FY05 Budget Proposal
description
Transcript of FY05 Budget Proposal
1
FY05 Budget Proposal
March 4, 2004
2
Presentation Overview
FY04 ridership and improvements FY05 backgroundFY05 anticipated outcomesFY05 budget highlightsLooking beyond FY05
3
Rail and Bus Ridership Setting
New Highs
Cumulative GrowthRail Bus Avg.
annual growth rate Bus
Rail
1/01 – 1/02 13% 15% 15% 13%
1/01 – 1/03 32% 37% 15% 17%
1/01 – 1/04 41% 44% 12% 13%
3000400050006000700080009000
10000110001200013000140001500016000
'Jan 0
1 Jul
'Jan 0
2 July
'Jan 0
3 July
'Jan
04
VRE RidershipBus
4
Ridership growth rates – Why have they slowed?
VRELimited available seatingParking shortages
BusFare increase reduced OmniLink ridership more than anticipatedTransitional difficulties resulting from contractor change
5
FY04 Bus Service Improvements
PRTC Website enhancement (August 03)Delivery of 8 MCI buses (September 03)Implementation of Fare/Ticketing Plan Phase I (October 03)Added trips to relieve crowding (October 03 and February 04)MDTs Phase I operational (November 03)Customers’ perceptions of service quality have rebounded (January 04), marking end of transition – better now in most areas than WMATA at its best
6
FY04 Rail Service Improvements
Gallery cars introduced to expand seating capacity (November 03 and incrementally thereafter)New ticket vending machines fully implemented (January 04)Expanded parking to ease shortage at Rippon (March 04)New AMTRAK agreement through end of FY05 (March 04) to afford time for negotiation of longer-term agreementTrain tracking program enhancement (“Train Brain”) implemented (March 04)
7
FY05 Background Observations
Follows Commission's adopted budget principles Summary of principles
“Existing service expansion” allowance to handle ridership growth
Phase II fare/ticketing plan for bus services deferred to FY06 Bus service formerly supported by reimbursable funding to
be sustained with local funds Additional Ride/Link services:
Saturday Link service for easterly Link routes Linton Hall Ride service Ridgefield Road Ride service
OmniLink subsidy allocation formula change adopted by Commission to achieve equitable cost sharingEmbraces PRTC share of VRE budget as accepted by commissions
8
Anticipated FY05 Outcomes -- Bus
New all-time ridership highContinued gains in customer satisfactionAward contract for as many as 21 OmniRide busesDelivery of 18 Gillig busesNew fareboxes installedRehabilitation of 17 OmniRide busesLand Acquisition/Environmental Assessment for Transit Center parking expansionUpdated bus service improvement plan
9
Anticipated FY05 Outcomes -- Rail
All gallery cars placed in service to expand seating capacityParking expansion Surface lots completed @ Woodbridge,
Broad Run, and Old Town Manassas Deck plans fully designed @ Old Town
Manassas and Burke
New rolling stock procurement plans prepared Mid-day yard storage capacity expansion plans finalized
10
FY05 Local Subsidy in BriefJurisdiction FY04 FY05 Chg Prince William $5.183M $6.192M 19%Manassas .388M .332M (14%)Manassas Park .120M .149M 24%Stafford .054M .045M (17%)Fredericksburg .026M .024M (8%)
PRTC Local Subsidy $5.771M $6.742M 17% (Excluding VRE)
VRE Subsidy (from PRTC $3.151M $3.148M 0%
Jurisdictions)
Total PRTC Subsidy $8.922M $9.890M 11%
11
Looking Beyond FY05 -- Bus
Expanded Bus Service: Increased OmniRide Route One
service (FY06) Supplemental OmniLink Route One
service (FY06) Possible longer-term service additions
as outgrowths of updated bus service plan and prospective HOT lanes
Transit Center parking expansion
12
Looking Beyond FY05 -- Rail
Capacity expansion as envisioned by completed strategic plan and as resources allowPossible system extensionsLong-term agreement with AMTRAK ensuring terminal access rights
13
FY06 – FY09 Local Subsidy Implications
__ _ FY06___ FY07___ _FY08___FY09_ PWC $7.617M $6.742M $6.632M $6.697M
Manassas .337M .330M .329M .339MManassas Park .151M .148M .147M .151MStafford .046M .033M .019M .019MFredericksburg .024M____.018M____ _.010M___ _.010M
Total $8.175M $7.271M $7.137M $7.216M
(Excluding VRE)
VRE Subsidy $3.492M $3.758M___$4.096M $7.747M from PRTC Jurisdictions)
Total Subsidy $11.667M $11.029M $11.233M $14.963M
14
Projected Fuel Tax Revenue
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,0004,000,000
4,500,000
5,000,000
5,500,000
6,000,000
6,500,000
7,000,000
7,500,000
FY05 FY06 FY07 FY08 FY09
15
Projected Fuel Tax Fund Balances
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
FY05 FY06 FY07 FY08 FY09