  • 8/7/2019 Gannt it and Forget It!

    1/15

    WEBSITE PROJECT 1

    Running head: WEBSITE PROJECT

    Website Project

    Brenda Mok, Ben Chheuth,

    David Toby Meyers and Ray Hernandez

    Professor Edward Drummond

    CMGT-410/ Project Planning and Implementation

    March 16, 2009

  • 8/7/2019 Gannt it and Forget It!

    2/15

    WEBSITE PROJECT 2

    Introduction

    Bona Fide Natural Foods (BFNF) is a relatively new and independent natural food store

    that specializes in organic produce, vegan, vegetarian, and alternative products. BFNF has

    shown much success on the local level, and they are seeking to expand their market to

    neighboring cities. One of their major goals is to reach consumers through the web. They

    believe that having a web presence will help their business grow. In order to accomplish this,

    they plan to create a website fully capable of serving multiple needs of consumers. BFNF has

    contacted Chipmunk Designs to complete this goal.

    BFNF has provided a set of requirements that the project must meet. Among these

    requirements are:

    - A roll out date before Christmas.

    - An overall budget of less than fifteen thousand dollars.

    - A design congruent with contemporary trends

    - Inclusion of particular company information

    - Database of all products accompanied with complete nutritional value

    - Online ordering capability

    - Web 2.0

    - Flash Navigation

    - Security

    - Complete web optimization and compliance

    - Maintenance & Troubleshoot plan

  • 8/7/2019 Gannt it and Forget It!

    3/15

    WEBSITE PROJECT 3

    The deliverables include end-of-the-week reports indicating progress made on each phase of

    the project. Indicated on the Gantt chart, reports will also include screenshots of coding and

    layout of necessary and releases of the site available for demo.

    Chipmunk Designs Representatives

    Signature of agreement: x _______________________________________

    Signature of agreement: x _______________________________________

    Signature of agreement: x _______________________________________

    Signature of agreement: x _______________________________________

    Bona Fide Natural Foods Co. Representatives

    Signature of agreement: x _______________________________________

    Signature of agreement: x _______________________________________

  • 8/7/2019 Gannt it and Forget It!

    4/15

    WEBSITE PROJECT 4

    CCB

    We had a Change meeting to talk about an idea that the stakeholder had in mind that should

    improve the website. One idea that the stakeholder had in mind is to add recipes and meals into

    their website. Under recipes and meals, some ideas that are: 15-minute recipes, tips, techniques

    and recipes. This will give customers ideas on what to cook throughout the week. Give tips on

    beef/steak, fish and cutting, recipe search if customers are interested in cooking a specific meal. By

    adding recipes and meals into the website, customers would be able to have better ideas on what to

    cook, which makes customers buy more of Bona Fide Natural Foods' products.

    Assumptions

    In the website that 'Chipmunk Designs' prepared for 'Bona Fide Natural Foods', customers

    should obtain convenience in viewing the website. Customers should be able to view products with

    pictures; products should also have nutritional facts. Pricing should be available for each product.

    The more you shop at Bona Fide Natural Foods the more gas rewards you get.

    Project Organization

    Team

    Member

    Functions Qualifications Responsibilities Capabilities

    Ray

    Background &

    Scope Statement

    Writing

    Communicating

    Sharing ideas

    Reviewing

    ideas

    Critiquing ideas

    Presenting

    case to client

    Develop

    charter and

    plan

    Identifies

    processes,

    product, and

    Project

    manages

    Sales

    Marketing

  • 8/7/2019 Gannt it and Forget It!

    5/15

    WEBSITE PROJECT 5

    services

    Ben CCB &

    Assumptions

    Math

    Organizing

    Time

    Time

    manages

    Accounting

    Finance

    manages

    Accounting

    Finance

    manages

    Purchasing

    Brenda Projection

    Organization

    Coordinating

    Organizing

    Time manages

    Structuring

    Personal

    manages

    Designing

    Personal

    manages

    (HR)

    Time

    manages

    Organizing

    Structuring

    Coordinating

    Personal

    manages (HR)

    Organizing

    Coordinating

    Toby Task/

    Responsibility

    Matrix

    Technical

    supporting

    Sharing ideas

    Reviewing

    ideas

    Critiquing ideas

    Technical

    supporting

    Information

    systems

    manages

    Designing

    Technical

    supporting

    Designing

    Rays qualification is on writing and communicating, so he is responsible for sales and

    marketing proportion. In this new project, Ray is presenting Chipmunk Design to giving

    updates to our clients regarding their website.

  • 8/7/2019 Gannt it and Forget It!

    6/15

    WEBSITE PROJECT 6

    Bens qualification is on accounting and finance, so he responsible for accounting and

    finances manages. In this new project, Ben is managing budgets and change control. If our

    client (Bona Fide Natural food) has any change regarding to the website, Ray needs to work

    with Ben to have a new contract and budget updated and approved.

    Brendas qualification is on organizing and personal manages, so she responsible for

    HR and coordinating. Since Brenda possesses a background in graphic design, she will also

    support Toby on web designing as well.

    Tobys qualification is technical, so he is responsible for technical support, training and

    researching information. In this new project, Toby will respond on creating website.

    In visual representation on the preceding page:

    TASK/RESPONSIBILITY MATRIX

    Ray Ben Toby Brenda

    Manpower X X

    Software

    Available

    X

    Website layout X

    Navigation X X

    Product page X X

    Nutrition page X X

    Online ordering

    page

    X X

    Privacy page X

    Term of use

    page

    X

    Site map page X

    Membership X X

  • 8/7/2019 Gannt it and Forget It!

    7/15

    WEBSITE PROJECT 7

    page

    Approval X X

    Kick off

    meeting

    X X X X

    Database page X

    Web 2.0 X

    Customer data X

    Credit data X

    Transaction

    data

    X X

    Prototype

    testing

    X X X X

    Final approval X X X X

    Public release X

    Maintenance X

    Close project X X

    Evaluation X X X X

    As the above schedule shows, we are dividing tasks according to normal web site

    creation steps.

  • 8/7/2019 Gannt it and Forget It!

    8/15

    WEBSITE PROJECT 8

  • 8/7/2019 Gannt it and Forget It!

    9/15

    WEBSITE PROJECT 9

    According to our Cost Plan, we are paying hourly wages according to how many hours

    it takes to fulfill tasks. See attached file. The Gant Chart shows our activities for 185 days. Our

    report continues below.

  • 8/7/2019 Gannt it and Forget It!

    10/15

    WEBSITE PROJECT 10

  • 8/7/2019 Gannt it and Forget It!

    11/15

    WEBSITE PROJECT 11

    WBS:

    The Work Breakdown Structure shows our tasks linked to the Public Website Release

    of Bona Fide Natural Foods. The orange-colored section is the first level or end result. The

    blue-colored section is the second level or major tasks. The red-colored section is the third

    level, or the detailed tasks. The green-colored section is the fourth level, or the sub tasks. The

    black-colored level is the fifth level, or the work packages. Each task with the same color

    belongs on the same level of the hierarchy.

  • 8/7/2019 Gannt it and Forget It!

    12/15

    WEBSITE PROJECT 12

    The Critical Path on this project is to make compliant the optimizations in less than two

    days.

  • 8/7/2019 Gannt it and Forget It!

    13/15

    WEBSITE PROJECT 13

    Money

    Time

    14,950

    ActualC

    ost

    15

    ,000

    budgetconstraint

    Estimated cost and rollout date

    15,000 Budget Christmasroll out date

    14,950 Actual cost

    Productfinished

    on12/2/09

    Performance as measured according to task efficiency. Task managers reported start,

    finish dates and compared them against the estimated project timeline. The visual

    representation of that is in the enclosed document. The outcome of the analysis; the project

    used its time wisely, taking opportunity to start projects as early as possible and thereby

  • 8/7/2019 Gannt it and Forget It!

    14/15

    WEBSITE PROJECT 14

    coming out ahead of schedule. This came out in the proposed budget and in 168 days

    instead of 185, bringing the project in 17 days early.

    PROJECT TERMINATION

    Closing Checklist1. Beta-Test passed for release

    2. Project Auditing

    a. Verify all functions are completeb. Create final presentation

    c. Close all accounts

    d. Archive work3. Celebration

    4. Meeting with Clients

    a. Review Design (Presentation)

    i. Specifications Auditingii. Approval

    iii. Formal Transfer to Company

    1. Schematics2. Design Copies

    3. Codes

    4. Hardwareb. Review Finance Report

    i. Cost Analysis

    c. Billing

    d. Acknowledge Contributions

    e. Website Public Release5. Maintenance & Troubleshoot Training/Plan

    6. Follow-up Discussiona. Discuss Future Plans

    7. Evaluation

    a. Analyze Performancei. Cost

    ii. Human Resources

    iii. Etc.

  • 8/7/2019 Gannt it and Forget It!

    15/15

    WEBSITE PROJECT 15

    Summary of Lessons Learned

    In our project, we encountered various hurdles, expected and unexpected, which

    provided insight into future methods of project management. We found that in the contract,

    cost estimation and schedule estimation, there should be ample room for overages. Since we

    fell over our budget, disclosing this information earlier would be more beneficial to both

    parties. Furthermore, we found that particular websites that require databases require much

    attention to time. In our efforts, scheduling time with the store and employees was difficult.

    This knowledge could prove useful for future projects that involve similar features in the site.

    Ultimately, estimation and scheduling should prompt more creativity and consideration for all

    resources involved.

    This project meets the requirements of the customer in accordance within budgeted time.

    Therefore, this was a profitable and timely project with solutions to unforeseen problems by

    taking opportunity to use the extra time wisely.