FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil &...
-
Upload
nguyenkien -
Category
Documents
-
view
217 -
download
1
Transcript of FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil &...
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
ANCHOR DESIGN & CONSTRUCTION FOR SHORING SYSTEMS
FUNDAMENTALS and AS4678 Civil & Structural Engineering Panel
19 March 2013 Andrew Shirley & Simon Fagg
SHIRLEY CONSULTING ENGINEERS PTY LTD INVESTIGATIVE, REMEDIAL & GROUND ENGINEERING
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
INTRODUCTION - 1
1. Soil & Ground Anchors for Shoring Systems. 2. Failures due to limited understanding &
reliance on ‘expert contractors’. 3. Some engineers are simplistic in their anchor
specifications, and just ‘call up the load required’.
4. Become litigation ‘targets’ when the anchor / shoring system fails.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
INTRODUCTION This Presentation will cover: 1. The Fundamentals of Anchor Design for Shoring
Systems. 2. The differences between soil anchors & anchors and
usual reasons why anchors & shoring systems fail. 3. The requirements of AS 4678 and its implications for
design engineers. 4. Five case studies of failures because the Design
Fundamentals have not been followed. 5. Lessons for Design Purposes. 6. The Risks & Liability Issues for Engineers 7. A pdf version of the PowerPoint Slides will be available
on our website www.shirley.net.au
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
EXAMPLE OF TYPICAL ANCHOR SPEC.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
EXAMPLE OF TYPICAL ANCHOR SPEC. A correct understanding of the way in which the anchors interact with the structural shoring system [viz: soil / structure interaction] is essential.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
ANCHORS FOR SHORING SYSTEMS
1. Anchors are NOT the same.
2. Many types of anchor; each type of anchor interacts differently with the structural part of the shoring.
3. Only limited information on the design of shoring wall anchors is generally available [e.g. CIRIA C580].
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
ANCHORS FOR SHORING SYSTEMS
Anchors fall into three Categories
Rock Anchors • Stiff Anchorage
• No load transferred from the Rock to the Soil
• No interaction between Anchorage Zone and Restrained Zone
Dead Man Anchors • Shallow Anchorage
• Surficial Failure of Dead Man, typically not within the Restrained Zone
• Minimal interaction between Anchorage Zone and Restrained Zone
Soil Anchors • Deformable Anchorage
• Anchorage Zone Interacts with the Restrained Zone
• Where problems are most frequent, and topic of this talk
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
1. Rock anchors are ‘stiff’ elements.
2. Rock Anchors form Structural Frame with the rock and structural parts.
3. Rock Anchors have a Large Overload Capacity.
ANCHORS WITH AN ANCHORAGE IN ROCK
Anchorages in rock are very common & rarely fail unless they are too short. Why?
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
SOIL ANCHORS vs ROCK ANCHORS
• Anchors into rock form a ‘Frame’
• Soil Anchors do NOT create a ‘Frame’. Only a Restrained Cantilever
• Soil Anchor MUST be able to ‘self tension’
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
Why do Soil Anchors Fail?
1. No Structural Frame.
2. Minimal / No Overload Capacity.
3. Incorrect Lock-Off Load.
4. Unable to ‘self tension’ if installed at too steep an angle.
ANCHORS WITH AN ANCHORAGE IN SOIL
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
SHORING WALL TERMINOLOGY
ACTIVE SIDE
(Adjoining Property / Ground)
PASSIVE SIDE
(Excavation)
Shoring Wall Shoring Wall
Restrained Zone
Anchorage Zone
Anchor
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
ANCHOR COMPONENT TERMINOLOGY
Tendon
Shoring Wall
Drilled Hole
Shoring Wall
Anchor Head
See AS4678, Clause B2 : Anchor Components
Anchorage Zone
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
ANCHOR LOAD SPECIFICATION
THE TERM SWL SHOULD NOT BE USED
Symbol Name Description
PW Working Load The Maximum or Ultimate calculated load in the anchor during the construction processes.
PP Proof Load The load to which the ground anchor is to be loaded to check the adequacy.
PLO ‘Lock Off’ Load The load which will be left in the ground anchor when stressed. [i.e. The residual anchor load after the proof loading is complete].
PLT Long-term design load
The long-term residual load in the anchorage following its construction, prestressing, creep and subsequent ground movements.
Note: Whilst AS4678 (2002) describes the Working load as the “load necessary to ensure that the structure behaves in a satisfactory manner”, in the context of a shoring system and as the load changes during construction, the above definition is considered to be more precise.
Australian Standard [AS4678: Clause B4.4] requires the following loads to be specified by a designer:
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
1. The Anchorage Zone can interact with the Restrained Zone.
2. As Soil Anchors can ‘creep’ and loose tension under load, soil anchors need to be able to ‘self-tension’.
3. Limited Capacity for Overload
ANCHORS WITH AN ANCHORAGE IN SOIL FAILURES & CAUSES OF PROBLEM
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
SOIL ANCHOR SELF TENSIONING
As the shoring wall moves:
• Really Steep Anchors lose tension.
• Anchors which cross the failure plane at right angles only act in shear.
• Shallow Anchors can ‘self tension’, as movement of the potential failure wedge creates anchor tension.
Really steep anchor Loses Tension
Steep anchor Only acts in shear
Shallow anchor Self Tensions
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
LOAD TRANSFER DURING EXCAVATION
Soil Material
Passive Pressure
Where does the removed passive resistance go?
• Deformation of the Retained Soil
• Deflection of the Wall.
• Increased Anchor Load
• Increased Passive Pressure at the Toe of the Wall
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
1. An anchor tensioned to the Rankine active load doesn’t work, particularly when the tension can ‘relax’ due to Anchorage creep.
2. Rankine analysis not suitable – must use finite element methods [e.g. Wallap].
3. The selection of the right ‘lock-off’ load is a trade off of deflection and anchor load – the Optimal Range’.
ANCHOR LOCK-OFF LOADS & DEFLECTIONS
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
ANCHOR LOCK-OFF LOADS & DEFLECTIONS – (2)
Anchor Lock-off Load [kN]
Max
imum
Wal
l Def
lect
ion
[mm
]
0
5
10
15
20
25
30
35
0 50 100 150 200 250 300 350 400
6m Excavation
5m Excavation
Optimal Range
NOTE: THIS DIAGRAM IS NOT A DESIGN CHART. IT IS AN EXMAPLE BASED ON A SPECIFIC SITES GEOTECHNICAL CONDITIONS, WALL AND ANCHOR PROPERTIES.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
0
50
100
150
200
250
300
350
1 2 3 4 5 6
ANCHOR LOCK-OFF LOADS VS EXCAVATION DEPTH
Excavation Depth [m]
Anc
hor L
oad
[kN
]
Opt
imal
D
efle
ctio
n Lo
ck-o
ff
For a 6m Excavation
PLO = 150 kN
PP = 256 kN
1.25x PW = 206 kN
NOTE: THIS DIAGRAM IS NOT A DESIGN CHART. IT IS AN EXMAPLE BASED ON A SPECIFIC SITES GEOTECHNICAL CONDITIONS, WALL AND ANCHOR PROPERTIES.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
1. Failure does not mean ‘Collapse’. 2. Principal causes of failure:
• Wrong Specification by the designer [e.g. the angle of installation is too steep and can’t self tension, etc.].
• Anchors too short. • Incorrect load testing procedures & wrong
lock-off load. 3. Construction Problems.
ANCHORS WITH AN ANCHORAGE IN SOIL FAILURES & CAUSES OF PROBLEMS
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
MONITORING OF SHORING & ANCHOR PERFORMANCE
MONITORING: Checks Anchor Performance wrt design. Must perform monitoring because Factor of Safety normally 1.2 to 1.25. Good anchor load test records. Monitoring Points must be continued down the shoring wall, and accurate to 2 mm. Includes visual ‘walk around’ the site every day Enables action to avert failure
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
INCIDENCE & EXAMPLES OF ANCHOR INDUCED SHORING FAILURES
Incidence of Anchor Failures Common in Sands & Soils
Occasional in Clay Rarely in Rock
Examples – by Simon Fagg Global Failures
Anchorage & Pull-out Failures
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 1 EASTERN SUBURBS, SYDNEY
This project involved: • a 5m deep excavation in sandy alluvial foundation material. • the installation of steel sheet piles and two rows of screw
anchors. • the excavation was to support a historical 3 storey building
and associated historical hall.
CASE STUDY 1 EASTERN SUBURBS, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 1 EASTERN SUBURBS, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 1 EASTERN SUBURBS, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 1 EASTERN SUBURBS, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 1 EASTERN SUBURBS, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 1 EASTERN SUBURBS, SYDNEY
CONSEQUENCE OF THE FAILURE Construction • A requirement to backfill against part of the collapsing shoring
system, resulting in delays in Construction. • The need to demolish, and then reconstruct, a heritage listed
building; • Several other neighbouring buildings ‘walking’ across the site
boundaries.
Long Term • The Builder [over 100 years in operation] incurred significant losses
on the project, and was placed in Liquidation 3 years later. • The Piling Contractor was placed in liquidation 4 years later. • The Engineer who designed the system has now retired.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 2 NORTHERN BEACHES, SYDNEY
This project involved: • a 12m deep excavation in sandy alluvial foundation material. • a high ground water level. • a sheet pile shoring system with four rows of ‘bar’ type anchors. • several neighbouring single & double storey commercial
premises.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 2 NORTHERN BEACHES, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 2 NORTHERN BEACHES, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
GLOBAL FAILURES NORTHERN BEACHES, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 2 NORTHERN BEACHES, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
GLOBAL FAILURES NORTHERN BEACHES, SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 2 NORTHERN BEACHES, SYDNEY
Design Deflection
Warning Limit
Action Limit
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 2 NORTHERN BEACHES, SYDNEY CONSEQUENCE OF THE FAILURE
Construction • Partial Backfilling was required to stabilise the wall; • Damage was caused to six neighbouring buildings; • One building being unrepairable and not able to be replaced
without a four level basement; three years after the completion of construction this building is still unable to be occupied.
Long Term • Significant rental losses to the neighbouring building owners. • Two local businesses failed due to the disruption and cracking. • The Builder was placed in liquidation 3 years after the works. • The Piling Contractor was placed in liquidation 3 years after the
works. The engineer has now retired
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
This project involved: • a 6m deep excavation in sandy foundation material. • a contiguous concrete pile shoring system with two rows of
anchors. • a high ground water level above the base of the excavation. • an arterial road with extensive services, including a water main.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
Monitoring Marks
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 3 SOUTHERN SYDNEY
CONSEQUENCE OF THE FAILURE Construction • Bursting of a high pressure water main. • The construction site was flooded for several weeks. • Backfilling was required against the shoring system to ensure
collapse did not occur; This caused significant delays in this area. • A probably excessive replacement shoring system was installed
before construction was allowed to continue in this area. Long Term • Main traffic artery closed for several months, with a significant cost
to the community. • Legal proceedings lasting for 4 years.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN SYDNEY
This project involved: • a 7m deep excavation in Silty Clay and weathered shale
materials. • a concrete pile shoring system with concrete infill panels • one row of anchors, ‘kept inside the boundary’.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN SYDNEY
‘Greasy backs’
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN SYDNEY
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 4 NORTH WESTERN, SYDNEY
CONSEQUENCE OF THE FAILURE
Construction • Collapse of the excavation, with consequent backfilling delaying
construction. • Loss of parking and limited access for the neighbouring residential
building. Long Term • Delayed project delivery due to the backfilling and additional
stabilisation works required. • Increased future insurance costs for the Builder on the project.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 5 MONA VALE
This project involved: • a 2.5m deep excavation in recent sand deposits. • a steel sheet pile shoring system. • one row of screw anchors.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 5 MONA VALE
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
CASE STUDY 5 MONA VALE
Grout
Anchor Shaft
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
REVIEW OF CAUSES What were the causes of these failures?
Other Causes: Design Errors • Using ‘Flexible’ retaining walls to support sensitive structures. • Failure to determine what services might be affected by the
shoring wall and anchors. • Failing to consider locally deeper excavations
[ie. Don’t forget the lift pits!]. • Using a Computer Program for design without understanding
how it works.
THE PRINCIPAL CAUSE WAS CUTTING CORNERS IN THE DESIGN PROCESSES!
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
REVIEW OF CAUSES What were the causes of these failures?
Other Causes – Specification & Construction Errors Anchor Specification Errors • Specifying anchors only in terms of the SWL • Specifying short anchors • Specifying steep anchors in sand
Construction Errors • Not following the geotechnical warnings given • Ignoring the warning signs that something was wrong
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
LESSONS FOR DESIGN
Before Starting your Design, you need to at least know: • Site Geotechnical Conditions
[i.e. A Geotechnical Report] • A Survey of the Site & Land surrounding the site
• Details of Services surrounding the site [Dial Before You Dig]
• Details of the Footing System of Buildings within the ‘Zone of Influence’ of the Anchors.
• Confirmation of the Permission to anchor under the neighbouring property.
DESIGN IS NOT CALCULATIONS (although calculations are a part of it)
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
LESSONS FOR DESIGN
The Design Process should at least include: 1. Determination of design limits based on the
surrounding structures & services. 2. Determine the design depth of the excavation
[e.g. including lift pits, footings, over excavation etc.]. 3. Evaluation of the best type of shoring wall to be used. 4. Calculations for the Shoring Wall & Anchors. 5. Documentation [i.e. The Drawings and / or Specification].
DESIGN IS NOT CALCULATIONS (although calculations are a part of it)
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
LESSONS FOR DESIGN
THE SPECIFICATION MUST SUMMARISE THE DESIGN
For Ground Anchors AS4678, Clause D4.6 requires: a) Type of Anchor (ie. Temporary or Permanent) and the Design Life. b) Expected Anchorage Zone material. c) Minimum free length. d) Ultimate Design Load. e) Test proof load and test load duration. f) Lock-off Load.
In addition, the Installation Angle is very important.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
LESSONS FOR DESIGN Specification : Monitoring Requirements
In addition, SCE recommend specifying the monitoring requirements for all shoring installations. This should include at least: 1. A daily ‘walk around’ of the site and regular photography. 2. Regular, accurate survey of monitoring points located both
along and down the face of the shoring wall. 3. Timeframe for the provision of monitoring results to the
engineer. [e.g. results to be provided with 48 hours]. 4. Warning and Action [e.g. backfilling] deflection limits.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
SOME LESSONS FROM THE FAILURES
1. AS 4678 is important and should be followed; non-compliance leads to failure.
2. A Failure to consider overall & global stability of the shoring system.
3. If the monitoring reveals a problem, it is a warning; so get independent engineering advice quickly – and preferably not from the anchoring / shoring designer.
4. An early independent review can usually avoid a catastrophe – why not ‘phone a friend’.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
SOME LESSONS FROM THE FAILURES (2) (EXPERTISE)
1. Appropriate expertise essential. 2. Interaction between Structural & Ground
Engineers – if poor, failure inevitable. 3. Ground & Geotechnical Engineers – don’t
assume that someone who can drill & test understands design processes.
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
ENGINEERING RISK & LIABILITY
Professional Issues 1. Code of Ethics & Relevant Expertise – don’t design
what you don’t understand. 2. Soil / Structure Interaction & Ground Engineering. 3. Comply with Standards [e.g. AS 4678, CIRIA C580]. 4. Be involved in the Contract Inspection & Review
processes. Commercial Issues • Can you afford to be sued? • What is your reputation worth?
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd
THANK YOU Any Questions?
A copy of this presentation is available on our website.
www.shirley.net.au, ‘Links & Downloads’, SCE Papers & Publications. http://www.shirley.net.au/index.php?page=links_downloads&id=2&table=downloads