Fs2013 july

80
Financial Statements For the Period September 1, 2012 July 31, 2013 For the Meeting of the Board of Trustees August 8, 2013 for Houston Community College System & Houston Community College Public Facility Corporation

Transcript of Fs2013 july

Page 1: Fs2013 july

Financial StatementsFor the Period

September 1, 2012 ‐ July 31, 2013

For the Meeting of the Board of Trustees ‐ August 8, 2013

for

Houston Community College System&

Houston Community College Public Facility Corporation

Page 2: Fs2013 july

Memorandum Management Discussion & Analysis

Summary HCCS Unrestricted Revenue & Expenditures 1

Exemptions & Waivers Detail 4

Fund Balances Balance Sheet By Fund   5

Adjusted Budgets by Division 6

Actual YTD by College  6

Cash Flow Analysis 7

Contact Hours Reimbursement 12

Enrollment Data 13

Charts Revenue & Expenditure YTD thru July 31, 2013 14

Revenue and Expenditures with Trendlines 15

Revenue Source Comparison By Year 16

Expenditure Source Comparison By Year 17

Designated Funds Budget Summary / Cash Position 18

Capital Projects & Unexpended Plant Fund Projects 19

    Unexpended 2004 CIP Projects 20

2013 CIP Projects 26

CIP Footnotes 31

CIP Residual Funds 32

    Plant Fund Maintenance Tax Notes 2006 (Central Utility Plant Project) 33

Maintenance Tax Notes/Sr. Lien Bonds 2008 34

Maintenance Tax Notes 2010  36

Maintenance Tax Notes 2011 37

Bonds/Notes Schedule of Bonds & Maintenance Tax Notes 39

Auxiliary Sources and Uses of Auxiliary Funds 41

Restricted Funds Grants, Contracts and Student Aid 43

Position Control 2013 Positions 50

Pos. Control Charts FTE (Full‐Time Equivalent) Monthly Comparison 57

Duplicated Headcount Monthly Comparison 66

Unduplicated Headcount Monthly Comparison 67

Table of ContentsFor the Period September 1, 2012 ‐ July 31, 2013

For the Meeting of the Board of Trustees

Houston Community College System

Page 3: Fs2013 july

Statement of Net Assets PFC 1

Statement of Cash Flows  (Cash Basis‐ Interim Period) PFC 2

Public Safety Institute PFC 3

Westgate PFC 4

Hayes Road ‐ Alief Project PFC 5

Northline Mall Project PFC 6

Houston Community College ‐ Public Facility Corporation

Table of Contents For the Period September 1, 2012 ‐ July 31, 2013

For the Meeting of the Board of Trustees

Page 4: Fs2013 july

MEMORANDUM   

 

To:    Houston Community College System          Board of Trustees 

 

    From:    Renee Byas, Acting Chancellor  

Date:    August 7, 2013  

Re:  Financial Report for Month Ended July 31, 2013     

 

Enclosed please find the preliminary financial reports for the month ending July 31, 2013 for your review.  The financial report is an internal management report submitted to the Board of Trustees to compare actual financial activities to the approved budgets, strategic priorities, and financial policies for the reported fiscal year.   

 

Operating Fund net revenue through July 31, 2013 is $281,855,493 which is 1.1% below last year.  Expenditures year‐to‐date total $243,561,714 which is 0.2% less than the same time last year, for a net of $38,293,779. 

 

The reserves for the month of July 2013 are $60,228,918 or 20.7% of revenues (see page III).  Thus, we continue to project a healthy fiscal strength for the college. 

Page 5: Fs2013 july

Managements Discussion and Analysis

Thru July 31, 2013

Revenues

Expenditures 

Total revenues and expenditures by expense type for the Operating Fund for 2012‐2013 are reported on page one, 

behind the tab Detailed Financial Statements. Highlights of financial activities year‐to‐date are as follows:

State Appropriations received year to date totaled $63,495,699, 0.4% below last year. Total appropriations 

received are expected to be $70,014,007.  This amount was reduced by $218,031 due to a formula reallocation 

to align with the Legislative Budget Board data and methodology.

Ad Valorem Tax collections totaled $104,405,862 year‐to‐date.  The year‐to‐date total is 0.1% above last year.  

The proportion of tax revenue applied to operations decreased this year due to the increase in tax revenue 

applied to debt service.  However, this decrease in tax revenue to operations is offset by the increase in tax 

revenue due to increases in property valuations. We project total tax revenue for the fiscal year will be 

$105,811,761.

Tuition and Fees net revenue year to date totaled $105,229,822 which is 3.3% lower than the same time last 

year.  Enrollment numbers for Fall 2012 declined 6.5% compared to last year, namely due to a 10% decline in 

international students compared to last year, Spring enrollment remained flat at 0.3% above the previous year 

and Summer enrollment shows a 6.6% decrease compared to the previous year.  We are projecting tuition and 

fees revenue to be $105,370,959.  

Insurance/Risk Management payments totaled $6,519,897 year‐to‐date, 7.1% above last year.  The increase is 

due to an increase in insurance premiums.  Total expenses for the year are expected to be within budget at 

$6,871,709.

Tuition & Fee‐Extended Learning receipts totaled $6,241,171 year to date, 0.74% above last year.  Total tuition 

and fees‐Extended Learning at fiscal year end are expected to be $6,287,729.

Rental and Leases expenses totaled $2,159,748 year‐to‐date, which is 48.8% below the previous year.  The 

decrease is due to the completion of IT projects. Total expenses at  year end are projected to be $2,831,514.

Total revenue collections, net of exemptions and waivers, totaled $281,855,493 year‐to‐date.  This is a 1.1% decrease below last year. 

Total Salaries are $148,766,993 year‐to‐date, 2.6% above the previous year, namely due to the 2% salary 

increases.  Total salaries at year end are expected to be $163,283,858.

Benefits costs totaled $14,751,325 year‐to‐date, 20% above last year.  This increase is due namely to  the 

reduction in the state's contribution to TRS and ORP and an increase in health insurance premiums. Total 

benefits at fiscal year end are expected to be $18,152,880.

Contract Services expense totaled $18,327,458 year‐to‐date, 10% above last year.  The increase is mainly due to 

IT hiring temporary personnel for projects, additional security staff at the District and using contract interpreters 

to fill the personnel shortages.  Fiscal year end expenses are projected to be $24,368,462.

Utilities costs totaled $7,063,294 year‐to‐date.   We will continue to monitor these costs.  Total utilities cost at 

fiscal year end is projected to $8,490,022.

i

Page 6: Fs2013 july

Managements Discussion and Analysis

Thru July 31, 2013

Budget Priorities funding allocated for the year are detailed below through July 31, 2013. 

Contingency/Budget Priority Funding

Expense:

Position Management

Capital Outlay & Equipment

Other

Total Contingency/Budget Priorities

Grants

Unexpended Plant Fund  

1,147,346$       

10,225,030     

11,372,376$    

6,095,773        

305,625           

3,823,632        

The 2013 CIP budgets are $425,137,284 and are 2.6% committed to‐date. Please see page 26 for the summary 

and pages 27 through 30 for details.

Budget expenditures for grant‐funded projects so far this year total $14,721,637.

ii

Capital Outlay expenses totaled $3,080,913 year‐to‐date.  Expenditures are projected to $6,479,509.

Transfers/Debt activities totaled $28,330,519 year‐to‐date, a 28.2% decrease compared to last year. The 

decrease is due to a transfer in FY2012 to purchase the Westheimer/Eldridge land.  Items in this expense 

category include all student revenue bond payments, transfers for scholarship matching funds, and transfers to 

the Unexpended Plant Fund.  Total expenses are expected to be $35,304,211.

Total operating fund expenditures year‐to‐date total $243,561,714, a 0.2% decrease below last year.  

Instructional and Other Materials expenses totaled $5,448,881 year‐to‐date, which is 29% above last year.  

COMPASS Internet Units, TCCTA Adobe Master Collection and additional support for Moodlerooms, Inc 

contributed to the increase.  Expenses in this area are projected to be $9,485,879.

The college has received $1,243,264 in new grant awards since the beginning of the current fiscal year. 

Total grant awards (federal, state & private) year‐to‐date total, $46,486,081.

Cash Position ‐ The use of the Unexpended Plant Fund Excluding 2004 CIP for deferred maintenance projects was 

discontinued in FY 2009.  All deferred maintenance expense is captured in the operating account.  See page 18 

for prior year encumbrances. 

Unexpended Plant Fund Projects include current construction, deferred maintenance, and property acquisition 

projects for a budget of $47,180,067.  Funds for these projects are 100% committed.  See page 19 for more 

details.

The 2004 CIP budgets are $263,779,995 and are 100% committed. The spending categories in the schedule have 

now been revised for more ease of reference to the Board approved budget.  Please see page 20 for the 

summary and pages 21 through 25 for details.

The Maintenance Tax Note 2006 tracks the financial progress of the Central Utility Plant.  Commitments year‐to‐

date total $12.5 million, 99.87% of budget.  See page 33 for the details. 

Page 7: Fs2013 july

Managements Discussion and Analysis

Thru July 31, 2013

Public Facility Corporation

Balance Sheet – Operating Fund   

Cash and Investments

Cash

Investments

    Total

Fund Balance

Audited Fund Balance, August 31, 2012

Projected Revenue @ 08/31/2013

Total Projected Revenue

Projected Expenses @ 08/31/2013

FY 2012 Purchase Order Roll 

Total Projected Expenses @ 08/31/2013

Ending Fund Balance (Beg. Fund Balance + Revenue ‐ Expenses)

Required Reserve for FY 2013 (11% Projected Revenues)

Added Reserves

Additional Expenditures Funded From Reserves:

Reimbursement to State for Insurance

Lump Sum Bonus

Total Expenses Paid From Reserves

Added Reserves

Required Reserve for FY 2013 (11% Projected Revenues)

Current Reserves

% of Total Operating Revenue

The Public Facility Corporation tracks the progress of the PFC ‐ Public Safety Institute, Katy Campus (Westgate), 

Alief and Northline Mall deferred maintenance, new construction and renovation projects.  Expenditures year‐to‐

date total $100.8 million, 98.7% of budget. See pages PFC 1‐6 for details. 

July 2013 July 2012

95,843,934$           78,064,707$          

357,182,263$            

286,369,094$            

2,395,994                   

18,781,770              7,984,305               

114,625,704$         86,049,012$          

66,664,585$              

The projected reserves at July 31, 2013 of $60,228,918 is an estimate at this time and represents 20.7% of expected 

general fund revenue for this fiscal year, which is within our financial stability policy requiring us to maintain a fund 

balance of 9% ‐11% of general fund revenues as of August 31.  

iii

31,956,945$              

60,228,918$              

20.7%

288,765,088$            

68,417,175$              

31,956,945$              

36,460,230$              

290,517,678              

(9,900,000)$       1,711,743$        (8,188,257)                 

28,271,973$              

Expense to Date  Balance Budget

(8,100,000)         ‐                           (8,100,000)                 

(1,800,000)         1,711,743           (88,257)                       

Page 8: Fs2013 july

YTD Adjusted Budget

YTD Actuals Thru 

July 31, 2013

YTD Actuals Thru 

July 31, 2012

2012‐2013 Inc/(Dec) 

vs. 2011‐2012

Actuals % 

Inc/(Dec)YTD vs. 

PriorYTD

Projected Actuals 

2012‐2013

Projected 2012‐2013 

Inc/(Dec) vs. Adj 

Budget

Projected 2012‐

2013 Inc/(Dec) vs. 

Adj Budget %

REVENUES

State Appropriations 70,232,038$           63,495,699$      63,779,106$      (283,407)$          ‐0.44% 70,014,007$      (218,031)$           ‐0.31%Ad Valorem Taxes 102,195,871           104,405,862     104,341,537     64,325               0.06% 105,811,761     3,615,890           3.54%Tuition, Net 43,067,676             40,158,942        41,978,987       (1,820,045)        ‐4.34% 40,216,106       (2,851,570)         ‐6.62%Fees 71,520,739             65,070,880        66,790,991       (1,720,111)        ‐2.58% 65,154,853       (6,365,886)         ‐8.90%Other Local Income* 2,517,960                2,020,706          1,399,374         621,332            44.40% 2,517,960         ‐                       0.00%Tuition & Fee, Net

 ‐‐ Extended Learning6,188,581                6,241,171            6,195,087           46,084                 0.74% 6,287,729           99,148                  1.60%

Grant Revenue 434,410                   462,232               462,356               (124)                     ‐0.03% 515,262               80,852                  18.61%

Total Revenues 296,157,275           281,855,493       284,947,439       (3,091,946)          ‐1.09% 290,517,678$     (5,639,597)$         ‐1.90%

EXPENSES

Faculty‐FT  53,987,382             50,991,693        49,784,819       1,206,874         2.42% 53,987,382       ‐                       0.00%

Faculty‐PT 31,277,914             27,138,113        26,787,552       350,561            1.31% 31,212,804       (65,110)               ‐0.21%

Librarian/Counselor‐FT  4,830,690                4,393,852          5,417,691         (1,023,839)        ‐18.90% 4,731,891         (98,799)               ‐2.05%

Librarian/Counselor‐PT 858,739                  555,892             508,023             47,870               9.42% 852,907             (5,832)                 ‐0.68%

Staff‐FT 66,155,644             59,195,927        56,076,984       3,118,943         5.56% 64,928,910       (1,226,734)         ‐1.85%Staff‐PT 10,180,997             6,491,516          6,432,874         58,642               0.91% 7,569,964         (2,611,033)           ‐25.65%

     Sub‐total Salaries 167,291,366           148,766,993       145,007,943       3,759,051           2.59% 163,283,858       (4,007,508)           ‐2.40%

Employee Benefits 18,152,880             14,751,325        12,295,929       2,455,396         19.97% 18,152,880       ‐                       0.00%

Supplies Gen Exp 6,123,125                4,660,200          4,398,092         262,109            5.96% 5,416,838         (706,287)             ‐11.53%

Travel 1,064,640                777,330             696,397             80,932               11.62% 1,030,126         (34,514)               ‐3.24%

Marketing Costs 1,766,634                1,299,364          936,196             363,168            38.79% 1,466,130         (300,504)             ‐17.01%

Rental & Leases 2,831,514                2,159,748          4,214,401         (2,054,653)        ‐48.75% 2,831,514         ‐                       0.00%

Insurance/Risk Mgmt 6,872,206                6,519,897          6,088,158         431,739            7.09% 6,871,709         (497)                    ‐0.01%

Contract Services 24,368,462             18,327,458        16,631,834       1,695,623         10.20% 24,368,462       ‐                       0.00%

Utilities 12,899,947             7,063,294          6,556,434         506,860            7.73% 8,490,022         (4,409,925)         ‐34.19%

Other Departmental Expenses 2,082,970                1,697,014          1,243,446         453,568            36.48% 1,863,291         (219,679)             ‐10.55%

Instructional & Other Materials 9,485,879                5,448,881          4,225,807         1,223,075         28.94% 9,485,879         ‐                       0.00%

Maintenance & Repair 1,537,173                678,779             671,517             7,262                 1.08% 1,324,665         (212,508)             ‐13.82%

Transfers/Debt 35,304,211             28,330,519        39,467,200       (11,136,682)     ‐28.22% 35,304,211       ‐                       0.00%

Contingency (4,802,111)              ‐                          ‐                          ‐                           0.00% ‐                          4,802,111           ‐100.00%Capital Outlay 11,178,379             3,080,913          1,567,921         1,512,992         96.50% 6,479,509         (4,698,870)           ‐42.04%

     Total Expenses  296,157,275           243,561,714     244,001,274     (439,560)           ‐0.18% 286,369,094     (9,788,181)         ‐3.31%

REVENUES H/(L) Vs EXPENSES 0                              38,293,779        40,946,165       (2,652,386)        4,148,584         4,148,584          

* Includes interest & dividends income, fines & penalties and parking fines

1

HOUSTON COMMUNITY COLLEGE2012‐2013 Revenues & Expenditures  HCCS CURRENT UNRESTRICTED

Page 9: Fs2013 july

State 

Appropriations Ad Valorem Taxes Tuition, Net Fees

Other Local 

Income

Extended 

Learning Grant Revenue

Total Projected 

Revenue

70,014,007                105,811,761            40,216,106                 65,154,853             2,517,960               6,287,729             515,262               290,517,678        

24.1% 36.4% 13.8% 22.4% 0.9% 2.2% 0.2%

Salaries Employee Benefits

General & Admin. 

Expenses Transfers/Debt

Total Projected 

Expenses

163,283,858            18,152,880                 69,628,145             35,304,211             286,369,094        

57% 6% 24% 12%

HOUSTON COMMUNITY COLLEGEProjected Revenues & Expenditures as of July 31, 2013

2

24%

36%

14%

23%

1% 2% 0%

Revenue State Appropriations

Ad Valorem Taxes

Tuition, Net

Fees

Other Local Income

Tuition & Fee, Net ‐‐ Extended LearningGrant Revenue

57%

7%

24%

12%

Expenses

Salaries

Employee Benefits

General & Admin.Expenses

Transfers/Debt

Page 10: Fs2013 july

Approved Budget Adjusted Budget

YTD Actuals Thru 

July 31, 2013

Encumbrances Thru 

July 31, 2013

Total Actuals & 

Encumbrances Thru 

July 31, 2013

Balance as of July 

31, 2013

YTD Actuals Thru 

July 31, 2012

Encumbrances Thru 

July 31, 2012

Total Actuals & 

Encumbrances Thru 

July 31, 2012

2012‐2013 Inc/(Dec) 

vs. 2011‐2012

Actuals & 

Encumbrances % 

Inc/(Dec)YTD vs. 

PriorYTD

EXPENSES

Faculty‐FT  53,987,382              53,987,382          50,991,693        1,193,923            52,185,616        1,801,766           49,784,819        2,114,695          51,899,514        286,102             0.55%

Faculty‐PT 31,277,914              31,212,804          27,138,113        1,062,574            28,200,687        3,012,117           26,787,552        1,282,612          28,070,164        130,523             0.46%

Librarian/Counselor‐FT  4,830,690                4,731,891            4,393,852          218,649                4,612,500          119,391               5,417,691          317,483             5,735,174          (1,122,673)        ‐19.58%

Librarian/Counselor‐PT 858,739                   852,907               555,892              108,285                664,178              188,729               508,023             111,516             619,539             44,639               7.21%

Staff‐FT 66,155,644              64,928,910          59,195,927        3,885,411            63,081,338        1,847,572           56,076,984        4,917,579          60,994,563        2,086,775         3.42%

Staff‐PT 10,180,997              7,569,964            6,491,516          1,527,556            8,019,072          (449,108)             6,432,874          1,243,784          7,676,658          342,414             4.46%

     Sub‐total Salaries 167,291,366           163,283,858       148,766,993        7,996,398              156,763,392        6,520,466            145,007,943       9,987,670            154,995,612       1,767,779           1.14%

Employee Benefits 18,152,880              18,152,880          14,751,325        1,872                    14,753,197        3,399,683           12,295,929        6,173                  12,302,101        2,451,096         19.92%

Supplies Gen Exp 6,123,125                5,416,838            4,660,200          756,638                5,416,838          (0)                          4,398,092          571,212             4,969,304          447,534             9.01%

Travel 1,064,640                1,030,126            777,330              400                        777,730              252,396               696,397             2,342                  698,740             78,990               11.30%

Marketing Costs 1,766,634                1,466,130            1,299,364          143,365                1,442,729          23,401                 936,196             169,801             1,105,997          336,732             30.45%

Rental & Leases 2,831,514                2,831,514            2,159,748          107,565                2,267,313          564,201               4,214,401          210,309             4,424,710          (2,157,397)        ‐48.76%

Insurance/Risk Mgmt 6,872,206                6,871,709            6,519,897          ‐                             6,519,897          351,812               6,088,158          ‐                           6,088,158          431,739             7.09%

Contract Services 24,368,462              24,368,462          18,327,458        4,035,250            22,362,707        2,005,755           16,631,834        2,422,584          19,054,418        3,308,289         17.36%

Utilities 12,899,947              8,490,022            7,063,294          41,847                  7,105,141          1,384,881           6,556,434          48,000                6,604,434          500,708             7.58%

Other Departmental Expenses 2,082,970                1,863,291            1,697,014          166,277                1,863,291          0                           1,243,446          61,756                1,305,202          558,089             42.76%

Instructional & Other Materials 9,485,879                9,485,879            5,448,881          2,508,788            7,957,670          1,528,209           4,225,807          389,067             4,614,874          3,342,796         72.44%

Maintenance & Repair 1,537,173                1,324,665            678,779              645,887                1,324,665          (0)                          671,517             623,457             1,294,974          29,691               2.29%

Transfers/Debt 35,304,211              35,304,211          28,330,519        ‐                             28,330,519        6,973,692           39,467,200        ‐                           39,467,200        (11,136,682)      ‐28.22%

Contingency (4,802,111)               ‐                            ‐                           ‐                           ‐                            ‐                           ‐                           ‐                          0.00%

Capital Outlay 11,178,379              6,479,509            3,080,913          3,398,596            6,479,509          0                           1,567,921          1,300,098          2,868,019          3,611,489         125.92%

     Total Expenses  296,157,275           286,369,094       243,561,714      19,802,884          263,364,598      23,004,496         244,001,274     15,792,470        259,793,744     3,570,854         1.37%

3

HOUSTON COMMUNITY COLLEGE2012‐2013 Revenues and Expenditures & Encumbrances  HCCS CURRENT UNRESTRICTED

Page 11: Fs2013 july

FY 2011‐12 FY 2012‐13

Tuition

Budget:Adjusted Budget FY 2012‐13 43,067,676$           

Exemptions & Waivers (6,798,328)              

Adjusted Budget FY 2012‐13, Net 36,269,348$           

Revenues Received:Tuition 48,824,432              48,860,870              46,957,270             

Waivers & Exemptions:Dual Credit (5,170,736)               (5,193,934)               (4,819,811)              

Other (1,693,502)               (1,687,950)               (1,978,517)              

Total Waivers & Exemptions (6,864,238)               (6,881,884)               (6,798,328)              

Total Tuition Revenue, Net 41,960,194$          41,978,986$          40,158,942$           

Tuition ‐ Extended Learning

Budget:Budget FY 2012‐13 6,188,581$             

Exemptions & Waivers (2,150,277)              

Budget FY 2012‐13, Net 4,038,304$             

Revenues Received:

Tuition 8,853,381                8,520,067                8,391,448                

Waivers & Exemptions:

Corrections (2,612,080)             (2,324,980)             (2,150,277)             

Total EL Tuition Revenue, Net 6,241,301$             6,195,087$             6,241,171$             

Exemptions & Waivers

Dept of Corrections 2,612,080$              2,324,980$              2,150,277$             

Dual Credit Waiver 5,170,736                5,193,934                4,819,811                

Other:

Employee Fee Exemptions 84,810                      84,690                      69,971                     

Firemen 42,521                      42,521                      25,475                     

Hazelwood 906,036                   904,271                   1,262,519                

Deaf & Blind 309,603                   309,615                   257,751                   

High Ranking Hi SCH Grad 868                           868                           2,418                        

Child of Disabled Vet ETC 431                           431                           1,686                        

Nonres Military Per & Dep 2,390                        2,390                        ‐                            

Emp of State Coll & Univ ‐                            ‐                            319                           

Nonres Teach/Research Asst 13,905                      13,905                      10,443                     

Nonres Competitive Scholar ‐                            ‐                            2,301                        

Senior Citizens 18,730                      18,447                      15,702                     

Scholarship Distribution 1,450                        1,450                        ‐                            

Apprenticeship Waivers (28)                            (28)                            (38)                            

Special Fees Waiver HFD 117                           117                           ‐                            

A VISA Waiver (Non‐Alien Waiver) 1,110                        1,110                  ‐                            

Refugee Waiver (1,554)                       (1,110)                       (162)                          

Foster Children‐Resident 294,543                   290,703                   305,407                   

Fire Academy Waiver 157                           157                           ‐                            

Undocumented Students 2,171                        2,171                        ‐                            

TX Tomorrow Waiver 2,874                        2,874                        ‐                            

Peace Officer Exemption 13,368                      13,368                      14,275                     

Stipends ‐                            ‐                            10,450                     

Total Other Exemptions 1,693,502                1,687,950                1,978,517                

Grand Total Exemptions & Waivers 9,476,318$             9,206,864$             8,948,605$             

Note:   As of December 31, 2008, the financial statements reflect all expenses incurred for Exemptions and Waivers as net of tuition and fee revenue.  Prior to this date Exemptions & Waivers were shown as an expenditure and revenue was shown as gross revenue.

4

Exemptions & Waivers

Thur July 31, 2013

Account

 End of Year 

Activity 

Year‐to‐Date 

Activity thru 

7/31/2012

 Year‐to‐Date 

Activity thru 

7/31/2013 

Page 12: Fs2013 july

     Unrestricted  Auxiliary  Restricted  Total 

Unexpended 

Plant Renewal 

 Retirement of 

Debt 

Investment in 

Plant  Total 

Consolidation & 

Elimination  Total All Funds 

ASSETSCurrent Assets:

Cash &  cash equivalents 95,843,934$        8,873,274$        ‐$                         104,717,208$     3,727,350$         16,001,802         ‐$                          19,729,152$            ‐$                              124,446,360$         

Restricted cash & cash equivalents ‐                             ‐                           12,830,909       12,830,909        470,230,704      27,240,704         ‐                           497,471,408           ‐                                510,302,317          

Short term Investments ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Accounts/Other receivable (net) 23,194,293          1,190,438           2,478,998          26,863,729        ‐                           585,577               ‐                           585,577                   ‐                                27,449,306            

Deferred charges 1,180,131             393,022              10,896               1,584,049           ‐                           ‐                           ‐                           ‐                                ‐                                1,584,049               

Prepaids 24,765                  5,058                  ‐                          29,823                881,382              ‐                           ‐                           881,382                   ‐                                911,205                  

Total Current Assets 120,243,123        10,461,792        15,320,803       146,025,718      474,839,436      43,828,083         ‐                           518,667,519           ‐                                664,693,237          

Non‐current Assets:

Deferred charges, net ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Restricted long‐term investments ‐                             ‐                           ‐                          ‐                           32,004,457        2,456,907            ‐                           34,461,364             ‐                                34,461,364            

Long‐term investments 18,781,770          ‐                           ‐                          18,781,770        ‐                           ‐                           ‐                           ‐                                ‐                                18,781,770            

Capital Assets, net ‐                             ‐                           ‐                          ‐                           102,951,981      ‐                           666,951,500      769,903,481           ‐                                769,903,481          

Total Non‐current Assets 18,781,770          ‐                           ‐                          18,781,770        134,956,438      2,456,907            666,951,500      804,364,845           ‐                                823,146,615          

Total Assets 139,024,893$      10,461,792$      15,320,803$      164,807,488$     609,795,874$     46,284,990$       666,951,500$     1,323,032,364$       ‐$                              1,487,839,852$      

LIABILITIESCurrent Liabilities:

Accounts payable 7,865,774             233,291              1,099,291          9,198,356           336,442              ‐                           ‐                           336,442                   ‐                                9,534,798               

Accrued liabilities 174,310                ‐                            24,809                 199,119                2,719                    ‐                            ‐                             2,719                         ‐                                  201,838                    

Compensated absences 2,351,464             ‐                           ‐                          2,351,464           ‐                           ‐                           ‐                           ‐                                ‐                                2,351,464               

Funds held for others ‐                             107,889              520,271             628,160              189,209              ‐                           ‐                           189,209                   ‐                                817,369                  

Deferred revenue 20,571,984          609,907              745,439             21,927,330        1,599,275           ‐                           (1,600,060)         (785)                         ‐                                21,926,545            

Notes payable‐current portion ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Bonds payable‐current portion ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Capital lease obligations‐current ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Total Current Liabilities 30,963,532          951,087$            2,389,810          34,304,429        2,127,645           ‐                           (1,600,060)         527,585                   ‐                                34,832,014            

Non‐current Liabilities:

Deposits ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Notes payable ‐                             ‐                           ‐                          ‐                           139,850,892      ‐                           37,761,145        177,612,037           ‐                                177,612,037          

Bonds payable ‐                             ‐                           ‐                          ‐                           465,221,463      27,838,473         294,379,496      787,439,431           ‐                                787,439,431          

Capital lease obligations ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           104,429,832      104,429,832           ‐                                104,429,832          

Total Non‐current Liabilities ‐                             ‐                           ‐                          ‐                           605,072,355      27,838,473         436,570,472      1,069,481,300        ‐                                1,069,481,300       

Total Liabilities 30,963,532$        951,087$            2,389,810$        34,304,429$       607,200,000$     27,838,473$       434,970,412$     1,070,008,885$       ‐$                              1,104,313,311$      

 Fund Balance‐ 

August 31, 2012 Audited  66,664,585          11,747,296         9,080,325            87,492,206          3,738,684             10,061,216         235,429,798        249,229,698             ‐                                  336,721,904            

Revenues Over Expenditures

     Unrestricted 41,396,777          (2,236,591)         39,160,186        39,160,186            

     Restricted 3,850,668          3,850,668           3,850,668               

     Net Investment in Plant     (1,142,808)         8,385,302            (3,448,710)         3,793,784                3,793,784               

Total Fund Balances 108,061,362$      9,510,705$        12,930,993$      130,503,060$     2,595,876$         18,446,518$       231,981,088$     253,023,482$          ‐$                              383,526,542$         

 Total Liabilities &  Fund Balances  139,024,894$      10,461,792$      15,320,803$      164,807,489$     609,795,874$     46,284,991$       666,951,500$     1,323,032,367$       ‐$                              1,487,839,852$      

      5 

PLANT & BOND FUNDS

Houston Community CollegeBalance Sheet By Fund

For Month Ended July 31, 2013

CURRENT & LOAN FUNDS

Page 13: Fs2013 july

 CENTRAL 

 NORTH

WEST 

 NORTH

EAST 

 SOUTH

WEST   SOUTH EAST   COLEMAN 

 EXTENDED 

LEARNING 

 CHAN‐

CELLOR 

DEPUTY CHAN‐

CELLOR 

INSTITU‐

TIONAL 

EFFECTIVE‐

NESS* 

 INSTRUC‐

TION 

 INFO

TECH 

 STUDENT 

SUCCESS   SYSTEM   HCCS 

 % of 

Adjusted 

Budget 

EXPENSES

Faculty‐FT  10,363,292      10,323,252      7,506,187         12,224,453     4,948,893       5,961,943       2,358,182       ‐                  3,000               ‐                   298,180          ‐                  ‐                  ‐                  53,987,382      18.23%

Faculty‐PT 4,799,369         6,308,299         4,115,361         5,771,364        3,851,946       2,033,783       3,662,833       ‐                  450                   ‐                   734,509          ‐                  ‐                  ‐                  31,277,914      10.56%

Librarian/Counselor‐FT  936,418            1,133,600         942,795            768,653           529,552          85,066            2,887              ‐                  ‐                    ‐                   344,733          ‐                  86,986            ‐                  4,830,690        1.63%

Librarian/Counselor‐PT 95,927              194,185            119,380            214,206           83,152            34,980            ‐                  ‐                  ‐                    ‐                   24,373            ‐                  92,536            ‐                  858,739           0.29%

Staff‐FT 5,724,016         4,684,151         4,879,110         5,759,968        3,908,827       2,426,599       3,799,680       4,587,175       14,811,129    ‐                   4,459,620       6,751,801       4,363,568       ‐                  66,155,644      22.34%

Staff‐PT 1,942,575         1,669,471         788,382            1,595,118        1,197,805       389,771          795,822          282,854          547,935           ‐                   346,124          207,010          418,130          ‐                  10,180,997      3.44%

     Sub‐total Salaries 23,861,597      24,312,958      18,351,215      26,333,762     14,520,175    10,932,142    10,619,404    4,870,029       15,362,514    ‐                   6,207,539       6,958,811       4,961,220       ‐                  167,291,366    56.49%

Employee Benefits ‐                     ‐                     ‐                     4                       ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  18,152,876    18,152,880      6.13%

Supplies Gen Exp 361,979            407,181            226,699            328,232           288,341          347,473          253,016          380,601          1,196,911        ‐                   233,604          347,149          (28,606)           1,780,545       6,123,125        2.07%

Travel 92,592              116,844            30,428              51,327             29,915            123,558          93,526            159,329          142,493           ‐                   115,467          71,905            37,256            ‐                  1,064,640        0.36%

Marketing Costs 43,979              47,528              56,696              39,443             79,482            32,472            405,734          171,085          888,215           ‐                   ‐                  2,000              ‐                  ‐                  1,766,634        0.60%

Rental & Leases 31,920              127,089            1,310,622         540,876           41,484            483,719          28,952            59,022            177,846           ‐                   3,738              23,760            2,486              ‐                  2,831,514        0.96%

Insurance/Risk Mgmt 794                    245                    ‐                     98                     ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  676                 ‐                  6,870,393       6,872,206        2.32%

Contract Services 269,304            282,236            40,260              26,707             177,893          343,590          363,063          535,819          13,004,067    ‐                   153,483          2,931,844       56,383            6,183,813       24,368,462      8.23%

Utilities 3,331                ‐                     4,600                ‐                   ‐                  ‐                  ‐                  ‐                  1,587,809        ‐                   ‐                  1,400,000       ‐                  9,904,207       12,899,947      4.36%

Other Departmental Expenses 40,065              46,820              42,491              28,721             41,488            130,696          52,742            388,668          187,247           ‐                   206,286          230,771          275,759          411,216          2,082,970        0.70%

Instructional & Other Materials 492,070            343,476            168,636            285,643           95,494            357,808          997,675          113,714          23,649             ‐                   1,050,421       5,297,020       260,273          ‐                  9,485,879        3.20%

Maintenance & Repair 143,433            48,060              56,993              24,563             21,372            83,949            159,700          1,265              973,011           ‐                   6,460              13,234            2,614              2,519              1,537,173        0.52%

Transfers/Debt ‐                     845,619            5,636,142         1,155,001        ‐                  ‐                  ‐                  ‐                  3,264               ‐                   ‐                  ‐                  494,389          27,169,796    35,304,211      11.92%

Contingency 50                       3,854                12,500              ‐                   11,632            5,860              ‐                  35,000            20,446             ‐                   ‐                  ‐                  6,202              (4,897,655)     (4,802,111)       ‐1.62%

Capital Outlay 579,366            325,007            297,973            118,059           275,868          592,573          44,634            62,350            3,236,614        ‐                   12,945            1,462,738       56,016            4,114,236       11,178,379      3.77%

Total Budget 25,920,480      26,906,917      26,235,255      28,932,436     15,583,144    13,433,840    13,018,446    6,776,882       36,804,086    ‐                   7,989,943       18,739,908    6,123,992       69,691,946    296,157,275    100.00%

  6 

 CENTRAL 

 NORTH

WEST 

 NORTH

EAST 

 SOUTH

WEST   SOUTH EAST   COLEMAN 

 EXTENDED 

LEARNING 

 CHAN‐

CELLOR 

DEPUTY CHAN‐

CELLOR 

INSTITU‐

TIONAL 

EFFECTIVE‐

NESS* 

 INSTRUC‐

TION 

 INFO

TECH 

 STUDENT 

SUCCESS   SYSTEM   HCCS 

 % of 

Actuals 

EXPENSES

Faculty‐FT  9,884,791         9,805,240         6,962,205         11,635,232     4,712,386       5,573,648       2,266,522       ‐                  2,925               ‐                   148,745          ‐                  ‐                  ‐                  50,991,693      20.94%

Faculty‐PT 4,240,049         5,598,686         3,536,382         5,141,864        3,598,783       1,645,692       3,005,478       ‐                  450                   ‐                   370,730          ‐                  ‐                  ‐                  27,138,113      11.14%

Librarian/Counselor‐FT  867,672            978,073            854,409            707,054           499,402          76,168            2,886              ‐                  ‐                    ‐                   333,874          ‐                  74,312            ‐                  4,393,852        1.80%

Librarian/Counselor‐PT 57,569              141,587            113,094            153,545           36,363            20,101            ‐                  ‐                  ‐                    ‐                   3,279              ‐                  30,354            ‐                  555,892           0.23%

Staff‐FT 5,150,398         4,159,543         4,257,319         5,190,498        3,527,340       2,202,609       3,449,942       3,970,750       13,357,550    ‐                   4,030,539       5,954,840       3,944,599       ‐                  59,195,927      24.30%

Staff‐PT 1,117,465         1,152,832         628,299            1,062,641        818,808          241,605          586,057          124,686          284,822           ‐                   173,918          115,978          184,404          ‐                  6,491,516        2.67%

     Sub‐total Salaries 21,317,944      21,835,961      16,351,709      23,890,835     13,193,082    9,759,822       9,310,884       4,095,436       13,645,747    ‐                   5,061,085       6,070,819       4,233,669       ‐                  148,766,993    61.08%

Employee Benefits ‐                     ‐                     ‐                     3                       ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  14,751,322    14,751,325      6.06%

Supplies Gen Exp 230,917            300,435            196,355            244,506           197,496          210,877          198,730          279,535          840,641           ‐                   200,548          159,877          122,594          1,477,690       4,660,200        1.91%

Travel 53,782              100,915            23,239              41,300             22,898            87,277            61,768            141,668          82,205             ‐                   92,759            42,173            27,344            ‐                  777,330           0.32%

Marketing Costs 26,753              41,966              49,689              35,483             43,339            28,485            169,345          135,006          769,298           ‐                   ‐                  ‐                  ‐                  ‐                  1,299,364        0.53%

Rental & Leases 31,898              64,052              904,100            503,073           32,380            386,624          12,995            38,145            164,484           ‐                   2,234              17,347            2,415              ‐                  2,159,748        0.89%

Insurance/Risk Mgmt 509                    245                    ‐                     ‐                   ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  6,519,144       6,519,897        2.68%

Contract Services 177,084            154,412            37,433              25,565             106,452          294,402          93,797            176,439          10,475,646    ‐                   110,659          1,619,200       49,548            5,006,820       18,327,458      7.52%

Utilities 3,330                ‐                     3,200                ‐                   ‐                  ‐                  ‐                  ‐                  592,412           ‐                   ‐                  1,125,248       ‐                  5,339,103       7,063,294        2.90%

Other Departmental Expenses 33,207              37,807              34,130              21,090             28,652            104,265          40,914            343,316          156,621           ‐                   169,684          144,099          181,745          401,481          1,697,014        0.70%

Instructional & Other Materials 393,581            291,556            125,458            266,966           64,351            202,839          569,729          ‐                  11,827             ‐                   628,129          2,658,052       236,395          ‐                  5,448,881        2.24%

Maintenance & Repair 49,193              18,437              33,508              17,563             7,408              37,079            109,937          724                 387,879           ‐                   6,459              8,394              2,198              ‐                  678,779           0.28%

Transfers/Debt ‐                     845,382            5,634,237         1,155,000        ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  494,389          20,201,510    28,330,519      11.63%

Contingency ‐                     ‐                     ‐                     ‐                   ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  ‐                  ‐                    0.00%

Capital Outlay 532,830            186,371            156,252            100,496           100,867          84,895            31,348            30,053            1,284,412        ‐                   6,160              566,844          386                 ‐                  3,080,913        1.26%

Total Expense 22,851,029      23,877,540      23,549,312      26,301,882     13,796,924    11,196,564    10,599,447    5,240,322       28,411,172    ‐                   6,277,718       12,412,053    5,350,683       53,697,069    243,561,714    100.00%% of Adjusted 

Budget by Division 88.16% 88.74% 89.76% 90.91% 88.54% 83.35% 81.42% 77.33% 77.20% 0.00% 78.57% 66.23% 87.37% 77.05% 82.24% 100.00%

Remaining Balance 3,069,451         3,029,377         2,685,943         2,630,554        1,786,220       2,237,276       2,418,999       1,536,560       8,392,914        ‐                   1,712,225       6,327,855       773,309          15,994,877    52,595,561     

*As of June 2013 Institutional Effectiveness is combine with Instruction

HOUSTON COMMUNITY COLLEGE2012‐2013 Expenditures

YTD Adjusted Budget by Division

YTD Actuals by Division

Page 14: Fs2013 july

Sept. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May June July  Aug.

Central                                 FY2013 8.77% 17.29% 26.04% 33.04% 39.26% 47.17% 57.14% 65.82% 73.39% 80.26% 88.16%

                                              FY2012 8.89% 17.89% 27.03% 35.01% 41.49% 49.28% 58.01% 66.97% 74.34% 81.43% 88.98% 94.59%

Northwest                          FY2013 8.26% 17.69% 26.42% 33.44% 38.94% 47.07% 55.52% 66.24% 73.83% 80.69% 88.74%

                                              FY2012 8.55% 18.72% 27.39% 33.69% 38.31% 46.70% 55.31% 66.77% 74.43% 81.57% 89.43% 95.09%

Northeast                           FY2013 6.80% 19.95% 27.15% 32.73% 37.67% 43.91% 50.45% 72.27% 78.06% 83.73% 89.76%

                                              FY2012 6.70% 20.76% 27.75% 33.82% 40.16% 46.70% 53.35% 76.04% 82.19% 88.46% 94.27% 98.45%

Southwest                          FY2013 8.59% 19.46% 28.35% 35.52% 42.81% 50.66% 58.75% 69.07% 76.64% 83.33% 90.91%

                                              FY2012 8.58% 19.19% 28.11% 36.68% 43.63% 50.96% 58.38% 71.97% 79.03% 85.23% 92.21% 96.87%

Southeast                            FY2013 7.94% 16.74% 25.87% 33.20% 39.17% 47.32% 56.36% 65.24% 73.23% 80.28% 88.54%

                                              FY2012 8.68% 17.97% 27.56% 35.39% 41.33% 49.39% 57.90% 67.21% 74.92% 81.69% 89.81% 95.46%

Coleman                              FY2013 8.06% 17.28% 24.93% 31.55% 37.77% 46.07% 53.62% 60.80% 67.75% 75.25% 83.35%

                                              FY2012 8.26% 17.29% 25.18% 32.46% 39.63% 47.52% 55.02% 63.80% 71.21% 79.83% 87.22% 93.29%

Extended Learning            FY2013 7.79% 15.60% 23.76% 31.35% 35.83% 43.18% 50.20% 58.35% 65.86% 73.65% 81.42%

7                                               FY2012 7.97% 15.68% 23.55% 30.39% 37.09% 45.43% 53.07% 60.96% 69.35% 76.72% 84.68% 91.63%

Chancellor                           FY2013 7.14% 13.81% 24.51% 30.61% 37.97% 44.47% 51.04% 57.47% 63.05% 70.54% 77.33%

                                              FY2012 8.66% 16.11% 23.27% 30.27% 39.34% 45.84% 53.37% 61.08% 68.18% 74.82% 81.30% 89.24%

Deputy Chancellor             FY2013 4.52% 10.80% 17.79% 31.74% 38.89% 45.25% 43.00% 54.57% 62.02% 67.90% 77.20%

                                              FY2012 4.52% 10.28% 16.85% 22.58% 31.70% 38.52% 45.34% 51.71% 59.06% 69.23% 76.82% 80.46%

Institute Effectiveness*     FY2013 8.33% 16.67% 25.00% 33.33% 41.67% 50.00% 58.33% 66.67% 75.00% 0.00% 0.00%

                                              FY2012 5.76% 15.21% 22.37% 29.85% 38.13% 45.15% 52.82% 59.23% 67.73% 76.94% 85.77% 94.82%

Instruction                          FY2013 6.55% 15.59% 22.53% 28.70% 33.58% 42.38% 49.16% 55.69% 63.65% 71.13% 78.57%

                                              FY2012 6.73% 16.23% 22.67% 28.96% 35.81% 42.78% 52.10% 59.22% 65.59% 72.63% 82.25% 89.27%

Info Tech                              FY2013 5.56% 12.11% 16.63% 20.99% 29.10% 35.17% 39.77% 47.07% 54.83% 60.15% 66.23%

                                              FY2012 20.14% 33.96% 40.28% 45.47% 52.99% 59.23% 64.92% 71.03% 76.35% 82.70% 88.44% 99.49%

Student Success                 FY2013 7.33% 14.68% 23.02% 30.31% 40.96% 44.53% 49.81% 58.28% 65.57% 72.81% 87.37%

                                              FY2012 8.33% 15.89% 23.44% 30.58% 40.76% 48.76% 56.63% 65.19% 72.58% 80.37% 90.28% 98.41%

System                                 FY2013 12.41% 18.87% 22.34% 27.24% 33.14% 37.21% 42.87% 66.35% 70.66% 72.23% 77.05%

                                              FY2012 22.23% 25.94% 29.46% 32.09% 36.45% 39.69% 43.39% 63.98% 68.16% 71.84% 79.45% 88.27%

Total HCCS                           FY2013 8.55% 16.77% 23.49% 30.55% 36.88% 43.38% 49.23% 63.07% 69.69% 75.04% 82.24%

                                              FY2012 12.05% 20.09% 26.81% 32.55% 38.82% 45.08% 51.63% 65.11% 71.48% 77.90% 85.35% 91.73%

*As of June 2013 Institutional Effectiveness is combine with Instruction

Houston Community College

Cash Flow Analysis ‐ Monthly Percentage of Budget UsedFY2013 vs. FY2012

Page 15: Fs2013 july

Adjusted Budget 

FY2012

YTD Actuals Thru 

7/31/2012 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

7/31/2013 % of Budget Used

EXPENSES

Faculty‐FT  10,353,763          9,866,559        95.29% 10,363,292        9,884,791          95.38%

Faculty‐PT 4,897,846             4,321,147        88.23% 4,799,369           4,240,049          88.35%

Librarian/Counselor‐FT  1,079,656             979,062           90.68% 936,418              867,672             92.66%

Librarian/Counselor‐PT 88,599                  44,814              50.58% 95,927                57,569                60.01%

Staff‐FT 5,334,062             4,834,291        90.63% 5,724,016           5,150,398          89.98%

Staff‐PT 1,848,246             1,215,526        65.77% 1,942,575           1,117,465          57.52%

     Sub‐total Salaries 23,602,172          21,261,400      90.08% 23,861,597        21,317,944        89.34%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 282,165                198,112           70.21% 361,979              230,917             63.79%

Travel 103,094                68,928              66.86% 92,592                53,782                58.09%

Marketing Costs 59,243                  36,246              61.18% 43,979                26,753                60.83%

Rental & Leases 80,498                  71,500              88.82% 31,920                31,898                99.93%

Insurance/Risk Mgmt 794                        444                   55.97% 794                       509                    64.05%

Contract Services 268,280                214,381           79.91% 269,304              177,084             65.76%

Utilities ‐                         ‐                    ‐                 3,331                  3,330                 0.00%

Other Departmental Expenses 59,311                  21,825              36.80% 40,065                33,207                82.88%

Instructional & Other Materials 474,133                394,907           83.29% 492,070              393,581             79.98%

Maintenance & Repair 155,115                65,651              42.32% 143,433              49,193                34.30%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency ‐                         ‐                    0.00% 50                         ‐                     ‐                      

Capital Outlay 114,409                89,641              78.35% 579,366              532,830             91.97%

     Total Expenses  25,199,214          22,423,035      88.98% 25,920,480        22,851,029        88.16%

Adjusted Budget 

FY2012

YTD Actuals Thru 

7/31/2012 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

7/31/2013 % of Budget Used

EXPENSES

Faculty‐FT  9,652,013             9,133,477        94.63% 10,323,252        9,805,240          94.98%

Faculty‐PT 5,867,925             5,161,350        87.96% 6,308,299           5,598,686          88.75%

Librarian/Counselor‐FT  1,039,104             958,024           92.20% 1,133,600           978,073             86.28%

Librarian/Counselor‐PT 145,675                121,693           83.54% 194,185              141,587             72.91%

Staff‐FT 3,961,874             3,581,502        90.40% 4,684,151           4,159,543          88.80%

Staff‐PT 1,439,139             1,050,390        72.99% 1,669,471           1,152,832          69.05%

     Sub‐total Salaries 22,105,730          20,006,437      90.50% 24,312,958        21,835,961        89.81%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 277,848                166,606           59.96% 407,181              300,435             73.78%

Travel 91,102                  71,971              79.00% 116,844              100,915             86.37%

Marketing Costs 43,145                  30,393              70.44% 47,528                41,966                88.30%

Rental & Leases 118,687                44,078              37.14% 127,089              64,052                50.40%

Insurance/Risk Mgmt 15                          ‐                    0.00% 245                       245                    0.00%

Contract Services 284,020                186,657           65.72% 282,236              154,412             54.71%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Other Departmental Expenses 47,541                  29,265              61.56% 46,820                37,807                80.75%

Instructional & Other Materials 226,057                169,903           75.16% 343,476              291,556             84.88%

Maintenance & Repair 25,520                  18,906              74.08% 48,060                18,437                38.36%

Transfers/Debt 883,899                878,970           99.44% 845,619              845,382             ‐                      

Contingency 5,407                    ‐                    0.00% 3,854                  ‐                     ‐                      

Capital Outlay 145,126                88,386              60.90% 325,007              186,371             57.34%

     Total Expenses  24,254,097          21,691,573      89.43% 26,906,917        23,877,540        88.74%

Central College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Northwest College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

8

Page 16: Fs2013 july

Adjusted Budget 

FY2012

YTD Actuals Thru 

7/31/2012 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

7/31/2013 % of Budget Used

EXPENSES

Faculty‐FT  6,933,487             6,576,622        94.85% 7,506,187           6,962,205          92.75%

Faculty‐PT 3,960,168             3,697,973        93.38% 4,115,361           3,536,382          85.93%

Librarian/Counselor‐FT  1,067,762             992,165           92.92% 942,795              854,409             90.63%

Librarian/Counselor‐PT 118,806                100,290           84.41% 119,380              113,094             94.73%

Staff‐FT 4,574,777             4,148,483        90.68% 4,879,110           4,257,319          87.26%

Staff‐PT 713,488                578,450           81.07% 788,382              628,299             79.69%

     Sub‐total Salaries 17,368,488          16,093,983      92.66% 18,351,215        16,351,709        89.10%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 289,705                274,688           94.82% 226,699              196,355             86.61%

Travel 32,839                  23,785              72.43% 30,428                23,239                76.37%

Marketing Costs 54,559                  49,150              90.09% 56,696                49,689                87.64%

Rental & Leases 1,296,974             1,242,595        95.81% 1,310,622           904,100             68.98%

Insurance/Risk Mgmt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Contract Services 29,798                  26,376              88.52% 40,260                37,433                92.98%

Utilities 3,800                    2,850                75.00% 4,600                  3,200                 0.00%

Other Departmental Expenses 39,617                  30,909              78.02% 42,491                34,130                80.32%

Instructional & Other Materials 139,321                106,467           76.42% 168,636              125,458             74.40%

Maintenance & Repair 54,912                  44,563              81.15% 56,993                33,508                58.79%

Transfers/Debt 5,640,942             5,639,337        99.97% 5,636,142           5,634,237          ‐                      

Contingency 11,607                  ‐                    0.00% 12,500                ‐                     ‐                      

Capital Outlay 46,000                  40,317              87.65% 297,973              156,252             52.44%

     Total Expenses  25,008,562          23,575,018      94.27% 26,235,255        23,549,312        89.76%

Adjusted Budget 

FY2012

YTD Actuals Thru 

7/31/2012 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

7/31/2013 % of Budget Used

EXPENSES

Faculty‐FT  12,219,531          11,561,888      94.62% 12,224,453        11,635,232        95.18%

Faculty‐PT 6,227,997             5,688,057        91.33% 5,771,364           5,141,864          89.09%

Librarian/Counselor‐FT  1,262,189             1,183,728        93.78% 768,653              707,054             91.99%

Librarian/Counselor‐PT 192,494                149,677           77.76% 214,206              153,545             71.68%

Staff‐FT 5,176,829             4,725,099        91.27% 5,759,968           5,190,498          90.11%

Staff‐PT 1,555,994             1,228,556        78.96% 1,595,118           1,062,641          66.62%

     Sub‐total Salaries 26,635,033          24,537,005      92.12% 26,333,762        23,890,835        90.72%

Employee Benefits ‐                         ‐                    ‐                 4                           3                         ‐                 

Supplies Gen Exp 290,852                203,391           69.93% 328,232              244,506             74.49%

Travel 52,626                  34,144              64.88% 51,327                41,300                80.47%

Marketing Costs 45,952                  34,796              75.72% 39,443                35,483                89.96%

Rental & Leases 754,003                671,412           89.05% 540,876              503,073             93.01%

Insurance/Risk Mgmt 56                          56                     ‐                 98                         ‐                     0.00%

Contract Services 46,109                  35,437              76.85% 26,707                25,565                95.72%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Other Departmental Expenses 29,122                  21,315              73.19% 28,721                21,090                73.43%

Instructional & Other Materials 214,430                173,255           80.80% 285,643              266,966             93.46%

Maintenance & Repair 27,935                  19,420              69.52% 24,563                17,563                71.50%

Transfers/Debt 2,484,173             2,484,044        99.99% 1,155,001           1,155,000          100.00%

Contingency 7,024                    ‐                    0.00% ‐                        ‐                     #DIV/0!

Capital Outlay 96,837                  80,554              83.18% 118,059              100,496             85.12%

     Total Expenses  30,684,152          28,294,828      92.21% 28,932,436        26,301,882        90.91%

9

Northeast College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Southwest College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Page 17: Fs2013 july

Adjusted Budget 

FY2012

YTD Actuals Thru 

7/31/2012 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

7/31/2013 % of Budget Used

EXPENSES

Faculty‐FT  4,859,539             4,601,859        94.70% 4,948,893           4,712,386          95.22%

Faculty‐PT 3,551,588             3,335,814        93.92% 3,851,946           3,598,783          93.43%

Librarian/Counselor‐FT  714,338                658,603           92.20% 529,552              499,402             94.31%

Librarian/Counselor‐PT 79,814                  46,451              58.20% 83,152                36,363                43.73%

Staff‐FT 3,375,775             3,003,471        88.97% 3,908,827           3,527,340          90.24%

Staff‐PT 1,057,975             763,092           72.13% 1,197,805           818,808             68.36%

     Sub‐total Salaries 13,639,030          12,409,289      90.98% 14,520,175        13,193,082        90.86%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 269,351                174,427           64.76% 288,341              197,496             68.49%

Travel 42,912                  22,057              51.40% 29,915                22,898                76.54%

Marketing Costs 67,782                  59,906              88.38% 79,482                43,339                54.53%

Rental & Leases 172,373                162,474           94.26% 41,484                32,380                78.05%

Insurance/Risk Mgmt 105                        105                   ‐                 ‐                        ‐                     ‐                 

Contract Services 154,744                124,609           80.53% 177,893              106,452             59.84%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Other Departmental Expenses 72,613                  27,477              37.84% 41,488                28,652                69.06%

Instructional & Other Materials 60,754                  48,076              79.13% 95,494                64,351                67.39%

Maintenance & Repair 14,162                  7,058                49.84% 21,372                7,408                 34.66%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency 5,436                    ‐                    0.00% 11,632                ‐                     0.00%

Capital Outlay 86,453                  64,179              74.24% 275,868              100,867             36.56%

     Total Expenses  14,585,715          13,099,659      89.81% 15,583,144        13,796,924        88.54%

Adjusted Budget 

FY2012

YTD Actuals Thru 

7/31/2012 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

7/31/2013 % of Budget Used

EXPENSES

Faculty‐FT  6,106,406             5,737,660        93.96% 5,961,943           5,573,648          93.49%

Faculty‐PT 1,849,491             1,504,388        81.34% 2,033,783           1,645,692          80.92%

Librarian/Counselor‐FT  165,915                149,267           89.97% 85,066                76,168                89.54%

Librarian/Counselor‐PT 30,635                  24,382              79.59% 34,980                20,101                57.46%

Staff‐FT 2,323,566             2,112,882        90.93% 2,426,599           2,202,609          90.77%

Staff‐PT 343,656                237,889           69.22% 389,771              241,605             61.99%

     Sub‐total Salaries 10,819,669          9,766,468        90.27% 10,932,142        9,759,822          89.28%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 348,700                213,029           61.09% 347,473              210,877             60.69%

Travel 83,560                  53,636              64.19% 123,558              87,277                70.64%

Marketing Costs 6,523                    2,020                30.97% 32,472                28,485                87.72%

Rental & Leases 488,309                385,496           78.95% 483,719              386,624             79.93%

Insurance/Risk Mgmt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Contract Services 329,121                229,099           69.61% 343,590              294,402             85.68%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Other Departmental Expenses 74,931                  57,250              76.40% 130,696              104,265             79.78%

Instructional & Other Materials 353,980                253,384           71.58% 357,808              202,839             56.69%

Maintenance & Repair 54,423                  28,554              52.47% 83,949                37,079                44.17%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency 36,819                  ‐                    0.00% 5,860                  ‐                     0.00%

Capital Outlay 30,205                  23,352              0.00% 592,573              84,895                0.00%

     Total Expenses  12,626,240          11,012,289      87.22% 13,433,840        11,196,564        83.35%

Southeast College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Coleman College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

10

Page 18: Fs2013 july

Adjusted Budget 

FY2012

YTD Actuals Thru 

7/31/2012 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

7/31/2013 % of Budget Used

EXPENSES

Faculty‐FT  2,320,138             2,199,360        94.79% 2,358,182           2,266,522          96.11%

Faculty‐PT 3,553,094             2,830,360        79.66% 3,662,833           3,005,478          82.05%

Librarian/Counselor‐FT  67,910                  62,251              91.67% 2,887                  2,886                 99.97%

Librarian/Counselor‐PT ‐                         ‐                    0.00% ‐                        ‐                     0.00%

Staff‐FT 3,584,988             3,287,988        91.72% 3,799,680           3,449,942          90.80%

Staff‐PT 639,763                447,456           69.94% 795,822              586,057             73.64%

     Sub‐total Salaries 10,165,893          8,827,415        86.83% 10,619,404        9,310,884          87.68%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Supplies Gen Exp 190,378                145,134           76.23% 253,016              198,730             78.54%

Travel 71,942                  43,239              60.10% 93,526                61,768                66.04%

Marketing Costs 186,702                159,775           85.58% 405,734              169,345             41.74%

Rental & Leases 39,509                  21,519              54.47% 28,952                12,995                44.88%

Insurance/Risk Mgmt ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Contract Services 50,260                  33,851              67.35% 363,063              93,797                25.83%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Other Departmental Expenses 46,467                  34,902              75.11% 52,742                40,914                77.57%

Instructional & Other Materials 948,718                639,920           67.45% 997,675              569,729             57.11%

Maintenance & Repair 118,803                100,763           84.81% 159,700              109,937             68.84%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Capital Outlay 14,381                  13,160              0.00% 44,634                31,348                70.23%

     Total Expenses  11,833,053          10,019,677      84.68% 13,018,446        10,599,447        81.42%

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

11

Division of Extended Learning

Page 19: Fs2013 july

2006-07 2007-08 2008-09 2009-10 2010-11 2011-12Academic 12,077,904 12,739,232 14,345,992 16,652,752 17,802,080 17,354,256

Technical 4,378,250 4,422,336 4,883,890 5,680,164 5,924,078 5,822,072

Continuing Education 2,091,365 1,847,195 1,810,761 1,880,857 1,914,445 1,798,940

Total Fundable Contact Hrs 18,547,519 19,008,763 21,040,643 24,213,773 25,640,603 24,975,268

Source: Certified CBM004 & CBM00C.

12

HOUSTON COMMUNITY COLLEGEAnnual Fundable Contact Hours 

FY 2006-07 thru FY 2011-12

0

5,000,000

10,000,000

15,000,000

20,000,000

25,000,000

30,000,000

2006‐07 2007‐08 2008‐09 2009‐10 2010‐11 2011‐12

Continuing Education Technical Academic

+5.9%+15.1%

+10.7%+2.5%

‐2.6%

Page 20: Fs2013 july

HOUSTON COMMUNITY COLLEGEUnduplicated Headcount Comparison Semester‐To‐Semester (FY 2010‐11 thru FY 2013‐14)

Fall Semester (Unduplicated Enrollment ‐ All Students)*

Spring Semester (Unduplicated Enrollment ‐ All Students)

Summer Semester (Unduplicated Enrollment ‐ All Students)*

* As of August 2, 2013.

13

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

-69

-59

-49

-39

-29

-19 -9 1 11 21 31 41 51 61 71 81 91 101

111

121

131

Spr 13

Spr 12

Spr 11

Census Day

First Class Day

Spr 13 Enrollment:+0.1% (Spr13 to 12)‐5.8% (Spr13 to 11)

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

-62

-52

-42

-32

-22

-12 -2 8 18 28 38 48

Sum 13

Sum 12

Sum 11

Census Day

First Class Day

Sum 13 Enrollment:‐6.5%  (Sum13 to 12)‐6.6% (Sum13 to 11)

0

10000

20000

30000

40000

50000

60000

70000

80000

-110

-100 -90

-80

-70

-60

-50

-40

-30

-20

-10 0 10 20 30

Fall 13

Fall 12

Fall 11 Fall 13 Enrollment:‐6.9%  (Fall13 to 12)‐3.9% (Fall13 to 11)

First Class Day

Census Day

Page 21: Fs2013 july

HOUSTON COMMUNITY COLLEGERevenues & Expenditures Comparison Year to Date Thru July 31, 2013

2009 Positions

Revenues Expenditures Rev H/(L) Exp

YTD Actuals Thru July 31, 2013 281,855,493         243,561,714        38,293,779       

YTD Actuals Thru July 31, 2012 284,947,439         244,001,274        40,946,165       

(3,091,946)            (439,560)              

14

 220,000,000

 230,000,000

 240,000,000

 250,000,000

 260,000,000

 270,000,000

 280,000,000

 290,000,000

Revenues Expenditures

Page 22: Fs2013 july

` HOUSTON COMMUNITY COLLEGEMonthly Revenues & Expenditures Comparison Year to Date By Month

Revenues SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 58,227,650  9,431,856  25,352,097  36,128,428 60,245,426 41,908,473 9,764,951 17,027,931  14,879,839 9,286,385 8,551,062

2011‐2012 61,685,752  9,480,515  24,214,599  37,832,575 66,013,487 35,495,964 10,116,378 16,794,724  15,263,177 9,332,949 7,924,181 9,726,145

2009 Positions

Expenditures SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 28,324,834  24,699,442  20,905,041  21,510,456 20,451,195 19,565,831 17,598,083 41,691,992  20,176,089 16,109,839 21,477,516

2011‐2012 37,698,782  23,302,047  20,581,833  17,164,427 19,407,583 18,185,253 18,965,252 39,130,360  18,696,899 18,586,628 21,489,075 18,505,226

15

 ‐ 5,000,000

 10,000,000 15,000,000 20,000,000 25,000,000 30,000,000 35,000,000 40,000,000 45,000,000 50,000,000 55,000,000 60,000,000 65,000,000 70,000,000

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐ 5,000,000

 10,000,000 15,000,000 20,000,000 25,000,000 30,000,000 35,000,000 40,000,000 45,000,000 50,000,000 55,000,000 60,000,000 65,000,000 70,000,000

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 23: Fs2013 july

HOUSTON COMMUNITY COLLEGERevenues Comparison Year to Date Thru July 31, 2013 by Source

2009 Positions

State 

Appropriations Ad Valorem Taxes Tuition, Net Fees

Other Local 

Income* Extended Learning Grant Revenue Total Revenues

YTD Actuals Thru July 31, 2013 63,495,699  104,405,862 40,158,942 65,070,880 2,020,706 6,241,171 462,232 281,855,493

YTD Actuals Thru July 31, 2012 63,779,106  104,341,537 41,978,987 66,790,991 1,399,374 6,195,087 462,356 284,947,439

(283,407)  64,325 (1,820,045) (1,720,111) 621,332 46,084 (124) (3,091,946)

16

 ‐

 20,000,000

 40,000,000

 60,000,000

 80,000,000

 100,000,000

 120,000,000

StateAppropriations

Ad Valorem Taxes Tuition, Net Fees Other LocalIncome*

Extended Learning Grant Revenue

Page 24: Fs2013 july

HOUSTON COMMUNITY COLLEGEExpense Comparison Year to Date Thru July 31, 2013 by Source

2009 Positions

YTD Actuals Thru Faculty‐FT  Faculty‐PT

Librarian/

Counselor‐FT 

Librarian/

Counselor‐PT Staff‐FT Staff‐PT

Employee 

Benefits

Supplies Gen 

Exp Travel

Marketing 

Costs

Rental & 

Leases

Insurance/

Risk Mgmt

Contract 

Services Utilities

Other 

Departmental 

Expenses

Instructional & 

Other 

Materials

Maintenance & 

Repair

Transfers/

Debt Capital Outlay      Total Expenses 

 July 31, 2013  50,991,693  27,138,113  4,393,852  555,892  59,195,927  6,491,516  14,751,325  4,660,200  777,330  1,299,364  2,159,748  6,519,897  18,327,458  7,063,294  1,697,014  5,448,881  678,779  28,330,519  3,080,913  243,561,714 

 July 31, 2012  49,784,819  26,787,552  5,417,691  508,023  56,076,984  6,432,874  12,295,929  4,398,092  696,397  936,196  4,214,401  6,088,158  16,631,834  6,556,434  1,243,446  4,225,807  671,517  39,467,200  1,567,921  244,001,274 

1,206,874  350,561  (1,023,839)  47,870  3,118,943  58,642  2,455,396  262,109  80,932  363,168  (2,054,653)  431,739  1,695,623  506,860  453,568  1,223,075  7,262  (11,136,682)  1,512,992  (439,560) 

17

 ‐

 1,000,000

 2,000,000

 3,000,000

 4,000,000

 5,000,000

 6,000,000

 7,000,000

 8,000,000

 9,000,000

 10,000,000

 11,000,000

 12,000,000

 13,000,000

 14,000,000

 15,000,000

 16,000,000

 17,000,000

 18,000,000

 19,000,000

 20,000,000

 21,000,000

 22,000,000

 23,000,000

 24,000,000

 25,000,000

 26,000,000

 27,000,000

 28,000,000

 29,000,000

 30,000,000

Page 25: Fs2013 july

TOTAL 

Unexpended Plant Funds

Total Unexpended Plant Fund Balances per Books (1,121,850)$        

  Spending/Encumbrances/Reserve for Future Use

‐ Encumbrances/PO Issued General Unexpended FY13 1,121,850            

Total  Plant Fund PO 1,121,850$         

     Anticipated Unexpended Plant Shortfall ‐$                         

HOUSTON COMMUNITY COLLEGEUnexpended Plant Fund Excluding 2004 CIP

Cash Position to July 31, 2013

18

Page 26: Fs2013 july

Description of Use

Total Budget to 

Date

Total 

Expenditures      

To Date

Encumbrances To 

Date Unexpended

DEFERRED MAINTENANCE FY05

System Administration 604,863$                604,863$                ‐$                              ‐$                             

Subtotal 604,863$               604,863$               ‐$                              ‐$                           

DEFERRED MAINTENANCE  FY06

System Administration 649,625$                649,624$                ‐$                              ‐$                             

Northwest College 412,743                412,743                ‐                               ‐                            

Coleman College 190,738                190,736                ‐                               ‐                            

Subtotal 1,253,106$            1,253,103$            ‐$                              ‐$                           

DEFERRED MAINTENANCE  FY07

System Administration 775,610$                775,610$                ‐$                              ‐$                             

Central College 373,917                373,917                ‐                               ‐                            

Northwest College 599,383                599,383                ‐                               ‐                            

Northeast College 1,059,733             1,059,733             ‐                               ‐                            

Southwest College 74,607                  74,607                  ‐                               ‐                            

Southeast College 38,742                  38,742                  ‐                               ‐                            

Coleman College 9,900                    9,900                    ‐                               ‐                            

Subtotal 2,931,893$            2,931,892$            ‐$                              ‐$                           

DEFERRED MAINTENANCE  FY08

System Administration 10,195$                  10,195$                  ‐$                              ‐$                             

Central College 478,637                478,637                ‐                               ‐                            

Northwest College 1,217,755             1,217,755             ‐                               ‐                            

Northeast College 494,886                494,886                ‐                               ‐                            

Southwest College 42,063                  42,063                  ‐                               ‐                            

Coleman College 73,813                  73,813                  ‐                               ‐                            

Subtotal 2,317,348$            2,317,349$            ‐$                              ‐$                           

OTHER GENERAL PROJECTS

Minor Construction 657,807$               657,807$               ‐$                              ‐$                           

System 11,481,737           11,134,281           347,456                 ‐                            

Central College 3,218,637             3,129,754             88,883                   ‐                            

Northwest College 4,060,039             4,051,428             8,611                     ‐                            

Northeast College 1,106,793             700,228                406,565                 ‐                            

Southwest College 1,587,304             1,325,995             261,309                 ‐                            

Southeast College 1,995,204             1,989,030             6,174 ‐                            

Coleman College 1,341,161             1,341,159             2 ‐                            

Subtotal 25,448,682$         24,329,682$         1,119,000$             ‐$                           

SURPLUS PROPERTY

Palmetto Property ‐ Purchase 495,154$               495,154$               ‐$                              ‐$                           

Dixie Property‐ Refund 20,000                  20,000                  ‐                            

 288 Property‐ Purchase 1,142,402             1,139,552             2,850                     ‐                            

Warehouse Property 12,966,619           12,966,619           ‐                               ‐                            

Subtotal 14,624,175$         14,621,325$         2,850$                    ‐$                           

Total Anticipated Uses 47,180,067$          46,058,214$          1,121,850$             ‐$                             

UNEXPENDED PLANT FUND PROJECTSas of July 31, 2013

19

HOUSTON COMMUNITY COLLEGE

Page 27: Fs2013 july

 

Total Budget 

to Date

Total 

Expenditures   

To Date

Encumbrances 

To Date

% of 

Expen‐ 

ditures Unexpended

% of 

Total 

BudgetSources:

Central College 2001A Bond 25,318,535$      

2003 Limited Tax Bond and Premium 150,748,497      

Actural Interest Earned 2003 Limited Tax Bonds 20,868,074         

2005 Limited Tax and Building Bond 1,875,000           

2003/2005 LTD Bond Issuance Cost (2,068,522)          

2006 Jr Lien Bond Std Revenue Bond 30,000,000         

Bond Issuance Cost (913,149)             

Actual Interest Earned 2006 Jr Lien Bonds 2,608,533           

Transferred to Fund 7305/Hayes Road (3,169,049)          

2008 Maintenance Tax Notes 56,912,320         

2008 MTN Bond Issuance Cost (1,056,912)          

Actual Interest Earned 2008 MTN 1,654,029           

2008 Sr. Lien Bond             1,714,953 

Transferred to Residual CIP Funds         (20,712,314)

Total Available with Reclassification 263,779,995$    

Uses:

Construction 119,635,550$     119,628,602$     6,948$                  100% ‐$                          0%

CPMS PGAL  11,121,809          11,121,809          ‐                             100% ‐                             0%

Facility Planning 1,677,989            1,677,989            ‐                             100% ‐                             0%

Architect Fees and Engineering 7,507,764            7,505,762            2,002                    100% ‐                             0%

Other Costs including Bldg/Land Purchase 2,262,477            2,258,218            4,259                    100% ‐                             0%

Inspectors 890,000               890,000               ‐                             100% ‐                             0%

Design Standard 103,370               103,370               ‐                             100% ‐                             0%

Site Improvement and Infrastructure Development 52,582,367          52,073,872          508,496                100% (0)                           0%

IT Infrastructure Master Plan 29,507,115          29,173,797          333,318                100% 0                            0%

Furniture and Fixtures 13,979,273          13,908,378          70,895                  100% 0                            0%

Small Business 567,383               567,383               ‐                             100% ‐                             0%

Administrative Services 3,413,568            3,381,849            22,500                  100% 9,219                    0%

Material Testing 542,445               537,606               4,839                    100% (0)                           0%

Contingency for Construction 717,302               0% 717,302               100%

Surveying 465,888               460,552               5,335                    100% 0                            0%

Design and Geotech 110,111               110,111               100% ‐                             0%

Signage 70,000                  70,000                  100% ‐                             0%

Blue Light Security 126,000               120,600               5,400                    100% ‐                             0%

PGAL Website Development 181,208               181,208               ‐                             100% ‐                             0%

System Architect Furniture Consultant 11,367                  11,367                  100% ‐                             0%

Northline Demolition‐Pizza Hut 226,246               226,246               100% ‐                             0%

Police Cars 342,223               341,613               610                        100% ‐                             0%

Bering St. Property 50,687                  50,687                  100% ‐                             0%

General Repairs & Maintenance 2,079,239            2,079,239            100% ‐                             0%

Land Purchase 1,919,729            1,919,729            100% ‐                             0%

Amateur Sports Complex ‐ Willie Gay Hall 2,240,764            2,233,764            7,000                    100% ‐                             0%

Total Construction Cost 252,331,871$     250,633,753$     971,602$              100% 726,521$             0%

Note: Expenditures Not In Construction Schedule

Deferred Maintenance 5,000,000$          5,000,000$          ‐$                           100% ‐$                          0%

IT Development 6,448,123            6,448,122            ‐                             100% ‐                             0%

263,779,995$     262,081,875$     971,603$              100% 726,521$             0%

Anticipated Budget Shortfall/Surplus (0)                          

*Footnote on next page

HOUSTON COMMUNITY COLLEGE2004 CIP Projectsas of July 31, 2013

20

Page 28: Fs2013 july

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

Central ‐ San Jacinto:*

Construction Cost 1,241,868$         1,241,868$         ‐$                         

CPMS PGAL 111,440              111,440              ‐                         ‐                          

Facilities Space Programming 393,715              393,715              ‐                         ‐                          

Material Testing  ‐                           ‐                           ‐                         ‐                          

IT Infrastructure Capital Projects 5,687                  5,687                  ‐                         ‐                          

Design Standards 3,904                  3,904                  ‐                          

  Total Central ‐ San Jacinto 1,780,694$          1,780,694$          ‐$                        ‐$                          

Central ‐ Learning Hub/Science Bldg:*

Construction Cost 21,504,724$       21,499,805$       4,919$               -$ CPMS PGAL 1,967,801           1,967,801           ‐                          

Facilities Space Programming 148,096              148,096              ‐                          

Architect and Engineering 1,242,506           1,242,506           ‐                          

Furniture, Fixtures & Equipment 2,019,706           2,019,706           ‐                          

Inspectors 187,000              187,000              ‐                          

Project Software 7,614                  7,614                  ‐                          

Design Standards 15,086                15,086                ‐                          

Site Infrastructure Improvements 5,688,425           5,428,687           259,738            ‐                          

IT Infrastructure Master Plan 2,726,528           2,726,528           ‐                          

Design Geotech 10,150                10,150                ‐                          

Material Testing  32,994                32,356                638                    ‐                          

Surveying  69,453                64,118                5,335                 ‐                          

Blue Light Security 18,000                17,100                900                    ‐                          

  Total Central ‐ Learning Hub/Science 

Bldg:*

35,638,083$        35,366,553$        271,530$           ‐$                          

NEC ‐ Learning Hub:*

Construction Cost 14,001,119$       14,001,119$       ‐                          

CPMS PGAL 1,187,440           1,187,440           ‐                          

Facilities Space Programming 145,889              145,889              ‐                          

Architect and Engineering 723,556              723,556              ‐                          

Furniture, Fixtures & Equipment 1,651,908           1,651,908           ‐                          

Other Costs including Bldg/Land Purchase ‐                           ‐                          

Inspectors 205,000              205,000              ‐                          

Project Software ‐                           ‐                          

Design Standards 9,015                  9,015                  ‐                          

Site Infrastructure Improvements 92,682                92,682                ‐                          

IT Infrastructure Master Plan 1,249,836           1,249,836           ‐                          

Design Geotech ‐                           ‐                          

Material Testing  123,607              123,607              ‐                          

Surveying  71,081                71,081                ‐                          

  Total NEC ‐ Learning Hub 19,461,133$        19,461,133$        ‐$                        ‐$                          

HOUSTON COMMUNITY COLLEGE2004 CIP Projectsas of July 31, 2013

21

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 29: Fs2013 july

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projectsas of July 31, 2013

NEC ‐ Science Engineering & Technology:*

Construction Cost 11,626,428$       11,626,428$       ‐$                         

CPMS PGAL 857,203              857,203              ‐                          

Facilities Space Programming 52,058                52,058                ‐                          

Architect and Engineering 635,906              635,906              ‐                          

Furniture, Fixtures & Equipment 643,154              607,016              36,138              ‐                          

Other Costs including Bldg/Land Purchase 73,800                73,800                ‐                          

Inspectors ‐                           ‐                          

Project Software ‐                           ‐                          

Design Standards 6,818                  6,818                  ‐                          

Site Infrastructure Improvements 15,423,461        15,357,930        65,531              ‐                          

IT Infrastructure Master Plan 1,160,897           1,160,824           73                      ‐                          

Design Geotech 28,500                28,500                ‐                          

Material Testing  95,465                95,465                ‐                          

Surveying  10,035                10,035                ‐                          

Blue Light Security 18,000                17,100                900                    ‐                          

  Total NEC ‐ Science Eng & Technology 30,631,725$        30,529,083$        102,642$           ‐$                          

NEC ‐ Pinemont:

CPMS PGAL 6,269$                 6,269$                 ‐$                        ‐$                         

Facilities Space Programming 71,292                71,292                ‐                         ‐                          

Other Costs including Bldg/Land Purchase 102,156              102,156              ‐                          ‐                            

Surveying  22,483                22,483                ‐                         ‐                          

  Total NEC ‐ Pinemont 202,200$              202,200$              ‐$                        ‐$                          

SEC ‐ Felix Fraga (Drennan):*

Construction Cost 12,419,858$       12,417,829$       2,029$               ‐$                         

CPMS PGAL 1,216,969           1,216,969           ‐                          

Facilities Space Programming 227,023              227,023              ‐                          

Architect and Engineering 835,511              835,511              ‐                          

Furniture, Fixtures & Equipment 1,007,619           977,469              30,150              ‐                          

Other Costs including Bldg/Land Purchase 62,466 62,466                ‐                          

Inspectors - ‐                          

Project Software - ‐                          

Design Standards 6,873                  6,873                  ‐                          

Site Infrastructure Improvements 5,993,954           5,960,197           33,757              ‐                          

IT Infrastructure Master Plan 1,268,478           1,268,405           73                      ‐                          

Design Geotech 18,200                18,200                ‐                          

Material Testing  137,662              137,662              ‐                          

Surveying  27,674                27,674                ‐                          

HUB/Small Business Program ‐                           ‐                           ‐                         ‐                          

HUB/Small Business Program ‐                           ‐                          

Bering St Property 50,687                50,687                ‐                          

Signage ‐                           ‐                          

Blue Light Security 18,000                17,100                900                    ‐                            Total SEC ‐ Felix Fraga (Drennan):* 23,290,974$        23,224,065$        66,909$             ‐$                          

22

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 30: Fs2013 july

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projectsas of July 31, 2013

SEC ‐ Felix Morales:*

Construction Cost 3,653,330$         3,653,330$         ‐$                         

CPMS PGAL 667,905              667,905              ‐                          

Facilities Space Programming 62,181                62,181                ‐                          

Architect and Engineering 353,970              351,968              2,002                 ‐                          

Furniture, Fixtures & Equipment 902,023              898,276              3,747                 ‐                          

Inspectors ‐                           ‐                          

Project Software ‐                           ‐                          

Design Standards 3,117                  3,117                  ‐                          

Site Infrastructure Improvements 98,015                96,070                1,945                 ‐                          

IT Infrastructure Master Plan 1,135,522           1,008,321           127,201            0                         

Design Geotech ‐                           ‐                          

Material Testing  10,009                5,808                  4,201                 ‐                          

Surveying  1,225                  1,225                  ‐                          

  Total SEC ‐ Felix Morales 6,887,296$          6,748,200$          139,096$           0$                         

SEC ‐ Learning Hub:*

Construction Cost 16,550,039$       16,550,039$       ‐$                         

CPMS PGAL 1,744,048           1,744,048           ‐                          

Facilities Space Programming 126,588              126,588              ‐                          

Architect and Engineering 875,415              875,415              ‐                          

Furniture, Fixtures & Equipment 1,839,167           1,838,307           860                    ‐                          

 Other Costs including Bldg/Land Purchase  32,480                  28,221                  4,259                  ‐                            

Inspectors 258,000              258,000              ‐                         ‐                          

Project Software ‐                           ‐                          

Design Standards 9,367                  9,367                  ‐                          

Site Infrastructure Improvements 12,149,303        12,038,386        110,917            ‐                          

IT Infrastructure Master Plan 2,157,010           2,157,010           ‐                          

Administrative Services ‐                           ‐                          

Design Geotech 9,525                  9,525                  ‐                         ‐                          

Material Testing  115,883              115,883              ‐                          

Surveying  144,094              144,094              ‐                          

Blue Light Security 18,000                18,000                - ‐                          

  Total SEC ‐ Learning Hub 36,028,917$        35,912,883$        116,036$           ‐$                          

23

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 31: Fs2013 july

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projectsas of July 31, 2013

SW ‐ Missouri City:*

Construction Cost 8,891,630$         8,891,630$         ‐$                         

CPMS PGAL 601,635              601,635              ‐                         ‐                          

Facilities Space Programming 194,111              194,111              ‐                          

Architect and Engineering 958,905              958,905              ‐                         ‐                          

Furniture, Fixtures & Equipment 1,011,146           1,011,146           ‐                         ‐                          

 Library & Bookstore  1,991,575           1,991,575           ‐                          

Inspectors ‐                           ‐                          

Project Software ‐                           ‐                          

Design Standards 4,999                  4,999                  ‐                          

Site Infrastructure Improvements 5,061,234           5,061,234           ‐                         ‐                          

IT Infrastructure Capital Projects 2,246,083           2,246,083           ‐                         ‐                          

Design Geotech ‐                           ‐                          

Material Testing  ‐                           ‐                          

Surveying  48,311                48,311                ‐                          

Blue Light Security 18,000                17,100                900                    ‐                          

  Total SW ‐ Missouri City 21,027,628$        21,026,728$        900$                   ‐$                          

SW ‐ West Loop Phase I:*

Construction Cost 9,031,922$         9,031,922$         ‐$                        ‐$                         

CPMS PGAL 1,033,865           1,033,865           ‐                          

Facilities Space Programming 76,260                76,260                ‐                          

Architect and Engineering 718,694              718,694              ‐                          

Furniture, Fixtures & Equipment 2,154,214           2,154,214           ‐                         ‐                          

Design Standards 8,170                  8,170                  ‐                          

IT Infrastructure Capital Projects 2,864,190           2,864,190           ‐                         ‐                          

Design Geotech 22,116                22,116                ‐                          

Material Testing  21,141                21,140                ‐                         ‐                          

Surveying  14,995                14,995                ‐                         ‐                          

Exterior Signage 70,000                70,000                ‐                         ‐                          

Blue Light Security 18,000                17,100                900                    ‐                          

  Total SW ‐ West Loop Phase I 16,033,566$        16,032,665$        900$                   ‐$                          

24

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 32: Fs2013 july

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projectsas of July 31, 2013

SW ‐ Learning Hub ‐ Stafford:*

Construction Cost 20,714,629$       20,714,629$       ‐$                        ‐$                         

CPMS PGAL 1,727,234           1,727,234           ‐                          

Facilities Space Programming 180,778              180,778              ‐                          

Architect and Engineering 1,155,688           1,155,688           ‐                         ‐                          

Furniture, Fixtures & Equipment 2,750,339           2,750,339           ‐                         ‐                          

Inspectors 240,000              240,000              ‐                          

Project Software ‐                           ‐                          

Design Standards 15,845                15,845                ‐                          

Site Infrastructure Improvements 8,075,292           8,038,685           36,607              ‐                          

IT Infrastructure Capital Projects 2,535,820           2,535,820           ‐                         ‐                          

Design Geotech 21,620                21,620                ‐                          

Material Testing  ‐                           ‐                          

Surveying  56,536                56,536                ‐                          

Blue Light Security 18,000                17,100                900                    ‐                          

  Total SW ‐ Learning Hub ‐ Stafford 37,491,782$        37,454,275$        37,507$             ‐$                          

System ‐ Network:

IT Infrastructure Capital Projects 12,158,847$       11,952,876$       205,971$           ‐                          

Administrative Services 3,413,568           3,381,849           22,500              9,219                 

PGAL Website Development 181,209              181,208              1                        ‐                          

HUB/Small Business Program 567,383              567,383              ‐                         ‐                          

 System Architect Furniture Consultant  11,367                11,367                ‐                           Ft. Bend Library Inflation Cost Increase  ‐                           ‐                          Northline Demolition‐Pizza Hut 226,246              226,246              ‐                          

Police Cars 342,223              341,613              610                    ‐                          

General Repairs & Maintenance 2,079,239           2,079,239           ‐                          

Land Purchase 1,919,729           1,919,729           ‐                          

Amateur Sports Complex ‐ Willie Gay Hall 2,240,764           2,233,764           7,000                 ‐                          

  Total ‐ System ‐ Network 23,140,575$        22,895,274$        236,080$           9,219$                 

Construction Contingency 717,302$             ‐$                           ‐$                        717,302               

Subtotal Above 252,331,875$      250,633,752$      971,600$           726,521$             

100.00% 99.33% 0.39% 0.29%

EXPENDITURES NOT IN CONSTRUCTION SCHEDULE

Deferred Maintenance 5,000,000$         5,000,000$         ‐$                        ‐$                         

IT Development 6,448,123           6,448,122           ‐                         ‐                          

GRAND TOTAL 263,779,998$      262,081,874$      971,600$           726,521$             

100.00% 99.36% 0.37% 0.28%

25

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 33: Fs2013 july

 

Total Budget to 

Date

Total 

Expenditures To 

Date

 Encumbrances 

July 31, 2013  Unexpended

Sources:

Bond Proceeds 454,167,571$      

Capitalized Interest (26,559,053)         

Issuance Cost & Underwriters' Discount (2,608,518)           

Interest Earned 137,284               

Total Available with Reclassification 425,137,284$      

Uses:

Land 8,171,973$            8,171,973$       ‐$                          ‐$                        

Construction Cost 1,754,655             364,006            1,390,649          ‐                     

Architect and Engineering 133,880                82,065              51,815                ‐                     

Site Infrastructure Improvements 89,660                   864                    88,796                ‐                     

Inspection 135,960                ‐                     135,960              ‐                     

Material Testing 248,327                111,522            136,805              ‐                     

IT Infrastructure Capital Projects 47,282                   ‐                     47,282                ‐                     

Furniture, Fixtures & Equipment 565,883                ‐                     565,883              ‐                     

Contingency for Construction(Int. Earned) 3,500,000             ‐                     ‐                      3,500,000         

Small Business 2,000,000             ‐                     5,985                  1,994,015         

Administrative Services 660,000                ‐                     ‐                      660,000            

Construction Auditor 137,284                ‐                     ‐                      137,284            

Total Construction Cost 17,444,902$          8,730,430$       2,423,174$         6,291,299$        

Anticipated Budget Shortfall/Surplus 407,692,382        

26

HOUSTON COMMUNITY COLLEGE SYSTEM2013 CIP ProjectsAs of July 31, 2013

Page 34: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

July 31, 2013 Unexpended

Central Campus: 23,071,888               23,071,888          

Land ‐                        ‐                            ‐                            

Construction Cost ‐                        ‐                            ‐                            

Architect and Engineering ‐                        ‐                            ‐                            

Site Infrastructure Improvements 87,500                       ‐                        87,500                ‐                            

Inspection ‐                        ‐                            ‐                            

Material Testing  ‐                        ‐                            ‐                            

IT Infrastructure Capital Projects ‐                        ‐                            ‐                            

Furniture, Fixtures & Equipment ‐                        ‐                            ‐                            

Contingency ‐                        ‐                            ‐                              Total Central Campus 23,159,388$             ‐$                       87,500$               23,071,888$        

South Campus Workforce Building 24,142,734$             24,142,734$        

Land ‐                    ‐                      ‐                        

Construction Cost ‐                    ‐                      ‐                        

Architect and Engineering ‐                    ‐                      ‐                        

Site Infrastructure Improvements 2,160                         864                   1,296                  ‐                        

Inspection ‐                    ‐                      ‐                        

Material Testing ‐                        

IT Infrastructure Capital Projects ‐                    ‐                      ‐                        

Furniture, Fixtures & Equipment ‐                    ‐                      ‐                        

Contingency ‐                    ‐                      ‐                          Total South Campus 24,144,894$             864$                  1,296$                 24,142,734$        

Northline 19,710,118$             19,710,118$        

Land ‐                    ‐                      ‐                            

Construction Cost ‐                    ‐                      ‐                            

Architect and Engineering ‐                    ‐                      ‐                            

Site Infrastructure Improvements ‐                    ‐                      ‐                            

Inspection ‐                    ‐                      ‐                            

Material Testing ‐                            

IT Infrastructure Capital Projects ‐                    ‐                      ‐                            

Furniture, Fixtures & Equipment ‐                    ‐                      ‐                            

Contingency ‐                    ‐                      ‐                              Total Northline 19,710,118$             ‐$                       ‐$                          19,710,117$        

Northforest Workforce & Early College 29,169,687$             29,169,687$        

Land 8,102,273                  8,102,273        ‐                            ‐                            

Construction Cost 1,633,824                  364,006           1,269,818          ‐                            

Architect and Engineering ‐                        ‐                            ‐                            

Site Infrastructure Improvements ‐                        ‐                            ‐                            

Inspection ‐                        ‐                            ‐                            

Material Testing 199,996                     107,998           91,998                ‐                            

IT Infrastructure Capital Projects 47,282                       ‐                        47,282                ‐                            

Furniture, Fixtures & Equipment 267,174                     ‐                        267,174              ‐                            

Contingency ‐                        ‐                            ‐                              Total Northforest & Early College 39,420,235$             8,574,277$      1,676,272$         29,169,687$        

HOUSTON COMMUNITY COLLEGE SYSTEM2013 CIP ProjectsAs of July 31, 2013

27

Page 35: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

July 31, 2013 Unexpended

HOUSTON COMMUNITY COLLEGE SYSTEM2013 CIP ProjectsAs of July 31, 2013

Acres Homes 12,797,976$             ‐$                          12,797,976$        

Land 13600 13600 ‐                            ‐                            

Construction Cost ‐                        ‐                            ‐                            

Architect and Engineering ‐                        ‐                            ‐                            

Site Infrastructure Improvements ‐                        ‐                            ‐                            

Inspection ‐                        ‐                            ‐                            

Material Testing ‐                            

IT Infrastructure Capital Projects ‐                        ‐                            ‐                            

Furniture, Fixtures & Equipment ‐                        ‐                            ‐                            

Contingency ‐                        ‐                            ‐                              Total ‐ Pinemont  12,811,576$             13,600$            ‐$                          12,797,976$        

Alief Campus 9,851,535$               9,851,535$          

Land ‐                    ‐                      ‐                        

Construction Cost ‐                    ‐                      ‐                        

Architect and Engineering ‐                    ‐                      ‐                        

Site Infrastructure Improvements ‐                    ‐                      ‐                        

Inspection ‐                    ‐                      ‐                        

Material Testing 3,524                         3,524               ‐                      ‐                        

IT Infrastructure Capital Projects ‐                    ‐                      ‐                        

Furniture, Fixtures & Equipment ‐                    ‐                      ‐                        

Contingency ‐                    ‐                      ‐                          Total ‐ Alief  9,855,059$               3,524$              ‐$                          9,851,535$          

Westside Campus 52,226,812$             52,226,812$        

Land 0 0 ‐                        

Construction Cost ‐                        ‐                            ‐                        

Architect and Engineering 5,000                         ‐                        5,000                  ‐                        

Site Infrastructure Improvements ‐                        ‐                            ‐                        

Inspection ‐                        ‐                            ‐                        

Material Testing ‐                        

IT Infrastructure Capital Projects ‐                        ‐                            ‐                        

Furniture, Fixtures & Equipment ‐                        ‐                            ‐                        

Contingency ‐                        ‐                            ‐                          Total ‐ Westside  52,231,812$             ‐$                       5,000$                 52,226,812$        

Southeast Campus 26,071,099$             26,071,099$        

Land 0 0 ‐                        

Construction Cost ‐                        ‐                            ‐                        

Architect and Engineering ‐                        ‐                            ‐                        

Site Infrastructure Improvements ‐                        ‐                            ‐                        

Inspection ‐                        ‐                            ‐                        

Material Testing 44,807                       ‐                        44,807                ‐                        

IT Infrastructure Capital Projects ‐                        ‐                            ‐                        

Furniture, Fixtures & Equipment ‐                        ‐                            ‐                        

Contingency ‐                        ‐                            ‐                          Total ‐ Southeast 26,115,906$             ‐$                       44,807$               26,071,099$        

28

Page 36: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

July 31, 2013 Unexpended

HOUSTON COMMUNITY COLLEGE SYSTEM2013 CIP ProjectsAs of July 31, 2013

Felix Fraga Campus 15,083,715$             15,083,715$        

Land ‐                    ‐                      ‐                        

Construction Cost 120,831                     ‐                    120,831              ‐                        

Architect and Engineering 128,880                     82,065             46,815                ‐                        

Site Infrastructure Improvements ‐                    ‐                      ‐                        

Inspection 135,960                     ‐                    135,960              ‐                        

Material Testing ‐                    ‐                      ‐                        

IT Infrastructure Capital Projects ‐                    ‐                      ‐                        

Furniture, Fixtures & Equipment 298,709                     ‐                    298,709              ‐                        

Contingency ‐                    ‐                      ‐                          Total ‐ Felix Fraga  15,768,094$             82,065$            602,314$            15,083,715$        

Westloop Campus 17,739,106$             ‐$                          17,739,106$        

Land ‐                        

Construction Cost ‐                        

Architect and Engineering ‐                        

Site Infrastructure Improvements ‐                        

Inspection ‐                        

Material Testing ‐                        

IT Infrastructure Capital Projects ‐                        

Furniture, Fixtures & Equipment ‐                        

Contingency ‐                          Total ‐ Westloop  17,739,106$             ‐$                       ‐$                          17,739,106$        

Braes Oak Campus 11,826,071$             11,826,071$        

Land ‐                        

Construction Cost ‐                        

Architect and Engineering ‐                        

Site Infrastructure Improvements ‐                        

Inspection ‐                        

Material Testing ‐                        

IT Infrastructure Capital Projects ‐                        

Furniture, Fixtures & Equipment ‐                        

Contingency ‐                          Total ‐ Braes Oak 11,826,071$             ‐$                       ‐$                          11,826,071$        

Stafford Campus 26,608,659$             26,608,659$        

Land ‐                    ‐                      ‐                        

Construction Cost ‐                        ‐                            ‐                        

Architect and Engineering ‐                        

Site Infrastructure Improvements ‐                        

Inspection ‐                        ‐                            ‐                        

Material Testing ‐                        ‐                            ‐                        

IT Infrastructure Capital Projects ‐                        ‐                            ‐                        

Furniture, Fixtures & Equipment ‐                        ‐                            ‐                        

Contingency ‐                        ‐                            ‐                          Total ‐ Stafford Campus 26,608,659$             ‐$                       ‐$                          26,608,659$        

29

Page 37: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

July 31, 2013 Unexpended

HOUSTON COMMUNITY COLLEGE SYSTEM2013 CIP ProjectsAs of July 31, 2013

Missouri City  21,188,376$             ‐$                       ‐$                          21,188,376$        

Land ‐                        ‐                            ‐                            

Construction Cost ‐                        ‐                            ‐                            

Architect and Engineering ‐                            

Site Infrastructure Improvements ‐                            

Inspection ‐                        ‐                            ‐                            

Material Testing ‐                        ‐                            ‐                            

IT Infrastructure Capital Projects ‐                        ‐                            ‐                            

Furniture, Fixtures & Equipment ‐                        ‐                            ‐                            

Contingency ‐                            21,188,376$             ‐$                       ‐$                          21,188,377$        

  Total ‐ Missouri City

Coleman 118,204,606$           118,204,606$      

Land 56100 56100 ‐                            ‐                            

Construction Cost ‐                        ‐                            ‐                            

Architect and Engineering ‐                        ‐                            ‐                            

Site Infrastructure Improvements ‐                        ‐                            ‐                            

Inspection ‐                        ‐                            ‐                            

Material Testing ‐                        ‐                            ‐                            

IT Infrastructure Capital Projects ‐                        ‐                            ‐                            

Furniture, Fixtures & Equipment ‐                        ‐                            ‐                            

Contingency ‐                            ‐                              Total ‐ Coleman 118,260,706$           56,100$            ‐$                          118,204,606$      

Small Business 3,500,000                   ‐                      ‐                        3,500,000             Administrative Services 2,000,000                  ‐                    5,985                  1,994,015             

Construction Auditor 660,000                      ‐                      ‐                        660,000                

Construction Contingency 137283.52 ‐                    ‐                      137,284                Total Construction Cost 6,297,284$               ‐$                       5,985$                 6,291,299$          

GRAND TOTAL 425,137,284$           8,730,430$      2,423,174$         413,983,681$      

30

Page 38: Fs2013 july

2003/2005 Limited Tax Bonds 2003 2005 TotalBond counsel fees 150,000 57,000 207,000Underwriters' discount 814,813 57,000 871,813Insurance premium 558,764 558,764Financial advisory fee 205,391 68,081 273,472Rating agencies fees 114,350 16,000 130,350Printing costs 10,386 4,506 14,892CPA consent letter fee 1,500 1,500 3,000Verification fees 3,500 3,500Paying agent fee 300 5,432 5,732

1,855,504 213,018 2,068,522

2006 Jr Lien Revenue BondsBond counsel fees 79,500Underwriters' discount 509,509Insurance premium 117,904Financial advisory fee 137,910Rating agencies fees 54,850Printing costs 3,502CPA consent letter fee 1,500Verification fees 3,500Paying agent fee 4,974

913,149

2008 Maintenance Tax NotesBond counsel fees 63,500Underwriters' discount 342,526Insurance premium 498,600Financial advisory fee 95,105Rating agencies fees 47,100Printing costs 9,617Paying agent fee 463

1,056,912

Limited Tax General Obligation Bonds, Series 2013Bond counsel fees 698,040Underwriters' discount 1,213,220Financial advisory fee 462,628Rating agencies fees 190,000Printing costs 2,273CPA consent letter fee 4,000Paying agent fee 500

2,570,661

31

HOUSTON COMMUNITY COLLEGE2004 & 2013 CIP Projects Footnotes

as of July 31, 2013

Page 39: Fs2013 july

 

Total Budget to 

Date

Total 

Expenditures to 

Date  Encumbrances  Unexpended

Sources:Transferred CIP Funds 20,712,314

Uses:

Central Learning Hub/Science Bldg:

Site Infrastructure Improvements 6,599,554$         252,464$               33$                        6,347,057$        

South Campus:

Site Infrastructure Improvements 11,000 11,000                  ‐                             ‐                         

NEC ‐ Science Engineering & Technology:

Site Infrastructure Improvements 367,959 254,897 113,063                ‐                         

SEC ‐ Learning Hub:

Site Infrastructure Improvements 2,002,604 1,498,589            504,015                ‐                         

Material Testing 23,368 22,077                  1,291                     ‐                         

Katy Campus:

Architecture 155,200 ‐                             155,200                ‐                         

System ‐ Network:

IT Infrastructure Capital Projects 7,569,405 7,431,911            102,018                35,476              

Site Infrastructure Improvements 96,600 64,722                  31,878                  ‐                         

 

 Construction Contingency 851,755 ‐                             851,755            

Contingency* 3,034,869           ‐                             3,034,869         

Total Construction Cost 20,712,314$       9,535,661$           907,497$              10,269,157$     

Anticipated Budget Shortfall/Surplus (0)                        

*All of these funds, except for the Coningency of $3,034,869, arose from Maintenance Tax Notes which are intended

 for infrastructure and maintenance and repairs (capital‐related). The unexpended balance of $10,271,546 can be used

 throughout the district.

32

HOUSTON COMMUNITY COLLEGE SYSTEMResidual CIP Funds

as of  7/31/13

Page 40: Fs2013 july

Total Budget 

to Date

Total 

Revenues /  

Expenditures 

To Date

Encumbrances To 

Date Unexpended

Sources of funds:

Proceeds from 

2006 Tax Maintenance Notes 12,000,000$   

Discount (88,756)            

Bond Issuance Cost (256,244)          

Interest Income 835,395           

Funds Available 12,490,395$  

Uses of funds:

Site Infrastructure 341,092$          327,728$          13,364$                 ‐$                     

Project Management 450,479            450,479            ‐                              ‐                       

Construction 8,805,292         8,805,292         ‐                              ‐                       

Design Phase 1,117,820         1,117,820         ‐                              ‐                       

Architecture 17,822              17,822              ‐                       

Material Testing & Inspection 6,399                6,399                ‐                              ‐                       

Land/Demolition 420,541            420,541            ‐                              ‐                       

Survey 9,473                9,473                ‐                              ‐                       

Construction‐Maintenance 1,259,003         1,247,114         11,889                   ‐                       

Contingency 62,473              46,700              15,773            

Grand Total Uses 12,490,395$    12,449,368$    25,253$                 15,773$          

Net Available 0$                    

33

HOUSTON COMMUNITY COLLEGEMaintenance Tax Notes 2006 (Central Utility Plant Project)

as of July 31, 2013

 Note: Budgets are adjusted as contracts are awarded; otherwise, budget is preliminary from inception. 

Page 41: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances To 

Date Unexpended

Sources:

2008 Maintenance Tax Notes 39,780,489$     

2008 Maintenance Tax Notes‐Phase 1 Infrastructure 15,078,286      

Transferred to CIP Residual Fund (7170) (17,522,242)     

Interest Earned To date 1,679,542        

Funds Available for Projects 39,016,075$     

Uses:

Site Infrastructure Improvements 5,679,383$        5,410,266$       269,117$              ‐$                       

Architectural/Engineering Fees 165,537            151,654           13,883                  ‐                         

IT Infrastructure Master Plan 19,553,388       19,243,543      309,845                ‐                         

Furniture, Fixtures & Equipment 5,043,248         4,572,572        470,676                ‐                         

Material Testing 33,351               29,035              4,316                    ‐                         

Construction 5,437,915         5,425,796        12,119                  ‐                         

Construction Management  132,478            132,478           ‐                         

Campus Security 243,116            242,415           600                       101                   

Truck Driving School 99,200               99,200              ‐                         

Land 517,306            517,306           ‐                         

Energy  Services 8,860                 8,860                ‐                         

Design GEOTECH 5,189                 5,189                ‐                             ‐                         

Surveying 16,310               16,310              ‐                             ‐                         

Contracted Services 2,079,239         2,079,239        ‐                             ‐                         

Residual Funds for Completion of CIP Projects 1,555                 1,555                

Total  39,016,075$      37,933,863$    1,080,556$           1,656$               

Bond Issuance Cost:

Bond counsel fees 63,500$            

Underwriters' discount 342,526           

Insurance premium 498,600           

Financial advisory fee 95,105              

Rating agencies fees 47,100              

Printing costs 9,617                

CPA consent letter fee 463                   

Total 1,056,912$       

HOUSTON COMMUNITY COLLEGE SYSTEM 2008 Maintenance Tax Notes & Senior Lien Bonds

as of July 31, 2013

Fund 7203 

Fund 7203 ‐ Maintenance Tax Notes

34

Page 42: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances To 

Date Unexpended

Source:

2008 Senior Lien Bonds:

Southeast Workforce Project 14,300,000$     

  Emergency Preparedness 1,000,000        

Interest Earned To date 470,997           

Funds Available for Projects 15,770,997$     

Uses:

Operation and Maintenance 77,034               77,034              ‐                    

Major Repairs and Renovation 821,560            820,726           834                       ‐                    

South East Work Force Project 3,838,668         3,732,470        106,198                ‐                    

Land  Purchase (Rosalie Property) 2,314,967         2,314,967        ‐                    

Material Engineering and Testing 8,380                 4802 3,578                    ‐                    

Construction of Workforce Building 7,267,592         7,222,409        45,183                  ‐                    

Residual Funds for All Projects 1,442,796         1,442,796        

15,770,997$      14,172,408$    155,793$              1,442,796$       

Bond Issuance Cost:

Bond counsel fees 123,267$          

Underwriters' discount 336,128           

Insurance premium 620,827           

Financial advisory fee 100,981           

Rating agencies fees 51,750              

Printing costs 5,880                

Paying agent fee 460                   

Verification fee 5,000                

Escrow agent fee 4,600                

1,248,893$       

35

Fund 7308 ‐ Senior Lien Bonds

HOUSTON COMMUNITY COLLEGE SYSTEM 2008 Maintenance Tax Notes & Senior Lien Bonds

Fund 7308as of July 31, 2013

Page 43: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances To 

Date Unexpended

Central 

San Jacinto Memorial 21,391,231$      10,148,893      7,619,849            3,622,489$       

J.B. Whitely Bldg.  4,540,000         1,588,086        632,832                2,319,083        

Theater One 1,699,500         216,728           20,979                  1,461,793        

Staff Instructional Services 846,921            203,839           ‐                             643,082           

Curriculum Innovation Center 249,549            48,403              201,146                ‐                         

Fine Arts Parking Structure 190,000            171,082           5,100                    13,818              

Crawford Annex 68,200               18,138              ‐                             50,062              

Learning Hub/Science Bldg. 132,214            121,553           10,661                  ‐                         

Planned Parenthood Renovation 1,697,585         1,647,211        50,374                  ‐                         

  Total Central  30,815,200$      14,163,933$     8,540,942$           8,110,327$       

Northeast 

Automotive Tech. Training Ctr. 4,000,000$        669,400$          163,107$              3,167,493$       

Pinemont  66,558               39,237              ‐                             27,321              

Codwell Hall  438,000            376,108           55,067                  6,826                

Codwell Hall Shower (Temp) 150,000            ‐                        150,000           

Roland Smith Truck Driving Ctr.  140,000            54,406              ‐                             85,594              

Northline 120,000            34,602              2,235                    83,163              

Public Safety Institute 115,000            86,245              14,906                  13,849              

NE Science and Tech. Bldg 49,500               ‐                        49,500              

NE Learning Hub 47,500               6,309                ‐                             41,191              

  Total Northeast 5,126,558$        1,266,306$       235,314$              3,624,937$       

Southeast 

Angela Morales 599,000$           562,862$          616$                      35,521$            

Office City 38,500               ‐                        ‐                             38,500              

  Total Southeast 637,500$           562,862$          616$                      74,021$            

Southwest

Stafford Campus (7 Bldgs) 4,279,423$        4,212,447$       66,451$                 525$                  

Scarcella Center 890,339            448,740           183,491                258,108           

Alief 138,680            132,664           ‐                             6,016                

Academic Ctr Sienna Plantation 93,500               93,396              ‐                             104                   

Stafford Learning Hub 54,000               10,294              1,112                    42,594              

Applied Technology Center 50,000               1,715                ‐                             48,285              

Greenbriar Annex 30,000               22,033              ‐                             7,967                

  Total Southwest 5,535,942$        4,921,290$       251,054$              363,599$          

System

System Building  3,034,547$        2,179,517$       855,029$              ‐$                       

Teaching Enhancement Renovations 2,719,072         1,216,870        296,375                1,205,827        

Surface Parking & Civil Infrastructure 1,743,001         1,600,867        16,146                  125,988           

Parking Structure 2,403,380         2,294,506        108,874$              ‐                         

  Total System 9,900,000$        7,291,759$       1,276,425$           1,331,815$       

Grand Total 52,015,200$      28,206,150$    10,304,350$         13,504,699$     

HOUSTON COMMUNITY COLLEGE SYSTEM2010 Maintenance Tax Notes

as of July 31, 2013

36

Page 44: Fs2013 july

 

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

 Encumbrances 

To Date  Unexpended

Sources:

2011 Maintenance Tax Notes 40,000,000

Uses:

San Jacinto College Renovation

Construction 35,000,000$       18,958,784$      16,041,216$      ‐$                       

Architect & Engineering ‐                         ‐                         

Site Infrastructure Improvements ‐                         ‐                         

Inspection ‐                         

IT Infrastructure ‐                         ‐                         

Furniture ‐                         ‐                         

Contingency 5,000,000           5,000,000         

40,000,000$       18,958,784       16,041,216       5,000,000         

37

HOUSTON COMMUNITY COLLEGE SYSTEM2011 Maintenance Tax Notes: Fund 7207

As of  July 31, 2013

Page 45: Fs2013 july

  Total Budget to Date

Total Revenues /  

Expenditures To 

Date

 Encumbrances To 

Date  Unexpended

Sources:

2011A Maintenance Tax Notes 21,000,000

Uses:Alief ‐ Hayes Road 3,479,754$                 3,479,754$               

Architect & Engineering 1,208,820                   1,172,760                 36,060                        ‐                                  Construction 7,988,362                   6,207,884                 1,780,478                  ‐                                  Site Infrastructure Improvements 6,402                           6,402                         ‐                                   ‐                                  Material Testing 21,647                         16,795                      4,852                          IT Infrastructure 197,649                       ‐                                  197,649                      ‐                                  Inspection 163,318                       112,678                    50,640                        ‐                                  Furniture 934,049                       118,801                    815,248                      ‐                                  

14,000,000$               7,635,319                 2,884,927                  3,479,754                 

NE ‐ North ForestArchitect & Engineering 136,695                       104,536                    32,159                        ‐                                  Construction ‐                                  ‐                                   ‐                                  Site Infrastructure Improvements ‐                                  ‐                                   ‐                                  IT Infrastructure ‐                                  ‐                                   ‐                                  Furniture ‐                                  ‐                                   ‐                                  

136,695 104,536                    32,159                        ‐                                 

SW ‐ West Loop 2,575,591 2,575,591                 Architect & Engineering 13,000                         10,000                      3,000                           ‐                                  Construction 951,767                       524,174                    427,593                      ‐                                  Site Infrastructure Improvements ‐                                  ‐                                   ‐                                  IT Infrastructure ‐                                  ‐                                   ‐                                  Furniture ‐                                  ‐                                   ‐                                  Painting 262,257                       239,064                    23,193                        ‐                                  

3,802,616 773,238                    453,786                      2,575,591                 

SW ‐ Alief BissonnetArchitect & Engineering 186,225                       115,443                    70,782                        ‐                                  Construction 6,083                           ‐                                  6,083                           ‐                                  Site Infrastructure Improvements 5,076                           ‐                                  5,076                           ‐                                  IT Infrastructure ‐                                  ‐                                   ‐                                  Furniture ‐                                  ‐                                   ‐                                  

197,384 115,443                    81,941                        ‐                                 

SE ‐ Workforce BldgArchitect & Engineering 154,594                       129,211                    25,383                        ‐                                  Construction ‐                                  ‐                                   ‐                                  Site Infrastructure Improvements ‐                                  ‐                                   ‐                                  IT Infrastructure ‐                                  ‐                                   ‐                                  Furniture ‐                                  ‐                                   ‐                                  

154,594 129,211                    25,383                        ‐                                 

3100 Main System BldgArchitect & Engineering 10,000 6,000                         4,000                           ‐                                  Construction 376,316 269,779                    106,537                      ‐                                  Site Infrastructure Improvements ‐                                  ‐                                   ‐                                  IT Infrastructure ‐                                  ‐                                   ‐                                  Furniture 79,483 71,535                      7,948                           ‐                                  Painting 11,597 10,437                      1,160                           ‐                                  

477,396 357,751                    119,645                      ‐                                 

Contingency 2,231,315 2,231,315                 

Total Construction Cost 21,000,000$                9,115,498$                3,597,842$                 8,286,661$               

38

HOUSTON COMMUNITY COLLEGE SYSTEM2011A Maintenance Tax Notes: Fund 7208

As of  July 31, 2013

Page 46: Fs2013 july

DescriptionOriginal Bond

AmountPrincipal Payments Principal Balance

Principal & Interest FYE

2013

Revenue Bonds 255,830,000 (51,675,000) 204,155,000 23,689,199

Limited Tax Bonds 652,420,000 (143,700,000) 508,720,000 13,753,759

Maintenance Tax Notes 189,600,000 (22,225,000) 167,375,000 15,180,595

PFC Lease Revenue Bonds 126,595,000 (20,940,000) 105,655,000 8,957,391

1,224,445,000 (238,540,000) 985,905,000 61,580,944

Note: This schedule represents all bonds and maintenance tax notes with outstanding principal balances as of 7/31/13; previously retired debt issues are not shown

39

HOUSTON COMMUNITY COLLEGE SYSTEM

Summary Schedule of Bonds and Maintenance Tax NotesAs of  July 31, 2013

Page 47: Fs2013 july

Description Date Issued

Original Bond 

Amount

Principal 

Payments Principal Balance

Principal & 

Interest FY12

Final Due 

Date Call Dates

Foot‐

note

2005 Senior Lien Revenue/Refunding Bonds 04/15/05 51,285,000 (18,240,000) 33,045,000 6,676,363 04/15/20 04/15/15 (A)

2006 Junior Lien Revenue/Refunding Bonds 11/01/06 72,815,000 (18,885,000) 53,930,000 6,274,230 04/15/30 04/15/16 (A)  (B)

2008 Senior Lien Revenue Bonds 05/14/08 54,540,000 (7,810,000) 46,730,000 4,075,100 04/15/30 04/15/18 (A)

2010 Senior Lien Revenue Bonds 07/29/10 27,250,000 (1,775,000)        25,475,000 2,124,275 04/15/31 04/15/20 (A) 

2011 Junior Lien Revenue Refunding Bonds 03/10/11 33,940,000 (4,965,000)        28,975,000 4,150,431 04/15/25 04/15/21 (A)

2011T Senior Lien Revenue Bond 11/15/11 16,000,000 16,000,000 388,800           04/15/21 11/15/13 (A)

2003 Limited Tax Bonds 12/01/03 144,155,000 (143,700,000) 455,000 782,175 02/15/14 (C)

2011 Limited Tax Refunding Bonds 10/20/11 109,490,000 109,490,000 5,308,300 02/15/28 02/15/21 (C)

2013 Limited Tax General Obligation Bonds 03/19/13 398,775,000 398,775,000 7,663,284 02/15/43 02/15/15 (E)

2006 Maintenance Tax Notes 02/01/06 12,000,000 (3,165,000) 8,835,000 890,550 02/15/26 02/15/16 (C)

2008 Maintenance Tax Notes 03/01/08 54,975,000 (9,825,000) 45,150,000 4,171,426 02/15/28 02/15/18 (C)

2009 Maintenance Tax Notes 09/01/09 13,830,000 (2,200,000) 11,630,000 1,242,569 02/15/25 02/15/19 (C)

2010 Maintenance Tax Notes 07/29/10 47,645,000 (3,720,000)        43,925,000 3,998,400        02/15/29 02/15/20 (C)

2011 Maintenance Tax Notes 03/10/11 41,560,000 (2,645,000)        38,915,000 3,293,775 02/15/31 02/15/21 (C) 

2011A Maintenance Tax Notes 10/12/11 19,590,000 (670,000)           18,920,000 1,583,875 02/15/31 02/15/21 (C) 

PFC Series 2005A Lease Revenue Bonds 06/01/05 11,605,000 (2,880,000) 8,725,000 837,663 04/15/28 04/15/15 (A)

PFC Series 2005C Lease Revenue Bonds 12/01/05 19,155,000 (3,755,000) 15,400,000 1,313,456 04/15/30 04/15/15 (A)

PFC Series 2006 Lease Revenue Bonds 10/01/06 36,950,000 (6,290,000) 30,660,000 2,484,773 04/15/31 04/15/16 (A)  (D)

PFC Series 2007 Lease Revenue Bonds 02/01/07 58,885,000 (8,015,000) 50,870,000 4,321,500 04/15/31 04/15/17 (A) 1,224,445,000 (238,540,000) 985,905,000 61,580,944

Note: This schedule represents all bonds and maintenance tax notes with outstanding principal balances as of 7/31/13; 

             previously retired debt issues are not shown (i.e. 1997, 1998, 1999, 2001, 2001A, 2003 LTD, 2005 LTD)

Footnotes:

(A)  Funded from current operations, Fund 1110

(B)  Approximately $3.4 MM annually through 8/31/17 to be funded from student technology fees, Fund 8110; remainder from 

       current operations

(C)  Funded from real estate taxes, Fund 8300

(D) $1,329,772 of interest expense to be funded from real estate taxes

(E) Funded from capitalized interest

Schedule of Bonds and Maintenance Tax Notes

For the Month Ended July 31, 2013

Houston Community College

40

Page 48: Fs2013 july

3101‐3100 Main 

Leasing

**3102‐

Conference 

Training Center3103‐HCC‐TV 

Auxiliary

3105‐HCCS ‐ PFC 

Leasing **3110‐Auxiliary

3111‐ Auxiliary 

Student Services

3201‐Cafe Club 

NEO 3100 Main

3202‐Fitness 

Center‐Central

3204‐Heinen 

Theater

3207‐

International 

Initiatives

3208‐Saudi 

Consulting 

Services 3209‐Qatar Subtotal

Fund Balance 8/31/12 16,575,935$       (744,125)$         36,165$          898,968$           (6,225,160)$       (724,173)$           (1,362,924)$       (76,298)$           33,917               (82,495)               203,712             807,349        9,340,870        

FY2013 Revenue  4,878,918               81,840                   ‐                           19,862                   2,845,733               365                          469,942                   13,197                   21,885                   46,666                     6,526,299        14,904,707         

 Salaries  210,279                   7,335                     554,589                   252,263                   244,210                   597                         1,600                     4,000                       5,082,166        6,357,039            

 Benefits  53,620                     2,406                     108,400                   55,553                     55,998                     3                             911,614           1,187,595            

 Supplies Gen Exp  21,563                     26,789                   328,982                   7,394                       13,222                     7,870                     8,945                     6,485                       19,975             441,225               

 Travel  68,892                     71,427                     9,122                       57,253             206,694               

 Marketing Costs  412,441                   412,441               

 Rental & Leases  4,899                     39,790                     1,518                       46,207                 

 Contract Services  1,453,120               835,525                   850                         140,080           2,429,575            

 Utilities  360,774                   913                          361,687               

 Departmental Expenses  2,750                       3,868,792               270                         7,050                       598                   3,879,460            

 Instructional & Other Materials  600                          3,763                       213,092                   2,817                       220,273               

 Maintenance & Repair  3,551                       6,297                       1,245                     2,384                     13,477                 

 Insurance/Risk Mgmt  ‐                            

 Exemptions and Waivers  1,738                       150                          1,888                    

 Transfer  ‐                            

 Capital Outlay  792,309                   9,666                  306,234                   1,108,209            

 Total Expense  2,895,016               41,429                  9,666                  ‐                              6,532,698               386,637                  535,250                  9,715                     14,048                   29,624                     ‐                              6,211,685       16,665,770         

Contribution to Fund Balance 1,983,903           40,411              (9,666)             19,862               (3,686,965)          (386,272)             (65,308)               3,482                 7,837                 17,042                ‐                         314,614        (1,761,063)      

18,559,838         (703,714)           26,499            918,830             (9,912,125)          (1,110,446)          (1,428,233)          (72,816)             41,753               (65,454)               203,712             1,121,963    7,579,808        

*Restricted by limitations; must comply with laws, statues and regulations.

**Common Area Expense

41

HOUSTON COMMUNITY COLLEGE SYSTEMAuxiliary Budget By Fund

as of July 31, 2013

Auxiliary Funds*

Net Fund Balance 

Page 49: Fs2013 july

HOUSTON COMMUNITY COLLEGE SYSTEMAuxiliary Budget By Fund

as of July 31, 2013

3110‐ Student 

Vending 

Commission

3111‐Auxiliary 

Student 

Activities

3112‐Auxiliary 

Student Athletic 

Fee Subtotal Grand Total

Fund Balance 8/31/12 227,335            594,123          1,584,968         2,406,426           11,747,296        

FY2013 Revenue  120,099                1,106,272           887,951                 2,114,322               17,019,029        

 Salaries  10,730                   25,566                190,355                 226,651                   6,583,691          

 Benefits  68                        32,462                   32,530                     1,220,125          

 Supplies Gen Exp  40,523                   602,007              249,130                 891,660                   1,332,885          

 Travel  5,995                     72,387                67,089                   145,471                   352,166             

 Marketing Costs  ‐                                412,441             

 Rental & Leases  ‐                                46,207               

 Contract Services  1,800                     60,087                202,790                 264,677                   2,694,252          

 Utilities  ‐                                361,687             

 Departmental 

Expenses 

12,434                   19,130                9,820                     41,384                     3,920,844          

 Instructional & 

Other Materials 

‐                                220,273             

 Maintenance & 

Repair 

140                        140                          13,617               

 Insurance ‐ Risk 

Mgmt 

70                           1,327                  6,944                     8,341                       8,341                  

 Exemptions and 

Waivers 

12,484                   30,025                42,509                     44,397               

 Transfer  935,555                 935,555                   935,555             

 Capital Outlay  932                         932                          1,109,141          

 Total Expense  84,177                  810,597              1,695,077             2,589,851               19,255,620            

Contribution to Fund Balance 35,923              295,675          (807,126)           (475,529)             (2,236,591)         

263,258            889,798          777,842             1,930,897           9,510,705          

*Funds can only be used for services related to students

42

Net Fund Balance 

Student Auxiliary Funds ‐ Restricted*

Page 50: Fs2013 july

Federal Grantor Perform‐ Federal

Pass‐through Grantor ance CFDA Total Budget Total Award DeobligatedProgram Title Period Number Expenditures Amount Amount** Ends Starts Budget

U. S. Department of Education

Direct Programs:

Higher Education ‐ Institutional Aid 5 yrs. 84.031A 115,846            450,183             1,542,133         9/30/2014 10/1/2009

TRIO ‐ Student Support Services 5 yrs. 84.042 379,287            436,682             2,065,270         8/31/2015 9/1/2010

TRIO ‐ Upward Bound ‐ Southeast 4 yrs. 84.047 1,399                 16,669               1,172,562         ^^ 8/31/2012 9/1/2007 15,271          

TRIO ‐ Upward Bound ‐ Southeast 5 yrs. 84.047 256,493            291,335             1,465,615          8/31/2017 9/1/2012

TRIO ‐ Upward Bound ‐ Central 5 yrs. 84.047A 486,715            949,456             2,845,845         5/31/2017 6/1/2012

Astra Stem Grant 3 yrs. 84.120A 141,465            293,375             881,873            9/30/2014 10/1/2011

Vast Academy TPSID 5 yrs. 84.407A 407,456            862,617             2,498,250         9/30/2015 10/1/2010

Pass‐Through From:

Texas Educational Agency

Adult Education ‐ State Grant Program 1 yr. 84.002 4,772,875         5,508,680          5,542,104         *   9/15/2013 7/1/2012

Adult Education ‐ State Grant Program 1 yr. 84.002 116,451            128,780             128,780            *   9/15/2013 7/1/2012

University of St. Thomas

Higher Education ‐ Institutional Aid 5 yrs. 84.031C 687,421            870,174             3,243,025         9/30/2016 10/1/2011

 Texas Higher Education Coordinating Board 

Vocational Education ‐ Basic Grants to States 1 yr. 84.048 631,037            1,171,019          1,171,019         8/31/2013 9/1/2012

College Access Challenge Grant Program 1 yr. 4 mos. 84.378A 15,000              26,707               208,548            ^^ 8/31/2012 4/6/2011 11,707          

College Access Challenge Grant Program 1 yr.  84.378A 140,017            154,140             171,798            8/13/2013 8/14/2012

Total Department of Education 8,151,461$       11,159,817$      22,936,822$    

U.S. Department of Agriculture

Direct Programs:

Hispanic Serving Institutions Education Grants 2 yrs. 10.223 15,497              36,414               298,538            ^   8/31/2013 8/1/2009

Hispanic Serving Institutions Education Grants 2 yrs. 10.223 17,180              26,428               244,000            ^   8/14/2013 8/15/2010

    Hispanic Serving Institutions Education Grants 2 yrs. 10.223 119,239            135,610             445,000            ^   8/31/2013 9/1/2010

Hispanic Serving Institutions Education Grants 2 yrs. 10.223 115,329            202,726             245,000            8/31/2013 9/1/2011

Pass‐Through From:

Texas A & M University‐Corpus Christi 2 yrs 10.223 16,770              30,435               48,700              ^   8/31/2013 40,422         

Sam Houston State University 1,417                 39,264               39,264              8/15/2015 9/1/2012

Total Department of Agriculture 285,432$           470,877$            1,320,502$      

* Scholarship grants are not included in this schedule.

** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

^^ Grant is Over

43

HOUSTON COMMUNITY COLLEGE

as of July 31, 2013

Date Grant

Schedule of Federal Awards *

FY12 ‐ 13

Page 51: Fs2013 july

Federal Grantor Perform‐ Federal

Pass‐through Grantor ance CFDA Total Budget Total Award Deobligated

Program Title Period Number Expenditures Amount Amount** Ends Starts Budget

U.S. Department of Housing and Urban Development

Direct Programs:

Pass‐Through From:

Child Care Council of Greater Hous. Inc

Community Development Block Grant‐Entitlement Grant 1 yr 14.218 10,787              17,309               32,000              ^^12/31/12 8/1/2011 6,522             

Total Department of Housing And Urban Development 10,787$             17,309$              32,000$            

Department of Justice

Direct Program: Bulletproof Vest Partnership Program 1 yr‐cont. 16.607 ‐                          ‐                          11,078              until expended 9/1/2004

Total Department of Justice ‐$                        ‐$                        11,078$            

U.S. Department of Labor

DOL‐Logistics Technician Training 3yrs. 104,352$           159,097             327,404            12/31/2013 7/1/2010

Pass‐Through From:

Harris County Department of Education

Integrated Career Awareness 10 mos. 17.278 53,729 53,800 53,800 6/30/2013 8/1/2012

Counseling to Career 17.278 9,991 10,000 10,000 6/30/2013 2/1/2013

Texas Workforce Commission

Recovery ‐ WIA Dislocated Worker Formula Grant 1 yr. 17.278 10,261 61,804 243,163 ^^9/30/2012 7/1/2011 51,543          

Total Department of Labor 178,334$           284,701$            634,367$          

U.S. Department of State

Pass‐Through From:

Northern Virginia Community College 1 yr 19.009 74,580 73537.51 109830 41455 40976

Northern Virginia Community College 1 yr 19.009 5,447                 159,707             159,707            6/30/2014 7/1/2013

Total Department of State 80,027$             233,245$            269,537$          

U.S. Department of Transportation

Commerical Truck Driving Training 18 mos. 20.235 6,432                 175,529             175,529            3/31/2014 9/1/2012

Total Department of Transportation 6,432$               175,529$            175,529$          

* Scholarship grants are not included in this schedule.

** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

^^ Grant is Over

44

as of July 31, 2013

HOUSTON COMMUNITY COLLEGE

Schedule of Federal Awards *

Date Grant

FY12 ‐ 13

Page 52: Fs2013 july

Federal Grantor Perform‐ Federal

Pass‐through Grantor ance CFDA Total Budget Total Award Deobligated

Program Title Period Number Expenditures Amount Amount** Ends Starts Budget

Institute of Museum & Library Services

Pass‐Through From:

Texas State Library Archive Commission

Libraries for ALL 1 yr 45.310 25,859              75,000               75,000              8/31/2013 9/1/2012

Tex Share Mobile Project 1 yr 45.310 7500 7500 15000 41517 41310

Total Department of State 33,359$             82,500$              90,000$            

National Science Foundation

Direct Programs:

 Education and Human Resources 4 yrs. 47.076 55,702              64,204               491,728            ^5/31/2013 2/15/2009 8,502             

Pass‐Through From:

University of Houston System

Education and Human Resources 5 yrs. 47.076 40,983              47,212               190,000            8/31/2013 9/1/2011

Total National Science Foundation 96,685$             111,415$            681,728$          

U. S. Department of Energy

Energy Sector Grant (SECO) 8 mos 81.041 37,180              63,836 460,480 ^^9/30/2012 5/10/2010 26,656          

Solar Energy Technical Program 13 mos 81.087 194,657 591,069             750,000            12/30/14 11/1/2012

Pass Through From:

City of San Antonio 4.5 mos. 81.117

Energy Efficiency & Rene Energy Info Dissen Outrea,Train,&Tech Analy/Assist 14,465 15,000               15,000              02/14/13 9/1/2012 535                 

Total U. S. Department of Energy 246,302$           669,905$            1,225,480$      

U. S. Department of Health and Human Services

Direct Programs:

Head Start 5 yrs. 93.600 14,472 16,045               936,660            9/29/2013 9/30/2008

Head Start 5 yrs. 93.600 152,184 207,477             936,660            9/29/2013 9/30/2008

Pass‐Through From:

Texas Education Agency

Temporary Assistance for Needy Families 1 yr. 93.558 10,178              10,200               208,614            ^^8/31/2012 9/1/2011 22                   

Temporary Assistance for Needy Families 1 yr. 93.558 211,233            253,850             244,749            *  9/15/2013 9/1/2012

* Scholarship grants are not included in this schedule.

** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

^^ Grant is Over

45

as of July 31, 2013

FY12 ‐ 13

Date Grant

HOUSTON COMMUNITY COLLEGE

Schedule of Federal Awards *

Page 53: Fs2013 july

Federal Grantor Perform‐ Federal

Pass‐through Grantor ance CFDA Total Budget Total Award Deobligated

Program Title Period Number Expenditures Amount Amount** Ends Starts Budget

U. S. Department of Health and Human Services

YMCA of Greater Houston

Refugee and Entrant Assistance ‐ Targeted Assistance Grants 1 yr. 93.584 19,869              82,578               374,938            ^^9/30/2012 10/1/2011 62,709          

Refugee and Entrant Assistance ‐ Targeted Assistance Grants 1 yr. 93.584 255,125            342,105             342,105            9/30/2013 10/1/2012

Pitt Community College

Health Information Tech Professionals 2 yrs. 93.721 348,218            490,362             1,287,568         9/30/2013 4/2/2010

University of Texas at Austin

Block Grant‐Prevent & Treatment of Substance Abuse 1 yr. 93.959 12,730              22,000               22,000              9/30/2013 9/29/2012

Total Department of Health and Human Services 1,024,010$       1,424,617$        4,353,294$      

U. S. Department of Homeland Security

Direct Programs:

 Homeland Security 2 yrs. 97.062 16,497              58,856               250,000            ^^12/31/12 9/1/2010 42,359          

Total Department of Homeland Security 16,497$             58,856$              250,000$          

Total  Federal Financial Assistance 10,129,325$     14,688,771$      31,980,336$    

* Scholarship grants are not included in this schedule.

**Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

^^ Grant is Over

as of July 31, 2013

FY12 ‐ 13

Date Grant

46

HOUSTON COMMUNITY COLLEGE

Schedule of Federal Awards *

HOUSTON COMMUNITY COLLEGE

Schedule of Federal Awards *

as of July 31, 2013

Page 54: Fs2013 july

Perform‐

ance Total Budget Total Award Deobligated

Program Title ‐ State Grantor Period Expenditures Amount Amount** Ends Starts Budget

Texas Education Agency

Adult Education 1 yr. 24,618$             24,615$              1,165,635$       ^^  8/31/2012 9/1/2011 (3)                    

Adult Education 1 yr. 1,223,433         1,292,271          1,165,635         *  9/15/2013 9/1/2012

Drop‐Out Recovery Performance Pay 1 yr. 58,433              94,334               181,784            until expended 6/1/2010

Temporary Assistance for Needy Families 1 yr. 16,311              16,869               111,445            ^^  8/31/2012 9/1/2011 558                 

    Temporary Assistance for Needy Families 1 yr. 106,768            122,182             131,283            8/31/2013 9/1/2012

       Total Texas Education Agency 1,429,562$       1,550,271$        2,755,782$      

Texas Higher Education Coordinating Board

Adult Basic Education Innovation Grant 1 yr. 155,110$           158,314             500,000            8/31/2013 9/1/2012

Collegiate G‐Force Mentorship 1 yr. 17,856              27,148               50,000              8/31/2013 9/1/2009

First Year Experience 13 mos. 5,577                 8,709                  50,000              until expended 7/18/2011

HPI 1 yr. 7,200                 10,000               10,000              8/31/2013 9/1/2012

Nursing Shortage Reduction Program 4 yrs. 37,147              112,280             157,314            8/31/2014 9/1/2010

Nursing Shortage Under 70 Program 1 yr. 72,564              383,891             383,891            8/31/2013 9/1/2012

Rider 58 ATCP School Grant 8 1/2 mos. 4,800                 13,960               46,360              until expended 12/18/2009

Pass‐Through From:

University of Tex Health Science Center

Navigator Grant 1 yr. 30,466              51,452               129,195            ^^11/30/2012 6/1/2011 20,986          

       Total Texas Higher Education Coordinating Board 330,720$           765,754$            1,326,760$      

Texas Workforce Commission

Skills Development ‐ Skills for Small Business Initiatives 1 yr. 410                    18,791               20,000              5/31/2014 6/1/2012

Ben E Keith Co. 1 yr. 60,626              103,469             103,469            2/28/2014 2/11/2013

The Methodist 14 mos. 519,266            902,965             902,965            10/31/2013 8/20/2012

TSTC TYCO 12 1/2 mos. 7,138                 236,633             236,633            2/28/2014 2/11/2013

VITAS 13 mos. 56,500              389,051             389,051            4/30/2014 3/1/2013

Pass‐Through From:

       Total Texas Workforce Commission 643,940$           1,650,909$        1,652,118$      

Total State Financial Assistance 2,404,222$       3,966,934$        5,734,660$      

* Scholarship grants are not included in this schedule.** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension^^ Grant is Over

47

Date Grant

as of July 31, 2013

Schedule of State Awards *

FY12 ‐ 13

HOUSTON COMMUNITY COLLEGE

Page 55: Fs2013 july

Deobligated

Program Title ‐ Private Grantor Period Expenditures Budget Award Amount** Ends Starts Budget

Achieving the Dream ‐ Initiative 1 yr.‐cont. ‐                          9,433                  20,000              until expended 12/1/2009

Achieving the Dream ‐ Gates Foundation 3 yrs. 195,658            262,135             743,000            ^^12/31/2012 7/1/2009 66,478          

Adult Education/We Can Work 1 yr. ‐                          ‐                          11,500              until expended 1/1/2010

American Chemical Society 8 mos 177                    248                     500                    until expended 9/1/2011

AT&T High School Success Grant 1 yr. 7 mos. ‐                          25,216               35,000              until expended 1/31/2010

Bank of America  2 yrs. ‐                          316                     50,000              until expended 5/1/2008

Baylor Summer Interns 1 yr. ‐                     1,638                  60,000              until expended 5/1/2010

Brown Foundation 1 yr.‐cont. ‐                     ‐                          100,000            until expended 2/1/2008

Capital Idea project 1 yr. 115,410            73,794               341,000            until expended 8/1/2010

Carnegie FDTN 1 yr 15,599              30,901               67,500              until expended 1/1/2012

Citibank ‐ College Connection Program 1 yr. 3,433                 20,475               41,718              until expended 8/15/2007

Civic Ventures 1 yr. 1 mo. 1,233                 1,246                  25,000              until expended 7/1/2010

Dow Male Minority Initiative Summer Prog. 1 yr. ‐                     12,588               23,986              until expended 1/2/2012

Early College High School (Southeast) ‐ Gates/Dell 5 yrs. ‐                          6,779                  400,000            until expended 6/10/2005

Financial Empowerment Strat. Student Success 2 yrs. 28,413              60,808               63,050              12/31/2013 1/1/2012

Goldman Sachs Grant ‐ Phase I 5 yrs. 1,104,517         1,955,011          1,955,011         5/31/2016 1/3/2011

Gulf Coast Pass 3 yrs. 268,188            602,625             1,175,000         12/31/2014 1/1/2012

Hammill FDTN ‐ Veterans Grants 2 yrs. ‐                          11                      18,191              until expended 9/1/2010

Houston Endowment Grant 3 yrs. ‐                          814                     267,000            until expended 11/16/2005

Houston Pathways Initiative 2 yrs. 121,503            345,471             1,580,000         8/31/2013 3/26/2009

Interlocal Metro (PSI) 10 yrs. ‐                          45,000               200,000            8/23/2017 8/23/2008

Interlocal Stafford ‐ City of Stafford 1 yr. 64,000              161,986             161,986            until expended 10/1/2010

KBR Veterans Orientation 1 yr.‐cont. ‐                          5,540                  19,685              until expended 9/1/2008

Kresge Fdtn‐Coordinator/Evaluation 1 yr. 56,090              72,187               82,450              until expended 9/1/2011

Kresge Fdtn‐Parent Academy 1 yr. 50,962              89,881               89,881              until expended 9/1/2011

Kresge Fdtn‐Veterans Grant 1 yr. 89,547              136,698             136,698            until expended 9/1/2011

MDRC ‐ Learning Community Demonstration Grant ‐ Northeast 4 yrs. ‐                          26,495               60,233              until expended 11/1/2007

MDRC ‐ Learning Community Demonstration Grant ‐ Southeast 4 yrs. ‐                          738                     75,000              until expended 11/1/2007

MDRC ‐ Learning Community Demonstration Grant ‐ Central 4 yrs. ‐                          385                     33,000              until expended 11/1/2007

Metlife Caregiving for Older Americans 1 yr.‐cont. ‐                          18,012               23,855              until expended 7/1/2007

Microsoft Elevate America 1 yr. 3,261                 31,985               34,969              until expended 3/20/2012

* Scholarship grants are not included in this schedule.

**Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

^^ Grant is Over

48

FY12 ‐ 13

HOUSTON COMMUNITY COLLEGE

Schedule of Local Government and Private Awards *

as of July 31, 2013

Page 56: Fs2013 july

Deobligated

Program Title ‐ Private Grantor Period Expenditures Budget Award Amount** Ends Starts Budget

Mobile Go Center ‐ Valero 1 yr.‐cont. ‐                          494                     7,293                 until expended 9/1/2007

National Articulation & Transfer Network Council(NATN) 1 yr.‐cont. ‐                          29,273               29,273              until expended 4/1/2005

North Forest GED Preparation 3 mos 330                    6,799                  25,000              until expended 10/1/2011

St. Luke's Episcopal Health Charities Immunization Fellowship 2 yrs. ‐                          4,178                  142,650            until expended 9/10/2008

Susan B Komen Breast Cancer Initiative 1 yr. ‐                          6,610                  123,230            until expended 4/1/2010

Texas Pioneer Foundation Grant 1 yr. 846                    22,851               23,117              8/31/2013 1/26/2012

TG‐ATD Texas Peer Coaching 1 yr. 9,998                 10,000               10,000              8/31/2013 9/1/2012

THECB_TG‐T‐STEM Challenge Scholarship Program 20 mos. 44,218              323,700             323,700            1/31/2015 5/1/2013

Vast Job Developer 1 yr. 9,304                 20,299               94,898              until expended 11/1/2009

Verizon Foundation Grant 1 yr. ‐                          510                     12,510              until expended 1/1/2010

Verizon‐Simmons CAST 14 mos. 2,665                 12,500               12,500              12/18/2013 10/12/2012

Walmart ‐ Minority Male Initiative 1 yr. ‐                          25,215               40,000              until expended 9/1/2009

Washington Mutual 1 yr.‐cont. 2,740                 16,717               31,700              until expended 9/1/2006Total Private Financial Assistance 2,188,090$       4,477,563$        8,771,085$      

* Scholarship grants are not included in this schedule.

**Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

^^ Grant is Over

49

         HOUSTON COMMUNITY COLLEGE ‐ Schedule of Local Government and Private Awards *

Schedule of Local Government and Private Awards * continued

as of July 31, 2013

FY12 ‐ 13

Page 57: Fs2013 july

Salary

CHANCELLOR97,613$

51,923$

70,469$

70,469$

46,448$

46,000$

46,000$

45,000$

46,000$

55,000$

55,000$

50,000$

45,555$

71,761$

58,000$

39,900$

96,000$

75,000$

60,000$

62,000$

92,834$

50,000$

22     1,330,972$       

DEPUTY CHANCELLOR45,857$

45,857$

45,857$

48,150$

24,473$

25,000$

24,473$

24,473$

27,000$

61,074$

45,746$

39,504$

66,578$

34,908$

34,908$

37,943$

65,540$

49,500$

169,195$

142,503$

48,806$

New Postions

Houston College Community Systems

2012‐2013 Positions

Employee Name Department Job Title Comments Month

Wanda Pleasant Procurement Sr. Buyer

Alfred Kessellie, II Procurement Supervisor New Position‐Budget 12‐13‐Hired External Nov

Kerry Doucette Procurement Supervisor New Position‐Budget 12‐13‐Hired External Nov

New Position‐Budget 12‐13‐Hired External Nov

50

Michael Schurwon Procurement Sr. Buyer New Position‐Budget 12‐13‐Hired External Jan

Barlett Sheinberg Resource & Economic Dev Interim Dir., Resource & Economic Dev New Position‐Budget 12‐13‐Hired Internal Sep

Thomas Richardson Procurement Buyer New Position‐Budget 12‐13‐Hired External Nov

Mimi Lemmons Procurement Sr. Buyer New Position‐Budget 12‐13‐Hired External Nov

Andrea Stroller Foundation Alumni Specialist New Position‐Budget 12‐13‐Hired External Nov

Freddy Conde Procurement Buyer New Position‐Budget 12‐13‐Hired External Nov

Armand Villacorte Procurement Sr. Buyer New Position‐Budget 12‐13‐Hired External Jan

Reginald Harmon Procurement Sr. Buyer Repl Sheila Perla‐Hired External Nov

Victor Camargo Business Services Inventory Control Supervisor New Position‐Budget 12‐13‐Hired External Nov

Christopher Burton Procurement Dir., Procurement Operations Repl Jeffery Bonnardel‐Hired External Apr

Ching Hua Procurement Sr. Buyer New Position‐Budget 12‐13‐Hired External Mar

Olivia Harris Records Retention Records Retention Technician New Position‐Budget 12‐13‐Hired External Apr

Sharon Flowers General Counsel Legal Assistant New Position‐Budget 12‐13‐Hired External Feb

Sandra Garica General Counsel Assistant General Counsel I Repl Jessica Saldivar‐Hired External Mar

Beatrice Emanuel‐Sims Foundation Coordinator, Dev Workforce New Position‐Budget 12‐13‐Hired External Jul

Cydney Peters Foundation Interim Executive Director Repl Kelly Zuniga‐Hired Internal Jul

Susana Rodriquez Internal Audit Sr., Internal Auditor New Position‐Budget 12‐13‐Hired External May

Frank Khan Internal Audit Internal Auditor New Position‐Budget 12‐13‐Hired External May

Severin Zindler Procurement Buyer Repl Wanda Pleasant‐Hired External Jul

1        New Position‐External 15     Interim 1        

Edwin Johnson Police Department Corporal Repl Anthony Maxie‐Hired Internal Sep

Chancellor Replacement‐Internal 1        Replacement‐External 4        New Position‐Internal

Shirley Voisin Police Department Corporal New Position‐Budget 11‐12‐Hired Internal Sep

My'Keshia Robinson Police Department Security Officer Repl Victor Fisher‐Hired External Oct

Tobin Anderson Police Department Corporal Repl Timothy Ramirez‐Hired Internal Sep

Navidad Martinez Police Department Corporal New Position‐Budget 11‐12‐Hired Internal Sep

James Lindsey Police Department Security Officer Repl Grayland Jones‐Hired External Oct

Antonio Hill Police Department Security Officer Repl Kenneth Bridges‐Hired External Oct

Ules Harris Police Department Security Officer Repl Majid Iqbal‐Hired External Oct

Katherine McCabe Police Department Security Officer Repl Willie Rostan‐Hired External Oct

Maria Alarcon Accounts Payable Accounting Specialist Repl Norma Jackson‐Hired Internal Oct

Manhal Chbat QEP Instructor New Position‐Hired Internal Jan

Patricia Thompson HR‐Compensation Manager Repl John Chen‐Hired External‐Temp Oct

Aracelia Saucedo Business Affairs Executive Secretary Repl Alice Binkley‐Hired Internal Oct

Bapakaye Tamuno Police Department Police Trainee New Position‐Budget 12‐13‐Hired External Nov

Shirley Parish Human Resources Interim HRIS Manager Repl Tasharra Pickens‐Hired Internal Nov

Jeremy Hardeway Police Department Police Trainee New Position‐Budget 12‐13‐Hired External Nov

Keith Harris Police Department Police Trainee New Position‐Budget 12‐13‐Hired External Nov

Karen Edwards Human Resources Interim Chief HR Officer Repl Willie Williams‐Hired Internal Jan

William Thomson Student Financial Svs Accountant II New Position‐Budget 12‐13‐Hired Internal Feb

Brittany Kaighen HR‐Payroll Payroll Support Specialist Repl Juanita Mei‐Hired External Jan

Willie Williams Deputy Chancellor VC, Administrative Special Projects New Position‐Hired Internal Jan

Page 58: Fs2013 july

Salary

Houston College Community Systems

2012‐2013 Positions

Employee Name Department Job Title Comments Month

DEPUTY CHANCELLOR continued47,492$

37,943$

142,000$

32,500$

66,130$

101,000$

38,000$

85,680$

37,943$

66,130$

51,132$

55,000$

61,074$

31,579$

37,740$

43,174$

86,621$

45,857$

45,857$

45,857$

50,953$

50,953$

50,953$

50,953$

47,000$

86,621$

70,469$

23,600$

34,908$

34,908$

40,979$

52     2,808,351$       

VICE CHANCELLOR INSTRUCTION52,423$

41,427$

53,320$

43,557$

36,220$

52,000$

35,000$

43,174$

48,010$

35,982$

34,500$

64,500$

New Postions

51

Maya Durnovo Economic Dev & Entrep AVC, Economic Dev & Entrep. Initiatives New Position‐Budget 12‐13‐Hired Internal Feb

Alobidey Mohammed Broadcasting  Media Videographer Repl Joseph Smith‐Hired External Feb

Delphine Campbell Student Financial Svcs Accountant II New Position‐Budget 12‐13‐Hired Internal Feb

Hector Silva Police Department Peace Officer Repl Tobin Anderson‐Hired External Feb

Shante Kelley Business Affairs Accounting Specialist Repl Polly Cooper‐Hired Internal Feb

Lesa Spivey Community Relations Dir, Community Relations & Small Bus. Dev New Position‐Budget 12‐13‐Hired Internal Feb

Jonathan Brook Police Department Lieutenant New Position‐Budget 10‐11‐Hired External Feb

Ricardo Solis Economic Development Exec. Dir of Economic Development New Position‐Budget 12‐13‐Hired External‐Temp Feb

Alden Tiggs Audio Visual AutoCAD Specialist Repl Alden Tiggs‐Hired External Apr

James Leftwich  Office Fiscal Planning & Budgeting Sr., Financial Analyst Repl Dawn Wilton‐Hired External Apr

Samoan Scott Police Department Peace Officer Repl Edwin Johnson‐Hired External Mar

Alfred Postel Police Department Lieutenant Repl James Young‐Hired Internal Mar

Gisselia Torre Business Affairs Accounting Specialist Repl Delphine Campbell‐Hired Internal May

Mary Hinojosa Grant Accounting Specialist Repl Kathy Chapnick‐Hired Internal Jun

Diana Sanders Communications Interim, Dir., Public & Media Relations Repl Lesa Spivey‐Hired Internal Apr

Roy Castleberry Business Services Distribution Rep II Repl Elbert Newsome‐Hired External Apr

Demitra Thompson Police Department Corporal Repl Tobin Anderson‐Hired Internal Jul

David Quan Police Department Corporal Repl Lawrence Wheeler‐Hired Internal Jul

Christopher Bourne Communications Interim Dir., HCCTV Repl Debra Mcgaughery‐Hired External Jun

Louis Ybarra Police Department Corporal Repl Shirley Voisin‐Hired Internal Jul

Lawrence Wheeler Police Department Peace Officer Sr. New Position‐Budget 12‐13‐Hired Internal Jul

Edwin Johnson Police Department Peace Officer Sr. Repl Alfred Postel‐Hired Internal Jul

Shirley Voisin Police Department Peace Officer Sr. New Position‐Budget 12‐13‐Hired Internal Jul

Tobin Anderson Police Department Peace Officer Sr. New Position‐Budget 12‐13‐Hired Internal Jul

Elizabeth Semien Human Resources Human Resource Generalist Sr. Repl James Mitchell‐Hired External Jul

Benjamin Portillo Facilities Campus Service Technician Repl Michael Collins‐Hired External Jul

Viola Poinsette Police Department Police Coordinator Repl Cindy Lee‐Hired External Jul

Christopher Bourne Communications Interim Dir., HCCTV Repl Debra McGaughey‐Hired External Jul

Landon Davis Police Department Peace Officer Repl David Quan‐Hired External Jul

April Pikes Police Department Police Trainee New Position‐Budget 12‐13‐Hired External Jul

Joshua Phillips Police Department Police Trainee New Position‐Budget 12‐13‐Hired External Jul

Kimberly Davis Instructional Instructional Designer New Position‐Hired External Oct

Scott Godley Workforce Initiatives Program Manager Repl Deshaunta Stewart‐Hired Internal Oct

New Position‐Internal 11     New Position‐External 8        Interim 2        Deputy Chancell Replacement‐Internal 13     Replacement‐External 18    

Latrish Tarhini DOEL English Language Skills Instructor New Position‐Budget 12‐13‐Hired External Nov

Jesse Shelton TLR Instructional Designer New Position‐Budget 12‐13‐Hired External Nov

Somaye Najafi‐Shostari ESL English Language Skills Instructor New Position‐Budget 12‐13‐Hired External Oct

Manuel Ramos DOEL English Language Skills Instructor New Position‐Budget 12‐13‐Hired External Nov

James Heironimus Police In‐Service Instructor New Position‐Budget 12‐13‐Hired External Jan

Anamaria Lopez Opeerations of CTCE Financial Aid Associate Repl Shanetta Burke‐Hired Internal Feb

Israel Salazar Distance Education Advisor New Position‐Budget 12‐13‐Hired External Nov

Touhid Chowdhury Distance Education Advisor New Position‐Budget 12‐13‐Hired Internal Dec

Marion Davis Business Dvlp&Outreach Student Recruiter Repl Scott Godley‐Hired External Feb

Thomas Tynan Continuing Education Director Program Construction Repl Fred Woolridge‐Hired External Feb

Page 59: Fs2013 july

Salary

Houston College Community Systems

2012‐2013 Positions

Employee Name Department Job Title Comments Month

VICE CHANCELLOR INSTRUCTION continued32,538$

101,000$

35,000$

35,000$

45,967$

47,743$

48,000$

35,000$

20     

920 361$VICE CHANCELLOR STUDENT SUCCESS

65,000$

38,000$

39,960$

37,000$

35,500$

37,000$

34,374$

27,165$

34,374$

45,546$

40,000$

40,000$

34,006$

34,374$

117,300$

35,676$

43,321$

17     

738,596$          

VICE CHANCELLOR INFORMATION TECHNOLOGY61,074$

60,000$

63,240$

114,000$

48,000$

67,002$

59,382$

52,200$

53,013$

61,074$

65,000$

11     

703,985$          

New Postions

52

Exec. Dir of International Initiatives FebRicardo Solis International Initiatives See Original hire on Deputy Chancellor (Title Change)

Patricia Hernandez Academic Resource Dev Secretary II New Position‐Budget 12‐13‐Hired Internal Feb

Shirley Santibanez SCE CE Records Specialist Repl Rosa Huerta‐Hired External Mar

Mekussa Martinez  Operations CTCE Operations Compliance Specialist Repl Karmesha Sargent‐Hired External Feb

Latash Hussey Distance Educational  Systens Administrator I Repl Feliciano Arrazolo‐Hired External Jul

Blanca Perez Operations of CTCE CE Records Specialist Repl Anamaria Lopez‐Hired Internal (Grant) Jul

Veronica Medina Research & Inn Research Analyst I, Data Warehouse Repl Hazel Milan‐Hired Internal Apr

Linh Tran Instructional Executive Secretary Repl Gail Beach‐Hired Internal Apr

‐         New Position‐External 10     Interim ‐         

Paul Donaldson Outreach & Student Dev Dir., Outreach & Student Development Repl Shantay Grays‐Hired External Sep     

VC Instr Replacement‐Internal 5        Replacement‐External 5        New Position‐Internal

Randi Sprouse Registrar Transcript Evaluator New Position‐Hired External Oct

Leslie Dye Registrar Transcript Evaluator New Position‐Hired External Oct

Larke Clishe Student Information Svcs Advisor Repl Laura Collins‐Hired External Sep     

Henry Thomas Registrar Transcript Evaluator New Position‐Hired External Oct

Kevin Lacey International Student Recording Imaging New Position‐Budget 12‐13‐Hired Internal‐Temp Nov

Cassandra Millhouse Financial Aid Financial Aid Associate Repl Victoria Thomas‐Hired Internal‐Temp Nov

Mona Terrell Registrar Transcript Evaluator New Position‐Hired External Oct

Ashley Martin VA/Student Support Svcs Advisor New Position‐Budget 12‐13‐Hired Internal Nov

Leila Abdullahi International Student DSO/Advisor New Position‐Budget 12‐13‐Hired External Jan

Clairta Duron Student Information Svcs Student Information Representative New Position‐Budget 12‐13‐Hired Internal Jan

Liliana Silva Admissions Student Records Specialist New Position‐Budget 12‐13‐Hired Internal Dec

Gabrielle Kay International Student DSO/Advisor New Position‐Budget 12‐13‐Hired External Jan

Delbert Adivnovak International Student Office Manager Repl Gail Battiest‐Hired Internal Jul

Constance McDaniel Financial Aid Financial Aid Coordinator Repl Letricia Gallegos‐Hired External Jul

Tamara Jones Advisor Online Student Services Repl Helen McMillan‐Hired External‐Temp Jan

JoEllen Soucier Financial Aid Executive Director of Financial Aid Repl Scott Moore‐Hired External Jul

New Position‐Internal 4        New Position‐External 6        Interim ‐         VCSS Replacement‐Internal 1        Replacement‐External 6       

Katie Herod System Support Sr. Network Analyst New Position‐Hired Internal‐Temp Jan

Bieu Nguyen Administrative Services Director, Administrative Services Repl Celia Gee‐Hired External Feb

Wanda Taft Application Dev System Analyst Repl David Lin‐Hired Internal Sep

Hazel Milan Inst Research & Innovation Research Analyst II‐Special Projects Repl Emily Leffler‐Hired Internal Oct

LaMont Humphrey Communications Multi‐Media Coordinator New Position‐Hired Internal Apr

Ijeoma Ezebuilo Application Dev Business Analyst II Repl Wanda Taft‐Hired External Apr

Demeita Johnson Administrative Services Contract Analyst Repl Amando Jasso‐Hired External  Apr

Kimberly Monroe Application Dev Sr. Programmer Analyst/PS Student Repl Zulma Alvarado‐Hired Internal Apr

Swetha Ennamuri Application Dev Sr. Programmer Analyst  Repl Jordan Nguyen‐Hired External Jul

Karmesha Sargent Application Dev Business Analyst II Repl Juan Medrano‐Hired Internal May

Melissa Anderson Application Dev Sr., Business Analyst PS Student Repl Maria Garica‐Hired Internal Jun

New Position‐Internal 2        New Position‐External 1        Interim ‐         VCIT Replacement‐Internal 5        Replacement‐External 3       

Page 60: Fs2013 july

Salary

Houston College Community Systems

2012‐2013 Positions

Employee Name Department Job Title Comments Month

CENTRAL82,681$

45,555$

56,000$

34,996$

48,954$

25,513$

28,000$

58,077$

41,839$

34,374$

55,000$

45,000$

36,000$

77,794$

14     

669,783$          

NORTHWEST41,447$

44,339$

53,244$

31,312$

27,709$

44,615$

41,004$

43,469$

39,270$

41,004$

43,469$

34,374$

27,165$

38,678$

35,053$

38,300$

43,452$

39,960$

35,000$

35,000$

38,000$

39,000$

35,780$

45,008$

58,255$

42,631$

38,000$

101,501$

33,000$

New Postions

53

Dora Whiteside Student Services ADA Counselor New Position‐Hired External Oct

James Connery Construction Instructor Repl Johnny Watson‐Hired External‐Temp Oct

Jason Wilson Student Services Interim Dean of Student Dev Repl Cheryl Johnson‐Hired Internal Sep

Sonya Sneed Student Services Student Life Coordinator Repl Danny Smith‐Hired External Oct

Saqueena Sutton Child Care Child Care Specialist II Repl Kinaya Palmer‐Hired Internal Jan

Erica Hubbard Library Librarian Repl Marcia Braun‐Hired Internal Jan

Brigid Wilson VAST Instructor Repl Frank Colmenero‐Hired External Nov

Rodney Sam Library Library Assistant I Repl Marion Kennedy‐Hired External Jan

Senta Eastern Counseling Counselor Repl Dora Whiteside‐Hired External Feb

Karl Mayes Student Services Advisor Repl Mirna Romero‐Hired External Mar

Kevin Hamby Interior Design Instructor Repl Benjamin Johnston‐Hired External Jan

Isabel Zamora Student Services Financial Aid Associate Repl Maria Dabrowski‐Hired Enternal Feb

Meishon Bell Student Services Advisor Repl Touhid Chowdury‐Hired External Mar

Debra McGaughey Public Relations Director of Public Relations Repl Lamont Humphrey‐Hired Internal Apr

‐         New Position‐External 1        Interim 1        

Eva Foster English Instructor Repl Joaquin Torres‐Hired External‐Temp Sep 

Central Replacement‐Internal 2        Replacement‐External 10     New Position‐Internal

Anika Chowdhury COO Cashier II Repl Stella Villarreal‐Hired External‐Temp Sep 

Sandra Brooks Admissions Enrollment Service Assistant Repl Makeba Brown‐Hired External‐Temp Sep 

Steven Cohan Biology Instructor Repl Manhal Chbat‐Hired External‐Temp Sep 

Nellie Bradley Public Relations Director of Public Relations Repl Kimberly Crocker Montgomery‐Hire External‐Temp Sep 

Natalia Noland English Instructor New Position‐Budget 12‐13‐Hired External Oct

Christine Moore Student Services Senior Advisor New Position‐Budget 12‐13‐Hired Internal Oct

Rima Adil COO Community Outreach Coordinator Repl Nellie Bradley‐Hired Internal‐Temp Sep 

Anthony Hilliard Fine Arts Instructor Repl Bonnie Gallup‐Hired External‐Temp Oct

Laleh Golestani Instruction‐Testing Testing Associate Repl Rima Adil‐Hired External‐Temp Oct

Lusinda Eshelman Student Services Enrollment Service Assistant Repl Carlana Brooks‐Hired External‐Temp Oct

Paul Brady Accounting Instructor Repl Mallikarjun Shintri‐Hired External‐Temp Oct

Vimlarani Chopra Biology Instructor Repl Ida Huard‐Hire External Dec

Sherin Isaac Student Services Advisor Repl Laura Wilborn‐Hired External Nov

Goddrick Austin Student Services Senior Advisor New Position‐Budget 12‐13‐Hired Internal Nov

Bharat Sutaria Engineering Instructor New Position‐Budget 12‐13‐Hired External‐Temp Oct

Thomas Tankersley Technician Services Hardware/Software Technician Repl Samuel Sannl‐Hired External Oct

Pamela Walls Student Services Advisor New Position‐Budget 12‐13‐Hired Internal Nov

Jaime Flores Student Services Advisor New Position‐Budget 12‐13‐Hired Internal Nov

Sherhonda Le Financial Aid Financial Aid Associate Repl Diane Wilborn‐Hired External Nov

Courtney Martinez Public Relations Student Recruiter New Position‐Budget 12‐13‐Hired Internal Nov

Corey Aeck Student Services Advisor New Position‐Budget 12‐13‐Hired Internal Nov

Manhal Chbat Biology Instructor Repl Steven Cohan‐Hired Internal Dec

Contrice Kendall Student Services Advisor New Position‐Budget 12‐13‐Hired Internal Nov

Olivia Blake COO  Secretary II Repl Adriana Jimenez‐Hired External Nov

Mark Tiller Student Services Associate Dean, Instruction New Position‐Budget 12‐13‐Hired Internal Jan

Walter Oduk Technician Services Hardware/Software Technician Repl Joseph Ogbechie‐Hired External Jan

Eva Foster English Instructor Repl James Bishop‐Hired External‐Temp Jan

Fidel Simmons Student Services Advisor New Position‐Budget 12‐13‐Hired External Jan

Page 61: Fs2013 july

Salary

Houston College Community Systems

2012‐2013 Positions

Employee Name Department Job Title Comments Month

NORTHWEST continued30,500$

43,469$

34,374$

27,708$

79,112$

89,364$

43,469$

34,374$

44,615$

39,171$

30,153$

35,000$

27,165$

44,615$

42,613$

35,276$

34,374$

37,074$

47     

$ 1 961 465NORTHEAST

99,000$

38,344$

40,124$

48,010$

37,981$

47,085$

37,061$

45,762$

38,415$

31,312$

38,000$

35,982$

38,678$

41,810$

52,200$

43,544$

36,791$

40,214$

41,004$

60,000$

27,165$

55,000$

21,500$

34,374$

42,018$

25     

New Postions 1,071,374$       

54

Deborah Adesokan Counseling Advisor Repl Christine Battle Moore‐Hired External‐Temp Jan

Sandra Brooks Student Services Enrollment Service Assistant Repl Augie Sanchez‐Hired Internal Jan

Shahrooz Torkian Far Technician Services Hardware/Software Technician Repl Pradip Patel‐Hired External Jan

Gina Calderone Philosophy Instructor Repl Thomas Urban Hired External‐Temp Jan

Richard Mottram English Instructor Repl Betty Shine‐Hired External‐Temp Mar

Brandon Davidson Student Services Advisor New Position‐Budget 12‐13‐Hired External Mar

Evelyn Velasquez Workforce Development Interim Dean, Workforce Repl Maya Durnovo‐Hired Internal Feb

Robert Harris Student Development Interim Associate Dean, Student Dev Repl Maria Cisneros‐Hired External Feb

Jonathan Smith Technician Services Hardware/Software Technician New Position‐Hired External‐Temp Apr

Giang Pham COO Procurement Liaison Repl Jackie Nguyen‐Hired External Apr

Susan Thompson Student Services Program Director Repl Bartlett Sheinberg‐Hired External‐Temp Apr

Samuel Thomas Biology Lab Assistant Senior Repl Kristy Mueck‐Hired Internal Apr

Gerald Faler, Jr. Student Services Enrollment Service Associate Repl Corey Aeck‐Hired Internal May

Latasha Henderson Student Services Enrollment Service Associate Repl Liza Chau‐Hired Internal May

Lisa Padilla Student Services Enrollment Service Assistant Repl Carlana Brooks‐Hired External May

Antonio Nutall COO Evening Campus Manager II New Position‐Hired External    May

John Harrell II Student Services Enrollment Service Associate Repl Makeba Brown‐Hired External‐Temp May

LaToya Smith‐Jiles COO Office Manager Repl Gerald Faler‐Hired Internal Jul

7        New Position‐External 7        Interim 2        

Ronald Dewlen Instructional Dean Instruction Repl Lois Avery‐Hired External Sep

Northwest Replacement‐Internal 7        Replacement‐External 23     New Position‐Internal

Hosein Tahvilian Electronic Engineering Instructor Repl Pratap Talusani‐Hired External Sep

Nicki Norman Student Services Office Manager Repl Barbara Smith‐Hired Internal Sep

Ifeanyi Oramulu Technology Instructor Repl Homer Stewart‐Hired External‐Temp Sep

Khansaa Almansor Electronic Engineering Instructor Repl Nicky Haddock‐Hired External Sep

David Jones Student Services Advising Manager New Position‐Budget 12‐13‐Hired Internal Oct

Lesley Savoy‐Green Student Services Enrollment Services Associate Repl Alonia Whitmore‐Hired Internal Oct

William Nicholson Technology Instructor Repl John Jagdish‐Hired External‐Temp Sep

Betty Keller Student Services Retention Specialist Repl Joseph Willis‐Hired Internal Sep

Hoang Nguyen Student Services Advisor Repl Ana Canek‐Hired Internal Dec

Sazar Ali Process Technology Instructor Repl Homer Stewart‐Hired External Jan

Cybele Ayaquica COO Secretary II Repl Bridgette Bauman‐Hired External Nov

Jose Cordero Student Services Advisor Repl David Jones‐Hired External Nov

Randall Murphy Psychology Instructor Repl Tamara LeDuc‐Hired External Feb

Gregory Dock Automotive Instructor Repl Martin See‐Hired External Feb

Kristin Wallace Business Administration Instructor Repl Philip Palese‐Hired External Jan

Leroy Chevalier COO Manager Weekend/Evening Repl Keffus Falls‐Hired External‐Temp Feb

Ayesha Farr Counselor Counseling New Position‐Budget 12‐13‐Hired External Feb

Francis Pollo Testing Testing Assistant/Proctor Repl Lesley Savoy Green‐Hired External Feb

Shawket Alnakkash Petroleum Engineering Instructor New Position‐Budget 12‐13‐Hired External Feb

Farrish Betton Petroleum Engineering Instructor New Position‐Budget 12‐13‐Hired External Feb

Rodney Harrison Student Services Enrollment Services Associate Repl Rosa Martinez‐Hired External Jul

Ann Le COO Student Accounts Representative Sr. Repl Bertha Lauve‐Hired External Jul

Tamara Petty Counseling Counselor New Position‐Hired External Jul

Jose Gonzalez Science Engineering Lab Assistant I Repl Betty Keller‐Hired External Jul

1        New Position‐External 4        Interim ‐         Northeast Replacement‐Internal 4        Replacement‐External 16     New Position‐Internal

Page 62: Fs2013 july

Salary

Houston College Community Systems

2012‐2013 Positions

Employee Name Department Job Title Comments Month

SOUTHWEST13,810$

47,647$

38,678$

24,800$

48,954$

49,511$

57,000$

42,631$

45,555$

60,500$

35,000$

41,810$

41,141$

40,695$

40,000$

47,085$

39,824$

84,866$

31,906$

36,791$

43,557$

27,165$

35,406$

26,000$

27,000$

45,225$

35,044$

43,173$

39,187$

44,615$

45,780$

31,312$

22,300$

106,759$

34     

1,440,727$       

SOUTHEAST39,960$

32,538$

35,000$

42,000$

40,769$

53,706$

37,981$

98,566$

8        

380,520$          New Postions

55

Lorraine Donovan Academic Instructor Repl Adballah Cherif‐Hired External‐Temp Sep

Jose Cruz COO Campus Service Technician Repl Belinda Defalco‐Hired Internal Oct

Jennifer Williams English Instructor Repl Panqing Wu‐Hired External Oct

Kelli Caraway Student Dev/Advising Senior Advisor New Position‐Budget 12‐13‐Hired Internal Oct

Brandi Gaza English Instructor Repl Margie Ricks‐Hired External‐Temp Oct

Wendy Allen Digital Communication Instructor Repl Paul Roberts‐Hired External‐Temp Nov

David Stacy Student Dev/Advising Senior Advisor New Position‐Budget 12‐13‐Hired External Nov

Christine Moore Student Dev/Advising Senior Advisor New Position‐Budget 12‐13‐Hired Internal Oct

Dashiel Geyen Counseling Counselor New Position‐Budget 12‐13‐Hired Internal Nov

Wendy Robbins Digital Communication Instructor Repl Margo Reece‐Hired External‐Temp Nov

Sabiha Mir Student Development Advisor New Position‐Budget 12‐13‐Hired External Nov

Todd Duplantis Public Relations Director, Public Relations Repl Martha Barrera‐Hired External Nov

Aketa Guillory Student Dev/Advising Advisor New Position‐Budget 12‐13‐Hired External Nov

Wendy Robbins Digital Communication Instructor Repl Margo Reece‐Hired External Jan

Nicol Alexander Digital Communication Instructor Repl Lloyd Schuh‐Hired External Jan

Emilio Mendoza Student Development Advisor Repl Kelli Caraway‐Hired Internal Dec

Lucille Gore Student Dev/Advising Senior Advisor New Position‐Budget 12‐13‐Hired External Jan

Johanne Huber Digital Communication Instructor Repl Ian Mayer‐Hired External‐Temp Jan

Juanna Shin Library Librarian Repl Bill Hord‐Hired External Jan

Gholam Pahlavan Physical Science Instructor Repl Abdallah Cherif‐Hired Internal Jan

Lanny Kwan Computer Science Secretary II Repl Dipal Parekh‐Hired External‐Temp Jan

Lliya Lliev COO A/V Technician New Position‐Budget 12‐13‐Hired External Feb

Ramiro Monsivais Castorena COO A/V Technician New Position‐Budget 12‐13‐Hired External Feb

Ansonia Jones Student Services Enrollment Service Assistant Repl Ngoc Tien Nguyen‐Hired External Feb

Ashley Martin Student Development Advisor Repl Hoang Minh Thi Nguyen‐Hired Internal Feb

Rhonda Tripeaux Student Services Advisor Repl Johnny Martinez‐Hired Internal Apr

Rita Majidi COO Budget Analyst Repl Patrick Muhammad‐Hired External‐Temp Apr

Zhiqin Jiang Drafting & Design  Instructor Repl Seymour Tatar‐Hired External Feb

Sherry Hill Student Services Financial Aid Associate Repl Thomas Sneed‐Hired Internal Apr

Mayra Herrera Student Dev Secretary II Repl Sabiha Mir‐Hired Internal Jun

Troy Tabner COO Campus Service Technician Repl Jose Cruz‐Hired External Jun

Melaine Knight Public Relations Community Outreach Cordinator Repl Susie Molina‐Hired External May

Piper Butler Student Services Testing Associate Repl Gretchen Johnson‐Hired Internal Jun

Betty Fortune Instruction & Student Svcs Executive Dean, Instruction & Student Svcs New Position‐Budget 12‐13‐Hired Internal Jul

3        New Position‐External 6        Interim ‐         

Micalyn Flagg Financial Aid Financial Aid Associate Repl Verlicia Pope‐Hired External Oct

Southwest Replacement‐Internal 9        Replacement‐External 16     New Position‐Internal

LaTrista Funchez Student Services Student Life Coordinator Repl Tara Webb‐Hired External Nov

Araceli Alvarez Workforce Office Manager Repl Mercedes Gonzales‐Hired Internal Jun

Nancy Garcia Natural Sciences Secretary II New Position‐Hired External Oct

Christy Muniz Student Services Advisor Repl Vivian Flores‐Hired External Oct

Grisel Cano Instructional Support Associate Dean of Instructional Support New Position‐Budget 12‐13‐Hired Internal Jul

Antonio Quintero Educational Technology Svc Sr., Web Developer  Repl Johnny Pea‐Hired Internal Jun

Gloria Ruiz Public Relations Office Manager Repl Marco Calderon‐Hired External Jul

New Position‐Internal 1        New Position‐External 1        Interim ‐         Southeast Replacement‐Internal 3        Replacement‐External 3       

Page 63: Fs2013 july

Salary

Houston College Community Systems

2012‐2013 Positions

Employee Name Department Job Title Comments Month

COLEMAN35,754$

56,900$

62,781$

30,000$

65,272$

65,272$

44,615$

38,000$

35,000$

35,500$

53,618$

52,200$

63,993$

13     New Postions 638,905$          

Adm. Totals Replacement‐Internal Replacement‐External New Position‐Internal New Position‐External Interim 122   

College Totals Replacement‐Internal Replacement‐External New Position‐Internal New Position‐External Interim 141   

Grand Total Replacement‐Internal Replacement‐External New Position‐Internal New Position‐External Interim 263   

Over all Total 12,665,039$    

56

Grand Total Salaries

Charmaine Lewinson‐Evans Vocational Nursing Instructor Repl Pearlie Watts‐Hired External Sep

Caroline Couto‐Ortiz Health Science Dental Hygiene Operations Assistant New Position‐Budget 12‐13‐Hired External Sep

Daniel Guzman Simulation Center Clinical Simulation Lab Technician New Position‐Budget 12‐13‐Hired Internal Sep

Ashley Nichols Vocational Nursing Instructor Repl Sharon McCowan‐Hired External Sep

Veronica Mckissic Student Services Learning Success Coordinator Repl Roxine Simms‐Hired External‐Temp Nov

Carmela Blackshear Student Services Advisor Repl Carmen Gentry‐Hired Internal Jan

Rita Callahan Vocational Nursing Instructor Repl Maria Reyes‐Hired External Nov

Jason Smith Vocational Nursing Instructor Repl Independencia Delacruz‐Hired External Nov

Virginia Otieno Health Science Instructor Repl Linda Williams‐Hired External‐Temp Jan

Hope Pamplin Student Services Counselor, Disability Services New Position‐Budget 12‐13‐Hired External‐Temp Feb

David Pereida Student Services Advisor Repl Lorenzo Walker‐Hired Internal Jan

John Smith  Student Services Enrollment Service Associate Repl Rory Gupta‐Hired External Jan

Turquessa Francis Occupational Therapy Instructor Repl Naydean Blair‐Hired External Apr

Coleman Replacement‐Internal 2        Replacement‐External 8        New Position‐Internal

263  

52     112   31     61     6        

27     76     13     21     3        

1        New Position‐External 2        Interim ‐         

25     36     18     40     3        

Page 64: Fs2013 july

HOUSTON COMMUNITY COLLEGEFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 1,361    1,514    1,534    1,487    828       1,480    1,533    1,575    1,548    1,009    1,108   

2011‐2012 1,451    1,582    1,598    1,564    823       1,530    1,573    1,598    1,576    1,003    1,098    955      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 1,401    1,426    1,449    1,351    1,438    1,456    1,383    1,476    1,447    1,441    1,456   

2011‐2012 1,429    1,415    1,425    1,327    1,407    1,429    1,396    1,404    1,410    1,397    1,391    1,429   

F

T

E

F

T

E

57

 ‐

 200

 400

 600

 800

 1,000

 1,200

 1,400

 1,600

 1,800

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 200

 400

 600

 800

 1,000

 1,200

 1,400

 1,600

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 65: Fs2013 july

CENTRAL COLLEGEFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 238       270       272       270       153       256       274       281       278       166       199      

2011‐2012 254       293       296       293       159       279       298       300       291       184       204       178      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 155       159       164       145       161       164       153       169       159       161       160      

2011‐2012 161       158       165       145       155       163       157       157       158       156       154       161      

58

F

T

E

F

T

E

 ‐

 50

 100

 150

 200

 250

 300

 350

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 66: Fs2013 july

COLEMAN COLLEGEFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 108       107       113       110       78          106       107       109       104       95          98         

2011‐2012 115       112       113       109       82          109       107       110       110       99          98          84         

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 56          55          55          52          58          58          55          58          55          53          54         

2011‐2012 58          58          59          55          56          58          55          55          57          54          54          55         

F

T

E

F

T

E

59

 ‐

 20

 40

 60

 80

 100

 120

 140

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 10

 20

 30

 40

 50

 60

 70

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 67: Fs2013 july

NORTHWEST COLLEGEFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 281       310       310       306       156       306       316       319       317       200       230      

2011‐2012 267       292       293       307       155       323       330       334       335       198       224       190      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 131       135       143       125       142       145       129       151       147       147       147      

2011‐2012 104       106       108       108       129       138       122       129       130       132       131       138      

F

T

E

F

T

E

60

 ‐

 50

 100

 150

 200

 250

 300

 350

 400

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 68: Fs2013 july

NORTHEAST COLLEGEFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 187       208       212       205       119       199       211       218       215       146       150      

2011‐2012 200       211       216       207       112       204       212       212       211       129       137       124      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 126       125       128       118       124       128       119       128       128       124       126      

2011‐2012 127       126       128       118       121       128       124       127       126       126       126       128      

F

T

E

F

T

E

61

 ‐

 50

 100

 150

 200

 250

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 69: Fs2013 july

SOUTHWEST COLLEGEFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 318       385       375       370       187       364       376       381       377       224       249      

2011‐2012 380       433       435       422       183       377       382       386       382       229       252       217      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 152       154       161       142       154       163       150       168       160       161       163      

2011‐2012 185       184       182       145       146       155       144       150       152       151       147       153      

62

F

T

E

F

T

E

 ‐

 50

 100

 150

 200

 250

 300

 350

 400

 450

 500

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 70: Fs2013 july

SOUTHEAST COLLEGEFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 130       160       164       163       74          158       174       180       179       105       115      

2011‐2012 143       168       173       169       77          161       178       183       179       101       120       95         

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 96          103       104       95          102       105       95          106       105       101       103      

2011‐2012 99          96          97          86          94          98          91          95          96          99          96          101      

F

T

E

F

T

E

63

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 71: Fs2013 july

Division of Extended Learning (DOEL)FTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 90          67          79          57          58          73          67          77          70          67          63         

2011‐2012 85          69          68          56          55          72          63          67          64          59          57          64         

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 79          81          81          76          80          86          82          88          87          86          87         

2011‐2012 78          79          79          75          79          80          77          79          79          79          78          81         

F

T

E

F

T

E

64

 ‐

 10

 20

 30

 40

 50

 60

 70

 80

 90

 100

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 10

 20

 30

 40

 50

 60

 70

 80

 90

 100

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 72: Fs2013 july

DISTRICTFTE Comparison Year‐To‐Date Thru July 31, 2013 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 8            7            8            5            3            9            9            10          8            5            4           

2011‐2012 7            4            4            1            ‐             5            4            5            3            4            4            3           

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 606       612       614       598       617       609       600       609       605       607       615      

2011‐2012 616       609       608       595       627       609       625       612       614       601       605       612      

F

T

E

F

T

E

65

 ‐

 2

 4

 6

 8

 10

 12

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 100

 200

 300

 400

 500

 600

 700

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 73: Fs2013 july

HOUSTON COMMUNITY COLLEGEDuplicated Headcount Comparison Year‐To‐Date Thru July 31, 2013 by Type

FACULTY HEADCOUNT

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

12‐13 FT 787       795       795       797       794       796       797       796       796       768       763      

12‐13 PT 1,992    2,361    2,491    2,224    409       2,207    2,291    2,383    2,311    932       1,274   

12‐13 Total Fac 2,779    3,156    3,286    3,021    1,203    3,003    3,088    3,179    3,107    1,700    2,037    ‐            

11‐12 FT 792       797       793       788       793       785       784       782       783       768       757       794      

11‐12 PT 1,911    2,334    2,390    2,331    275       2,387    2,391    2,351    2,367    1,075    1,372    679      

11‐12 Total Fac 2,703    3,131    3,183    3,119    1,068    3,172    3,175    3,133    3,150    1,843    2,129    1,473   

STAFF HEADCOUNT

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

12‐13 FT 1,238    1,250    1,264    1,260    1,263    1,279    1,277    1,289    1,276    1,273    1,292   

12‐13 PT 840       833       851       842       703       801       820       851       858       769       826      

12‐13 Total Staff 2,078    2,083    2,115    2,102    1,966    2,080    2,097    2,140    2,134    2,042    2,118    ‐            

11‐12 FT 1,256    1,256    1,238    1,235    1,253    1,242    1,249    1,235    1,240    1,201    1,240    1,250   

11‐12 PT 877       879       883       839       629       822       834       828       846       767       790       790      

11‐12 Total Staff 2,133    2,135    2,121    2,074    1,882    2,064    2,083    2,063    2,086    1,968    2,030    2,040   

66

 

S

t

a

f

f

 

Headcount

 

F

a

c

u

l

t

y

Headcount

 ‐

 500

 1,000

 1,500

 2,000

 2,500

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 200

 400

 600

 800

 1,000

 1,200

 1,400

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 74: Fs2013 july

HOUSTON COMMUNITY COLLEGEUnduplicated* Headcount Comparison Year‐To‐Date Thru July 31, 2013 by Type

UNDUPLICATED HEADCOUNT

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

12‐13 Total  4,475    4,446    4,551    4,726    3,085    4,629    4,717    4,550    4,775    3,467    3,702   

11‐12 Total  4,543    4,902    4,917    4,833    2,891    4,728    4,814    4,805    4,806    3,373    3,575    3,303   

* Includes Full‐time and Part‐time Faculties, Librarians, Counselors, and Staffs 

67

Unduplicated* Headcount

 ‐

 500

 1,000

 1,500

 2,000

 2,500

 3,000

 3,500

 4,000

 4,500

 5,000

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 75: Fs2013 july

Non‐current assets:

Restricted cash 6,811$                  

Restricted investment in trust accounts 2,033,119

Lease receivable from HCCS 165,775,579        

Deferred charges ‐ bond issuance costs ‐                             

Capital Assets:

Land ‐                         

Other Structures ‐                         

Furniture & equipment ‐                         

Leasehold improvements ‐                         

Construction in process 1,361,614        

1,361,614            

TOTAL ASSETS 169,177,123$      

Current liabilities:

Accounts payable ‐ HCC 144,304$             

Accounts payable 239,526                

Accrued liabilities ‐ interest ‐                             

Current bond payable ‐                             

Total current liabilities 383,831$             

Non‐current liabilities:

Deposits 440                       

Arbitrage payable ‐                             

Unearned interest income (23 years) ‐ HCC 67,759,804          

Premium on bonds 2,209,548            

Bonds payable 105,655,000        

Total non‐current liabilities 175,624,793$      

TOTAL LIABILITIES 176,008,623        

TOTAL NET ASSETS ‐ restricted (6,831,500)$         

PFC 1

Houston Community College ‐ Public Facility CorporationStatement of Net Assets

Cash Basis ‐ Interim Period

as of July 31, 2013

ASSETS

LIABILITIES

Page 76: Fs2013 july

Cash Flows from Capital Financing Activities

Receipt from HCCS for lease payment 8,956,434$     

Purchases of capital assets (1,082,251)      

Payment on capital debt ‐ principal and interest (8,957,391)      

Net cash provided (used by) in financing activities (1,083,209)      

Cash Flows from Investing Activities

  Interest income 2,426

Increase (decrease) in restricted cash and 

restricted investment in trust accounts (1,080,783)      

Restricted cash and restricted investment in 

trust accounts ‐ beginning of year 3,120,712        

Restricted cash and restricted investment in 

trust accounts ‐ end of period 2,039,929$     

Houston Community College System Public Facility CorporationStatement of Cash Flows

Cash Basis ‐ Interim Period

Eleven Month Ended as of July 31, 2013

PFC 2

Page 77: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

To Date Unexpended

Sources of funds:

Proceeds from 

2005C Lease Revenue Bond 19,155,000$   

Discount (170,064)        Land Purchase (4,212,644)    Bond Issuance Cost (606,201)        Interest Expense (524,785)        

13,641,306$  Interest Income 1,003,844      Vendor Contract Refund 102,706         Transfer to Payment Account (1,354,990)    

Funds Available 13,392,866$  

Uses of funds:4,092$             4,092$             ‐$ ‐$                   

11,550,643    11,550,643    ‐                      ‐                    Maintenance 408,920          380,017          28,903           ‐                    

6,443              6,443              ‐                    563,928          563,928          ‐                    

7,200              7,200              ‐                      ‐                    27,403            26,326            1,077              ‐                    24,940            24,940            ‐                    44,695            44,695            ‐                      ‐                    

596,787          596,787          ‐                      ‐                    

157,815            8,100                149,715         

Grand Total Uses 13,392,866$   13,213,171$   29,980$          149,715$     

Net Available ‐$                     

  PFC requires GMP before inception.

Total Proceeds from Bond

Houston Community College ‐ Public Facility CorporationPublic Safety Institute

as of July 31, 2013

PFC 3

Bank Service ChargesConstruction

Waste Water Management *Geo Technical Services*

Survey*Architect

Engineering ServicesFFE

Contingency

 * Included in GMP 

Site Infrasturcture

Page 78: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

to Date

Encumbrances    

to Date Unexpended

Sources of funds:

Proceeds from 

 2005 A Bonds  11,605,000$   

 Premium Received             492,931 

 Accrued Interest Received               53,425 

 Interest Income                    998 

 Bond Issuance Costs           (391,474)

 Repayment of Loans     (11,392,147)

Funds Available 368,733$        

Uses of funds:

Debt Service 53,425$            53,425$          ‐$                        ‐$                       

Renovation & Construction  169,759            169,759          ‐                          ‐                         

Demolish & Renovate Office 56,244              56,244            ‐                          ‐                         

Furniture & Fixtures 46,857              46,857            ‐                          ‐                         

Legal Fees 42,448              42,448            ‐                         

Grand Total Uses 368,733$         368,733$       ‐$                        ‐$                      

Net Available ‐$                     

Note 1: PFC requires GMP before inception.

Houston Community College ‐ Public Facility CorporationWestgate (Katy)as of July 31, 2013

PFC 4

Page 79: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

To Date Unexpended

Sources of funds:

Principal Amount on Bonds 36,950,000$   

Discount on Bonds (546,238)          

Underwriter's Discount (209,273)

Accrued Interest on Bonds 98,080             

Amount Available 36,292,569$   

Issuance Costs (490,131)          

 Accrued and Capitalized Interest (1,449,023)      

Repair and Replacement (1,000,000)      

Title Fees Capitalized (81,379)            

Amount Available for Project 33,272,036$   

Repayment to HCC (188,006)          

Project Account Balance 33,084,030$   

Administrative & Legal Fees (29,486)            

Interest Income 836,883           

Transfer Cost Issuance 85,509             

Interest Expense on Notes (135,299)          

Funds Available 33,841,637$  

Uses of funds:

Land & Building 17,807,972$    17,807,972$    ‐$                     ‐$                

Maintenance Rehabilitation & 

Deferred Maintenance

12,856,469      12,856,469      ‐                  

CPMS PGAL 211,959            211,959            ‐                  

Facilities Space Programming 214,620            214,620            ‐                  

Furniture, Fixtures & Equipment 1,006,277         1,006,277         ‐                       ‐                  

Site Infrastructure 859,844            854,984            4,859               ‐                  

Architect and Engineering 428,355            428,355            ‐                       ‐                  

Repair & Maintenance Contingency   ‐ 

per bond requirement

456,141            83,089              ‐                       373,052     

Grand Total Uses 33,841,637$   33,463,726$   4,859$            373,052$  

Net Available ‐$                     

  PFC requires GMP before inception.

Houston Community College ‐ Public Facility CorporationHayes Road ‐ Alief Project

as of July 31, 2013

PFC 5

Page 80: Fs2013 july

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

To Date Unexpended

Sources of funds:

Principal Amount of 2007 Series Bonds 58,885,000$   

Premium on Bonds 3,094,498        

Underwriter's Discount (346,244)          

Accrued Interest Income‐ Bonds 173,733           

Total Amount Available 61,806,987$   

Issuance Cost (839,837)          

Accrued  and Capitalized Interest (4,632,122)      

Repair and Maintenance Account ‐                        

Amount Available for Project 56,335,028$   

Interest Income on Trust Account 2,499,031        

Interest Expense on Notes (414,601)          

Transfer to Trustee Payment Account (4,715,422)      

Vendor Contract Refunds 230,035           

Sale of Land 569,890           

Funds Available 54,503,961$  

Uses of funds:

Land & Building 10,671,234$    10,671,234$    ‐$                     ‐$                    

Construction Cost‐ Building 18,200,000      18,200,000      ‐                       ‐                      

Construction‐Demolition 494,972            ‐                         ‐                       494,972         

Constuction‐ Site 640,988            636,957            4,030              ‐                      

Site Improvement 14,221,544      13,888,633      332,911          ‐                      

Site Demolition & Abatement 791,298            791,298            ‐                      

CPMS PGAL 1,391,958         1,391,958         ‐                       ‐                      

Site and Infrastructure Design 2,334,840         2,334,840         ‐                       ‐                      

Facilities Space Programming 29,274              29,274              ‐                       ‐                      

Architect and Engineering 1,256,727         1,256,727         ‐                      

Furniture, Fixtures & Equipment 1,828,332         1,818,281         10,051            ‐                      

Library 66,564              66,182              382                 ‐                      

Inspections 214,981            214,981            ‐                       ‐                      

Design Geotech 17,500              17,500              ‐                       ‐                      

Material Testing  24,503              24,503              ‐                       ‐                      

Communications IT‐ PGAL 253,614            253,614            ‐                      

IT Telephone & Communications 790,467            790,467            ‐                      

Surveying  62,398              59,124              3,274              ‐                      

Administrative Expenses 34,505              34,505              ‐                      

Preconstruction Costs 886,377            886,377            ‐                      

Contingency 291,833            186                    ‐                       291,649         

Grand Total Uses 54,503,907$   53,366,640$   350,647$       786,621$     

Net Available 54$                  

  PFC requires GMP before inception.

as of July 31, 2013

PFC 6

Houston Community College ‐ Public Facility CorporationNorthline Mall Project