FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil &...

68
www.shirley.net.au © Shirley Consulting Engineers Pty Ltd ANCHOR DESIGN & CONSTRUCTION FOR SHORING SYSTEMS FUNDAMENTALS and AS4678 Civil & Structural Engineering Panel 19 March 2013 Andrew Shirley & Simon Fagg SHIRLEY CONSULTING ENGINEERS PTY LTD INVESTIGATIVE, REMEDIAL & GROUND ENGINEERING

Transcript of FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil &...

Page 1: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

ANCHOR DESIGN & CONSTRUCTION FOR SHORING SYSTEMS

FUNDAMENTALS and AS4678 Civil & Structural Engineering Panel

19 March 2013 Andrew Shirley & Simon Fagg

SHIRLEY CONSULTING ENGINEERS PTY LTD INVESTIGATIVE, REMEDIAL & GROUND ENGINEERING

Page 2: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

INTRODUCTION - 1

1. Soil & Ground Anchors for Shoring Systems. 2. Failures due to limited understanding &

reliance on ‘expert contractors’. 3. Some engineers are simplistic in their anchor

specifications, and just ‘call up the load required’.

4. Become litigation ‘targets’ when the anchor / shoring system fails.

Page 3: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

INTRODUCTION This Presentation will cover: 1. The Fundamentals of Anchor Design for Shoring

Systems. 2. The differences between soil anchors & anchors and

usual reasons why anchors & shoring systems fail. 3. The requirements of AS 4678 and its implications for

design engineers. 4. Five case studies of failures because the Design

Fundamentals have not been followed. 5. Lessons for Design Purposes. 6. The Risks & Liability Issues for Engineers 7. A pdf version of the PowerPoint Slides will be available

on our website www.shirley.net.au

Page 4: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

EXAMPLE OF TYPICAL ANCHOR SPEC.

Page 5: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

EXAMPLE OF TYPICAL ANCHOR SPEC. A correct understanding of the way in which the anchors interact with the structural shoring system [viz: soil / structure interaction] is essential.

Page 6: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

ANCHORS FOR SHORING SYSTEMS

1. Anchors are NOT the same.

2. Many types of anchor; each type of anchor interacts differently with the structural part of the shoring.

3. Only limited information on the design of shoring wall anchors is generally available [e.g. CIRIA C580].

Page 7: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

ANCHORS FOR SHORING SYSTEMS

Anchors fall into three Categories

Rock Anchors • Stiff Anchorage

• No load transferred from the Rock to the Soil

• No interaction between Anchorage Zone and Restrained Zone

Dead Man Anchors • Shallow Anchorage

• Surficial Failure of Dead Man, typically not within the Restrained Zone

• Minimal interaction between Anchorage Zone and Restrained Zone

Soil Anchors • Deformable Anchorage

• Anchorage Zone Interacts with the Restrained Zone

• Where problems are most frequent, and topic of this talk

Page 8: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

1. Rock anchors are ‘stiff’ elements.

2. Rock Anchors form Structural Frame with the rock and structural parts.

3. Rock Anchors have a Large Overload Capacity.

ANCHORS WITH AN ANCHORAGE IN ROCK

Anchorages in rock are very common & rarely fail unless they are too short. Why?

Page 9: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

SOIL ANCHORS vs ROCK ANCHORS

• Anchors into rock form a ‘Frame’

• Soil Anchors do NOT create a ‘Frame’. Only a Restrained Cantilever

• Soil Anchor MUST be able to ‘self tension’

Page 10: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

Why do Soil Anchors Fail?

1. No Structural Frame.

2. Minimal / No Overload Capacity.

3. Incorrect Lock-Off Load.

4. Unable to ‘self tension’ if installed at too steep an angle.

ANCHORS WITH AN ANCHORAGE IN SOIL

Page 11: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

SHORING WALL TERMINOLOGY

ACTIVE SIDE

(Adjoining Property / Ground)

PASSIVE SIDE

(Excavation)

Shoring Wall Shoring Wall

Restrained Zone

Anchorage Zone

Anchor

Page 12: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

ANCHOR COMPONENT TERMINOLOGY

Tendon

Shoring Wall

Drilled Hole

Shoring Wall

Anchor Head

See AS4678, Clause B2 : Anchor Components

Anchorage Zone

Page 13: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

ANCHOR LOAD SPECIFICATION

THE TERM SWL SHOULD NOT BE USED

Symbol Name Description

PW Working Load The Maximum or Ultimate calculated load in the anchor during the construction processes.

PP Proof Load The load to which the ground anchor is to be loaded to check the adequacy.

PLO ‘Lock Off’ Load The load which will be left in the ground anchor when stressed. [i.e. The residual anchor load after the proof loading is complete].

PLT Long-term design load

The long-term residual load in the anchorage following its construction, prestressing, creep and subsequent ground movements.

Note: Whilst AS4678 (2002) describes the Working load as the “load necessary to ensure that the structure behaves in a satisfactory manner”, in the context of a shoring system and as the load changes during construction, the above definition is considered to be more precise.

Australian Standard [AS4678: Clause B4.4] requires the following loads to be specified by a designer:

Page 14: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

1. The Anchorage Zone can interact with the Restrained Zone.

2. As Soil Anchors can ‘creep’ and loose tension under load, soil anchors need to be able to ‘self-tension’.

3. Limited Capacity for Overload

ANCHORS WITH AN ANCHORAGE IN SOIL FAILURES & CAUSES OF PROBLEM

Page 15: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

SOIL ANCHOR SELF TENSIONING

As the shoring wall moves:

• Really Steep Anchors lose tension.

• Anchors which cross the failure plane at right angles only act in shear.

• Shallow Anchors can ‘self tension’, as movement of the potential failure wedge creates anchor tension.

Really steep anchor Loses Tension

Steep anchor Only acts in shear

Shallow anchor Self Tensions

Page 16: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

LOAD TRANSFER DURING EXCAVATION

Soil Material

Passive Pressure

Where does the removed passive resistance go?

• Deformation of the Retained Soil

• Deflection of the Wall.

• Increased Anchor Load

• Increased Passive Pressure at the Toe of the Wall

Page 17: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

1. An anchor tensioned to the Rankine active load doesn’t work, particularly when the tension can ‘relax’ due to Anchorage creep.

2. Rankine analysis not suitable – must use finite element methods [e.g. Wallap].

3. The selection of the right ‘lock-off’ load is a trade off of deflection and anchor load – the Optimal Range’.

ANCHOR LOCK-OFF LOADS & DEFLECTIONS

Page 18: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

ANCHOR LOCK-OFF LOADS & DEFLECTIONS – (2)

Anchor Lock-off Load [kN]

Max

imum

Wal

l Def

lect

ion

[mm

]

0

5

10

15

20

25

30

35

0 50 100 150 200 250 300 350 400

6m Excavation

5m Excavation

Optimal Range

NOTE: THIS DIAGRAM IS NOT A DESIGN CHART. IT IS AN EXMAPLE BASED ON A SPECIFIC SITES GEOTECHNICAL CONDITIONS, WALL AND ANCHOR PROPERTIES.

Page 19: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

0

50

100

150

200

250

300

350

1 2 3 4 5 6

ANCHOR LOCK-OFF LOADS VS EXCAVATION DEPTH

Excavation Depth [m]

Anc

hor L

oad

[kN

]

Opt

imal

D

efle

ctio

n Lo

ck-o

ff

For a 6m Excavation

PLO = 150 kN

PP = 256 kN

1.25x PW = 206 kN

NOTE: THIS DIAGRAM IS NOT A DESIGN CHART. IT IS AN EXMAPLE BASED ON A SPECIFIC SITES GEOTECHNICAL CONDITIONS, WALL AND ANCHOR PROPERTIES.

Page 20: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

1. Failure does not mean ‘Collapse’. 2. Principal causes of failure:

• Wrong Specification by the designer [e.g. the angle of installation is too steep and can’t self tension, etc.].

• Anchors too short. • Incorrect load testing procedures & wrong

lock-off load. 3. Construction Problems.

ANCHORS WITH AN ANCHORAGE IN SOIL FAILURES & CAUSES OF PROBLEMS

Page 21: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

MONITORING OF SHORING & ANCHOR PERFORMANCE

MONITORING: Checks Anchor Performance wrt design. Must perform monitoring because Factor of Safety normally 1.2 to 1.25. Good anchor load test records. Monitoring Points must be continued down the shoring wall, and accurate to 2 mm. Includes visual ‘walk around’ the site every day Enables action to avert failure

Page 22: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

INCIDENCE & EXAMPLES OF ANCHOR INDUCED SHORING FAILURES

Incidence of Anchor Failures Common in Sands & Soils

Occasional in Clay Rarely in Rock

Examples – by Simon Fagg Global Failures

Anchorage & Pull-out Failures

Page 23: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 1 EASTERN SUBURBS, SYDNEY

This project involved: • a 5m deep excavation in sandy alluvial foundation material. • the installation of steel sheet piles and two rows of screw

anchors. • the excavation was to support a historical 3 storey building

and associated historical hall.

CASE STUDY 1 EASTERN SUBURBS, SYDNEY

Page 24: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 1 EASTERN SUBURBS, SYDNEY

Page 25: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 1 EASTERN SUBURBS, SYDNEY

Page 26: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 1 EASTERN SUBURBS, SYDNEY

Page 27: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 1 EASTERN SUBURBS, SYDNEY

Page 28: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 1 EASTERN SUBURBS, SYDNEY

CONSEQUENCE OF THE FAILURE Construction • A requirement to backfill against part of the collapsing shoring

system, resulting in delays in Construction. • The need to demolish, and then reconstruct, a heritage listed

building; • Several other neighbouring buildings ‘walking’ across the site

boundaries.

Long Term • The Builder [over 100 years in operation] incurred significant losses

on the project, and was placed in Liquidation 3 years later. • The Piling Contractor was placed in liquidation 4 years later. • The Engineer who designed the system has now retired.

Page 29: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 2 NORTHERN BEACHES, SYDNEY

This project involved: • a 12m deep excavation in sandy alluvial foundation material. • a high ground water level. • a sheet pile shoring system with four rows of ‘bar’ type anchors. • several neighbouring single & double storey commercial

premises.

Page 30: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 2 NORTHERN BEACHES, SYDNEY

Page 31: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 2 NORTHERN BEACHES, SYDNEY

Page 32: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

GLOBAL FAILURES NORTHERN BEACHES, SYDNEY

Page 33: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 2 NORTHERN BEACHES, SYDNEY

Page 34: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

GLOBAL FAILURES NORTHERN BEACHES, SYDNEY

Page 35: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 2 NORTHERN BEACHES, SYDNEY

Design Deflection

Warning Limit

Action Limit

Page 36: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 2 NORTHERN BEACHES, SYDNEY CONSEQUENCE OF THE FAILURE

Construction • Partial Backfilling was required to stabilise the wall; • Damage was caused to six neighbouring buildings; • One building being unrepairable and not able to be replaced

without a four level basement; three years after the completion of construction this building is still unable to be occupied.

Long Term • Significant rental losses to the neighbouring building owners. • Two local businesses failed due to the disruption and cracking. • The Builder was placed in liquidation 3 years after the works. • The Piling Contractor was placed in liquidation 3 years after the

works. The engineer has now retired

Page 37: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

This project involved: • a 6m deep excavation in sandy foundation material. • a contiguous concrete pile shoring system with two rows of

anchors. • a high ground water level above the base of the excavation. • an arterial road with extensive services, including a water main.

Page 38: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 39: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 40: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 41: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Monitoring Marks

Page 42: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 43: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 44: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 45: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 46: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

Page 47: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 3 SOUTHERN SYDNEY

CONSEQUENCE OF THE FAILURE Construction • Bursting of a high pressure water main. • The construction site was flooded for several weeks. • Backfilling was required against the shoring system to ensure

collapse did not occur; This caused significant delays in this area. • A probably excessive replacement shoring system was installed

before construction was allowed to continue in this area. Long Term • Main traffic artery closed for several months, with a significant cost

to the community. • Legal proceedings lasting for 4 years.

Page 48: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN SYDNEY

This project involved: • a 7m deep excavation in Silty Clay and weathered shale

materials. • a concrete pile shoring system with concrete infill panels • one row of anchors, ‘kept inside the boundary’.

Page 49: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN SYDNEY

Page 50: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN SYDNEY

‘Greasy backs’

Page 51: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN SYDNEY

Page 52: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN SYDNEY

Page 53: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN SYDNEY

Page 54: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN SYDNEY

Page 55: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 4 NORTH WESTERN, SYDNEY

CONSEQUENCE OF THE FAILURE

Construction • Collapse of the excavation, with consequent backfilling delaying

construction. • Loss of parking and limited access for the neighbouring residential

building. Long Term • Delayed project delivery due to the backfilling and additional

stabilisation works required. • Increased future insurance costs for the Builder on the project.

Page 56: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 5 MONA VALE

This project involved: • a 2.5m deep excavation in recent sand deposits. • a steel sheet pile shoring system. • one row of screw anchors.

Page 57: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 5 MONA VALE

Page 58: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

CASE STUDY 5 MONA VALE

Grout

Anchor Shaft

Page 59: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

REVIEW OF CAUSES What were the causes of these failures?

Other Causes: Design Errors • Using ‘Flexible’ retaining walls to support sensitive structures. • Failure to determine what services might be affected by the

shoring wall and anchors. • Failing to consider locally deeper excavations

[ie. Don’t forget the lift pits!]. • Using a Computer Program for design without understanding

how it works.

THE PRINCIPAL CAUSE WAS CUTTING CORNERS IN THE DESIGN PROCESSES!

Page 60: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

REVIEW OF CAUSES What were the causes of these failures?

Other Causes – Specification & Construction Errors Anchor Specification Errors • Specifying anchors only in terms of the SWL • Specifying short anchors • Specifying steep anchors in sand

Construction Errors • Not following the geotechnical warnings given • Ignoring the warning signs that something was wrong

Page 61: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

LESSONS FOR DESIGN

Before Starting your Design, you need to at least know: • Site Geotechnical Conditions

[i.e. A Geotechnical Report] • A Survey of the Site & Land surrounding the site

• Details of Services surrounding the site [Dial Before You Dig]

• Details of the Footing System of Buildings within the ‘Zone of Influence’ of the Anchors.

• Confirmation of the Permission to anchor under the neighbouring property.

DESIGN IS NOT CALCULATIONS (although calculations are a part of it)

Page 62: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

LESSONS FOR DESIGN

The Design Process should at least include: 1. Determination of design limits based on the

surrounding structures & services. 2. Determine the design depth of the excavation

[e.g. including lift pits, footings, over excavation etc.]. 3. Evaluation of the best type of shoring wall to be used. 4. Calculations for the Shoring Wall & Anchors. 5. Documentation [i.e. The Drawings and / or Specification].

DESIGN IS NOT CALCULATIONS (although calculations are a part of it)

Page 63: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

LESSONS FOR DESIGN

THE SPECIFICATION MUST SUMMARISE THE DESIGN

For Ground Anchors AS4678, Clause D4.6 requires: a) Type of Anchor (ie. Temporary or Permanent) and the Design Life. b) Expected Anchorage Zone material. c) Minimum free length. d) Ultimate Design Load. e) Test proof load and test load duration. f) Lock-off Load.

In addition, the Installation Angle is very important.

Page 64: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

LESSONS FOR DESIGN Specification : Monitoring Requirements

In addition, SCE recommend specifying the monitoring requirements for all shoring installations. This should include at least: 1. A daily ‘walk around’ of the site and regular photography. 2. Regular, accurate survey of monitoring points located both

along and down the face of the shoring wall. 3. Timeframe for the provision of monitoring results to the

engineer. [e.g. results to be provided with 48 hours]. 4. Warning and Action [e.g. backfilling] deflection limits.

Page 65: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

SOME LESSONS FROM THE FAILURES

1. AS 4678 is important and should be followed; non-compliance leads to failure.

2. A Failure to consider overall & global stability of the shoring system.

3. If the monitoring reveals a problem, it is a warning; so get independent engineering advice quickly – and preferably not from the anchoring / shoring designer.

4. An early independent review can usually avoid a catastrophe – why not ‘phone a friend’.

Page 66: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

SOME LESSONS FROM THE FAILURES (2) (EXPERTISE)

1. Appropriate expertise essential. 2. Interaction between Structural & Ground

Engineers – if poor, failure inevitable. 3. Ground & Geotechnical Engineers – don’t

assume that someone who can drill & test understands design processes.

Page 67: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

ENGINEERING RISK & LIABILITY

Professional Issues 1. Code of Ethics & Relevant Expertise – don’t design

what you don’t understand. 2. Soil / Structure Interaction & Ground Engineering. 3. Comply with Standards [e.g. AS 4678, CIRIA C580]. 4. Be involved in the Contract Inspection & Review

processes. Commercial Issues • Can you afford to be sued? • What is your reputation worth?

Page 68: FUNDAMENTALS and AS4678 - Sydney Forensic · PDF fileFUNDAMENTALS and AS4678 . Civil & Structural ... Five case studies of failures because the Design Fundamentals have not ... interact

www.shirley.net.au © Shirley Consulting Engineers Pty Ltd

THANK YOU Any Questions?

A copy of this presentation is available on our website.

www.shirley.net.au, ‘Links & Downloads’, SCE Papers & Publications. http://www.shirley.net.au/index.php?page=links_downloads&id=2&table=downloads