Fry creek Restoration (Aberdeen)
112-06-2016Lower Basin Share Session
PRESENTATION #4
www.ezview.wa.gov/aberdeenfloodrelief
www.ezview.wa.gov/site/alias__1492/34489/local_projects.aspx
![Page 2: Fry creek Restoration (Aberdeen) - Wa](https://reader030.fdocuments.in/reader030/viewer/2022012721/61b368bc7e29de5fbe1b9546/html5/thumbnails/2.jpg)
Project Description/Overview:
2December 6, 2016Lower Basin Share Session
Fry Creek Restoration and Flood Reduction
• Restore Fry Creek to reduce flooding, improve habitat, and create public space:• Install high-capacity, fish-friendly culverts• Grade stream bank to create a floodplain
bench to improve conveyance and flood storage
• Include public access and recreation amenities• Daylight piped creek• Design pump station and tide gate
improvements, including features that improve fish passage
• Tie improvements in with other projects, including the North Shore Levee
![Page 3: Fry creek Restoration (Aberdeen) - Wa](https://reader030.fdocuments.in/reader030/viewer/2022012721/61b368bc7e29de5fbe1b9546/html5/thumbnails/3.jpg)
Current Status:
3December 6, 2016Lower Basin Share Session
• Project is a recommendation of the Timberworks Master Plan
• Design funded through Chehalis River Basin Flood Authority ($500,000)
• Consultant team selected December 5, 2016
• Partial construction funds included in 2017-2019 Washington Coast Restoration Initiative ask ($2,215,000)
![Page 4: Fry creek Restoration (Aberdeen) - Wa](https://reader030.fdocuments.in/reader030/viewer/2022012721/61b368bc7e29de5fbe1b9546/html5/thumbnails/4.jpg)
Upcoming Planned Activities:
4December 6, 2016Lower Basin Share Session
• Design kick-off late December 2016 or early January 2017• Design complete 2017• Construction 2018 (contingent on funding)
![Page 5: Fry creek Restoration (Aberdeen) - Wa](https://reader030.fdocuments.in/reader030/viewer/2022012721/61b368bc7e29de5fbe1b9546/html5/thumbnails/5.jpg)
Potential Issues:
5December 6, 2016Lower Basin Share Session
• Fully funding construction• Property acquisition• Property impacts with daylighting piped creek
![Page 6: Fry creek Restoration (Aberdeen) - Wa](https://reader030.fdocuments.in/reader030/viewer/2022012721/61b368bc7e29de5fbe1b9546/html5/thumbnails/6.jpg)
Further Information:
6December 6, 2016Lower Basin Share Session
• Project contact:
Kris Koski, PECity EngineerCity of Aberdeen(360) [email protected]