Gaborone Dam 70% Full October 2006 - Water Summit · E-mail : [email protected] Cell: +267-71300841....
Transcript of Gaborone Dam 70% Full October 2006 - Water Summit · E-mail : [email protected] Cell: +267-71300841....
Somarela Thothi Water Loss Reduction Partnership
WRP Pty Ltd 1
2015/08/28
Presented by: Moeti Matswiri
BACKGROUNDBACKGROUND
Botswana and Limpopo River BasinBotswana and Limpopo River Basin Project area characteristicsProject area characteristicsWater supply to approximately 560 000 people (>25% of Botswana population)
Experience worst drought since 1983
Water rationing introduced in April 2013
2012/13 demand without rationing = 3.6 million m3/month
2014/15 demand with rationing = 3.0 million m3/month
Severe drought and load shedding – unable to operate water treatment plants and pumps
108 Ml/day treatment capacity not available due to failure of Gaborone dam
Water supply to approximately 560 000 people (>25% of Botswana population)
Experience worst drought since 1983
Water rationing introduced in April 2013
2012/13 demand without rationing = 3.6 million m3/month
2014/15 demand with rationing = 3.0 million m3/month
Severe drought and load shedding – unable to operate water treatment plants and pumps
108 Ml/day treatment capacity not available due to failure of Gaborone dam
Letsibogo dam (46.7%)
Bokaa dam (0%)
Gaborone dam (0%)
Molatedi dam (south Africa) (9.4%)
North South Carrier is the main water resource 1000 to 1400mm diameter 356km pumping main 4 major pumping stations Unreliable power supply
Supply from Molatedi dam (SA) curtailed due drought in NW
Gaborone Dam 70% FullOctober 2006
Gaborone Dam 70% FullOctober 2006
Somarela Thothi Water Loss Reduction Partnership
WRP Pty Ltd 2
2015/08/28
Gaborone Dam 2% Full July 2015
Gaborone Dam 2% Full July 2015
View from yacht club
Bulk water supply to Greater Gaborone
Bulk water supply to Greater Gaborone
0
500000
1000000
1500000
2000000
2500000
3000000
3500000
4000000
4500000
Apr‐03 Apr‐04 Apr‐05 Apr‐06 Apr‐07 Apr‐08 Apr‐09 Apr‐10 Apr‐11 Apr‐12 Apr‐13 Apr‐14 Apr‐15
Volume Water Supplied
(m
3 /month)
Treated water to Greater Gaborone (without rationing) Treated water to Greater Gaborone (with rationing)
Rationing startedApril 2013
Mmamashia WTWDesign capacity = 110Ml/d
Gaborone WTWDesign capacity = 108Ml/day
All areas previously supplied from Gaborone
WTW must now be supplied from
Mmamashia WTW
Area supplied fromMmamashia WTW
Area supplied fromGaborone WTW
35km
Impact of Gaborone dam failureImpact of Gaborone dam failure
PROJECT SOMARELA THOTHIPROJECT SOMARELA THOTHI
Project Partnership (PPP)Project Partnership (PPP)
Fund awareness campaign
Fund bulk metering and sectorisationReinvest project savings
Fund pressure management
Project objectivesProject objectives
Implement technical and social interventions in the Greater Gaborone area to reduce water losses
Model has a country wide replication potential through an innovative re-investing model
WUC committed themselves to ring fence 5.49 Pula for every m³ water saved through the project
Training and capacity building of WUC staff to replicate project
Implement technical and social interventions in the Greater Gaborone area to reduce water losses
Model has a country wide replication potential through an innovative re-investing model
WUC committed themselves to ring fence 5.49 Pula for every m³ water saved through the project
Training and capacity building of WUC staff to replicate project
Somarela Thothi Water Loss Reduction Partnership
WRP Pty Ltd 3
2015/08/28
InterventionsInterventions
Community awareness- Creating informed community
- Establish partnership between WUC and community
- Encourage ownership and responsibility
Bulk metering and sectorisation- Identification and quantification of high water loss
areas and subsequent interventions
- Benchmarking of water losses
Pressure management- One of the most cost effective water loss
interventions
Community awareness- Creating informed community
- Establish partnership between WUC and community
- Encourage ownership and responsibility
Bulk metering and sectorisation- Identification and quantification of high water loss
areas and subsequent interventions
- Benchmarking of water losses
Pressure management- One of the most cost effective water loss
interventions
Awareness trainingAwareness training
COMMUNITY AWARENESSCOMMUNITY AWARENESS
Schools awareness campaignsSchools awareness campaigns
Outreach activitiesOutreach activities
Somarela Thothi Water Loss Reduction Partnership
WRP Pty Ltd 4
2015/08/28
BASELINES, BULK METERING AND SECTORISATIONBASELINES, BULK METERING AND SECTORISATION
Baseline assessmentBaseline assessment
0
50 000
100 000
150 000
200 000
250 000
300 000
Volume W
ater Supplied (m
3/m
onth)
Mochudi pre‐rationing Mochudi post‐rationing Linear (Mochudi pre‐rationing) Linear (Mochudi post‐rationing)
Pre-rationing Post-rationing
Baseline assessment critical component of project to measure savings
Difficult to measure savings due to rationed water supply
Typical pressure logging in rationed DMA
Typical pressure logging in rationed DMA
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
2013
/07/
20
2013
/07/
31
2013
/08/
19
2013
/08/
29
2013
/09/
09
2013
/09/
23
2013
/10/
28
2013
/11/
08
2013
/11/
19
2013
/11/
29
2013
/12/
10
2014
/01/
03
2014
/02/
01
2014
/02/
13
2014
/02/
23
2014
/03/
06
2014
/03/
17
2014
/03/
27
2014
/04/
07
2014
/04/
17
2014
/04/
28
2014
/05/
09
2014
/05/
19
2014
/05/
30
2014
/06/
10
2014
/06/
20
2014
/07/
01
2014
/07/
11
2014
/07/
22
2014
/08/
02
2014
/08/
12
2014
/09/
22
2014
/10/
03
2014
/10/
13
2014
/10/
24
2014
/11/
03
2014
/11/
14
2015
/04/
02
2015
/04/
12
2015
/04/
23
Pre
ssu
re (
bar
)
GW02W (Ph2 Masa) Flow and pressure logging
P average
Phakalane night flow analysisPhakalane night flow analysis
0
50
100
150
200
250
300
350
2015/05/1100:00
2015/05/1300:00
2015/05/1500:00
2015/05/1700:00
2015/05/1900:00
2015/05/2100:00
Flo
w r
ate
(m3/
h)
Flow Expected MNF AVG MNF
Average flow = 140m3/h
Measured minimum night flow = 65m3/h
Expected minimum night flow = 12m3/h
Excess night flow = 53m3/h
MNF / AVG = 46%
MNF remains consistent irrespective of rationing
Only reliable method to determine savings
SectorisationSectorisation
It is important to properly document project findings and results.
Train and capacitate client to continue process
Somarela Thothi Water Loss Reduction Partnership
WRP Pty Ltd 5
2015/08/28
PRESSURE MANAGEMENTPRESSURE MANAGEMENT
High Pressure Photo: Courtesy Ken Brothers
Low PressureLow Pressure Photo: Courtesy ken Brothers
Mogoditshane
Sebeli
Northern suburbs
Block / Airport PRV
Glen Valley
Existing PRV
Proposed PRV
Tlokweng
Ostrich
Gaborone Current & Proposed Pressure Management AreasGaborone Current & Proposed Pressure Management Areas
GaboroneWTW
MmamashiaWTW
More than 20 existing PRVs have been identified during the project – started with 5
Most PRVs not operational
PRV maintenancePRV maintenance Pressure Management ResultsPressure Management Results
Somarela Thothi Water Loss Reduction Partnership
WRP Pty Ltd 6
2015/08/28
Pressure at BOBS critical pointPressure at BOBS critical point
0
1
2
3
4
5
6
7
8
Pre
ssu
re (
bar
)
June 2015 – PRVs setJune 2014 - PRVs open
Average pressure = 5.2 bar
Average pressure 2.1 bar
A significant reduction in the number of bursts
has been observed
Mogoditshane Pressure Management
Mogoditshane Pressure Management
0
50
100
150
200
250
300
2015/07/1300:00
2015/07/1500:00
2015/07/1700:00
2015/07/2400:00
2015/07/2600:00
2015/07/2800:00
2015/07/3000:00
2015/08/0100:00
2015/08/0300:00
2015/08/0500:00
Flow rate (m
3/h)
PRVs set
Average flow = 74m3/hAverage MNF = 12m3/h
Average flow = 140m3/hAverage MNF = 112m3/h
Saving = 77m3/h = 1848m3/day = 674 520m3/annum
PRVs open Rationed water supply
Broadhurst PRVBroadhurst PRV Training and capacity building Training and capacity building
Repair of visible leaksRepair of visible leaks December 2015 targetsDecember 2015 targets
3.1 million m³ water saved
Ring fencing and reinvestment of savings for countrywide replication
17 million Pula financial savings for an initial investment of 5 million Pula
3.1 million m³ water saved
Ring fencing and reinvestment of savings for countrywide replication
17 million Pula financial savings for an initial investment of 5 million Pula
Somarela Thothi Water Loss Reduction Partnership
WRP Pty Ltd 7
2015/08/28
ConclusionsConclusions
Success of the Project Somarela Thothi will not only benefit Botswana but the river basin
Start water conservation and water demand management as early as possible
Difficult to implement WDM and measure savings with rationing and the MNF only reliable measure
Rationing is detrimental to infrastructure, demotivates staff, loss of income, affects water quality, corrupts water meters and politically sensitive
There is huge scope for private sector participation as they are equally affected by the drought
Success of the Project Somarela Thothi will not only benefit Botswana but the river basin
Start water conservation and water demand management as early as possible
Difficult to implement WDM and measure savings with rationing and the MNF only reliable measure
Rationing is detrimental to infrastructure, demotivates staff, loss of income, affects water quality, corrupts water meters and politically sensitive
There is huge scope for private sector participation as they are equally affected by the drought
AcknowledgementsAcknowledgements
Thank youThank youMr Moeti Matswiri
Leakage Control Engineer
Botswana Water Utilities Corporation
E-mail : [email protected]
Cell: +267-71300841
Mr Moeti Matswiri
Leakage Control Engineer
Botswana Water Utilities Corporation
E-mail : [email protected]
Cell: +267-71300841