Garage Project Presentation Accu-Crete 2/28/2016.

22
Garage Project Presentation Accu-Crete 06/17/22

description

CIP vs PreCast CIP More integrated and stable structure Safer environment for workers and garage users Long life expectancy Less initial cost: bills paid mostly as work is completed Cracks that expose steel to corrosive agents minimized Pieces held together with caulked and welded joints Higher insurance cost than CIP projects Frequent maintenance required Up to 50% garage cost required before any on-site progress More structural problems exist : Double Ts, Joints and Cracks Precast

Transcript of Garage Project Presentation Accu-Crete 2/28/2016.

Page 1: Garage Project Presentation Accu-Crete 2/28/2016.

Garage Project Presentation

Accu-Crete 05/08/23

Page 2: Garage Project Presentation Accu-Crete 2/28/2016.

Introduction

• What we are doing• CIP garage for multi-family residential bldg.

Page 3: Garage Project Presentation Accu-Crete 2/28/2016.

CIP vs PreCastCIP

• More integrated and stable structure

• Safer environment for workers and garage users

• Long life expectancy • Less initial cost: bills paid

mostly as work is completed• Cracks that expose steel to

corrosive agents minimized

• Pieces held together with caulked and welded joints

• Higher insurance cost than CIP projects

• Frequent maintenance required• Up to 50% garage cost required

before any on-site progress• More structural problems

exist : Double Ts, Joints and Cracks

Precast

Page 4: Garage Project Presentation Accu-Crete 2/28/2016.

CIP vs PreCastCIP Precast

Less disturbance to the surrounding area

More flexibility in terms of finish and shape

Plans can be altered as construction progresses

Benefits the local economy, boosting the community and small businesses

• Large amount of on-site storage space needed for concrete and equipment

Page 5: Garage Project Presentation Accu-Crete 2/28/2016.

History and Experience

• Alexan North Hills; Raleigh, NC

Page 6: Garage Project Presentation Accu-Crete 2/28/2016.

History and Experience

• Alexan North Hills; Raleigh, NC

Page 7: Garage Project Presentation Accu-Crete 2/28/2016.

Technology-Quantity TakeoffAccu-Crete adopts the most efficient and

renown software in the construction industry to provide competitive and accurate bids.

An example of such is On-Screen-Takeoff.

Page 8: Garage Project Presentation Accu-Crete 2/28/2016.

• The use of digital blueprints allows the quick take-off of materials. This translates into higher productivity, faster response time and more accurate estimates.

Accuracy

Page 9: Garage Project Presentation Accu-Crete 2/28/2016.

Technology-Estimating

• Beam, Decks, Columns Formwork Material– Total project area – Layout and # of formsets– Type and length of each beam– # of Columns– Stair or high bay situations

Page 10: Garage Project Presentation Accu-Crete 2/28/2016.

Technology-Estimating

• Options– Beam shoring: PERI, Symons GBS– Deck panels: 4’x8’ or 4’x12’ HDO Plywood– Joists: Symons Aluminum, H20 (wood), EFCO E-

beamEX:

Page 11: Garage Project Presentation Accu-Crete 2/28/2016.

Technology-Estimating

• Process– Input information and selections in highlighted fields

(green)– Program will automatically assign relevant

components to formwork estimate–Obtain output in terms of cost and quantity of

formwork material– Final cost given per SF total project area

Page 12: Garage Project Presentation Accu-Crete 2/28/2016.

Technology-Estimating• Quantity and Price Output

Page 13: Garage Project Presentation Accu-Crete 2/28/2016.

Technology-Scheduling

• Primavera 6• Resources loaded from Estimate• Multiple formset/cycle options

Page 14: Garage Project Presentation Accu-Crete 2/28/2016.

Technology- 4D modeling

• Visual Intelligence for Construction Management

• Clear Visualization and Less Miscommunication with GC/clients/laborers

Page 15: Garage Project Presentation Accu-Crete 2/28/2016.

Technology- 4D modeling

Page 16: Garage Project Presentation Accu-Crete 2/28/2016.

Innovation: Ribbon Beam System

• Additional Floor to Ceiling Height• More Natural Light• Easier Access to Parking• Less Requirements for Electrical Light

Page 17: Garage Project Presentation Accu-Crete 2/28/2016.

Innovation: Ribbon Beam System

Looking up the ramp at the entry to garage. Note the utility pipes for drainage located in the drive lane. Better planning could have avoided this. These utility pipes are causing a loss of overall height.

Page 18: Garage Project Presentation Accu-Crete 2/28/2016.

Innovation: Ribbon Beam System

Electrical lighting is reduced due to openness. Columns have been moved back making access to parking easier. Concrete curb wall with plinths and barrier cables may be used.

Page 19: Garage Project Presentation Accu-Crete 2/28/2016.

Innovation: Ribbon Beam System

Entry into garage. Note the openness and how much natural light .

Page 20: Garage Project Presentation Accu-Crete 2/28/2016.

Innovation: Ribbon Beam System

View at the drive and parking lane. More natural light. Less requirements for electrical fixtures. No deep drop beams block light.

Page 21: Garage Project Presentation Accu-Crete 2/28/2016.

Garage WalkThrough

Page 22: Garage Project Presentation Accu-Crete 2/28/2016.

Q & A