Gate Installation Work Procedures
description
Transcript of Gate Installation Work Procedures
-
3x15MW WAMPU HEPP PROJECTDOCU. NO. :1000-0175-EM-463-000
Rev. No. : A
Page. No : CoverTITLE GATE INSTALLATION WORKPROCEDURES
GATE INSTALLATION WORK PROCEDURES
DISCIPLINE : MECHENICAL
PROJECT NAME : 315MW WAMPU HEPP PROJECT
-
3x15MW WAMPU HEPP PROJECTDOCU. NO. :1000-0175-EM-463-000
Rev. No. : A
Page. No : 1 / 6TITLE GATE INSTALLATION WORKPROCEDURES
GATE INSTALLATION WORK PROCEDURES
DISCIPLINE : MECHANICAL
PROJECT NAME : 315MW WAMPU HEPP PROJECT
A 29/10/14 For Approval S.G.LEEM J.H.CHO N/A C.W. JUNG
REV.NO.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
REV.NO.
PREPARATIONGROUP.
PREPARATION CHECK REVIEW APPROVAL
A CIVIL E&MS.G.LEEM J.H.CHO N/A C.W. JUNG
29/10/14 29/10/14 - 29/10/14
For Approval
-
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE OF APPLICATION
3.0 GENERAL SPECIFICATION
4.0 RESPONSIBILITY
5.0 PREPARATION
6.0 WORKING PROCEDURE
7.0 ATTACHMENTS
PAGE 2 OF 6
DATE 2014.10.29TITLE
3x15MW WAMPU HEPP PROJECT
GATE INSTALLATION WORKPROCEDURES
DOCU. NO
Rev. No.
1000-0175-EM-463-000
A
-
1.0 PURPOSE
1.1 This procedure has purpose about that it enhance costruction ability and economics
through quality improvement and safety of workers and construction.
For construction ability and economics This procedure has working procedure about
gate facilities of WAMPU HEPP project
2.0 SCOPE OF APPLICATION
2.1 This procedure apply to gate facilities of WAMPU HEPP
3.0 GENERAL SPECIFICATION
3.1 Quality provisions from preparing for installaion to installation of guide frame, overall gate
facilities perform this procedure.
4.0 RESPONSIBILITY
4.1 SITE MANAGER
It has overall responsibility about installaion of gate facilities.
4.2 HEAD OF THE CONSTRUCTION DEPARTMENT
It has overall responsibility about management of regulated provisions according to
procedure and technical specification.
4.3 HEAD OF THE QUALITY CONTROL MANAGEMENT DEPARTMENT
It has overall responsibility about fulfillment of inspection.
4.4 THE PERSON IN CHARGE OF CONSTRUCTION AT SITE
It has overall responsibility about fulfillment of regulated provisions according to
procedure and technical specification.
TITLEGATE INSTALLATION WORK
PROCEDURES
DATE 2014.10.29
PAGE 3 OF 6
3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000
Rev. No. A
-
4.5 PERSON RESPONSIBLE FOR SAFETY
It has overall responsibility about fulfillment for protection safety accident through
safety education to workers.
5.0 PREPARATION
5.1 All equipment installation shoud follow according to supply installation guide and drawing,
construction specification.
5.2 The person in charge of construction at site should confirm whether packing list of drawing
and construction specification match to taking equipments over.
5.3 When it takes all equipment over it should check whether or not all equipments is true.
If it have damage it should transfer to site after restoration to the original state.
5.4 The equipments protected should be handle carafully for not removing protector.
But if this removed for inspection it should reinstall after inspection.
5.5 When equipments transfer to installation site from storage it should confirm obstacle
on passage after protection for avoiding damage through crash.
6.0 WORKING PROCEDURE
6.1 Structure and order procedure review
Guide frame installation should be planed for the first time according to structure procedure
because of multi work with structure concrete work.
So it should not disrupt precedence process.
TITLEGATE INSTALLATION WORK
PROCEDURES
DATE 2014.10.29
PAGE 4 OF 6
3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000
Rev. No. A
-
6.2 Preparation before installation
6.2.1 Confirms about material condition and drawings, procedure
6.2.2 Check datum line ,Center line , Elevation
6.2.3 Check for route of heavy equipment and working position
6.2.4 Check civil interference
6.2.5 Preparation tempory fixture material and jig
6.2.6 Check power source
6.3 Guide frame Installation
6.3.1 Guide frame assemble on ground 3~6M through site conditions
6.3.2 Frame should be assemble before rebar and form installation for avoiding civil
interference.
6.3.3 Rail control gap through using adjuster bolt.
6.3.4 Frame should be fixed for avoiding move after alignment through Frame right and left
span is under +5mm, perpendicularity is under 2mm by based bench mark.
6.3.5 It should inspect after installation according to inspection plan
- Center of gate
- Elevation of gate
- Datum line
- Allow scope
6.3.6 It should not leakage of mortar in gap through sealing with taping to contact face after
installation form.
TITLEGATE INSTALLATION WORK
PROCEDURES
DATE 2014.10.29
PAGE 5 OF 6
3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000
Rev. No. A
-
6.3.7 It is grinding on rail surface and concrete surface after removing form. So it measures
variation between pouring before and pouring after.
6.4 Gate installation
6.4.1 It should check items to obstacle installation and impurities on sill beam before
installation gate and cleaning on guide frame surface.
6.4.2 Gate transfers to installation site using crane after fetch inspection under owner
supervision.
6.4.3 When it lifts for installation through crane it use lifting beam assembly jig.
6.4.4 It check rubber sealing conditions and side roller right position when gate comes down
in guide rail home.
6.4.5 Final check whether it has interference or not and guide rail contact conditions against
gate when gate moving top and bottom.
7.0 ATTACHMENTS
7.1 CHECK LIST FOR INSTALLATION
7.2 CHECK LIST FOR INSPECTION
7.3 DIMENSION INSPECTION RECORD
7.4 DIMENSION INSPECTION RECORD
3x15MW WAMPU HEPP PROJECTDOCU. NO 1000-0175-EM-463-000
TITLEGATE INSTALLATION WORK
PROCEDURES
DATE 2014.10.29
Rev. No. A
PAGE 6 OF 6
-
`WAMPU HEPP
NAME SIGNATURE DATE
MBW Inspect. by
PEN Witness. by
WEP Approv. by
CONTENT :
DIVISION
CHECK LIST FOR INSTALLATION
PROJECT
EQUIPMENT
Q I P NEMBER
REFERENCE DRAWING
SUBJECT
-
`* Accept : A, Reject : R
CHECK LIST FOR INSPECTIONPAGE 1 OF 1
EQUIPMENT :
NO. ITEMS CHECK POINT RESULT REMARK
1Material
Inspection
1. Check whether material inspection is true or not
2. Check whether painting damage and violent modify
is true or not
3. Check Frame Assembly
2Guide
Installation
1. Check criteria center line
2. Check assembly conditions on ground before
installation
3. Check civil construction interference
4. Check alignment & centering
5. Check guide vertical and horizontal condition
6. Check frame strengthen condition
7. Check interference between form and rebar
3
Form
Installation
and Removal
1. Check the gap between frame and form
2. Check concrete surface condition
DIVISION NAME SIGNATURE DATE
MBW Inspect. By
PEN Witness. By
WEP Approv. By
-
Equipment : Subject :
Project : WAMPU HEPP DWG N0 :
CHECK POINT : GATE SILL BEAM ELEVATION CHECK
1 2 3 4 5 6 7
* Allowance :3mm
61 3 4 5
2 7
"A"-"A"section
DIMENSION INSPECTION RECORD
DIVISION NAME SIGNATURE
SILL BEAM ELEVATION CHECK
Division DWGMeasurement Point
DATE
Approv. ByWEP
MBW Inspect. By
Witness. ByPEN
length
FLOW
BOTTOM FRAME DETAIL DWG
ACTUAL
-
Equipment : Subject :
Project : WAMPU HEPP DWG N0 :
CHECK POINT : GATE SIDE GUIDE FRAME DIMENSION & SPAN CHECK
G
F
E
D
C
B
A
(L)
1) Vertical CHK Position DWG Allowance 1 2 3 4 5 6 7 Result
2) SPAN CHK Position DWG Allowance 1 2 3 4 5 6 7 Result
DIMENSION INSPECTION RECORD
L
R
L
R
DIVISION NAME SIGNATURE DATE
MBW Inspect. By
Approv. By
Witness. ByPEN
WEP
1
2
5
4
7
6
3
(R)
FLOW
length
5mm
5mm
2mm
2m
Vertical
5mm
-
Project : WAMPU HEPP Subject :
CHECK POINT : GATE FRAME DWG.NO :
UPPERBEAM
Left(F1) Right(F2)
NO DWG Allowance ACTU
A 3
A1 3
B 3
B1 3
C 3
C1 3
D 3
D1 3
E 3
E1 3
LEft(F1) 3
Right(F2) 3
MBW Inspect. By
WEP Approv. By
NAME SIGNATURE DATE
PEN Witness. By
DIMENSION INSPECTION RECORD
GUIDE ROLLER END TO END
Result
DIVISION
A
A1
B
B1
C
C1
D D1
E E1