Equipment : Subject :

    Project : WAMPU HEPP DWG N0 :

    CHECK POINT : GATE SIDE GUIDE FRAME DIMENSION & SPAN CHECK

    G

    F

    E

    D

    C

    B

    A

    (L)

    1) Vertical CHK Position DWG Allowance 1 2 3 4 5 6 7 Result

    2) SPAN CHK Position DWG Allowance 1 2 3 4 5 6 7 Result

    DIMENSION INSPECTION RECORD

    L

    R

    L

    R

    DIVISION NAME SIGNATURE DATE

    MBW Inspect. By

    Approv. By

    Witness. ByPEN

    WEP

    1

    2

    5

    4

    7

    6

    3

    (R)

    FLOW

    length

    5mm

    5mm

    2mm

    2m

    Vertical

    5mm

  • Project : WAMPU HEPP Subject :

    CHECK POINT : GATE FRAME DWG.NO :

    UPPERBEAM

    Left(F1) Right(F2)

    NO DWG Allowance ACTU

    A 3

    A1 3

    B 3

    B1 3

    C 3

    C1 3

    D 3

    D1 3

    E 3

    E1 3

    LEft(F1) 3

    Right(F2) 3

    MBW Inspect. By

    WEP Approv. By

    NAME SIGNATURE DATE

    PEN Witness. By

    DIMENSION INSPECTION RECORD

    GUIDE ROLLER END TO END

    Result

    DIVISION

    A

    A1

    B

    B1

    C

    C1

    D D1

    E E1