Fusion Bonded Epoxy Coated Rebars_tcm45 345955

4
Fusion-bonded epoxy-coated rebars Tackling the reinforcing-steel corrosion problem: prevention versus repair A mong the most promising methods of combating steel rebar corrosion in concrete parking decks bridge decks and other areas is the use of fusion-bond - ed epoxy-coated rebars in new construction and in re- pair. The chief danger to uncoated steel bars in north- ern and coastal states is from corrosion that occurs after calcium chloride or sodium chloride seeps into the con- crete. The sources of these chlorides are deicers or sea- water spray. Many concrete parking ramps and bridge decks constructed as recently as 5 to 10 years ago are d e t e ri o rating to the point where major repair or re- placement is already necessary. The problem results in millions of dollars worth of damage each year. Combating corrosion The use of a fusion-bonded epoxy coating on rebars is considered by many engineers to be among the most effective techniques for combating corrosion though it has been in use for only a few years. Other approach- es— some used in conjunction with epoxy coating— have met with varying degrees of success. These include membrane coverings of bridge decks and parking ramps, latex concrete overlays, corrosion inhibiting ad- mixtures, polymer impregnation, use of galvanized re- bars, cathodic protection of rebars, and the Iowa method of bonding a dense, low-slump concrete to the base. All these have the purpose of (1) keeping chloride-bearing water from seeping down through the concrete to the re- bars or (2) preventing chloride-bearing water in the con- crete from touching the reinforcing bars. Costs tend to vary widely. Those of such techniques as polymer impregnation and use of galvanized rebars fall on the high side. Use of epoxy-coated rebars is usu- ally priced considerably lower. The rate of deterioration of a concrete deck due to cor- roding steel increases with time. As the rebars corrode, the iron oxide which forms causes an expansion in vol- ume of up to 20 times that of the original volume of the portion of the bar that has corroded. The inevitable re- sult is immense pressure between the bars and the sur- rounding concrete, which causes the all-too-familiar Fusion-bonded epoxy-coated rebars in place for a 6-inch composite structural slab. The completed parking deck will serve the office building in the background.

Transcript of Fusion Bonded Epoxy Coated Rebars_tcm45 345955

Page 1: Fusion Bonded Epoxy Coated Rebars_tcm45 345955

Fusion-bondedepoxy-coated

rebarsTackling the reinforcing-steel corrosion

problem: prevention versus repair

Among the most promising methods of combatingsteel rebar corrosion in concrete parking decks

bridge decks and other areas is the use of fusion-bond-ed epox y-coated rebars in new construction and in re-p a i r. The chief danger to uncoated steel bars in nort h-e rn and coastal states is from corrosion that occurs aftercalcium chloride or sodium chloride seeps into the con-crete. The sources of these chlorides are deicers or sea-water spra y. Many concrete parking ramps and bri d g edecks constructed as recently as 5 to 10 years ago ared e t e ri o rating to the point where major repair or re-placement is already necessary. The problem results inmillions of dollars worth of damage each year.

Combating corrosion

The use of a fusion-bonded epoxy coating on re b a r sis considered by many engineers to be among the moste f f e c t i ve techniques for combating corrosion though ithas been in use for only a few ye a r s. Other appro a c h-es— some used in conjunction with epoxy coating—h a ve met with va rying degrees of success. These includem e m b rane cove rings of bridge decks and park i n gra m p s, latex concrete ove r l a y s, corrosion inhibiting ad-m i x t u re s, polymer impregnation, use of galva n i zed re-b a r s, cathodic protection of re b a r s, and the Iowa methodof bonding a dense, low-slump concrete to the base. Allthese have the purpose of (1) keeping chlori d e - b e a ri n gwater from seeping down through the concrete to the re-bars or (2) pre venting chlori d e - b e a ring water in the con-c rete from touching the re i n f o rcing bars.

Costs tend to va ry widely. Those of such techniquesas polymer impregnation and use of galva n i zed re b a r sfall on the high side. Use of epox y-coated rebars is usu-ally priced considerably lowe r.

The rate of deteri o ration of a concrete deck due to cor-roding steel increases with time. As the rebars corro d e,the iron oxide which forms causes an expansion in vo l-ume of up to 20 times that of the original volume of thep o rtion of the bar that has corroded. The inevitable re-sult is immense pre s s u re between the bars and the sur-rounding concre t e, which causes the all-too-familiar

Fusion-bonded epoxy-coated rebars in place for a 6-inch composite structural slab. The completed parking deck willserve the office building in the background.

Page 2: Fusion Bonded Epoxy Coated Rebars_tcm45 345955

c racking and spalling. The resulting disruption of thes u rface and the loss of large pieces of concre t e, in turn ,mean greater vulnerability to waterborne chlori d e s,which leads to more spalling.

Two parking deck projects in the Minneapolis and St .Paul area—one involving new construction and the oth-er repair—offer a dramatic contrast between the cost ofp re venting rebar corrosion during new constru c t i o n ,and the cost of repair of an existing stru c t u re alre a d ydamaged by corro s i o n .

Fusion-bonded rebars in new construction

A new parking deck constructed at Pa rkdale Plaza inSt. Louis Pa rk (suburban Minneapolis) consists of as t ru c t u ral deck and a gro u n d - l e vel slab within an are athat measures approximately 215 by 240 feet. The cast-in-place upper deck, supported by steel framing, is di-vided into quarters with good slope for dra i n a g e. Thep a rking stru c t u re is designed to accommodate 136 cars

on the upper deck and 140 in the lower section.A low-slump mix was used with a high cement content

(588 pounds per cubic yard).2 Special care was taken inselecting the aggre g a t e. The mix contained 6 to 8 perc e n ta i r, and a re t a rder was used to delay set over steel beamsto eliminate minor cracking. The concrete was placed byp u m p, enabling the crew on one occasion to install12,500 square feet in a single day. After curing, a mini-mum of two coats of sealer was applied.

Ce n t ral to the design was the use of rebars with a fu-sion-bonded epoxy coating. The 6-inch-thick compositedeck slab allowed use of 2 inches of concrete cover ove rboth top and bottom bars, compared with the 3/4 inchof cover often used on earlier parking decks.

Ac c o rding to the supplier of the coated re b a r s, thee p oxy coating on projects of this type costs approx i-mately $300 to $350 per ton over the cost of uncoatedsteel re b a r s. Number 4 bars we re used in the Pa rk d a l ePlaza deck. Assuming a rebar weight of approx i m a t e l y

Coated rebars are tied with plastic-coated wire to ensure stability

during concrete placement.

The flexibility of thefusion-bonded epoxy

coating must be sufficientto prevent cracks and

breaks from occurring inthe coating during

fabrication bending.

Page 3: Fusion Bonded Epoxy Coated Rebars_tcm45 345955

21⁄2 pounds per square foot and a concrete area of 51,360s q u a re feet, the weight of rebars used in the deck couldbe calculated at a little over 64.2 tonsil For purposes ofthis example, if the cost of coated rebars we re calculatedat $860 per ton, and the cost of uncoated rebars at $540per ton, then the cost differential for the epoxy coatingwould be about 40 cents per square foot or $20,544 forthe entire deck—approximately 3.6 percent of the totalc o s t .

By contrast, Co n s e rva t i ve estimates of re p l a c e m e n tCosts range from $13 to $15 per square foot, which ismany times the estimated cost of using the coated re-

bars initially. Va rious studies, more ove r, have shown thatuse of the epoxy coating can greatly increase the effec-t i ve lifespan of such stru c t u re s.

Fusion-bonded rebars for repair

A project undertaken by a St. Paul retail outlet invo l ve sthe ramps of two side-by-side parking stru c t u res whichh a ve suffered extensive spalling and other deteri o ra t i o n .The stru c t u res—one of approximately 10,000 squarefeet and the other approximately 7000 square feet—we re constructed with uncoated re b a r s. Su b s e q u e n t l yboth we re subjected to calcium chloride attack from au-

Pumping concrete on the ParkdalePlaza parking deck.

Fusion-Bonded rebars: Update

Fusion-bonded epoxy coatings for rebars are notapplied on the job. Instead, the bars are coated in as t rictly controlled factory process where epoxy pow-ders are fusion-bonded to the steel surface after thesteel has been shotblasted. The National Bu reau ofSt a n d a rds found that such coatings should be about0.005 to 0.009 inch thick for adequate pro t e c t i o nagainst chloride attack and adequate flexibility dur-ing bending. The coated bars are bundled togetherwith nylon rope to minimize damage from ro u g hhandling during shipping and stora g e.

T h e re is a trade association of 20 companies thatm a n u f a c t u re epoxy powders or fabricate coated re-bars and supply them throughout the United St a t e sand Ca n a d a :

Fusion Bonded Coaters Association 25 Glen Head Ro a dGlen Head, New Yo rk 11545Phone: 516- 676-7811

The association presents a technical seminar onthe first day of each semiannual meeting. These

seminars are open to contra c t o r s, engineers, design-ers and others in the industry without charg e, pro-viding they pre re g i s t e r.

The association is pre p a ring standard specifica-tions that should be available soon. The Ameri c a nSociety for Testing and Ma t e rials is also pre p a ri n gs t a n d a rd specifications. The Ohio De p a rtment ofTra n s p o rtation has published proposed specifica-tions for epoxy coated rebars that include such itemsas coating materi a l s, surface pre p a ration, thickness-e s, curing, fabrication prov i s i o n s, handling re q u i re-m e n t s, placement, field-coating touchup, measure-ment and basis of payment. Copies of the Oh i odocument, “Ep oxy Coated Re i n f o rcing Steel, Pro p o s-al Note Number 112, December 4, 1978,” are ava i l-able fro m

Co n c rete Re i n f o rcing Steel In s t i t u t e180 No rth LaSalle St reet, Room 2110C h i c a g o, Illinois 60601Phone: 312-372-5059

The Kentucky Highway department now re q u i re sall new bridge decks to be built with epox y- c o a t e dre b a r s.

Page 4: Fusion Bonded Epoxy Coated Rebars_tcm45 345955

t o m o b i l e - b o rne deicing salts and the ramps re q u i red pe-riodic maintenance and repair during their first 16 ye a r sof life. Fi n a l l y, a repair project that may well cost in ex-cess of $100,000 was undertaken on the 7000-square -foot stru c t u re. In all pro b a b i l i t y, similar work will have tobe done on the larger stru c t u re.

In this most recent re p a i r- replacement project, half ofthe 7000-square-foot ramp was replaced, while the oth-er half was re p a i red with an ove r l a y, since it was ori g i-nally constructed over the store and could not be re-m oved without serious disruption of business.

A major dilemma facing the owners of the parking fa-cility invo l ved repair versus replacement. Both pro s p e c t sre p resented a major expense. To ensure that concrete re-

placement remains effective long into the future andthat spatting does not again become a problem, the ar-chitect/engineer specified epox y-coated rebars and ex-t reme care was taken in the project to ensure that alls t a n d a rds pertaining to the concrete constru c t i o n — t h emix, the aggre g a t e s, air entrainment and other factors—we re strictly adhered to.

Credits:Owner of Parkdale Plaza: MEPC Properties Inc., St. LouisPark, MinnesotaArchitects: Baker Associates Inc., MinneapolisEngineers: Clark Engineering, MinneapolisContractors: Acton Construction Company, Hugo, Minneso-taCoated rebar supplier: Simcote Inc., Newport, MinnesotaPowdered epoxy supplier: 3M, St. Paul, Minnesota

Major spalling on the bottom of a ramp in a St. Paul parkingfacility that was later repaired.

Epoxy-coated rebars in place on rebuilt ramp.

Entire floors were removed and replacedwith fusion-bonded epoxy-coated rebarsand new concrete.

PUBLICATION #C800587Co py right © 1980, The Ab e rdeen Gro u p

All rights re s e rve d