FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01,...

34
FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM •On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued to AIRWORK HOLDINGS LTD. of New Zealand, an aircraft leasing company, commemorating Palau

Transcript of FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01,...

Page 1: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM Dept. Transportation, Communications & Infrastructure

AIR CARRIERS IN THE FSM

•On August 01, 2004, a FSM Foreign Air Carrier

Permit (FACP) was issued to AIRWORK

HOLDINGS LTD. of New Zealand, an aircraft leasing

company, commemorating Palau Micronesia Air’s

(PMA) first flight to the FSM.

Page 2: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

AIR CARRIERS IN THE FSM

• PMA announced a temporary suspension of flight operations effective December 23, 2004.

• The FSM Department of TC&I is currently reviewing applications for Foreign Air Carrier Permits from ECO Airlines, an Australian based airline, and KARAT Airlines, a Russian registered airline

Page 3: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

AIR CARRIERS IN THE FSM

• based in Brisbane, Australia. KARAT airlines is proposing to provide a weekly Passenger/Cargo (Combi) air service from Brisbane to Pohnpei with intermediate stops in Solomon Islands and Majuro.

Page 4: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIRPORTS (SECURITY)

• An ICAO Universal Security Audit was conducted at the FSM Dept. of TC&I and Pohnpei Int’l Airport from June 22 to July 1, 2004.

• The FSM Department of TC&I is currently drafting an action plan to address the recommendations cited in the Security Audit

• The department is soliciting the assistance of U.S. Department of Homeland Security in providing technical assistance on improving the National Civil Aviation Security Plan and other programs.

Page 5: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIRPORTS (SECURITY)

• We are also studying the possibilities of preparing the FSM to take over screenings at all 4 FSM airports by January 2006. Another option is to enter into an agreement with Continental Airlines to continue to provide all screenings at the FSM airports.

Page 6: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIRPORTS

• A Scope of Work On The Study On The Improvement Of Pohnpei International Airport was agreed and signed between the FSM Government, Pohnpei State Government, and Pohnpei Port Authority And Japan International Cooperation Agency (JICA) on December 6, 2004.

• The purpose of this study is to determine the economic feasibility of extending the runway and improving the support facilities.

Page 7: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIRPORTS

• The department understands that this study will not interfere nor is a conflict to the FSM/FAA AIP projects. JICA is fully aware of the FSM/FAA AIP projects and will most likely proceed with any expansion of the airport facilities after the completion of the rehabilitation of Pohnpei Airport’s runway, taxiway and apron.

Page 8: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM Dept. Transportation, Communications & Infrastructure

•The FSM Department of Transportation,

Communications & Infrastructure is responsible for

the preparation and implementation of the FSM

Airports AIP projects under the guidance and

leadership of Secretary Akillino H. Susaia.

Page 9: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

The Honorable Akillino H. Susaia, Secretary Dept. of TC&I

Page 10: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIP PROJECTS

• On November 2004, an RFP for the FSM Airports AIP projects was advertised in newspapers in the FSM, Guam and Hawaii including the U.S. DOI’s website.

• Several reputable engineering companies responded with great interests.

Page 11: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIP PROJECTS

• The FSM AIP Selection committee selected three firms to assist the FSM in the preparation and implementation of its current 8 large scale projects.

• On February 18, 2005, a contract was signed and executed between the FSM and GMP Hawaii, Inc. GMP has since started working on its assigned projects.

Page 12: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIP PROJECTS

• On March 4, 2005, a contract between the FSM and Leo A. Daly Company was signed and executed for the design of the restoration and improvement of Yap Airport terminal. Another contract for the other awarded projects for Leo A Daly is scheduled to be executed this month.

• A contract between the FSM and E.M. Chen & Associates is also scheduled to be signed this month for the AOE surveys at the FSM airports.

Page 13: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM AIP PROJECTS

• Since the signing of their contracts, both companies (GMP and Leo A. Daly) have undertaken their first site visits.

• GMP has just wrapped up its topographic survey of Pohnpei International Airport.

• Leo A. Daly engineers were in Yap for their site visit. A proposed floor plan for the restoration of Yap’s terminal building has been submitted to my office and the FAA for our reviews.

Page 14: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

KOSRAE INT’L AIRPORT

Page 15: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

KOSRAE INT’L AIRPORT

• Kosrae Airport, under this AIP program, will be getting 1 ARFF vehicle with protective clothing and various required special tools.

• Expansion of the existing ARFF building to accommodate two 1500 gal ARFF vehicles

Page 16: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

KOSRAE INT’L AIRPORT

• Improvement & Expansion of terminal apron

• Improvement of Airfield Markings, Lighting & Signage

• Performance of Obstruction Evaluation in accordance with FAA No. 405

• Preparation of Airport Master Plan

Page 17: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

Sleeping Lady In Kosrae

Page 18: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

POHNPEI INT’L AIRPORT

Page 19: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

POHNPEI INT’L AIRPORT

• Pohnpei Airport, under the AIP program, will be getting two ARFF vehicles with protective clothing and various required specialized tools

Page 20: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

POHNPEI INT’L AIRPORT

• Rehabilitation of runway, taxiway and apron. • FAA has granted authorization for a quick-fix of

the two depression areas on the runway• Improvement of Airfield Marking, Lighting &

Signage.• New ARFF building to accommodate two ARFF

vehicles. We have been informed that the FAA wants the SAWR rooms build on top of these ARFF buildings to serve as observation decks.

Page 21: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

POHNPEI INT’L AIRPORT

• Performance of an Obstruction Evaluation in accordance with FAA No. 405

• Preparation of an Airport Master Plan

Page 22: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

Nanmadol Ruines in Pohnpei

Page 23: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

CHUUK INT’L AIRPORT

Page 24: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

CHUUK INT’L AIRPORT

• Chuuk Airport, under the AIP program, will be getting two 1500 gal ARFF vehicles with protective clothing and various required special tools

• New ARFF building to accommodate two ARFF vehicles

Page 25: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

CHUUK INT’L AIRPORT

• Improvement of Airfield Markings, Lighting & Signage

• Performance of Obstruction Evaluation in accordance with FAA No. 405

• Preparation of an Airport Master Plan

Page 26: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

Famous dive spots in Chuuk’s lagoon

Page 27: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

YAP INT’L AIRPORT

Page 28: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

YAP INT’L AIRPORT

• Design for the restoration/improvement of Yap terminal building is ongoing.

• Will be getting two 1500 gal ARFF vehicles with protective clothing & various required special tools

Page 29: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

Yap INT’L AIRPORT

• New ARFF building to accommodate two ARFF vehicles

• Improvement of Airfield Markings, Lighting & Signage

• Rehabilitation of apron area• Restoration of a temporary ARFF shed, perimeter

fencing that meets FAA specifications and other miscellaneous items that sustained damages from typhoon Sudal in February of 2004.

Page 30: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

Yapese boy voyaging on a bamboo raft

Page 31: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.
Page 32: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.
Page 33: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.
Page 34: FSM Dept. Transportation, Communications & Infrastructure AIR CARRIERS IN THE FSM On August 01, 2004, a FSM Foreign Air Carrier Permit (FACP) was issued.

FSM Dept. of Transportation, Communications & Infrastructure

Mahalo!

2005 Pacific Aviation Directors’ Workshop