Fundamentals of wholesale electricity prices
Transcript of Fundamentals of wholesale electricity prices
www. erranet.org
ERRA Tailor-made Training Course: Principles of Tariff Regulation
Implemented for: Oman Power & Water Procurement Company
December 2-4, 2018 • Muscat, Oman
Fundamentals of wholesale
electricity prices
David Williams
2ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Contents
A. The difficulties of electricity markets
B. Build-up of costs and LCOE
C. Economic dispatch
D. Contracting and PPA pricing
E. Annual Revenue Requirement
3ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Power supply and demand: what
makes electricity so difficult?
– Because demand is inelastic in
short-run, the demand schedule
is almost vertical.
– Market price, p*, and total
energy to be supplied, q*, is
determined by intersection of
supply and demand curves.
Demand side flaw 1:
Historically a lack of real-time demand elasticity: demand responds only minimally to price →System Operator must set price when clearing is not achieved
Demand side flaw 2:
Cannot control real-time flow to specific consumers enforcing bilateral contracts → requires System Operator to balance in real-time
4ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Power supply and demand: what
makes electricity so difficult?
– Storage is about timing of
delivery.
– Storage is about frequency
and balancing.
– There is a value to
flexibility
Supply side flaw:
Electricity cannot be stored as electricity → batteries, fly wheels, pumped storage etc convert to other energy forms at cost
0
20
40
60
80
100
120
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
£/M
Wh
MW
Half-hour
MW Price Imbalance price
Generate
Refill
5ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Build-up of costs (retail)
Multiple tariffs
– Commercial and industrial
– Social
Multiple services
– Energy efficiency
– Purchase of transmission
services
But essentially a bundled service
– Metering and meter
reading
– Transmission, distribution
– Energy and energy profile
– Price management
Wholesale energy – bought
off generators and varies
depending on demand
shape
Subsidies
Distribution network costs
Transmission network
and services costs
Renewables costs and other
statutory charges and taxes
Supplier costs (incl hedging)
Supplier margin
6ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Build-up of costs (wholesale)
Generation costs are
– Fuel
– Variable O&M
– Fixed O&M
– Investment (capital costs)
Hydro and many renewables
have negligible variable cost
– Valued at opportunity cost
Costs include:
– Risk (incl. balancing cost)
– Load profile (idle capacity)
Revenues from the market
– But also from alternative
markets such as ancillary
services
Generator fuel cost and
other variable cost
Generator investment
cost and profit margin
Generator fixed costs
Balancing cost
Transmission losses?
Ancillary services
7ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Simple assessment of competitiveness:
levelised cost of electricity
Levelised cost of electricity (LCOE)
– LCOE is cited as a measure for the comparison of the costs of alternative
power plant technologies.
– LCOE are commonly used for power development planning (selecting the
least cost stack of generation).
– LCOE is a single $/kWh price representing the per unit costs for the energy
generation from power plants.
8ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
LCOE calculation
– The levelised cost of electricity (LCOE) is the present value of the total cost
of building and operating a power plant over its lifetime.
– 𝐿𝐶𝑂𝐸 =𝐾×𝐶𝑅𝐹+𝐹
𝐸+ 𝑉, where:
– NB: The function –PMT in excel can be used for the CRF
𝑉 =
𝐹 =
𝐸 =
Total value of variable O&M
costs
Total value of fixed O&M
costs
Total energy generated
𝐶𝑅𝐹 =
𝑖 =
𝑛 =
𝐾 =
𝑖 1+𝑖 𝑛
1+𝑖 𝑛−1is used to discount
Interest rate (discount factor)
Life expectancy of power plant
Total capital cost
9ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Illustration of LCOE
– Botswana LCOE supply curve for 2020
– But is this the full story?
10ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
LCOE advantages and disadvantages
Advantages
– Provides a common basis for
the comparison of power
generating technologies
– Reflects time value of money
and inflation
– Relatively simple
Disadvantages
– It can not provide a reliable
comparison for scheduled vs
intermittent quantities
– It can be misleading in assets
with long vs short lifetime
– Does not capture the
suitability of power plants for
base vs peaking generation
– Does not show the financials
of the investment
– It is heavily based on the
assumption of the hours of
power generation
11ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
What gets dispatched? The Load
Duration Curve
Arranges load (demand) from largest to smallest, typically over a year
12ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
What gets dispatched? Merit order
and least-cost dispatch
Overlay on load for dispatch Sort available generators by their
variable costs and stack
0
500
1000
1500
2000
1 2 3 4 5 6 7 8
Hour
Ca
pa
city (
MW
)
Gen 1 Gen 2 Gen 3
Gen 4 Gen 5 Gen 6
Increasing variable cost
13ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Economic dispatch, short-run value of
generation and pricing
Merit order model for least cost dispatch
– Lowest variable cost generation will be
dispatched first
– Models consider transmission and system
constraints (including must-run
conditions)
Infra-marginal rent
Peaking value
– Short-run scarcity
In a liberalised market
– Price is set at clearing for all generators
– infra-marginal rent and peaking value
cover fixed costs
In a regulated market like Oman costs are
typically disaggregated and defined per
generator
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
00:0
0
01:0
0
02:0
0
03:0
0
04:0
0
05:0
0
06:0
0
07:0
0
08:0
0
09:0
0
10:0
0
11:0
0
12:0
0
13:0
0
14:0
0
15:0
0
16:0
0
17:0
0
18:0
0
19:0
0
20:0
0
21:0
0
22:0
0
23:0
0
MW
h
Exports
Solar
Wind
Reservoir
RoR
Imported Coal
Lignite
Natural Gas
14ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Reflection of costs in PPA (standard
approach)
Specific to each generator
– Maintain flexibility in portfolio establishment
– Ex Ante in nature
Commercial terms regarding timing of payments, application of interest,
independence of dispute resolution
Capacity Payments
– Capital to sustain the generation business
– May be linked to availability
Energy Transactions
– Flexibility to reflect generation type and demand need
– Based on expectation of short run marginal cost pricing
15ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Contract options
Contract options include
– Varying periods (daily, weekly, monthly or even multi-year contracts)
– Varying quantities
– Optionality (calling rights, insurance-type products)
16ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Beyond LCOE: Annual Revenue
Requirement
AR
R (
$/M
Wh)
– Generators must recover fixed
and variable costs – their annual
revenue requirement (ARR)
– Add variable costs to fixed
costs (capital costs converted to
annual MWh of de-rated
available capacity) to get ARR in
£/MWh
– A “screening curve” plots how
ARR changes with plant capacity
factor
– De-rated capacity to address
forced outages
– Translated to LDC this estimates
relative capacity needed from
each fuel source
Oil-fired capacity required
Coal fired capacity required
17ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
Applying to non-dispatchable
generation– But Solar PV and wind are not
dispatchable → adding to a
screening curve is problematic
– Using average capacity factor as
de-rated “availability” may
indicate relative economic
competitiveness at far right of
curve (see PV example, right)
– But this ignores need to sell all
generation when operating at
full capacity and any correlation
between load and output
– Cannot be used to assess
competitiveness
– Instead may use a chronological
load time-series and resource
pattern (for RE output)
computational model
0
10
20
30
40
50
60
70
80
0% 20% 40% 60% 80% 100%Ave
rag
e co
st o
f ca
pac
ity
($/M
Wh
)
Capacity factor of plant (after de-rating)
Coal Oil Solar PV
XSolar PV capacity?
X
W
THANK YOU
FOR YOUR ATTENTION!
ERRA Tailor-made Training Course: Principles of Tariff RegulationDecember 2-4, 2018 • Muscat, Oman
David Williams
E-mail: [email protected]
Web: www.eca-uk.com